ML19350E140

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-413/81-06 & 50-414/81-06 on 810226-0325. Noncompliance Noted:Drawing Approved & Issued for Hanger Installation Did Not Specify Weld to Shorten Sway Strut Assembly as ASME Weld
ML19350E140
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 04/08/1981
From: Bryant J, Vandoorn P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19350E131 List:
References
50-413-81-06, 50-413-81-6, 50-414-81-06, 50-414-81-6, NUDOCS 8106170039
Download: ML19350E140 (7)


See also: IR 05000413/1981006

Text

'

.

pa4

,

9'o

UMTED STATES

~

<8'

~

TORY COMMISSION

NUCLEAR REGU@ ION 11

o

q$

E

REG

)Q

[

101 MARIETTA ST., N.W., SUITE 3100

ATLANTA, GEORGIA 30303

s

++.**

Report Nos. 50-413/81-06 and 50-414/81-06

Licensee: Duke Power Company

422 South Church Street

Charlotte, NC 28242

Facility Name: Catawba

Docket Nos. 50-413 and 50-414

License Nos. CPPR-116 and CPPR-117

Inspection at Catawba site near Rock Hill, South Carolina

Inspector:

, Jm

8

/

P.K.VanDop

j

'

D&te Signed

Approved by:

/

m,b

+[/eI/

J.

Bfy'anE,dFction Chief, Division of

[Wte Signed

esident and Rea'ctor Project Inspection

-

SUMMARY

Inspection on ebruary 26 - March 25,1981

Areas Inspected

This routine unannounced inspection involved 163 resident inspector-hours on site

in the areas of safety-related piping

observation of weldi:g and non-welding

work activities (Units 1 anri 2); reactor coolant pressure boundary piping -

observation of welding work activities; (Units 1 and 2) containment (structural

concrete) - observation of work and work activities (Unit 2); observation of

-

housekeeping and storage / protection of equipment (Units 1 and 2); safety-related

pipe support and restraint systems (Unit 1); and observation of the Local Public

Document Room.

_

Results

Of the six areas inspected, no violaticns or deviations were identified in five

areas; two violations were found in one area (Failure to document corrective

action' concerning inadequate design of a hanger paragraph 9.c. and Failure to

follow procedure for installation of hangers and to provide appropriate

qualitative criteria on a hanger drawing paragraph 9.d.).

8106170 @

._

.

.

.

.

.

r

DETAILS

1.

Persons Contacted

Licensee Employees

D. G. Beam, Project Manager

S. R. Dressler, Senior Construction Engineer

L. R.-Barnes, Manager Support / Restraints

  • E. C. Wall, General Superintendent
  • R. A. Morgan, Senior QA Engineer
  • T. D. Mills, Construction Engineer Mechanical

A. R. Hollins, Construction Engineer Hangers

K. R. Webber, Mechanic Superintendent

  • J. C. Shropshire, QA Engineer Supervisor

T. A. Evans, Hanger Engineer

  • H. D. Mason, QA Engineer Supervisor
  • M. R. Hemphill, QA Engineer

D. H. Llewellyn, Welding Engineer

Other licensee employees contacted included 12 construction craftsmen, 4

technicians, 3 inspectors, and 3 office personnel.

  • Attended exit interview

2.

Exit Interview

The inspection scope and findings were summarized on March 25, 1981 with

those persons indicated in Paragraph 1 above.

The unresolved items and

violations described in paragraphs 5 and 9 respectively were discussed in

detail.

3.

Licensee Action on Previous Inspection Findings

(0 pen) Unresolved Item (413, 414/80-18-01) - Pipe design and inspection

clearance requirements. This item concerned the fact that the licensee had

not defined requirement.s for clearances between piping _ systems / components.

As a result an NRC inspector noted two examples of ',nons&fety-related piping

_

in contact with safety-related pipe / components.

On March 18, 1981, the

inspector noted that non-safety-related Hanger No.1-CWL-6656 was in contact

with the operator of Class A valve No. INV11-3. This is considered to be

another example of the previously identified pi ablem.

Licensee personnel

indicated that the requirements have been defined and procedures are being

developed for implementation. This item remains open until procedures are

issued and implemented.

I

.

- - - - - - - - - - - - -

-

,

.

.

'

.

2

4.

Unresolved Items

Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve violations or

deviations. One new unresolved item identified during this inspection is

discussed in par & graph 5.

5.

Independent Inspection Effort (Units 1 and 2)

a.

The inspector conducted general inspections of site work and work

activities and observed equipment protection / storage and housekeeping

in the auxiliary building, containment buildings and storage areas.

b.

The inspector observed the Public Document Room in Rock Hill,

South Carolina, to verify that NRC and facility documents are being

filed in an orderly manner and are available to the public.

c.

