ML20003E616
| ML20003E616 | |
| Person / Time | |
|---|---|
| Site: | Arkansas Nuclear |
| Issue date: | 10/31/1980 |
| From: | ABB COMBUSTION ENGINEERING NUCLEAR FUEL (FORMERLY |
| To: | |
| Shared Package | |
| ML20003E615 | List: |
| References | |
| NUDOCS 8104070232 | |
| Download: ML20003E616 (74) | |
Text
..
. _ =.
i i
1 CESEC SIMULATION OF NSSS TRANSIENTS TESTS AT ANO-2 t'
October,.1980 Plant System Analysis Plant Engineering C-E Power-Systems Combustion Engineering, Inc.
4.'
4 U
P
~
- 810.4 0 7'DSM4 '
~
TABLE OF CONTENTS Section
1.0 INTRODUCTION
~
')
BACKGROUND 3.0 CESEC
'4.0 PLANT DESCRIPTION 5.0 TURBINE TRIP 5.1
SUMMARY
.5.2 PRETEST PREDICTION 5.3 SEQUENCE OF EVENTS 5.4 POST-TEST COMPARISON 6.0 FOUR PUMP LOSS OF FLOK 6.1
SUMMARY
6.2 PRETEST PREDICTION.
6.3 SEQUENCE OF EVENTS 6.4 POST-TEST COMPARISON 7.0 FULL LENGTH CEA DROP 7.1
SUMMARY
7.2 PRETEST PREDICTION 7.3 SEQUENCE OF EVENTS 7.4 POST-TEST COMPARISON 8.0 PART LENGTH CEA DROP 8.1
SUMMARY
i 8.2 PRETrST PREDICTION 8.3 SE'.JENCE OF EVENTS 8.4 PC iT-TEST COMP /JtISON 9.0 CONCLt s'WS
10.0 REFERENCES
i
LIST OF TABLES TABLE TITLE 5-I INITIAL CONDITIONS FOR TURBINE TRIP TEST 5-2 OPERATING STATUS OF THE SDBCS VALVES DURING TURBINE TRIP TEST 5-3 SEQUENCE OF EVENTS FOR THE TURBINE TRIP TEST 5-4 CESEC INITIAL CONDITIONS FOR TURBINE TRIP TEST 5-5 CESEC SEQUENCE OF EVENTS FOR THE TURBINE TRIP TEST 6-I-INITIAL CONDITIONS FOR THE TOTAL LOSS OF FLOW TEST 6-2 OPERATING STATUS OF THE SDBCS VALVES DURlnG FOUR PUMP LOSS OF FLOW TEST 6-3 SEQUENCE OF EVENTS FOR THE TOTAL LOSS OF FLOW TEST 6-4 CESEC INITIAL CONDIT0NS FOR THE FOUR PUMP LOSS OF FLOW TEST 6-5 CESEC SEQUENCE OF EVENTS FOR THE TOTAL LOSS OF FLOW TEST 7-I INITIAL CONDITIONS FOR THE FULL LENGTH CEA (5-60)
DROP TEST 7-2 SEQUENCE OF EVENTS FOR THE FULL LENGTH CEA (5-60)
DROP TEST 7-3
'CESEC INITIAL CONDITIONS FOR THE FULL LENGTH CEA (5-60)
DROP TEST.
7-4 CESEC SEQUENCE OF EVENTS FOR THE FULL LENGTH CEA (5-60)
DROP TEST 8-I INITIAL CONDITIONS FOR THE PART LENGTH (P-24) CEA DROP TEST 8-2 SEQUENCE OF EVENTS FOR THE PART LENGTH (P-24) CEA DROP TEST 8-3 CESEC. INITIAL CONDITIONS FOR THE PART LENGTH (P-24) CEA
. DROP TEST
'8-4 CESEC SEQUENCE OF EVENTS FOR THE PART LENGTH (P-24) CEA DROP TEST Ld
1 LIST OF FIGURES FIGURE TITLE 5-1 TURBINE TRIP - NORMALIZED REACTOR COOLANT PUMP 1 FLOW RATE
.5-2 TURBINE TRIP - NORMALIZED REACTOR COOLANT PUMP 2 FLOW RATE 5-3 TURBINE TRIP - STEAM GENERATOR 1 MAIN STEAM FLOW RATE 5-4 TURBINE TRIP - STEAM GENERATOR 2 MAIN STEAM FLOW RATE 5-5 TURBINE TRIP - STEAM GENERATOR.1 FEEDWATER FLOW RATE 4
5-6 TURBINE TRIP - STEAM GENERATOR 2 FEEDWATER FLOW RATE 5-7 TURBINE TRIP - STEAM GENERATOR 1 PRESSURE 5-8 TURBINE TRIP - STEAM GENERATOR 2 PRESSURE 5-9 TURBINE TRIP - PRESSURIZER PRESSURE 5-10 TURBINE TRIP - PRESSURIZER 1 WATER VOLUME 5-11 TURBINE TRIP - STEAM GENERATOR I COLD LEG TEMPERATURE (LOOP 1A)
~
5-12 TURBINE TRIP - STEAM GENERATOR 1 COLD LEG TEMPERATURE (LOOP IB) 5-13 TURBINE TRIP - STEAM GENERATOR 2 COLD LEG TEMPERATURE (LOOP 2A) 5-14 TURBINE TRIP ' STEAM GENERAGOR 1 HOT LEG TEMPERATURE 6-1 LOSS OF FLOW - NORMALIZED REACTOR COOLANT PUMP FLOW RATE 6-2 LOSS OF FLOW - STEAM GENERATOR 1 MAIN STEAM FLOW RATE 6-3 LOSS OF FLOW - STEAM GENERATOR 2 MAIN STEAM FLOW RATE-6-4 LOSS OF FLOW - STEAM GENERATOR 1 FEEDWATER FLOW RATE 6-5 LOSS OF FLOW -
EAM GENERATOR 2 FEEDWATER FLOW RATE 6 LOSS'0F FLOW - STEAM GENERATOR 1 PRESSURE 6-7 LOSS OF FLOW - PRESSURIZER PRESSURE
.6-8
~. LOSS OF FLOW - PRESSURIZER LEVEL 6-9 LOSS OF FLOW - STEAM GENERATOR 1 HOT LEG TEMPERATURE
'6 LOSS.0F FLOW - STEAM GENERATOR 1 COLD LEG TEMPERATURE (LOOP 1A) s s
L.J
FIGURE TITLE 6-11 LOSS OF FLOW - STEAM GENERATOR 1 COLD LEG TEMPERATURE (LOOP IB) 6-12 LOSS OF FLOW - STEAM GENERATOR 2 HOT LEG TEMPERATUPI 6-13 LOSS OF FLOW - STEAM GENERATOR 2 COLD LEG TEMPERATURE (LOOP 2A) 6-14 LOSS OF FLOW - STEAM GENERATOR 2 COLD LEG TEMPERATLTE (LOOP 2B) 7-1 DROPPED CEA LOCATIONS 7-2 FULL LENGTH CEA DROP - TURBINE POWER 7-3 FULL LENGTH DEA DROP - STEAM GENERATOR 1 MAIN STEAM FLOW RATE
'4 FULL LENGTH DEA DROP - STEAM GENERATOR 2 MAIN STEAM FLOW RATE 7-5 FULL LENGTH CEA DROP - STEAM GENERATOR 1 FEEDWATER FLOW RATE 7-6 FULL LENGTH CEA DROP - STEAM GENERATOR 2 FEEDWATER FLOW RATE 7-7 FULL LENGTH CEA DROP - hTCLEAR POWER 7-8.
FULL LENGTH CEA DROP - PRESSURIZER PRESSURE 7-9 FULL IINGTH DEA DROP - PRESSURIZER LEVEL 7-10 FULL LENGTH CEA DROP - STEAM GENERATOR 1 PRESSURE 7-11 FULL LENGTH CEA DROP - STEAM GENERATOR 2 PRESSURE 12 FULL LENGTH CEA DROP - STEAM GENERATOR 1 HOT LEG TEMPERATURE 13 FULL LENGTH CEA DROP - STEAM GEhTRATOR 1 COLD LEG TEMPERATURE (LOOP 1A) 7-14 FULL LENGTH CEA DROP - STEAM GENERATOR 2 HOT LEG TEMPERATURE 7-15 FULL LENGTH CEA DROP - STEAM GENERATOR 2 COLD LEG TEMPERATURE (LOOP 2A) 8 PART LENGTH CEA DROP TURBINE POWER 8-2 PART LENGTH CEA DROP - STEAM GENERATOR 1 MAIN STFJLM FLOW RATE 3 PART LENGTH CEA DROP - STEAM GEhERATOR 2 MALN STEAM FLOW RATE 8 PART LENGTH CEA DROP - STEAM GENERATOR 1 FEEDWATER FLOW RATE 8-5 PART LENGTH CEA DROP STEAM GENERATOR 2 FEEDWATER FLOW RATE r
e
FIGURE TITLE 8-6 PART LENGTH CEA DROP - NUCLEAR PO ER 8-7 PART LENGTH CEA DROP - STEAM GENERATOR 1 HOT LEG TEMPERATURE 8-8 PART LENGTH CEA DROP - STEAM GENERATOR I COLD LEG TEMPERATLPE
'(IDOP IB) 8-9 PART LENGTH CEA DROP - STEAM GENERATOR 2 HOT LEG TEMPERATURE 8-10 PART LENGTH CEA DROP - STEAM GENERATOR 2 COLD LEG TEMPERATURE LOOP 2B) 8-11.
PART LENGTH CEA DROP - STEAM GENERATOR 1 PRESSURE 8-12 PART LENGTH CEA DROP - STEAM GENERATOR 2 PRESSURE 8-13 PART LENGTH CEA DROP - PRESSURIZER PRESSt%E 8-14 PART LENGTH CEA DROP - PRESSURIZER LEVEL 4-3 1
1.0 INTRODUCTION
This report documents the results obt ained with Combustion Engineering's System Excursion Code, CESEC, (Reference 1) in the sianlation of plant tests performed during the power ascension of Arkansas Nuclear One-Unit 2 (ANO-2). The comparisca of CESEC against plant test data re-sponds to a Nuclear Regulatory Commission (NRC) request (References 2 and 3) that this experimental data be used in the verification of the safety analysis system computer code used for the ANO-2 Final Safety Analysis Report, FSAR, (Reference 4).
The particular tests simulated included a turbine trip from 98.2 percent power, a four pump loss of flow from 81 percent power, a full length control element assembly
'(FLCEA) drop from 49.4 percent power, and a part length control element assembly (PLCEA) drop from 49.2 percentpower.
