Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Rept 50-271/80-21. Requests Addl Info Re Interim Corrective Actions Taken Until Hardware Receipt
ML19346A084
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 03/24/1981
From: Joyner J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Rich Smith
VERMONT YANKEE NUCLEAR POWER CORP.
Shared Package
ML19346A079 List:
References
NUDOCS 8106050033
Download: ML19346A084 (2)


See also: IR 05000271/1980021

Text

M

. g

' W.

UNITED STATES

S

NUCLEAR REGULATORY COMMISSION

'

., w

fj

(.

  • b

REGION l

5'\\

f

$31 PARK AVENUE

g

jgg

KING OF PRUS$lA, PENNSYLVANI A 19406

.,

.....

Docket No. 50-271

Vermont Yankee Nuclear Power Corporation

ATTN:

Mr. Robert L. Smith

Licensing Engineer

1671 Worcester Road

Framingham, Massachusetts 01701

Gentlemen:

Subject: Inspection 50-271/80-21

This refers to your letter dated February 4,1981, in response to our letter

dated January 14, 1981.

Thank you for informing us of the corrective and preventive actions documented

in your letter regarding Itam 1.

These actions will be examined during a future

inspection of your licensed program.

In regard to Item 2, we find that you have failed to correct the identified item

of noncompliance in a timely manner.

In your reply you have not indicated what

interim actions you have taken to comply with this requirement from December 2,

1980, when this item was identified.

Your reply only indicates that contingent

upon hardware receipt you expect to correct this matter by May 1, 1981.

You are required to reply to this letter, and in preparing your response you

should include a description of the actions taken by you since December 2,1980

to achieve compliance with this requirement.

In accordance with Section 2.790(.d) of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, documentation of findings of your control

and accounting procedures for safeguarding special nuclear materials and your

l

facility security procedures are exempt from disclosure; therefore, Attachment A

of the referenced letter will not be placed in the Public Document Room.

l

Your cooperation with us is appreciated. Should you have any questions concernb :

l

this letter, we will be pleased to discuss them with you.

Sincerely,

,

N

.J

f.p.x !) n:s W

,

(JamesH.Joyner, Chief

~ Technical Inspection Branch

i

81060500%

!

. . - . - - -

. . -

. _ . , .

- . - -

- - - , . - , . , _ - - . . - . . . ,

.

. , - , . ,

.

Vennon't Yankee Nuclear Power

2

14 MAR 1981

Corporation

cc:

,

Mr. Warren P. Murphy, Plant Superintendent

,

Mr. W. F. Conway, Vice President and Manager of Operations

f

K. Kniskern, Manager of Security

J. E. Griffin, President

L. H. Heider, Vice President

!

,

,