The inspector observed portions of the Unit 2 containment dome

structural concrete placement for conformance to requirements in the

areas of preplacement preparation; adequacy of crew, equipment and

l

techniques; control of special technique requirements implemenced for

l

the dome pour; preparation of construction joints and curing.

d.

On March 5,

1981, during a discussion with licensee . personnel

concerning interim valve storage requirements the inspector noted that

some requirements were contained in a Design Engineering Department

letter dated August 19, 1980.

These requirements had not yet been

implemented at the Catawba site.

The specific requirements of the

letter were of minimal safety significance.

However, additional

'

inspection is necessary to verify that this was an isolated case and to

determine if a control system is necessary to assure timely

implementation of design requirements.

This is Unresolved Item

.

413/414/81-06-01, Delay 1. Implementation of Design Requirements.

No violations or deviations were identified.

-

6.

Safety-Related Piping (Welding) - Ooservation of Work and Work Activities

(Units 1 and 2)

.

The applicable code for installation of safety-related piping is the ASME

Boiler and Pressure Vessel Code,Section III,1974 Edition plus addenda

through summer 1975. The inspector observed in process welds at various

'

,

stages of completion and reviewed records for conformance to code and

'

procedure requirements in the areas of docun,entation of pertinent infor-

,

mation and QC signoffs via a weld traveler, availability of pertinent

-

!

instructions, use of appropriate qualified welding procedure, provisions for

,

weld repair provided, certification of filler material, verification of base

!

material certification, control oi welding parameters, verification of

l

t

.

.

-

. .

. .

._

.-

. _ _ - . - -

-

- . . . - - . -

-

-

. , . - .

.

.

.

3

-

.

welder qualification, use of specified shielding.and purge gas, condition of

welding equipment, provisions for voltage and amperage checks, verification

of proper fitup, control of preheat and interpass temperature, condition of

weld and base metal surfaces, and verification that appropriate inspections

were being performed.

The following welds were observed:

Weld No.*

Size (In. Dia.)

Stage of Welding Observed

1-RN224-3

20

Bevel repair

2-KF60-2

8

Intermediate

2-KF60-3

8

Final

2-KF111-3

10

Intermediate

2-ND27-11

8

Intermediate

2-N025-11

8

Fitup

2-CA74-15

1

Intermediate

2-NI15-1

32

Bevel repair

  • First number of weld number indicates Unit number.

No violations'or deviations were identified.

7.

Reactor Coolant Pressure Boundary Piping (Welding) - Observation of Work and

Work Activities (Units 1 and 2)

The applicable code is delineated in paragraph 6.

The inspector observed

internediate welding and in process weld records of Weld Nos. 1-NC230-3 and

2-NI91-3 for conformance to code and procedure requirements in the areas

delineated in paragraph 6.

No violations or deviations were identified.

8.

Safety-Related Piping - Observation of Work and Work Activities (Unit 2)

The applicable code is delineated in paragraph 6.

The 1.u,pector observed

handling of piping for installation of Weld Nos. 2-KF40-16, 2-KF60-8,

-

-

2-KF111-3 and 2-FW42-20 for conformance to procedure and code requirements

in the areas of control of tools for grinding, brushing and filing; use of

appropriate handling and rigging equipment; control of cleanliness; and

,

_

control of cold spring where applicable.

The inspector noted on March 9,

l

1981 that internal Jacking was being employed for fitup of Weld No.

l

2-FW42-20. This is another example of the use of internal Jacking which has

been previously questioned (See Unresolved Item 413/414/81-03-02).

No violations or deviations were identified.

9.

Safety-Related Pipe Support and Restraint Systems (Unit 1)

!

l

a.

The applicable code for safety-related support and restraint instal-

!

lation is the ASME Boiler and Pressure Vessel Code,Section III,

,

Subsection NF,1974 Edition plus addenda through summer 1975.

The

inspector observed various activities associaLed with installation of

r

i

l

l.

L

. - -

_ _

. -

.

.

-.

.

-

,

,

4

supports and restraints to determine if code and procedure requirements

were being met. The inspector observed warehouse storage areas,.the

hanger fabrication shop and hanger pre-stage area to determine if

requirements were being met in the areas of storage / protection of

materials, control of prefabrication and presetting of cold load on

spring hangers.

During this inspection the inspector checked

approximately 20 snubbers for smoothness of shaft travel, verified cold

load settings for 6 spring hangers and observed shortening in progess

of the sway strut for Hanger No. 1-A-NV-8367.