In general, the input data was prepared for each test according to the measured initial conditions in the plant.
The forcing functions for the analyses were the measured steam flow, the feedwater flow and enthalpy, the primary system flow, and the time of reactor trip.
The transient data for all four tests shown in this report were recorded using a PDP-11 minicomputer and the existing plant instrumentation.
1 a
L__.
)
i i
i
2.0 BACKGROUND
The NRC requested that Arkansas Power and Light (AP&L) perform tests during the ANO-2 power ascension program in order to obtain data for the qualification of CESEC. AP&L gained approval to use four tests from their exiscing power ascension program. These four tests were selected to represent a range of typical PWR transients which would examine the capability of CESEC to predict system response in a comprehensive man-ner. The turbine trip test from 98.2 percent power provides the NSSS response to a load rejection transient initiated from the secondary system. The loss of flow test from 81 percent power provides the NSSS response to a power / cooling mismatch transient initiated from the pri-mary system. The FLCEA and PLCEA tests from 49 percent power provide the NSSS response to an anomaly in the core.
In preparation for the tests, AP&L reviewed the test procedures to ensure that all data needed to verify CESEC would be recorded, and developed pretest predictions of all four tests. The predictions were used in identifying the exprected trends and the characteristic varia-tions of the monitored NSSS parameters.
Cu
3.0 CESEC CESEC is a simulation tool developed at C-E for the analysis of normal and abnormal (non-LOCA) occurrences in a Nuclear Steam Supply System (NSSS) employing a Pressurized Water Reactior (PWR) design. The program is used in licensing analyses and for best estimate predictions of the dynamic response of the NSSS. CESEC utilizes the node-flowpath concept and is self-initializing for a consistent set of reactor operating conditions. The fluid in the primary system, outside of the pres-surizer, is treated as homogeneous and can be either subcooled or sat-urated. The pressurizer fluid is treated in separate water and steam regions that may or may not be in equilibrium. The code assumes 100 percent effectiveness of the spray flow in condensing vapor in the
-pressurizer. The secondary system is explicitly modeled up to the turbine admission valve. A detailed description of the code is provided in Reference 1.
m.
4.0 PLANT DESCRIPTIONS The ANO-2 plant includes a PWR NSSS supplied by C-E.
The NSSS is char-acterized by four primary coolant loops and two steam generators. The reactor core consists of 177 assemblies with an active length of 150 inches. The rated thermal output of the reactor is 2815 megawatts and the net electrical output is 912 megawatts. The primary system is designed to operate at a nominal gressure of 2250 psia, a full power core mass flow rate of 133.0 x 10 lbm/hr, and a full power core average coolant temperature of 579*F.
The normal secondary system pressure during full power operation is approximately 900 psia. A complete plant description is provided in Reference 4.
-w
- wee,
5.0 TURBINE TRIP 5.1
SUMMARY
The turbine trip test performed during the ANO-2 power ascension program was initiated from a power of 2764 Mwt (98.2%). The tur-bine trip is an event which results in a rapid increase in primary
- and secondary system pressures. With the plant control systems fully operational they can response automatically to stablize the system behavior without-a reactor trip.
l~
Hcwever, this particular ANO-2 turbine trip event was initiated with three out of the four dump valves in the steam dump and bypass control system (SDBCS) unavailable (one isolated and two in manual i
mode)..Therefore, the reactor tripped early in the transient on a low steam generator water le il signal because the reduced dump and
-bypass ~ capacity of the steam dump and bypass system resulted in a rapid decrease in steam generator water level.
In addition, the test unintentionally included one stuck open dump valve (failed to close after opening) and one partially stuck open perssurizer spray valve (fails to rescat after getting close signal). Therefore, following the initial primary and secondary presstre increases, the subsequent cooldown was enhanced by the valve failures. This excessive cooldown caused the pressurizer level to drop below the indicating range and the safety injection system was actuated on a
'ow pressurizer pressure signal. As per NRC directives the four reactor coolant pumps (RCPs) were tripped following the safety 1
injection actuation signal (SIAS). The cooldown was terminated by
. closure of the main steam isolation valves and the pressurizer subsequently refilled.
5.2 ' PRETEST PREDICTION The CESEC pretest: prediction for the turbine trip test assumed that
.all the plant. control systems would function automatically with the i
LSDBCS operating at its full dump'and bypass capacity, i.e.,
85 percent of.the ' full power steam flow. The resulting analysis showed that theLinitiation of the quick open signals to the dump and bypass valves upon turbine' closure' coupled with the operation l
of the reactor regulating. system (RRS) would prevent a reactor
' trip. The plant would then. stabilize by automatic modulation of c
-the SDBCS.-
. As a result of the differences in pretestLprediction assumptions -
and the actual test conditions ' outlined in Section 5.1, the pretest' prediction.results:are not' comparable to.the test results.
5.3' SEQUENCE OF EVENTS i-l 1The turbine trip test wastinitiated from the initial ~ conditions
.shown in Table 5-1..
The plant control systems were all in the
~
-automatic ~ mode and operating normally.except-for the SDBCS. LAs-i previously mentioned in Section 5.1,.one atmospheric dump valve o
.(ADV) located downstream!of the main steam isolation valves (MSIVs)
E-
was isolated and the two atmospheric dump valves located upstream af the MSIVs were in the manual mode. Table 5-2 provides addi-tional information relating to the operating characteristics of the SDBCS at the time of the test.
The test was initiated by manually tripping the main turbine from the control room.
The SDBCS responded to the turbine closure by
. initiating quick open signals to the dump and bypass valves.
However, the capacity of.the valves to pass steam was degraded to about 45 percent of the full power steam flow. The main feedwater flow which tried to match steam flow was also degraded. Therefore, as a result of the mismatch between energy generation and energy removal, both the primary and secondary systems internal energies increased, the primary and secondary temperatures increased, the primary and secondary pressures increased, and the steam generator level decreased. The pressurizer spray flow also increased in an attempt.to moderate the increa.se in pressurizer pressure. At 6.1 seconds into.the transient, the reactor tripped on a steam genera-tor low level water signal-Following the reactor trip, the pres-sure increases terminated.
After the-primary and secondary pressures reached peak values, the pressures began.to decline _and signals were generated-to close both
- the pressure spray valve and the steam dump and bypass valves.
The
. three turbine bypass valves fully closed, but the pressurizer spray valve failed to reseat and one atmospheric dump valve remained fully open. The unexpected failures of these valves enhanced the cooldown of the system.- All three charging pumps were automa-
~tically activated and a SIAS was generated.
The pressurizer pres-sure and temperature continued to decrease and the pressurizer enptied.' Following NRC's directive, the operator shut off all four RCPs after the SIAS was generated. _After isolation of the ADV by closure'of the MSIVs, following a main steam isolation valve signal (MSIS), the cooldown'was terminated and the pressure began to
- refill. Table 5-3 presents a detailed sequence of events for the transient.
' 5.4 -POST TEST COMPARISON
.~'
~ The CESEC post test comparison for the turbine trip test was per-I formed using the initial conditions.shown in Table 5-4.
The core-outlet, temperature. and the steam' generator pressure are calculated by the code-during the initialization proces.s. Comparison of the initial conditions in Table 5-4 with the test initial conditions-
~ (see_ Table _5-1) indicates' good agreement. The_ impact on transients results of the slight difference in. reactor. power and core mass flow rate'is minimal 1because of the' closeness of other key para-
. meters. The initial pressurizer level is off by 0.6 percent which~
is within the 1 percent measurement error. The normal steady state
. charging'and letdown flow (40'gpa each) were used'in the CESEC simulation. 1The plant recorded aJcharging_ flow of 45.2 gpa.
~
However, this flow accountsT for. leakage through the RCPs seals.
The seal leakage was not simulated in CESEC.
e l.
rx
i Preparation of the input data which was used in the simulation included the following assumptions:
1.
After the CEAs are fully inserted upon reactor trip the reactor kinetics calculation in the code was bypassed.
The ANS decay heat curve based on 30 days of continuous operation at full power was used to simulate the power level for the remainder of the transient. Parametric studies show negligible sensitivity on the transient results to variations in the values of the decay heat curve used.
2.
The fraction of primary system flow through each steam generator loop was input to CESEC in table form as a function of time. The fl7w through each steam generator loops was held constant at its initial value until the pumps were tripped. The RCPs were tripped by the oper-ator at slightly different times (see Table 5-3).
The costdown curves are shown in Figures 5-1 and 5-2 for loops I and 2, respectively.
CESEC was driven with the
. coastdown of curves measured in the test. A natural circulation flow of 4 percent was assumed for the re-mainder of the remainder of the transient.
3.
The steam flow out of each steam generator was calculated by the code-from a user input table of steam flow as a function of time. The steam flow tables were generated from the plant measured-data. The steam flow out of each steam generator is provided in Figures 5-3 and 5-4.
THe non-symmetric response results from two bypass valves and the single operable dump valve being connected to the steam generator 1 steam line header, while the third bypass valve was connected to the steam generator 2 steam line header. As seen from Figures 5-3 and 5-4 the steam flows drop suddenly from the initial values at the time of the turbine trip. Once the SDBCS triggers the opening of the bypass and atmospheric valves, the steam flow increases again. Subsequent closing of the bypass valves
'(while the dump valve sticks open) causes a decrease in the steam flow. The steam flows level out at a dump capacity of about 12 percent until the MSIVs are closed.
Closure of the MSIVs should terminate all steam flow.
However, the reduced data indicates a small flow frac-
~
tion. This inconsistency is believed to be due to un-certainty in-the ZhP measurement used to calculate the steam flow rate at a low flow conditions. The CESEC analysis assumed the steam flows to go to zero upon closure of the MSIVs.-
4.
In the same' manner, the feedwater flow of each steam generator represented by a table of flow as a ' function of 3-time. -The main feedwater flows for each steam generator are provided in Figures 5-5 and 5-6.
The curves only represent the main feedwater flow contribution. The L
emergency feedwater flow was not measured because the test circuitry used to measure this parameter was not available for the test.
The emergency feedwater was activated on steam generator low water level at 6.1 seconds into the transient.
Initially, the main feedwater flow follows the steam flow through the automatic control of the feedwater control system (FWCS). After reactor trip (6.1 seconds) the main feedwater flow ramps down to a value of about 10 percent of the full power value. The ramped down design value is 5 percent. This inconsistency can also be attributed, as with the steam flow, to uncertainty in the lip measure-ment at low flow conditions. The CESEC analysis assumed the ramped down design value for the main feedwater flow to be 5 percent.
