ML19327A057
| ML19327A057 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 07/18/1980 |
| From: | Burstein S WISCONSIN ELECTRIC POWER CO. |
| To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| IEB-80-11, TAC-42896, TAC-42897, NUDOCS 8008010110 | |
| Download: ML19327A057 (21) | |
Text
YN WISCONSIN Electnc eom courm i
231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 July 18, 1980 Mr. J. G. Keppler, Regional Director Office of Inspection and Enforcement, Region III U. S. NUCLEAR REGULATORY COMMISSION 799 Roosevelt Road Glen Ellyn, Illinois 60137
Dear Mr. Keppler:
DOCKET NOS. 50-266 AND 50-301 RESPONSE TO IE BULLETIN 80-11 MASONRY WALL DESIGN POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 This is to provide our initial response to IE Bulletin 80-11 dated May 8, 1980.
Enclosed herewith is the report entitled
" Interim Report On Masonry Wall Design" for Point Beach Nuclear Plant, Units 1 and 2.
This report provides information requested for the initial 60-day reporting period of the bulletin concerning masonry walls.
Based on a field inspection, we have identified fifty-two masonry walls or blockouts whose failure could affect safety related equipment.
These walls were originally designed accord-ing to Uniform Building Code criteria and not analyzed for specific FFDSAR loadings.
We intend to proceed with a program of either upgrading each wall to meet FFDSAR loading criteria, or to verify each wall's ability to meet required design loadings.
We have begun preparations for initiating the upgrading and verification work.
This effort, including any modifications that result from the analysis, will proceed as rapidly as possible.
We will advise you in detail of our progress in the 180-day response.
Very truly yours,
^
,/
Sol Burstein Executive Vice President Enclosures JUL 2 21980' Copy to NRC Resident Inspector, Point Beach Nuclear Plant 8008010//0 t
E INTERIM REPORT ON MASONRY WALL DESIGN FOR POINT BEACH NUCLEAR PLANT 1.
INTRODUCTION This report is the 60-day response to NRC IE Bulletin 80-11 dated May 8, 1980.
The bulletin requests all licensees and permit holders for nuclear power plants to provide information concerning masonry walls whose failure could affect safety-related equipment.
2.
BULLETIN ITEM 1 (IDENTIFICATION OF SAFETY-RELATED MASONRY WALLS)
An inspection survey of Point Beach was conducted from June 16 through July 2, 1980 to identify safety-related walls.
Prior to the survey, inspection packages were prepared to provide the field inspectors with marked-up drawings showing safety-related components.
The survey was conducted in accordance with
" Field Walk-Down Procedure for Concrete Masonry Walls and Blockouts for Point Beach Nuclear Plant".
The procedure is attached to this report as Appendix A.
The survey included identification of the following classes of walls:
a.
Concrete block and brick walls b.
Masonry blockouts in concrete walls c.
Unreinforced concrete blockouts in concrete walls d.
Brick walls used as fire protection for building columns The survey results indicate that 52 walls were found to be safety-related masonry due to the proximity or attachment of safety-related equipment.
A summary of the safety-related 4
walls identified is as follows:
18 Concrete block walls in the Auxiliary and Control Buildings 28 Reinforced concrete walls with one or more blockouts filled with concrete blocks, bricks, or unreinforced concrete 4
Steel building columns with brick facing used for fire protection 2
Facade stairwell walls The blockouts listed above were openings left in the plant concrete walls for routing piping, conduit, and cable tray, or for moving large equipment into a cubicle.
These were then filled with masonry or unreinforced concrete.
A list of all safety-related walls is attached to this report as Appendix B.
Each wall is identified by a unique number and the approximate plant location, type of wall construction, attachments, and safety-related equipment in proximity are identified. !
i M
-.-c
3.
BULLETIN ITEM 2A (EVALUATION PROGRAM)
The following is the prioritized list of safety-related walls that will be verified to meet FFDSAR loading criteria, or upgraded as required.
This is a partial list only and does not include all the walls.
First Priority Review all safety-related block walls or blockouts with external attachments greater than one hundred pounds.
The following walls are in this category:
19, 24, 39, and control room partitions Second Priority Review all unloaded unreinforced concrete block walls and blockouts.
The following walls are in this category:
3, 20, 22A, 26, 64, 68, 72, 86, 104, 128, 3-10, 5-5, and 5-29 Third Priority Review unloaded reinforced concrete block walls and blockouts.
The follow-ing walls are in this category:
40, 143, 151, and the facade stairwells
)
All walls which have been designated as reinforced or unreinforced were surveyed using a magnetic reinforcing f
locator.
