ML19332A288

From kanterella
Jump to navigation Jump to search
Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in IE Insp Repts 50-460/80-07 & 50-513/80-07
ML19332A288
Person / Time
Site: Washington Public Power Supply System
Issue date: 08/20/1980
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Ferguson R
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML19332A289 List:
References
NUDOCS 8009110415
Download: ML19332A288 (1)


See also: IR 05000460/1980007

Text

r

t * paa

&

9

. . UNITED STATES

g

.

8'

NUCLEAR REGULATORY COMMISSION

o

$.

,E

REGION V

e

-

1990 N. CALIFORNI A BOULEVARD

,o

SUITE 202, WALNUT CREEK PLAZA

e,,,,

WALNUT CR EE K, CALIFORNIA 94596

E 2 01920

i

Docket Nos. 50-460

50-513

Washington Public Power Supply System

P. O. Box 968

Richland, Washington 99352

Attention: Mr. R. L. F

Managing f

,.

Gentlemen:

Thank you for your letter dated July 25, 1980 informing us of the steps you

have taken to correct the item which we brought to your attention in our

letter dated June 26, 1980.

Your response to the specific itea of noncompliance indicated that the final

inspection on the support had not been completed.

It is the considered

opinion of IE:RV that completion of a first line QC inspection on an

activity is necessary and sufficient to expect compliance with those

attributes considered by the QC inspection criteria. This position was

discussed with you during the meeting at the IE:RV office on August 12, 1980.

The implementation of your identified corrective actions will be verified

during a future inspection.

Sincerely,

I

N

I

G. S. Spen:er, Chief

Reactor Construction and

Engineering Support Branch

t

8009110.;; ejl 5

_