In addition, a value of 2.0 percent of the full power feedwater flow was assumed for the emer-gency feedwater after trip. This value corresponds to the design capacity of the emergency feedwater system.
After the MSIS, the main feedwater isolation valves close terminating the feedwater. Therefore, the CESEC analysis assumed the feedwater decays linearly to the value for the emergency feedwater flow as the isolation valves close.
5.
The main feedwater enthalpy remained nearly constant at 420 Btu /lbm, according to the plant recording of the temperature. The temperature or enthalpy of the emer-gency feedwater was not measured in the test. A value of 58 Btu /lbm was assumed. The time dependant table of feedwater enthalpy input to CESEC assumed a constant value of 420 Btu /lbm until the feedwater flow ramp down started. The enthalpy was then ramped down to a value of 58 Btu /lba and remained constant thereafter. The 200 second rampdown is based on the estimated volume to be sweptoutoftgefeedlinesandthesteamgeneratordown-3 comers (150 ft and 250 ft, respectively) by the emer-gency feedwater flow.
I i
6.
The spray flow in the analysis was assumed to increase proportionally with pressure. Once the maximum value of 376 gpm is reached, the proportional spray remains con-stant at 376 gpm_until the RCPs are tripped. After the l'
pumps are tripped, the spray flow is teaminated.
The spray flow enthalpy is assumed to correspond to the cold j
leg water enthalpy.
7.
The safety injection _ actuation setpoint and the HPSI (high pressure safety injection) pump shut off head were l
input at the design values of 1740 and 1440 psia, respec-1.
tively. The flow rates as a function of system pressure I
are input to the code in tabular form'.
Two HPSI pumps were assumed available.
The steam generators 1 and 2 pressure responses are given in Figures 5-7 and 5-8, respectively, The pressure responses exhibit non-sy= metric behavior caused by the non-symmetric steam flow. Steam generator 1 ex-periences a lower peak pressure and a lower minimum pressure than steam generator 2.
This is consistent with the steam flow behavior which is caused by having two bypass valves and the single operable dump valve connected to the steam generator 1 steam line header and only the third bypass valve connected to the steam generator 2 steam line header. The calculated CESEC results agree well with the experimental results as seen from Figures 5-7 and 5-8.
The MSIS is predicted by CESEC to occur at about the same time as in the test (231.3 seconds (CESEC) versus 241.5 seconds (test)). The peak pressures calculated by CESEC are about 40 to 50 psi higher than those recorded in the tast. This difference in secondary peak pressure can be partly attributed to the selection of the data values for steam flow which were used for driving the CESEC code during this initial transient time period.
Figure 5-9 shows the response of the pressurizer pressure. The pres-surizer pressure calculated by CESEC agrees well with the test results over the entire transient-time simulated. The agreement is within the range of uncertainty one would expect to exist from the assumptions made in the analysis and from uncertainty within the data. The pressurizer water level was not directly recorded until about 22 minutes into the event. However, Figure 5-10 shows a comparison of the CESEC predicted water volume in the pressurizer against that calculated by related test data.
The recorded RCS cold leg temperature for loops 1 and 2 are shown in Figures 5-11 through 5-13.
The CESEC model assumes both A and B loops to be lumped together for both steam generators 1 and 2.
Thus, in Figures 5-11 and 5-12 the test data is compared against the CESEC re-sults for loop 1.
In Figure 5-13 the CESEC results for loop 2 are compared against the test data for loop 2A.
Since the mini-computer recording for the cold leg temperature in loop 2B is unreliable because of the settings used, no comparison is shown for this loop.
The hot leg temperature comparison between CESEC and the test data is shown in Figure 5-14.
The CESEC results agree as well with the test data as previously shown for the cold leg temperature comparison. The test = data plotted combines information recorded from the mini-computer and the plant computer. This combination of data was necessitated because the_ lower range of the mini-computer was too high for the event which_ occurred. This problem would not have happened if the event would have proceeded as originally planned. The comparison between CESEC results and test data is only shown for loop 1, since similar agreement was obtained for loop 2.
The seocence of events as predicted by CESEC is provided in Table 5-5.
Compartson of key events with data (see Table 5-3) shows good agreement.
The CESEC maximum pressurizer pressure (2362 psia) is predicted to occur at-9.55 seconds, while the recorded data values for the pressurizer peak pressure and its time of occurrence are 2832 psia and 8.0 seconds, respectively.
The secondary peak pressures and their times of occur-
rence were predicted by CESEC to be 1071 psia /18.5 seconds (steam gen-erator 1) and 1134 psia /18.3 seconds (steam generator 2).
The data shows the peak secondary pressures occurred at 12.7 seconds with values of 1029 psia and 1091 psia for steam generators 1 and 2,'respectively.
CESEC predicted a minLaum pressurizer pressure of 1229 psia as compared to the test data value of 1350 psia. The time at which the pressurizer starts to refill demonstrates once again the closeness of the CESEC prediction with test data (323.4 seconds (CESEC) versus 308.0 seconds (test)).
t h
W, -
'* i TABLE 5-1
' Initial Conditions for Turbine Trip Test
~
Core Power, Mwt 2764(98.2%)
Core Inlet Temperature, *F 552 Core Outlet Temperature, F
61 0 0
Vessel Mass Flow Rate,10 lbm/hr l'33 Pressurizer Pressure, psia 2256 Pressurizer Level, percent 49.2 Steam Generator Pressure, psia 908 Charging Flow, gpm 45.2 (one pumo)
Letdown Flow, gpm 40.4 Control System Status Pressurizer Pressure Automatic Presurizer Level' Automatic Reactor Regulating Automatic r
Feedwater Automatic Steam Dump and Bypass Automatic
~
e 4
4 e
i e
e e
+
t
TABLE 5-2 Operating Status of the SDBCS Valves During Turbine ~ Trip Test Valve Description Capacity (1bm/hr)
Status 6
13% Turbine Bypass 1.24 x 10 Operable 6
5% Turbine Bypass 0.69 x 10 Operable 6
13% Turbine Bypass 1.24. x 10 Operable 6
13% Atmospheric Dump 0.94 x.10 Isolated 0
. 13% Atmospheric Dump 0.94 x 10 Operable 6
13% Atmospheric Dump 0.94 x 10 Manual 6
13% Atmospheric Dump 0.94 x 10 Manual e
a O
e G
e G
e 5
4 e
6 4
9 4
0
~
TABLE 5-3 Sdquened of Events for the' Turbine Tric Test Time (sec)
Event Value 0.0 Manual trip of main turbine 2.0 Three turbine bypass valves and the
~
atmospheric dump valve receive a quick-open signal from the SDBCS.
2.0 Pressurizer spray valve opens on signal from PPCS.
~
3.0 Turbine bypass valves and atmospheric dump valves full-open.
6.1 Reactor trip initiated on low steam 49%
generator water level.
Emergency feedwater actuation signal generated.
8.0 Maximum pressurizer pressure 2382 psia 1091 (loop 2) 12.7 Maximum steam generator pressure 1029 (loop 1) 21.0 Pressurizer spray valve gets close signal but fails to reseat.
21.0 Turbine bypass valves and atmospheric
~
dump valve receive close signals.
Atmospheric dump valve remains open.
29.0 Turbine bypass valves fully closed.
Atmospheric dump valve remained full open.
52.0 All three charging pumps in operation; 133.0 GPM Letdown flow being throttihd back to (charging) minimum value.*
102.6 Low pressurizer pressure generates 1740 psia safety injection actuation signal (SIAS).
Due to a failure of the plant computer to printout all the trend groups, this was the first indication of maximum charging flow.
Maximum charging flow was actually' initiated before this time via a signal from the pres-surizer level control system.
e O
TABLE 5-3 (Continued)
Sequence of Events for the Turbine Trip Test Tidd (sec)
Event Value 107.6 Hot leg temperature (steam generator 1)
<550 drops off-scale low 117.4 Hot leg temperature (steam generator 2)
<550 drops off-scale low 144.0 Pressurizer empties
~
'200.0 Reactor coolant pumps lA & 18 tripped 201.0 Reactor coolant pumps 2A & 2B tripped 205.0 Hot leg temperatures' increasing; natural 525*F circulation begins
~
241.5 Low steam generator 1 pressure generates 728 psia main steam isolatic, signal (MSIS) 248.0 Minimum pressurizer pressure 1350 psia 274.0 Manually closed atmospheric dump valve 308.0 Pressurizer level back on-scale 50%
100.1.
Hot leg temperatures back on-scale
>550*F 1440.
Pressurizer pressure recovered 2100 psia e
9 D
e e
S 4
e
'm e
,e, s
e-
-e
d r
TABLE E-4 CESEC Initial Conditions for Turbine Trip Test 2815 Core Power, Hwt 552 Cora :nt ot remperature, 'F 609 Core Outlet Temperature, *F 6
127 Vessel Mass Flow Rate,10 lbm/hr Pressurizer Pressure, psia 2257 3
583' (level =48.6%)
Pressurizer Water Volume, ft 909 Steam generator pressure, psia 40.0(onepump)
Charging Flow, gap 40.0 Letdown Flow, gpm Control System Status:
Automatic
- Pressurizer Pressure Automatic
- Pressurizer Level Not Used
- Reactor Reguiating Not Used
- Feedwater Not Used
- Steam Dump and Bypass O
O
+
e O
e e
I
~
TABLE 5-5 CESEC Sequence of Events for -the rurbine Trip Test Time (ses, cvent Value 0.0 Manual trip of main turbine 3.2 Spray value starts to open 5.3 Spray valve fully open 376 gpm d.1 Reactor trip manually Feedwater startdd to ramp down to 5%
full power flow rate plus 2.0% emergency feedwater 9.55 Maximum pressurizer pressure 2362 psia 18.3 Maximum steam generator pressure 1134 (loop 2) 18.5 1071 (loop 1) 126.0 gpm (en.. y:-):
30.0 All three charging pumps in operation 29.0 gpa (letdown Letdown flow 72.0 Low pressurizer pressure generates 1740 psia safety injection actuation signal (SIAS) 165.0 Pressurizer empties 200.
Reactor coolant pumps 1A and 18 tripped 201.
Reactor coolant pumps 2A and 2B tripped U
213.
Hot leg temperature starts to increase, 525 F natural circulation begins 231.3 Low steam generator 1 pressure generates
~ 728 psia MSIS 235.1 MSIV closed, steam flow terminated 245.0 Minimum pressurizer pressure 1299 psia 323.4 Pressurizer starts to refill 1270.0 Pressurizar pressure recovered 2100 psia e
~
~.
