q
s
. . .
.
,p
.,#o
UNITED $TATES
!
g
NUCLEAR REGULATORY COMMISSION
o
g
ne
REGION 11
o,
f
101 MARIETTA ST., N.W., SUITE 3100
g
/
ATLANTA, GEORGIA 30303
O
In Reply Refer To:
JUN 2 41980
RII:DMM
50-338/80-25
50-339/80-26
Virginia Electric and Power Company
ATTN:
J. H. Ferguson
Executive Vice President-Power
P. O. Box 26666
Richmond, VA 23261
Gentlemen:
This refers to the ' inspection conducted by D. M. Montgomery of this office on
May 19 through 23, 1980 and June 2, 1980 of activities authorized by NRC License
es. NPF-4 and NPF-7 for the North Anna Power Station facility, and to the dis-
ion of our findings held with D. L. Bensen at the conclusion of the inspection.
M eas examined during the inspection and our findings are discussed in the
enclosed inspection report.
Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews with
,
personnel, and observations by the inspector. The Region II Mobile Laboratory
alSo brought to your site and used by the inspector to make certain indepen-
WdS
dent measurements. The basic purpose of these independent measurements is to
verify your capability for analyzing radioactive effluents, and to achieve and
maintain comparable methods of analyses between your facility and the NRC. The
complete data from these measurements will be reported in a subsequent Inspection
Report.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements. This iten: and references
to pertinent requirements are listed in the Notice of Violation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions. Section 2.201 requires you to submit to this office, within 20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results achieved; (2)
corrective steps which will be taken to avoid further noncompliance; and (3) the
date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter and the enclosed inspection
report will be placed in the NRC's Public Document Room. If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is claimed that
the information is proprietary, and should be prepared so that proprietary infor-
mation identified in the application is contained in a separate part of the
document. If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document Room.
8010010
291
F
-
,,
.
Virginia Electric and Power Company
-2-
JUN 2 41980
-
Should you have any questions concerning this letter, we will be' glad to discuss
them with you.
Sincerely,
p
,)l
'
.
?
/
'
. Philip S hr, Chief
uel Facili y and Materials
Safety Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos. 50-338/80-25
and 50-339/80-26
cc w/ encl:
W. R. Cartwright, Station Manager
Box 402
Mineral, VA 23117
P. G. Perry
Senior Resident Engineer
P. O. Box 38
Mineral, VA 23117
.
+