Selected walls were " chipped out" to verify the reinforcing and this work is continuing.
The chipping procedure is described in Appendix A.
The above priority of wall evaluation is listed in order of the potentially weakest to the strongest walls.
The wall strength evaluation required by bulletin Item 2b will be based on chipping investigations in addition to construction drawings.
The priority list for investigation will be completed when the field inspection data are summarized and the chipping program finished.
4.
BULLETIN ITEM 3 (JUSTIFICATION OF THE EVALUATION CRITERIA)
Justification for the review criteria will be submitted with the 180-day report (November 4, 198 0).
Justification will be based on the codes and established standards related to concrete and masonry design.
All FFDSAR loading criteria will be considered in the review.
m a
4 APPENDIX A FIELD WALKDOWN PROCEDURE FOR CONCRETE MASONRY WALLS AND BLOCK 0VTS FOR POINT BEACH NUCLEAR PLANT 4
)
,,,8
-~
.n+
<. - +
e
PURPOSE 3,0 This procedure specifies the items to'be performed and the data to be accumulated to aid in the response to NRC IE Bulletin 80-11, Masonry Wall Design, dated May 8, 19B0, (Appendix A).
_c 2.0 SCOPE 2.1 This survey shall be conducted and the data accumu-lated for all concrete mansonry walls, including openings in concrete walls filled with concrete block (blockouts) which are in proximity to or have attachments from safety related systems such that failure of the wall or blockout could affect the safety related system.
The cafety related cycheme-cre listed in Apper.d4*-B-v %4o Sufficient data is to be recorded to determine the 2.2 characteristics of the wall construction, geometry, location and magnitude of applied loads and corres-ponding connection details for safety and non-safety systems supported by the wall.
Selected walls will be identified in the home office 2.3
~
that will be analyzed.
3.0 SURVEY INFORMATION 3.1 An inspection package for each " wall will be prepared ir.-th; here affic+ prior to the. field survey.
0ikeo The inspection package will consist of the following
3.2 documents
(a)
Key plan locat,ing wall (arch. dwg.)
(b)
Wall Sketch of each side of the wall to be used to record. data. (See Appendix C)
(c)
Civil details of wall to include any penetration details.
(d)
General Arrangement (equipment) drawings show,
ing wall.
(e)
Elect'rical Raceway Layout drawings showing the wall.
(f)
HVAC drawings showing the wall..
(g)
Piping area drawings showing the wall.
~ M-28/2 t....
e
- '***"'"-N*-'M q
g
,?A Instrument Rack location drawings showing the (g)
J walls.
For items 3.2 (c), (d), (e), (f) and (g) the safety 3.3 related equipment will be marked on the drawing.
Selected walls will be indicated where maximum in-3.4 formation is required.
These are the walls where our initital evaluation indicates that the wall can be analyzed and determined to be satisfactory.
4.0 SURVEY REQUIREMENTS aredIin 4.1. Ske+ches of ~each side of+each wall will be e.s. -
advance hnd included In he inspec + ion pa Ad-Th'e sketches will be used to record the data.'
1 ditional sheets are to be used, as required, to These record plan views and attachment details.
shall be numbered as sheet 2, 3, etc. to the original wall number.
The survey team is to identify the location of any 4. 2.
cpn. crete masonry walls not shown on the design drawings.and is to survey those walls-in accordance with this procedure.
Areas inspected or not in-spected shall be identified and documented.
Photographs may'be taken of the walls surveyed.
4.3 Photographs shall be numbered to correspond with Inaccesible areas the wall numbering system.
(e.g., where high. radiation _ levels A re. encountered-)__._
Sketches will not be will only be photographed.
made in the field.
4.4 Access to the plant radiation areas will be con-trolled by the plant HP.
The team leader will 1
coordinate with the plant HP for access to all radiation areas.
Normally the coordination should be done no later than the day before the inspec-tion.
If the area is determined to be inaccessible and 4.5 the sketch of the wall will be so marked and the reason for inaccessibility included.
4.6 The survey,will cover the following items:
(a)
The dimensional location and identification of all items attached to the wall are.to be recorded if available.
All items attached to the walls will be identified with what-ever identification number is.shown on the equipment, tray, piping, pipe support etc.
t l
M-28/2 G
..,_m
~ ~... - - -
n--
\\
l
~
(b)
Record suf"ficient data for attachments so that' tributary gravity loads and seismic loads can be estimated.
This will consist of at least locating the next support on each side of the wall, not on the wall under consideration, for 3
all items and the next restraint for seismic i
~
Category I piping system.
(c)
Dimensio'ns shall be recorded to the nearest 6 inches.