1.0.-
Data 0.5 _
0.0 i
-5 0
5 10 15 20 25 30 TIIE (tilli.)
Figure 5-1.
Turbine Trip - ilormalized Reactor Coolant Pump 1 Flow Rate l. 0 '-
f 1
Data
.0.5 g
f
(
0.0 1
6 e
i i
i
.I
-5.00 0.00 5.00 10.00 15.00 20.00
'l 30.00 TIl4E (till{.)
Figure 5-2.
Turbine Trip - ilormalized Reactor Coolant Purc.p 2 Flow Rate j.
--e d
.g _
e oc o R$i Data Ed b.. -_ _
g i
j r
i 6
I 8
-5.00 0.00 5.00 10.00 15.00 20.00' 25.00 30.0@
TIME (MIN.)
Figure 5-3.
Turbint Trip-Steam Generator 1 Main Steam Flow Rate L.-
e w
meR R~
\\'
Data w
i i
i i
t
-$.00 0.00 5.00 10.00 15.00 20.00 25.00 30.@
TIME (MIN.)
Figure 5-4.
Turbine Trip-Steam Generator 2 Main Steam Flow Rate e
..~
g-d n: x m M E-Data
~
I s-i i
i
.i i
i
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.0@
TIME (MIN.)
Figure 5-5.
Turbine Trip-Steam Generator 1 Feedwater Flcw Rate l
l s
l y-
~
e
!! E~
Da t'a la d
l l
6 I
I I
I I
I
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.0t TIME (MIN.)
' Figure 5-6.
Turbine Trip-Steam Generatcr 2 Feedwater Flow Rate l
l s
y g
.o
.d Ed
\\
Data k
CESEC sg
)
o 1
28-
\\\\
/
o V
- Ei i
i i
i i
i 1
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 5-7.
Turbine Trip - Steam Generator 1 Pressure 8
1,,
t
\\
l
\\
Data k-CESEC
~~~
3 g_
\\
- - + ~ ~
Eg
\\
\\
s,*
,/
C, i
8 i
i a
i i
i i
"5 0
5 10 15 20 25 30 TIME (IIIH.)
Figure 5-8.
Turbine Trip - Steam Generator 2 Pressure
~';
e
~
S-N I
.e
~~ _ _. a h h-m -
R l,-
s y
Data s
N
CESEC e'
b M-1 I
l i
I i
i
-5.00 0.00 5.00 10~. 00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 5-9.
Turbine Trip.- Pressurizer Pressure, Harrow Range
g... _. l.....l.
.. e]_~..
......._ l __ _.q
_. g._ _. i. _..
- m.,
-.-.._..i.',,
..%A
-p g.,.
...,..J..
...iu i...
[
.. I.
.... l.
8_
-L
_=.
.a_._,..
=
.u.
m..
.a I
7-t
~
..6
,_m-
-1
- p.-
4_
.4;
__...g j__ _.
i i-.
._.. g
..f,._ _
=
. 5
.g
.n..
g
- e. _
.___ ___c_ _. _ _ _,n..,
.t o
--- -- t
. u.1-1-
__. i._1.
i O
c p
o w
r-. - '.- 4--! -
t, (3
.l_.,.
d
-9
- ___r, g
.s o.
. s +..
_ g._.
~3 g <,i..g
-a_
h..s.c.
--s 3__ _v(1__a s
t
.s 1:
p.
C") c'
.g 4
a
.. c._
d g
i g..
.s #,3 i
. t. _-
@ y O s.
t' U
.S G
n m
... g,._
< CL u.
s.
u.
.,3,
c_.,.
.. :.+
k.
._ l_ _._.
w __.
-. _.,. _. _ _. = _
t._
a 3..;
. l _.-..
__e_..
y_ __ _._.
..a l
d,.
,m
- e. O.
_1 l. -
"E*
4...
T' NE 1 8
.:. 8 a
- p......,
L.7 -
._:W..
- I
, ?.
1 y
f_
3 n.
e
._ m a._L
,>.~...
m
, g
. _ =..
e
._)
_y
..T,.
- .L.
C-
.8 F
b
.6
_.[g ~.
.o. -.a
. 4 g
g.r... '
.. ).....'
J
. _..I
.,2 g
.. 4..,. ]
...,6..
.J f,
.. C.
.. _a..
.e_.
"w l....
gn t.
.4.
a
~ ' 1-4 6.,.
- *2
.,...a.
.. ~.,... 7.._.9..
...;....).....
,.g 7,
I;.
.7
...t._...i...
5
.j....i......'
_.......j...
4 --..
\\...._._._.,_.
.i..
_....._.1.._
1..
o.._
...... u.
_. i..
. l
. l...
...i,....,,............
...l.._._......I.._.i..__,___._._._.__._...,..1......_...._...___..
i...
o
.._i.
. _ o.._.
. u.. _,.. o.. _. l........
a
.o
.... o
. n.,
n....,
._.. ! _.. _.o....
. _.. o..
... (.
.... o... l... =n
..i c
m
. v.. _.. n...:
..I.
, _. -o.
... in...
. _ _'r
....a. _.. g..
- tl _.. s..
_l j
i...!..__,........,.........SWWA EEN M.GEUT'G53%
_... I
....t....
i._.......
..p..._..
.s.
1d..
r - ---
c
.-)
8
.E.
N e.
.s..
r,
..;c..
..r.
+1.c...-..'... e'.::. m c.....~,m.,,..-...:..
.... ~......,,..
~.
?...-
o.
C ST 1
f\\
t N
Data e o g
CESEC
.4 E! P s
~ ' _
s N
\\
N r
ob 8
i i
i i
i 1
i
. -5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 5-11 Turbine Trip-Steam Generator 1 Cold Leg Tempe'rature (Loop 1A) g_.
t t
\\
Data i'
\\,
CESEC
^
g g
m._
\\
-x~*
\\
e i
&8 4
i i
e i
i l
-5.00 0.00 5.00 10.00 15.00 20.00.
25.0.0 30.0C TIME (MIN.).
Figure 5-12 Turbine Trip-Steam Generator 1 Cold Leg Temoerature (Loop 1B)
O e
I o.
8-m t
i
\\
Data u.: o
CESEC eg
, M 3-
-* ~_,
e
~
s V--.~.e-#
o b
.S 0.00 5.00 10.00 15.00 20.00 25.00 30.00:
I 8
i i
i l
i
-5.00 TIME (MIN.)
Figure 5-13 Turbine Trip-Steam Generator 2 Cold Leg Tempe.rature (Loop 2A) e g-i ta 5N Data
. E *_
--- CESEC y
t t
\\
l o
W I
I I
m J
'I I
I 20.00.
25.~00 30.0@
-5.00 0.00 5.00 10.00 15.00 TIME (MIN.)
Figure 5-14:
Turbine Trip-Steam. Generator 1 Hot Leg Temperature r e w
%s r -, -
,,--,m r
4
- ir-'
6.0 FOUR PUMP LOSS OF FLOW 6.1
SUMMARY
The four pump loss of forced primary coolant flow test performed during the ANO-2 power ascension program was initiated from a power of 2295 Mwt (81%). The four pump loss of flow results in a rapid decrease in the core flow. The transient is initiated by simul-taneously tripping all four reactor coolant pumps, which will cause a CPC low DNBR reactor trip followed by a turbine-generator trip.
The event was initiated with all plant control systems in the automatic mode and operating nonnally, except the SDBCS. Due to hardware problems, one turbine bypass valve and one atmospheric dump valve were isolated. Additionally, the two atmospheric dump valves located upstream of the MSIVs were placed in the manual mode and, thus, unavailable for the test. With the two available tur-bine bypass valves and one atmospheric dump valve, the dump capa-city of the SDBCS was reduced to about 31 percent of the full power steam flow. One charging pump was also isolated.
Soon after the four reactor coolant pumps were simultaneously tripped, the reactor tripped on a low DNBR signal. The following turbine trip resulted in the termination of steam flow through the turbine admission valves. The loss of forced flow through the RCS combined with the temporary loss of heat removal capability by the secondary system, produced a power / cooling mismatch causing the RCS and secondary system pressures to increase.
To control the pres-sure response in the secondary system, the available two bypass valves and one atmospheric dump opened.
Subsequent to the reactor trip, the RCS pressure peaked and then started to drop sharply.
Termination of the pressure decay followed the modulated closure of the SDBCS valves prior to establishment of aatural criculation flow.
6.2 PRETEST PREDICTION The CESEC pretest prediction for the four pump loss of flow test assumed all plant control systems would function automatically.
In addition, it was assumed that the SDBCS would operate at its full i
dump and bypass capacity, i.e., 85 percent of the full power steam j
flow. Finally the pretest prediction assumed that the feedwater enthalpy would follow power level (in the test, the feedwater enthalpy stayed constant).
As a result of the differences in pretest prediction assumptions and the actual test conditions as described in this section and Section 6.1, the pretest prediction results are not comparable to the test results.
6.3. SEQUENCE OF EVENTS The four pump loss of flow test was initiated from the initial conditions shown in Table 6-1.
The plant control systems were all L.
in the automatic mode and operating normally except the SDBCS. As previously mentioned in Section 6-1, one turbine bypass valve and one atmospheric dump valve were isolated and unavailable.
In addition, the two atmospheric dump valves located upstream of the MSIVs were in the manual mode and also unavailable for the test.
Table 6-2 provides additional information relating to the operating characteristics of the SDBCS at the time of the test.
The transient was initiated by silmultaneously tripping all four reactor coolant pumps. Due to the loss of flow the reactor tripped very quickly (0.2 seconds) on a low DNBR signal. Subsequent to the reactor trip, the turbine tripped (0.4 seconds). The SDBCS re-sponded to the turbine admission valve closure by initiating a quick open signal to the SDBCS (1.0 second). Due to the temporary loss of heat removal capability by the secondary system and the loss of forced flow in the RCS, the internal energies of both the RCS and the secondary system increased, the temperatures increased, and the pressures increased. As the CEAs started to enter the core the RCS pressure peaked (2265 psia at 2.2 seconds) and subsequently started to decay rapidly. Once the CEAs were fully inserted the core power reduced to decay heat levels.
The bypass capacity (fully open at 2 seconds) was not sufficient to remove all the excess heat and, thus, the single available atmo-spheric valve opened to vent the additional steam to the atmosphere (2.0 seconds). - The bypass valves remained fully open for about 10 seconds, while the atmospheric dump valve remained fully open for about 4 seconds. The bypass valves fully closed at 18 seconds into the transient.
