Forwards IE Insp Repts 50-413/80-12 & 50-414/80-12 on 800501-30 & Notice of Violation
ML19344A509
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 06/25/1980
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
Shared Package
ML19344A492 List:
References
NUDOCS 8008200528
Download: ML19344A509 (2)


See also: IR 05000413/1980012

Text

f

.

,

p>* U:0

9'o

UNITED STATES

c4

t

?

g

NUCLEAR REGULATORY COMMISSION

n

E

E

REGION 11

s

%.....p*['

~

o

101 MARIETTA ST

N.W.. SUITE 3100

ATLANTA, GEORCIA 3o303

JUN 2 51980

In Reply Refer To:

RII:GFM

50-413/80-12

50-414/80-12

Duke Power Company

ATTN:

W. O. Parker, Jr.

Vice President, Steam Production

P. O. Box 2178

Charlotte, NC 28242

Gentlemen:

This refers to the inspection conducted by G. F. Maxwell of this office on

May 1-30, 1980, of activities authorized by NRC Construction Permit Nos. CPPR-116

and CPPR-117 for the Catawba facility, and to the discussion of our findings

held with at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

We have examined actions you have taken with regard to previously reported

unresolved items. The status of these items is discussed in the enclosed

report.

During this inspection it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. These items and references

to pertinent requirements are listed in the Notice of Violation enclosed here-

with as Appendix A.

This notice is sent to you pursuant to the provisions of

Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal

Regulations.

Section 2.201 requires you to submit to this office, within 20

days of our receipt of this notice, a written statement or explanation in reply

including:

(1) corrective steps which have been taken by you and the results

achieved; (2) corrective steps which will be taken to avoid further noncom-

pliance; and (3) the date when full compliance will be achieved. With regard to

item B, corrective actions to prevent recurrence were completed prior to

conclusion of this inspection; therefore, a reply is not requested for this item.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietarf, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document.

If we do not hear from you in this regard within

the specified period, the report will be placed in the Public Document Room.

800820'0 7 [

F

.

.

.

f

Duke Power Company

-2-

JdN 2 51980

Should you have any questions cor.cerning this letter, we will be glad to discuss

them with you.

Sincerely,

h{

f

C. E. Murphy, Chie

Reactor Construction and Engineering

Support. Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report Nos. 50-413/80-12

and 50-414/80-12

< v/ encl:

W. Hampton, Station Manager

.

G. Beam, Project Manager