Where limited access prevents physical measurement, locations shall be estimated to the nearest 12 inches and noted that this is an estimate as well as the method
~
used to estimate.
5.0 SURVEY PROCEDURE 5.1 The survey team shall' complete the sketch of the
~
wall showing-(a')
Locations and sizes of all openings in ma-sonry-walls and blocked-in openings in co.ncrete walls.
The. function of each opening or blockout shall be identified (e.g.
clectrical opening, H&V opening 'etc.)
(b)
' ails of wall b'oundary conditions, i.e.,
' whether top or sides are visibly free or I
attached to walls, ceiling or steel beams.
The wall boundary.. conditions.will be verified for all walls that are to be analyzed.
The-verification will be performed by removing enough of the concrete block to verify the type of connection.
See Appendix E for details on how this is to be done as well as the repair method.
(c)
Support attachments including the manner of attachment to the wall, e.g., through bolted with backing plates, or concrete expansion anchors.
Record type, if can be identified, and size.
(d)
Type of wall construction and thickness, if
. visual determination is possible, for example:
Single Wythe Multiple Wythe with Mortar Composite - Two Wythe with Grout Core 4
M-28/2
-S-4
. _. 1.:. _ _z.. ------
\\
/
[
^
j
/
(e)
- The, location and size of structurally
/
significan't cracking as determined by the
~
/
survey team.
Survey the general condition of
/
wall.
the masonry wall and attachments to the masonry
/
(f)
Whether or *not wall supports or restrains -
safety related system.or equipment which may '
be safety related.
The systems and equipment shall be identified.
(g)
Whefher or not wall is in proximity to a system which may be safety related.
(Proximity is defined as within an. arc length equal to the masonry wall height from the base of each face of the masonry wall extending to the floor.
Proximity does not extend beyond compartments.)
Some walls may have bracing on one side in order to ensure that the wall will fall in one direction.
This should be recorded for the side where the wall.will fall.
Systems and items falling in this category shall be identified and the approximate location with
~Ye'spe'ct to the sall shall'be described.
~(Use additional sheets as required).
(h)
Bleeked-in openings in concrete walls smaller than 3 ft. will be noted.
Sciccted eraai" E Ain openin35 $rMer than S e fr.. dice.h are a fety related as J,gr'. b,.a i n Se<to a ~2-4 sha21 be recorded 6%C'
~..
5.2 A composite sketch shall be prepared for every wall, except 'where'-rich' afety 'related -egt.ipment..is.-located. e -
~
s In this case the sketch will be marked as containing no safety related equipment and the sketch verified by the team leader.
This sketch shall show all the information recorded by the survey team.
The fortnshown in. A fl1 led-in.forJach. *pp endix.D..shall b.e
5.3 alLSurveyed.~ 1t.
shall be filled in by the team leader as each wall is surveyed.
6.0 SKETCH PREPARATION 6.1 The sketch number'should contain the wall number and reference the drawing numbers (all drawings) where the' wall is located.
6.2 The side of the wall shown should be labeled as such:
North, South, East or West.
If more than one sketch is required for a side,1,2 3,, etc.
f will be added to wall number.
' M-28/2-
- 6.3 Column linms and referenca elevation should be
/
chown for orieritation.
/
PERSONNEL QUALIFICATION AND TRAINING 7,0 7.1 Two survey teams will be provided.
Each team will consist of an appropriate number of engin.eers se-lected from the following disciplines: Electrical, f
Hechanical, Plant Design and Civil.
The survey teams will be. led by one of the team civil engineers.
He will coordinate the inspection with plant personnel.
g He will also serve as technical leader to ensure that all required information is recorded.
7.2 Trr.ining of all team members will be conducted by the project civil group supervisor.
This training will be conducted at Point Beach plant site and will include the actual inspection of at least one con-crete block wall.
r l
.u.m di M-28/2 -
o
,_7.~_.-r.
_-m.
e y
1
I I
I II UD MAsobdRY WALL Sul:2MEY wAt."C eApaty astATeo vs.5 wo lg -
mat.Yele Rs4uinso Yes Wo J i
.13. )
.15~.
3)-l-
)
m%
ts I
I I
II I
I I
O I-1 I
p i
i 9-g O
m W
g
'3 JT' p
x m
EL.Adn'_I
=
c M
LGOE NEEIS.T.