The RCS cooldown triggered the second charging pump to automati-cally start and the letdown flow was reduced. The minimum pres-surizer pressure reached was 2008 psia at about 40 seconds after reactor trip.
The steam generator pressure peaked about 64 seconds into the transient with a maximum value of 1028 psia in steam generator 2.
Subsequently the steam generator pressure stabilized i
through the modulation of the bypass valves.
Table 6-3 presents a detailed sequence of events forthe transient.
l o
/
6.4 POST-TEST COMPARISON The _ CESEC post-test comparison for the four pump loss of flow test was performed using the initial conditions shown in Table 6-4.
As previously stated in Section 5.4, the core outlet temperature and the steam generator pressure are calculated by the code during the initialization process. Comparison of the initial conditions in Table 6-4 with the test initial conditions (see Table 6-1) indi-cates good agreement. Basically the only difference is in the vessel mass flow rate which shows a deviation of about 3 percent between CESEC and the test data. The difference in charging flow result from CESEC not simulating the RCP seal leakage flow.
Preparation of the input data which was used in the simulation included the following assumptions:
1.
CESEC does not include a CPC DNBR algorithm and, thus, the reactor trip was simulated by forcing a trip at the measured time value. After the CEAs are fully inserted upon reactor trip, the reactor kinetics calculation in the code was bypassed.
the ANS decay heat curve based on 30 days of continuous operation at full power was used to simulate the power level for the remainder of the tran-sient. This power level is slightly larger than the power level recorded in the test after the CEAs were fully. inserted.
'2.
The fraction of primary system flow through each steam generator was input to CESEC in table fona as a function of time. Figure.6-1 shows the'RCS flow coastdown after tripping of the RCPs.
CESEC was driven with the coast-down curve measured in the t'est. -A natural circulation flow of 4 percent was subsequently assumed for the re-mainder of the event.
3.-
The steam flow out of each steam' generator was obtained from the plant test-data and modelled using the SDBCS algorithm in CESEC. The measured flows are-provided for steam generators.1 and 2 in. Figures'6-2 and 6-3, respec-tively.- The.non-symmetrie: response results from one operable bypass valve and the single _ operable dump. valve
-being connected-to the steam generator 1 steam line header, while the other operable bypass valve was con-nected to the. steam generator 2 steam'line' header. -As seen from Figures 6-2 and 6-3 the steam flows drop sud-denly from the initial values at-tLe time of the turbine Ltrip. Once the SDBCS triggers the opening of the. bypass and atmospheric vilves, the steam flow increases again.
-Closing of the valves causes-a decay of:the' steam flows.
As seen in' Figures 6-2 and 6-3, the steam flow appears to-i stabilize at about 12 percent of the full power flow.
-Existence of this relatively high steam-flow at this time
~
Lin the transient is questionable since the bypass valves 7
- are modulated to.. control the secondary pressure and S
I- ?
L_
~_
o l
i temperature. The uncertainty in the A P measurement used to generate the steam flow rate from data during low flow conditions is also high. Therefore, the SDBCS algorithm in CESEC was used for sumulating the post-trip steam system transient behavior in order to overcome this uncertainty.
CESEC results are shown in Figures 6-2 and 6-3.
4.
The feedwater flow for each steam generator was repre-i sented by a table of flow as a function of time. The feedwater flows for each steam generator are provided in Figures 6-4 and 6-5.
However, once the feedwater flow is l
ramped down after reactor trip, CESEC assumes the design k
value of 5 percent for the duration of the event. Again, uncertainty in the 4 P measurement during low flow conditions is the reason for using the design value in the CESEC simulation.
i 5.
The main feedwater enthalpy is kept constant at a value of 420 Btu /lba according to the plant measurement. This value was assumed in the CESEC simulation.
6.
The spray flow which was turned'on at 2.0 seconds into
(-
the ' transient and was turned off at 4.0 seconds has no
'significant impact on the CESEC calculations.
The steam generator 1 pressure response is shown in Figure 6-6.
The pressure in.reases sharply following the closure of the^ turbine ad--
l mission. valve.
Once the bypass and dump valves open, a temporary dip in the recorded pressure is -o'oserved. The recorded pressure starts to rise
'again'once the SDBCS valves close. The measured peak pressure is reached while the SDBCS is modulating the secondary pressure and temperature behavior. The CESEC prediction-follows the plant test data within 20 psi.. The CESEC peak pressure is calculated to be about the_same as lthat from pla'nt data (1016 psia (CESEC) versus 1023 psia (test data)).
Figures 6-7 through 6-14 show the comparison between data and CESEC predictions for _the pressurizer pressure, the pressurizer level, the RCS hot leg temperatures, and the RCS cold leg temperatures, respectively.
The.CESEC predictions for the above parameters agree.well with the test i
data. The biggest difference in reaults was observed in the~ hot leg-temperatures response. This results from CESEC over predicting _the pressurizer level-drop and, thus, sending more saturated fluid into the system. - The CESEC pressurizer level: starts to rise with the increase in charging flow and the reduction in the letdown flow. The pressurizer.
pressure increases accordingly and, thus, the CESEC hot; leg temperature rises: also staying above the measured data. Thereafter, the.CESEC response is basically controlled by the modulation of the SDBCS.
The sequence of events as predicted by CESEC is provided in Table 6-5.
Comparison of_ key events with data (see Table 6-3)-shows good agreement..
~
the maximon hot let. temperatures-predicted by CESEClare within 2.4*F and 3.2*F of the testLdata values for steam generators 1 and 2, respectively.
L
4 The maximum and minimum pressurizer pressures predicted by CESEC are, respectively, within 7 psi and 5 psi of the test data values.
CESEC predicted a maximum pressurizer level which is 2.7 percent lower than the test data value. The time = of occurrence for all of the above key events were predicted by CESEs ;o be within 17 seconds of the recorded values.
i i
e i
d--.
TABLE 6-1 Initial Conditions for the Total Loss of Fl'ow Test Core Power, Hwt 2295 (81%)
Core Inlet Temperature, 'F 552 Core Outlet Temperature, 'F 596 6
Vessel Mass Flow Rate,10 lbm/hr '
133 Pressurizer Pressure, psia 2240 Pressurizer Level, percent 46.4 Steam Generator Pressure, psia 926 Charging Flow, gpm 44.5 (one pump)-
Letdown Flow, gpn 40.4 Control Systen Status:
- Pressurizer Pressure Automatic
- Pressurizer Level Automatic
- Feedwater Automatic
- Reactor Regulating Automatic
- Steam Dump and Bypass Automatic 6
F S
Q l-L 1
6 l.
l l
4 1
' ~
TABLE 6-2 Operating Status of the SDBCS Valves Durino Four pump Loss of Flow Test Valve Description capacity (1bm/hr)
Status 6
13% Turbine Bypass 1.24 x 10 Operable 6
5% Turbine Bypass 0.69 x 10 Operable 6
13% Turbine Bypass-1.24 x 10 Isolat&d 6
13% Atmospheric Dump 0.94 x 10 Isolated 6
13% Atmspheric Dump 0.94 x 10 Operable 6
13% Atmospheric Dump 0.94 x 10 Manual 6
13% Atmospheric Dump 0.94 x 10 hanual 4
9 e
9 e
4 e
)
,e O
O A.
4 TABLE 6-3 Seouence of Events for the Total Loss of Flow Test Time (sec.)
Event Value 0.0 Manual trip of all 4 reactor coolant pumps 0.2 Reactor trip initiated on low DNBR signal 1.3 0.4 Automatic turbine trip initiated on reactor trip 1.0 Turbine bypass valves receive quick-open signal 1.3 Maximum hot-leg temperature 599.1 (SG-1) 2.0 Pressurizer spray valve opens 2.0 Turbine bypass valves full-open (Relief capacity 2000 klbm/hr) 2.0 Atmospheric dump valve opens to vent remaining steam flow to atmosphere 2.2 Maximum pressurizer pressure 2265 psia 3.0 CEAs fully inserted; core power reduced to <TS%
4.0 Pressurizer spray valve closed 6.0 Atmospheric dump valve closed 12.0 Turbine bypass valves begin to close 17.0-Second charging pump started; charging 88.5 GPM i
flow reaches maximum value 17.0 Letdown flow throttled back 24.5 GPM 18.0 Turbine bypass valves fully closed l
39.0 Minimum pressurizer pressure 2008 psia 42.0 Minimum pressurizer level 26.2%
l 53.5 Turbine bypass valve opened to control secondary pressure and temperature 57.0 Letdown flow reduced to minimum value 13.2 GPM
64.0 Maximum steam generator pressure 1023 (SG-1) 1028 (SG-2) 637.0 Second charging pump turned off; normal 44.5 GPM charging flow established 667.0 Letdown flow increased 26.5 GPM 787.0 Turbine bypass valve closed t.
L
l TABLE 6-5 CESEC Sequence of Events for the Total Loss of Flow Test Time Event Value 0.0 Manual trip of all 4 reactor coolant pumps 0.2-Reactor trip manually 0.4 Automatic turbind trip initiated on reactor trip
~
3.3 Maximum hot-leg temperature 596.7 (SG-1) 596.7 (SG-2) 3.5 Pbximum pressurizer pressure 2259
- 9.0 Letdown flow throttled back 29 GPM 12.0 Second charging pump started; charging 84 GPM flow reaches maximum value
~
53.6 Minimum pressurizer pressure 2003 psia i
i 58.0 Minimum pressurizer level 23.5%
l i
57.5 Letdown flow reduced to minimum value 13.2 GPM l
47.2 Maximum steam generator pressure 1016 (SG-1 ) '
1016 (SG-2) l I
l e
l l
r O
e 4
~-
- E d
a e=_
Data yo m
e i
i 6
i I
i 6
d
-2.00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 TIllE (MIN.)
Figure 6-1.
Loss of Flow-Normalized Reactor Coolant Pump Flow Rate 8.
S 95 Data
. R o.
p'
CESEC E S-l'
,d "
Ot'\\
~
h l
l l
-2.00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 TIME (MIN.)
Figure 6-2.
Loss of Flow - Steam Generator 1 Main Steam Flow Rate k~
t m
Data E
4
CESEC
> g-4 ae i
d" 4
t-
\\
y
%.-___.-=--------=------:
J.
i i
t i
i I
I-
-2.00 0.00 2.00 4.00 6.00.
8.00 10.00 12.00 TIME (MIN.)
Figure 6-3.
Loss of Flow - Steam Generator 2 I4ain Steam Flow Rate
8-
[
m Da ta ec R 8-
\\
E2 d
- (
1[.00
-2.00 0.00 2.00 4.00 6.00 8.00 10.00 TIME (f4Ill.)
