Text
&
.
4
UNITED STATES
O i'
.A
~uctean neoutaronv co
iss'o~
{
j
REGION I
of
KING OF PRUS$l A, PENNSYLVANI A 19406
.....
Docket Nos. 50-317
7 980
1
50-318
Baltimore Gas and Electric Company
ATTN: Mr. A. E. Lundvall, Jr.
Vice President, Supply
P. O. Bo.< 1475
Baltimore, Maryland 21203
Gentlemen:
Subject: Combined Inspection Nos. 50-317/80-15 and 50-318/80-14
This refers to the routine inspection conducted by Messrs. R. Architzel and
C. Callahan of this office on September 1-29, 1980 at the Calvert Cliffs Nuclear
Power Plant of activities authorized by NRC License Nos. DPR-53 and DPR-69 and
to the discussions of our findings held by Mr. R. Architzel with Mr. L. Russell
and other members of your staff at the conclusion of the inspection.
Our inspector also verified the steps you have taken to correct one of the items
of noncompliance brought to your attention in a letter dated May 5,1980 (Item 2).
We have no further questions regarding your action at this . time.
Based on the results of this inspection, it appears that one of your activities
was not conducted in full compliance with NRC requirements, as set forth in the
Notice of Violation, enclosed herewith as Appendix A.
This item of noncompli-
ance has been categorized into the levels as described in our correspondence to
you dated December 31, 1974.
This notice is sent to you pursuant to the provi-
sions of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code
of Federal Regulations.
Section 2.201 requires you to submit to this office,
within twenty (20) days of your receipt of this notice, a written statement or
you and the results achieved; (2)(corrective steps which will be taken to avoid
explanation in reply including:
1) corrective steps which have been taken by
further items of noncompliance; and (3) the date when full compliance will be
achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
litle 10, Code of Federal Regulations, a copy of this letter and the enclosures
will be placed in the NRC's Public Document Room.
If this report contains any
information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application wi +1n 20 days to this office to
withhold such information from.public disclosure. Any such application must be
accompanied by an affidavit executed by the owner of the information, which
identifies the document or part sought to be withheld, and which contains a
statement of reasons which addresses with specificity the items which will be
considered by the Commission as listed in subparagraph (b) (4) of Section 2.790.
0101150 g Q
.
-*
e-
3
-w
w
- -
-
y
.
.
.
Baltimore Gas and Electric Company
2
7 1380
The information sought to be withheld shall be incorporated as far as possible
into a separate part of th'e affidavit.
If we do not hear from you in this
regard within the specified period, the report will be placed in the Public
Document Room.
Should you have any questions concerning this inspection, we will be pleased to
discuss them with you.
Sincerely,
[fkd
br h1
Eldon J. Brunner, Chief
Reactor Operations and Nuclear
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Combined Office of Inspection and Enforcement
Inspection Report Nos. 50-317/80-15 and
50-318/80-14
.
cc w/ enc 1:
R. M. Douglas, Manager, Qual.ity Assurance
L. B. Russell, Plant Superintendent
T. Sydnor, General Superviscr, Operations QA
R. C. L. Olson, Principal Engineer
J. Deegan, Assistant General Supervisor, Programs Unit
J. A. Tiernan, Manager, Nuclear Power
R. E. Denton, General Supervisor, Training and Technical Services
~~
s
-
-
.
.
- .
.