L0.0.KiiG ~ NDETFF E+
n t
a-O r
~1 porg,g:
St.p'c1.' 'A U X : N. Wl h!G gLEv. 5 2 '- O " P.t( @
cH5cK60 CS) c2 Ara @
- i. Tyrs op wAt.t.15C0~CC -~~
- a. oisclPLINS -
gspenas p,ww'p5 MEEL NW6R40RFORATION GAM P'IAWedoco
_ cz2m. -
.-.M - 54 j
Pol 9ffMACH NUCl,BAR F%NT
.bs No. lo+47 ol9 i
un i.e. um.~:137 -lTZ.Tuf l_.aE.-
O
/
/
APPENDIX C 4
/
/
INSTRUCTIONS FOR COMPLETING SKETCH
/'
(1)'To be completed by Home Ofdice (2)
Indicate discipline - Civil
- Electrical
- Mechanical
- Plant Design (3)
Indicate type of construction (4)
Name of person making survey (5)
Checker (to be used only for composite sketch of each wall.)
(6)
Additional sheets as required (7)
Date of survey (8)
Circle Yes or No, if conclusive 4.-
,e M-28/2 I.*..
s*.}.'
e pq
,-",F,
. %7 ' h M e - m M '; V-w--
4 e me a--
-e m.muumme e-c.
.e.
....-e.
j ll i*
g d
t ed c
ve A
oi) mf e eit Rd a od lM(
l h
'O ar c
'W o S
4 no i d te o
ar N
ci
/
iu s
fq e
ie Y
dR oM tc d
A se it) see e
yl t l pa nad a
(
AC 0
hc S
i l
t nn eo mid et e
)
can e
rmi t
ora a
fot d
nfb
(
inO eI R
I -
,II d
?
e lez d
lby e
e a
l t
Woa a
t n l
A G
e s
R
.e Y
t y
d t
lee s e lbv i
f a
o a
Wom L
S t eR y
e ev o
r N
u S
d ll e
9 a
yht) ecee W
vtlt repa ukmd SSc(
C D
l.
~
lo aN x
W
.[
i d
e e
n ga.-
e ko P
cN-e (s
a-P P
m
~h
?(
1 a
~
9 j
l l4
s
%IX Et Procadureffor Identifying Rebar and Anchors in Blockwalls o,nd for Repairing Holes in Blockwalla 1
l.
The reinforcement and end connections (anchors) in masonry walls (blockwalls) designated by the Team Leader shall be identified in accordance with this procedure.
Holes in blockwalls shall also be re-
-c paired in accordance with this procedure.
fr4cc Yo C OI ng U.n CMppin g 3 cuihn
, o r co eing to t
locale re.infonemen ad/oc co nnechons 3 'l k e 4 ea m LegMec shall codoci% (J Sconsin Elet'lrtc. d e RepresafdNe to vectk %'t emee premuitons ace TAk.en reyrd; c{ud to rol, cleamhneA5. #8C""
y> CI'*
profeLhon, and Jfh phystc.s.
ggp
, IDENTIFICATION OF REBAR AND ANCHORS M
Rebar finders shall be used to locate all vertical and horizontal rebar in the wall.
3.1 The diameter of the vertical rebar shall be determined by exposing at least one vertical rebar per wall.
3.2 The diameter of the horizontal rebar shall be determined by exposing a horizontal rebar in at least one horizontal bond beam per wall.
3.3 The type and diameter of floor anchors shall be deter-mined by exposing an area along the bottom of the wall that extends between two adjacent vertical rebar and is approximately 4 inches high.
3.4 The type and diameter of anchors along vertical edges of a blockwall shall be determined'by expdsing a 3 ft.
high by approximately 4 inches wide area along each edge of the wall.
3.5 Ceiling anchors are not expected-to exist,-however, an
=-
area along the top of at least four walls designated by the Team Leader shall be exposed and inspected for ceiling anchors.
The exposed area shall extend between-two adjacent vertical rebar and shall be approximately 4 inches high.
3.6 When anchorage is provided by dowels, the entire portion of.the dowel extending f.nto the blockwall shall be ex-
' posed so that its lengen can be recorded.
This shall lie done for at least cae dowel per wall.,
4.1 If the rebar/ anchor spacing is found to be equal to or les.s than than specified on the applicable civil or architectural drawing and if the rebar/ anchor dia-meter is equal to or greater than specified, then no further investigation of the reinforcement and. anchor-age of the wall need be performed.
r-n-
f the conditions of paragraph 4.1, above, are not metr vertical robar shall be exposed at 15 feet (maximum) intervals along the wall, horizontal rebar in each bond
(.
beam shall be exposed at 20 feet (maximum) intervals along L.C@F the wall, floor anchors shall be exposed at 20 feet (max-imum) intervals along the wall, and vertical edge anchors shall be exposed in one additional area.
p 4.3 P.ebar/ anchors may be exposed at additional locations at L.
the discretion of the Team Leader.
s-
, 5.1 Exposing rebar and anchors shall be done by chipping 4.
with chisels, impact tools or by coring with machines using masonry bits only.