Figure 6-4.
Loss of Flow - Steam Generator i Feedwater Flow Rate 9
l r
8-4 S
l l
Data lEd i g g-(
,N
(
i t_
i i
i l
l-di
-2.00_
0.00 2.00-4.00 6.00 8.00 10.00 12'.00 TIME (MIli.)
FiEmr0 6-5. Loss of Flow - Steam Generator 2 Feedwater Flow Rate
IS
- o--
,r
-e----------.-.-_---______-
5i g g--
I r
Data
CESEC
~
o 8
4 1
i 1
1
~8 0.i00 2.00 4.00 6.00 8.00 10.00 12.00
-2.00 TIME (MIN.)
Figure 6-6.
Loss of Flow-Steam Generator'1 Pressure dR-N
.t
-- -_ __ _ _ _ _ _ _ -- -+
,_y______.+
},
,I G
/
J'
\\
Data d
\\
,e
C ESEC a
s O
6 4
l l
l l
0 N
-2.00 0.00 2.00 4.00 6.00 8.00 10.00 12.0@
TIME (HIN.)
l Figure 6-7.
Loss of Flow - Pressurizer Pressure, Narrow Range o
c.
d 6
___ s Data e
CESEC J
o.
m-A
)
M l
A
---+-----___.______-4
(,
Q ~< j '
oo, N
i i
i i
i a
-2,00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 TIME (HIN.)
Figure f-8.
Loss of Flow - Pressurizer Level m
' $~ '.
__,f
=
W
$ m*
\\
,/
?
v,/
N Data
C ESEC C
s.,
i i
e i
i i
-2.00 0.00 2.00 4.00 6.00 8.00 10.00
~12.00
~
TIME (MItl.)
Figure 6-9.
Loss of Flow-Steam Generator i Hot leg Temperature o
\\
Data
CESEC m m 0 n'
~
M 5-
_ _ ' -+--
O5i a
a 1
i i
I
-2.00 0.00 2.00 4.00 6.00 8.00 10.00-12.0@
TIME (Mill.)
Figure 6-10. Loss of Flow-Steam Generator 1 Cold Leg Te. perature (Loop 1 A) a e
l
- \\
Data
CESEC
?
k ~ ~, ~ ~ -.
l w m
& n'
=
g 5-N-*--------.----_____.______.,
o5:
a i
i i
i i
1
-2.00 0.00 2.00 4.00 6.00 8.00 10.00 12.@
l-TIME (MIN.}
Figure 6-11. Loss of Flow-Steam Generator 1 Cold Leg Te.mperature (Loop ~18) s
. g-.
3
=
Data
C ESEC
' 't O.
',s---+-___"-+~__,,~-s---__,
i ig m-g j-a m
~
%,/
, yi i
e i
i i
-2.00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 TIi4E (liIN.)
Figure ~6-12.
Loss of Flow - Steam Generator 2 Hot Leg Temperature
.E ; -
m-Data
CESEC m
~
gg c
$6 e
v i
i
-2.00 0.00
- 2. 00 4;00 6.00 8.00 10.00 12.00 TI!4E (MIH.)
Figure 6-13.
Loss of Flow - Steam Generator 2 Cold Leg Temperature (Loop -2A) o m,
is Data
CESEC
\\
s m
k
't c
- N ' *
$g o
c.y 6
i e
a i
1
-2.00 0.00 2.00 4.00 6.00 8.00 10.00 12.00 TIME (MIN.)
Figure 6-14.
Loss of Flow - Steam Generator 2 Cold Leg Temperature (Loop 2B)
7.0 FULL LENGTH CEA DROP 7.1
SUMMARY
The FLCEA test performed furing the ANO-2 power ascension program was initiated from a power of 1391 Mwt (49.4%).
The FLCEA test provides the NSSS response to a core reactivity event. The event was initiated with all plant control systems in the automatic mode except for the reactor regulating system.
CEA 5-60 (see Figure 7-1) was selected for the test because of its alignment with the steam generator 2 hot leg. The alignment of the dropped CEA with the hot leg was expected to show the largest observable change in the NSSS response.
A sudden insertion.of the FLCEA resulted in a step reduction in the reactor power which led to a drop in the pressure of the primary coolant system and the secondary system. Since the FLCEA dropped was aligned with the steam generator 2 hot leg, the results of the test show a non-symmetric response. Manual control of the turbine demand was exercised by the operator subsequently in order to stabilize the NSSS response.
7.2 PRETEST PREDICTION The CESEC pretest prediction for the FLCEA drop test assumed all rods out, equilibrium xenon initial core conditions, all plant control systems are in the automatic mode, and no operator actions i
for at least sixty seconds after event initiation. Additionally, the pretest prediction was only run for 60 seconds of transient time.
In the test, the turbine load limit was adjusted to match the new average core power level immediately following the CEA drop. Thus, pretest predictions are not fully comparable to the test results.
7.3 SEQUENCE OF EVENTS The FLCEA drop test was initiated from the initial conditions shown in Table 7-1.
The plant control systems were all in the automatic mode except for the reactor regulating system which was removed from service to avoid any potential core related effects leading to a reactor trip during the test. The reactor was stable with all rods out and equilibrium xenon conditions.
The event was initiated by opening the CEA 5-60 disconnect circuit breaker.
Following the CEA drop, the core power decreased causing an initial decrease in the internal energies of the RCS and the secondary systee.
Thus, the cold and hot leg temperatures de-creased, the pressurizer pressure decreased, the pressurizer level decreased, and the secondary system pressure decreased. The oper-ator, following the CEA drop, took action in order to adjust the turbine load limit to match the new core average power level.
Reduction of the heat removal capability of the secondary system by balancing it with the heat generation of the reactor, allowed the
-system to be brought back to a stable condition.
Table 7-2 presents a sequence of events for the FLCEA transient.
7.4 POST-TEST COMPARISON The CESEC post-test comparison for the FLCEA drop test was per-formed using the initial conditions shown in Table 7.3.
Comparison of the initial conditions in table 6-3 with the test initial con-ditions (see table 7-1) indicates good agreement. The difference in charging flow results from CESEC not simulating the RCP seal leakage flow. As previously mentioned in Section 5-4, the core outlet temperature and the steam generator pressure are calculated by the code during the initialization process. Thus, the differ-ence in the vessel mass flow rate (about 9 percent) results form the balancing needed to match as close is possible the CESEC ini-tial conditions with the test data.
Preparation of the input data which was used in the simulation included the following assumptions:
1.
The forcing functions used for the simulation of the FLCEA drop event were the dropped CEA reactivity woth versus time and the turbine load variation with time (see Figure 7-2).
The dropped CEArcactivity variation with time table was obtained by combining design curves for rod worth versus fraction of rod inserted and rod in-sertion versus time.
2.
The CESEC core algorithm models the average reactor core and, thus, CESEC implicity smulates the non-symmetric NSSS behavior resulting from the insertion of CEA 5-60.
3.
The fraction of primary system flow through each steam generator was kept constant in time.
4.
The steam flow out of each steam generator was calculated by forcing the turbine load demand (see Figure 7-2) as a function of time.
The measured flows for steam genera-tors 1 and 2 are provided in Figures 2-3 and 7-4, respec-tively.
5.
The feedwater flow for each steam generator was assumed to follow the steam flow by using the feedwater control system. The measured flows for steam generators 1 and 2 are provided in Figures-7-5 and 7-6, respectively.
6.
The main feedwater enthalpy was essumed to follow power.
Figure 7-7 shows the power fraction response as measured by detec-tors NR001 and NR002 (opposite sides of core). Detector NR002 is closer to the dropped CEA than detector NR001 and, thus, exhibits a larger drop in the power.
The fractional power behasior as pre-dicted by CESEC falls in between the two measured responses as seen from Figure 7-7.
b
~-.
Figures 7-8 through 7-15 show the comparison between data and CESEC predictions for the pressurizer pressure, the pressurizer level, the steam generator pressure responses, the RCS hot leg tempera-tures, and RCS cold leg temperatures, respectively. As seen from Figures 7-10 through 7-15 CESEC reasonably simulates the non-sum-metric response resulting from the dropped CEA.
The RCS hot leg temperature data (Figures 7-12 and 7-14) shows a lower temperature response for the hot leg of steam generator 2 as expected, since it 4
is closest to the dropped CEA. The non-symmetric effect is carried into the steam generators pressure response (Figures 7-10 and 7-11) and into the response of the RCS cold leg temperatures (Figures 7-13 and 7-15*>.
I The CESEC feedwater control system algorithm assumes the feedwater flow to immediately follow the steam flow. That is, the delay in l
system response is not modelled by the CESEC algorithm. This effect is seen when comparing the CESEC results with the test data in Figures 7-5 and 7-6.
The major difference in the initial value of the feedwater flows between CESEC and data results from CESEC maintaining a stable water level during steady state by balancing feedwater flow and steam flow. According to the measured data, the initial feedwater flow is about 120 K1bm/hr higher than the mea-sured steam flow rate. This difference in initial conditions, that is, the excessive feedwater flow, can be attributed to be the steam generator blowdown rate. Thus, if the blowdown flow corrected steam generator feedwater flow is plotted, the CESEC results will compare more favorably with the measured data.
The pressurizer pressure response is shown in Figure 7-8.
After i
the turbine ioad is reduced and the pressure recovered, the system i
stabilizes at about 2250 psi as seen from the data.
One CESEC calculation predicted that the pressurizer pressure rise continues until~the pressure is stabilized at 2275 psia. The proportional spray setpoint being set at 2275 psi comes on to terminate the
~
l~
pressure rise. However, when CESEC is run with the proportional l
spray setpoint at 2251 psia, the comparison between data and the l
CESEC prediction is icproved. Thus, it is suspected that the j
operator may have taken manual action to control the pressure rise and/or the spray may have come in at a lower value as happened in the loss of flow test.(see Section 6-4).
This action, i.e., manual control of the PPCS, if taken was not recorded. The second esse was selected as the reference CESEC case for this study.
The sequena of events as predicted by CESEC is provided in l
' Table.7-4. Comparison of key events with data'(see Table 7-2) and overall system response (see Figures 7-3 through 7-15) shows good L
- agreement. The minimum pressurizer pressure and the time of its l
occurrence wereL predicted by CESEC to be 2194 psia and 62.4 se-l conds, respectively.