In addition, the

inspector observed installed hangers for conformance to requirements ,

(as applicable) in the areas of deterioration and corrosion; de#or-

mation of materials; tightness of bolts, nuts and fasteners; use of

lock nuts where required, cold load setting of snubbers, installation

clearances, control of materials and appearance of welds.

The

following hangers were observed:

Hanger No.

Type

1-A-NV-8255

Trapeze

1-R-N1-1399

Snubber

1-R-BB-1092

Sway Strut

1-R-BB-1093

Sway Strut

1-R-BB-1094

Sway Strut

1-R-N1-1351

Sway Strut

1-R-N1-1487

Snubber

1-R-NV-1768

Rigid

1-A-N1-4135

Rigid

1-R-NV-1764

Snubber

b.

On March 16, 1981, the inspector noted that cold load settings on

spring hangers located in the hanger pre-stage area were not in

accordance with the requirements of procedure CP-353, Rev.

8,

Adjustment, Installation and Modification of Pre-Engineered Hanger

Components. Procedure paragraph 1.B. requires the hanger feb shop to

set cold load per design requirements with no tolerance allowed.

-

Examples noted are as follows:

Hangor No.

Actual Setting (Ibs.)

Required Setting (lbs.)

1-R-NI-50

425

427

1-R-NV-240

24

25

1-R-CM-2138

505;

4991

1-R-SM-1552

11315

12387

1-A-NV-3C/1

212

211

1-R-NV-107

97

105

On March 18, 1981 the inspector noted that cold load settings on

snubbers for two hangers also were not in accordance with the require-

ments of procedure CP-353. Procedure CP-353, paragraph 2.D. requires

craft person :1 to stroke the snubbers upon installation to the cold

setting required by design drawings with no tolerance allowed. Hanpr

. _ . . -

,

- - . - . -

---

. . . .

.

.

.

.

5

Nos. 1-R-N1-1487 and 1-R-BB-1093 were set at 14 inch and 1

inch

respectively. The requirement for both hangers is 15/16-inch. Licensee

personnel indicated that the cold load settings required by CP-353 are

for fabrication purposes and not intended to be the final setiting.

Licensee personnel also indicated that some initial snubber settings

will change as additional hangers are added to the line. In addition,

the inspector noted that the applicable specification (CN-1206.-

00-04-0003, Rev. 6) does allow a 210% tolerance for spring hanger

settings and 2 -inch tolerance for snubbers. However, it appears that

settings made during fabrication can be made more accurately resulting

in improved final quality of the systems. Until the licensee addresses

the improvement of practices for initial cold load setting and until

the inspector can verify that a system to assure proper final cold load

settings is being implemented, this will

be Unresolved Item

.

413/414/81-06-02, Control of Hanger Cold Load Settings.

c.

On March 12, 1981 the inspector nr.ted that completed Hanger No.

1-A-NV-8255 was not supporting the piping it was designed to support.

It appeared that the design was such that the trapeze portion of the

hanger could easily become dislodged from the clamp around the pipe.

Licensee personnel indicated that this inadequate design had been

recognized and a drawing change had been issued for this hanger.

The

inspector verified that this hanger has been redesigned. However, it

appears- that this condition was not documented and reported to

appropriate levels of management as required by ' Criterion XVI of

Appendix B to 10 CFR 50. This could have resulted in additional design

problems not being identified. However, after the inspector questioned

the design, the licensee reviewed all possibly affected hanger designs.

This review, completed en March 23, 1981, indicated that the inadequate

design was an isolated case.

This is Violation, 413/81-06-03, Failure to Document Corrective

Action Concernin- Inaaewate Design of a Hanger.

d.

On March 18, 1981, examples of failure to ccmply with Criterion V of

-

Appendix B to 10 CFR 50 were identified. These are as follows:

(1) Hanger Nos.1-R-NI-1487 and 1-R-NV-1764 were installed without

-

'

meeting the angular tolerance allowed by procedure CP-385, Rev. 8,

[

Support / Restraint Erection Tolerances. The tolerance, allowed per

procedure CP-385, paragraph 2.11.2, is + 4*.

The measured angle

in both cases was 11.

.

(2) The drawing approved and issued for Hanger No.1-A-NI-4136 did not

specify the weld to shorten the sway strut assembly as an ASME,

Section III, Subsection NF weld as required by paragraph NF-1130.

This is Violation, 413/81-06-04, Failure to Follow Procedure for

Installation of Hangers and to Provide Appropriate Qualitative

Criteria on a Hanger Drawing.

,

I

. .

.

-

- - - - - - - .

.

- - - ~ -

-.

, , , -

,

w

-

-

.

-

.

.

..

.

6

No violations or deviations, except as described in paragraph 9.c. and 9.d.,

were identified.

'

.

m

S

l

l

l

,.-4