(The recorded data values are 2191 psia and
- 51.4 seconds,.respectively). The initial pressure drop predicted
[
by CESEC provides an even better agreement between: calculated and
' measured responses ((2250-2194=56 psi for CESEC) versus (2246-2191=
55 psi for test data)).- The minimum hot leg temperature and the time:of its occurrence were predicted by CESEC to be, respectively, within l'F and 2 seconds of the measured values..
e
.)
TABLE 7-1 Initial Conditions for the Full Length CEA(5-60) Drop Test Core Power, N t 1391 (49.4%)
Core Inlet Coolant Temperature, *F 546 Core Outlet Coolant Temperature. *F 577 0
Yessel Mass Flow Rate,10 lbm/hr 134.0 Pressurizer Pressure, psia 2246 Pressurizer Level, percent 39.1 Steam Generator Pressure, psia 932 Charging Flow, GPM 44.5 Letdown Flow, GPM 39.6 C6ntrol System Status:
Pressurizer Pressure Automatic Pressurizer Level Automatic Feedwater Automati c Steam Dump and Bypass Automati c 4
9 e
9 9
5
TABLE 7-2 Sequence of Events for the Full Length CEA(5-60) Drop Test Time (sec)
Event Value 0.0 CEA 5-60 trip breaker open,ed, CEA drop initiated 3.5 Asymptotic core power level achieved 36.5*
51. 4 Minimum pressurizer pressure 2191 psia
'152.
Minimum hot leg temperature 570*F 600.-
Reactor stable at slightly reduced core average power level 43%
4
- Power recorded by ex-core neutron detector closest to the dropped CEA.
Average core power is higher.
4 9
e f
g o
9' 4
e e
4
--5 L.
'a e
TABLE 7-3 CESEC Initial Conditions for the Full Length CEA(5-60) Droo Test Core Power, Mwt 1388 Core Inlet Coolant Temperature, *F 547 Core Outlet Coolant Temperature, 'F 577 6
Vessel Mass Flow Rate,10 l bm/hr 122.0 Pressurizer Pressure, psia 2250 3
Pressurizer Water Volume, ft 469 (level = 39.1%)
Steam Generator Pressure, psia 932 Charging Fl'ow, GPM 40.0 Letdown Flow, GPM
~ 40'.0 Control System Status:
- Pressurizer Pressure Automatic
- Pressurizer Level
'Automati c
- Feedwater Automatic
- Steam Dump and Bypass Automatic 6
e e
e
l TABLE 7-4 CESEC Sequence of Events for the Full Length CEA(5-60) Droo Test T_ime (sec)
Event Value 0.0 CEA 5-60 trip ' breaker opened, CEA drop initiated 62.4 Minimum pressurizer pressure 2194 psia 1 50.0 Minimum hot leg temperature 571 *F 1800.0
-Final steadystate pressure 2252 psia e
t I
9 3
D 4
.e I
N O
/
\\
/
N O
O
/
O O
Q O
O as
. i+
E O
O O
O O
O O
m
.g.
g
.o il O
O O
O O
O O
s.,i.
n
.m l
v x
, - =.
9 i
A x
as E
O O
O 6
O O
O i
=
'S-O O
O O
O O
4 O
O' Q
O O
/
O O
\\
/
o N
l L.-
m g
o m
=
O O
- 9. a 5
l 2
L 2
B. ' G
- 1..
O
e.
o IX 7 w
~
g yd-ME Data 8
N.
i i
i i
i i
i
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 7-2.
Full Lengui CEA Drop-Turbine Power 8M-Data yd
\\
CESEC CE-A
(
- g. m g
- * - ~ -
_ * - - - - - - - - + - - - _ - - _. _ _ _ _ _ - _
dc hi l
4 j
I I
I
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.03 l
TIME (MIN.)
Figure 7-3.,
Full Length CEA Drop-Steam Generator 1 Main ~ Steam Flow Rate Y~
Data
C FSEC E
5 2-i ig Ng, -
'W- -+- -- -
d i
j e.
l 4
I i
I I
I 8-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 l.
N TIME (MIN.)
Figure 7-4.
Full Length CEA Drop-Steam Generator 2 Main Steam Flow Rate
.'g n.
d2_
Data '(includes SG blowdown rate)
CESEC c~.
---1 e
~
g_
\\
e m A
t s,.'~~-~-
=
3
~ ~ - - - - - - -. - - - - - - - - _ - - _ _
x
&8 a
i i
e i
a ca
-5.00 0.00 5.00 10.00-15.00 20.00 25.00 30.0@
TIME (MIN.)
Figure 7.5.
Full Length CEA Drop-Steam. Generator 1 Feedwater Flow Rate d
2-Data (includes SG blowdown rate)
CESEC
-- g
_o s
cr ' S-k i"
N
M h_
1 g
+
l 2
I i
t I
a t-t
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
l-Figure 7.6.
Full Length CEA Drop-Steam Generator ~2 Feedwater Flow Rate
p*
g*
Data
C ESEC g NR001 N*~--+-~-._-_~~~~~---s---------_.___
o o
y
+ ______,
w 5"
N r NR002 1
I o
i i
i i
i o
i
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 7-7.
Full Length CEA Drop-Nuclear Power d
g-k,
_ _ _ _ _. 4_ - - _ _ - - o _ - _.- _ - # _ _
- - - + - - - - - -A k _-+ - - p i
l
<. o Data A2275 psia setpoint 7, N. -
CESEC c.
m e 2251 psia setpoint o
l
$ 00 0.'00 5.'00 id.00 1$.00 20.00 25.00 30.0@
TIME (MIN.1 Fu11. Length CEA Drop-Pressurizer Pressur.e, Harrow Range Figure 7-8.
k
~
r I
l c
lb o
[
i m as -
lE "
Data
\\
CESEC l
s i
A
/
M l-o o.
f i
N I
I i
i i
i
,5.00 0.00 5.00 10.00 15.00.
20.0Q 25.00 30.01 l
TIME (MIN.)
a Figure 7-9.
Full Length CEA Drop - Pressurizer Level
-m m.
a
o g.:.
f o
- . o
.a m-gm p_
/
Data
CESEC
/
o, y'
Cg i
i 1
i i
i
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.0@
TIME (MIN.)
Figure 7-10. Full Length.CEA Drop-Steam Generator 1 Pressure o
d8, Da ta
--- CESEC
-f
~
~ _ _ _ -.
o
- - * ~ ~
<d
- gg-c.
.d-
,/
d' o
1
.8 '
I i
l t
i I
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.0@
TIME (MIN.)
Figure 7-11. Full'l.ength CEA. Drop-Steam Generator 2 Pressure G
I e
L-
e l
' g.
m Data
CESEC W*-
)
.e m g
1 e
- f e
d N
l 4
l l
l I
l
- -5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.05 TIME (MIN.)
Figure 7-12.
Full Length CEA Drop-Steam Geners'or 1 Hot Leg Temperature s
C
.td~
Data
+- ~~___.
CESEC
/r, -
t o.
.,/
T $-
ge C
f t
O n
r 0.'00 5.'00 id.00 lb.00 20.00 25.00 30.0@
-!5. 00 TIME (MIN.)
Figure 7-13.
Full length CEA Drop-Steam Generator 1 Cold Leg Temperature (Loop la 4
C.
's _
wr
- Data
~
CESEC o
, u. ui y2-(
a
\\
h%
o d
S L
I I
i 1
g
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 7-14. Full Length CEA Drop-Steam Generator 2 Hot Leg. Temperature e
S._
=
/,
u.
i
/
Data
,a*.-
___. CESEC i
gm
\\
./
-a.
i i
t a
t 6
l'
-5.00 0.00 -
5.00 10.00 15.00 20.00 25.00 30.0@
. TIME (MIN.)
figure 7-15. Full Length CEA Drop-Steam Generator 2 Cold. Leg Temperature (Loop 2A
~
a h
.e r
-r-
8.0 PART-LENGTH CEA DROP 8.1
SUMMARY
The PLCEA test performed during the ANO-2 power ascension programs was initiated from a power of 1384 Mwt (49.2%). The PLCEA test provides, the same as the FLCEA drop test, the NSSS response to a core reactivity event. The event was performed approximately twelve hours after the FLCEA drop test. All plant control systems except the reactor regulating system were in the automatic mode.
The PLCEA selected was P-24 which is also aligned with the steam generator 2 hot leg (see Figure 7-1).
The insertion of the PLCEA resulted in an initial decrease in the reactor power. The power decrease was about half as for the FLCEA drop test, since the amount of negative reactivity inserted was smaller.
The system response was similar to that observed for the FLCEA drop test. The operator again adjusted the turbine load limit to match the resulting average core power subsequent to the PLCEA being dropped in order to stabilize the NSSS response.
8.2 PRETEST PREDICTION The CESEC pretest predictions for the PLCEA drop test are not fully comparable to the test results for the same reasons given in Sec-tion 7.2.
8.3 SEQUENCE OF EVENTS The PLCEA drop test was initiated from the initial conditons shown i
in Table 8-1.
The plant control system were all in the automatic mode except for the reactor regulating system. The reactor was stable with all rods out and a slight xenon oscillation of small amplitude and very long period relative to the transient and, thus, of negligible influence on the results.
The event was initiated by opening the CEA P-24 disconnect circuit bresker. Following the CEA drop, the core power and other system parameters initially decreased as observed for the FLCEA drop test.
However, the initial decrease in the key parameters'was smaller than for the FLCEA drop case, because of the smaller pertubation to the system. The operator again, as in the FLCEA drop test, took action to adjust the turbine load limit to match the reactor power to maintain a stable plant condition. However, unlike the smooth variation of the turbine load in the FLCEA drop test (Figure 7-2),
a drastic drop in the turbine load for the PLCEA drop test was observed during the first minute of the event (Figure 8-1).
This abrupt decrease in the turbine load (probably caused by a different operator and/or' operator. action) resulted in the subsequent pres-surizer. pressure increase in pressure for this test. Once the turbine load was returned to the value where it would balance the power generation, the pressurizer pressure decreased and started leveling 'off.
Table 8-2 presents a sequence of events for the FLCEA transient.
8.4 POST-TEST COMPARISON i
The CESEC post-test comparison for the PLCEA drop test was per-
)
formed using the initial conditions in Table 8-3.
The CESEC in-itial conditions for this test are the same as those used in the CESEC simulation of the FLCEA drop test (Table 7-3).
Therefore, remarks made in Section 7.4 regarding the initial conditions are also applicable for this test.
Preparation of the basedeck which was used in the simulation in-cluded similar assumptions to those discussed in Section 7.4.
Basically, only the dropped CEA reactivity versus time table was changed to represent the variation with time of CEA P-24.
Figures 8-2 through 8-5 shows the comparison of the steam flows and feedwater flows as predicted by CESEC against the test data. The steam flow out of each steam generator follows the variation in the turbine load (Figure 8-1).
The feedwater follows the steam flow.
Observations made in Section 7.4 regarding the feedwater flow are also applicable for v:riation this comparison.
Figure 8-6 compares the power fraction as detected by the two nu 1:ar power channels with the CESEC prediction. The CESEC pre--
diction is within the range of uncertainty of the detectors in the i
low power range.
Figures 8-7 through 8-10 compare the CESEC RCS hot leg and_ told leg te;nperatures with test data.
The variation in the temperatures is small.
this is consistent with the small pertubation introduced into the system.
Figures 8-11 and 8-12 show the comparison of the steam generators 1 and 2 pressure responses between CESEC and test data. Following the initial decrease in pressure, the subsequent pressure rise results from operator action in adjusting turbine load (Sec-tion 8.3).
The difference in peak prssure is within the errar range in the pressure measurement.
The pressurizer pressure and pressurizer level behavior are pro-vided in Figures 8-13 and 8-14, respectively. The CESEC pres-surizer pressure prediction compares very well to the plant data.
Small deviations are within the 15 psi measurement error range.
The difference in pressurizer pressure behavior between CESEC and test data after 10 minutes may have resulted from operator action (see Section 7-4' for similar comments). However, no operator actions, if any, were recorded. The pressurizer level prediction by CESEC is also good considering that the measurement of the water level exhibits a 1 percent error.
The sequence of events' as predicted by CESEC is provided in Table 8-4.
Key events predicted by CESEC agree well with data (minimum pres-surizer pressure: 2236 psia at 29.0 seconds (CESEC) versus 2234 psia at 29.0 seconds (test data), maximum steam generator pressure:
~
949 psia 'at 83.2 seconds (CESEC) versus 957 psia at 83.8 seconds
. (test data), maximum pressurizer pressure: 2277 psia at 83.8 sec-onds (CESEC) versus 2280 psia at 85.7 seconds (test data))..
1-e t
5 m
I'
_4
' N-
^
~,
TABLE 8-1 Initial. Conditions for th'e Part length (P-24) CEA Drop Test Core Power, Mwt 1384 (49.2%)
x Core Inlet Coolant Temperature, *F 546 Core Outlet Coolant Temperature, *F 577 6
Vessel Mass Flow Rate,10 lbm/hr 134.0 Pressurizer Pressure, psia -
2247 Pressurizer Level, percent 39.4 Steam Generator Pressure, psia 931 Charging Flow, GPM 44.5 k
Letdown Flow, GPM 35.4 Control System Status:
Pressurizer Pressure Automatic Pressurizer Level Automatic Automatic
- Feedwater 1
Reactor Regulating Not Used Steam Dump and Bypass Automatic e
9 D
/.
L l
l l
t h
l'L s-
TABLE 8-2 Sequence of' Events for the Part length (P-24) CEA Orop Test Time (sec)
Event Value CEA P-24 trip breaker opened; CEA drop 0.0
~
initiated 2.4 Asymptotic core power level achieved 46.4%
29.0 Minimum pressurizer pressure 2234 psia 33.7 Minimum hot leg temperature 575*F 83.8 Pkximum steam generator pressure 957 psia 85.7 Maximum pressurizer pressure 2280 psia r
250.0 Reactor stable at slightly reduced core average power level 46%
O e
b O
e e
s e
L_
TABLE 8-3
. CESEC Initiial Conditions for the Part length (P-24) CEA Drop Test Core Power, Mwt 1388
~ ~
Core Inlet Coolant Temperature, 'F 547
^
Core Outlet Coolant Temperature, 'F 577 6
Vessel Mass Flow Rate,10 ltrn/hr 122.0 Pressurizer Pressure, psia 2250.
Pressurizer Water Volume, ft W2(level =39.4%)
Steam Generator Pressure, ps.ia 932 Charging Flow, GPM 40.0
)
L'etdown Flow, GPM 40.0 Control System Status:
Pressurizer Pressure Automatic Pressurizer Level Automatic Feedwater Automatic Steam Dump and Bypass Not used e
e-e g
e 6
e e
G e
___L
TABLE 8-4
~
. CESEC Sequence of Events for the Part length (P-24) CEA Drop Test Time (sec)
Event Val ue
- 0.0 CEA P-24 trip breaker opened; CEA drop initiated 29.0 Minimum pressurizer pressure 2236 psia 31.2 Minimum hot leg temperature 576*F 83.2 Maximum steam generator pressure 949 psia 83.8 Maximum pressurizer pressure 2277 psia 9
9 l
I f
[..
l 9
L r
l' r.
?
[
.8 iM-
\\
g_
a m
Data oo, E:
i i
[
t i
i i
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 8-1.
Part length CEA Drop-Turbine Power
. 6 N-Data
CESEC 0
e6 b b~
Is u
L
+
p- - -.e-.+-
-- - _ s- - _. _ _ _e_ -- _ _ _.e- -- _ _._.e- _. -- - n - _. -._ _,
8
/
N I
i
.i i
i i
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.@
TIME (MIN.)
Figure 8-i.
Part length CEA Drop-Steam Generator 1 Main Steam Flow Rate d
~
Data H
C ESEC 5
eg_
-T
= m 1
8 V
N,,
I i
i i
i i
1
-5.00 0.00 5.00 10 00 15.00 20.00 25.00 30.0%
TIME (MIN.)
Figure 8-3.
Part length CEA Drop-Steam Generator 2 Main Steam Flow Rate w
8 Data (includes SG blowdown rate)
CESEC
,l gg
=
22-i e
x s
d h(-_.+-_---.-------._.-_.----._-._-_-.-----s--------e
\\ /
o V
M i
i 1
1 i
i 1
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
~~~
Figure 8-4.
Part Length CEA Drop-Steam Generator 1 Feedwater Flow Rate e
S-M Data (includes SG blowdown rate)
C ESEC d
- ^ -
g_
g y
RN 1
Q
\\
5;i
} p___.-.___-_
o*
\\!
7~
l i
i i
1 1
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 8-5.
Part length CEA Drop-Steam Generator 2 Feedwater Flow Rate e
l M~
3 Data
CESEC o
!E a -
we NR001 U-W g,
q, NR002 J g,
i i
I I
i J-5.00 0.00 5.00 10.00 15.00 20.00
, 25.00 30.0) e TIME (MIN.)
e o,
og_
Data CESEC o
. t d_
i
' 5*
i o
i 3,
w-.--.--.__________._
o N
Q, i
i i
i e
i 3
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 8-7.
Part length CEA Orop-Steam Generator 1 Hot leg Temperature I
l 1
A o
m t $_.
' A _ _. _ __ _ _._ _ _ _ _ _ _._ _ _ _ _ : _ _ h _ - _ -.
S=
M C
Data
CESEC o,
W 3
4 l
4 8
3 I
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.0@
TIME (MIN.)
Figure 8-8.
Part length CEA Orop-Steam Generator 1 Cold Leg Temperature (Loop 18) t
(
e r
o.
e' c-Data
C ESEC o, -
]
met t
gw s
\\,^, * -+- -s- - - - N - - -- -
_ +.____ _ _____
N
.o m i i
i i
i i
l l
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00; TIME (MIN.)
Figure 8-9.
Part l'ength CEA Drop-Steam Generator 2 Hot Leg Temperature l
g m-
.m l
I
- u. - o h h-l
-a
~
l Data l
CESEC o.
w.
E t
1 A
i n
4 i
l
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.@
l-TIN'(MIN.)
Figure 8-10.
Part i.ength CEA Drop-Steam Generator 2 Cold Leg Temperature (Loop 2@
7 l
9 o.
o g._
Data
CESEC-o k m*
A gg-
~
'w.
N c-
___.,__ --____,___.___.-____ h._.
s o,
o$
6 i
i j
i i
I
-5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
Figure 8-11.
Part length CEA Drop-Steam Generator 1 Pressure e
d Data g--
.... CESEC o
5g A
~
t's m
w-p g
N c.
cn fj
=.--_---------_---: --- =--.
J o,
o g -"i e
i i
I I
I F.
-5.00 0.00 5.00 10.00 15,00 20.00.
25.00 30.01 TIME (MIN.)
Figure 8-12.
Part length CEA Drop-Steam Generator 2 Pressure e
5
a.
d
. g _.
,k Da ta
CESEC a _______
N_
x m n-
~e -
NN 1
4 4
4 g
l 5.00 0.00 5.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.)
F.igure 8-13.
Part Length CEA Drop-Pressurizer Pressure, Narrow Range E
g_.
I Data
C ESEC 8
s d_
5*
A a s occ M
/\\
E i
1 7
%,_.-,-_---,____-_,..y.-
i,,o o.
u 6-1 I
I I
i 4
' - 5.00 0.00 s.00 10.00 15.00 20.00 25.00 30.00 TIME (MIN.}
Figure 8-14.
Part Length CEA Drop-Pressurizer Level 9
m e
i
9.0 CONCLUSION
S Observations that can be made concerning the results of this simu-lation are as follows:
1.
CESEC is able to satisfactorily predict the transient response both qualitatively and quantitatively. The code was qualified against relevant test data and predicted results which are consistent with the physical assump-tions made. Thus, assurance was obtained that the solu-tion technique is stable, the solution is convergeat, and that the code models, logic, and solution schemes appear to be correctly programmed.
2.
CESEC deviations from test data are in most cases within the uncertainty of the measurement.
3.
CESEC is basically a best estimate code. That is, the conservatism of the analysis performed in Chapter 15 of the safety analysis report for the non-LOCA events is mainly introduced through the input data rather than the code itself.
From this study it can be concluded that in CESEC C-E has a tool which is capable of predicting system response for PWR non-LOCA
. initiating events for a range of operating conditions. Thus, CESEC can be effectively used as a predictive tool for the non-LOCA events analyzed in Chapter 15 of the safety analysis report.
(
l i
i
[
10.0 REFERENCES
1.
CENPD-107, "CESEC: A Digital Simulation of a Combustion Engineering Steam Supply System", April, 1974.
2.
J. F. Stolz (NRC) to W. Cavanaugh (AP&L), " Request for i
Additional Information", September 7, 1977.
t 3.
J. F. Stolz (NRC) to W. Cavanaugh (AP&L), " Verification Testing for the CESEC Code", November 23, 1977.
4.
" Arkansas Nuclear One-Unit 2 Final Safety Analysis Report",
Arkansas Power and Light, Docket No. 50-368, May,1974.
1 I
l I
1
< - ~ ~ <
r
.