5.2 All holes shall extend 1,or 2 inches past the rebar or anchor, but no more than 2 inches past the center of the yall.
5.3 Whenever possible, holes shall be staggered along the r
length of the wall.so that the holes do not align ver-ticall.y.
6.
The
$hcing and diameter of all exposed vertical and horrro tal rebar shall be recorded.
The spacing, dia-meter and a description of all exposed anchors shall be recorded.
The projection of exposed dowels into block-walls shall be recorded.
O REPAIR OF. HOLES IN BLOCKWALLS 5
7.
Holes in blockwalls sha'll be repaired by drypacking or s. --
by grouting.
Drypacking is recommended for.. deep holes. -
2-s and for locations where grout cannot be poured.
Grouting b
is recommended for shallow or large holes.
When rebar is exposed, grouting is preferred.
8.
All loose block, mortar and grout shall be removed from the hole prior to filling.
t 9.
Holes shall be prepared for filling by either of the following methods-1.
Holes to be prepared by this first method shall be keyed.
The hole shall then be soaked with water r
and packed with wet burlap at least 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> before a
filling.
Soak the hole again, just prior to filling, and remove all exc,ess water.
Coat the inside of the s
hole with neat.3 rout just prior to filling.
s 2.
Coat all surfaces in the hole with an epoxy resin t
concrete adhesive just prior to filling the hole.
M-25/6 j
i Application of the adhesive shall conform to the manufacturer's instructions.
Epoxy resin concrete b
adhesives shall be Epoxtite (2385, 2390 or 2393) manufactured by W. R. Grace & Co., Epibond manu-
'factured by Furane Plastics Inc., or an approved v
equal.
10.
Holes shall be filled by either of the following methods:
1.
A drypack mixture consisting of'(by volume) 1 part portland cement to 2-1/2 parts of sand graded so that 100% will pass a No. 16 screen may be used.
Suffi-cient water shall be used to' produce a mortar that will stick together when molded into a ball by a slight pressure of the hands and will not exude water but will leave the hands damp.
The filling shall be of a consistency that is at the point of becoming rubbery when the material is solidly packed.
Dry-pack shall be packed in layers.
Each layer shall be solidly compacted over its entire surface using a hardwood stick and a hammer or a pneumatic hammer with a drypack head.
2.
Either of the following nonshrink grouts may be used:
Masterflow 713, Master Builders Co.
a.
b.
Five Star Grout, U. S. Grout Corp.
Grout shall be_ mixed in acco.rdance with..the_manufac _.
turers instructions.
Forms are required when nonshrink grout is used.
Typically, forms should be made of 1/2 or 3/4 inch plywood and should be held in place either by bracing from adjacent structures or by anchoring to the wall with ram-set powder driven nails.
A 2" high, wedge type opening should be lef t at the top of the form so that a pencil vibrator or a rod can be inserted into the hole to compact the grout.
About 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after grouting, the wedge shaped projection of grout at the top of the form should be removed.
'll.
Af ter the drypack has set for about 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> or the grout has set'for about'24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and the forms have been re-moved, the filling shall be cured by either of the fol-lowing methods:
~
'n-2s/12 m
- "*O-
+89**'**-
er
r The surface of the,repsired croa ehall ba keptBuricp kept wa
?'
1.
sheet laid directly on the surface after it has moist for 7 days.
been tho.-oughly wetted, shall be used to keep the surface moist.
After curing with water for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with pr.ragraph 11.1, above, a liquid membraneLiquid membrane 2.
curing compound, shall be applied.
curing compounds shall be Siksgard 665 manufactured by Sika Chemical Corporation, Kurez concrete curing compound manufactured by Euclid Chemical Company, Liquid mem-or en equal conforming to ASTM C-309.brane curing reg'uiring special coatings.
i
\\
" ~"
e e
i M.-28/12
. _e -
..q~-
k
.m m
w g--
4 e
APPENDIX B SAFETY-RELATED MASONRY WALLS l
l
APPENDIX B SAFETY RELATED MASONRY WALLS j
1 l
Wall 3 - 33" block wall; 4 wythe thick; Aux. Bldg., central part, El. -S'-3"; Attachments: None, Proximity: conduits 1003-1, 1 -851 B,
S260, 1-728.
Wall 8 concrete filled blockouts; Aux. Bldg., central part, El. -19'3";
Attachments: None, Proximity: pipes - 10"-SI-60l R, 8" - AC-60l R-4, 10"-AC-60lR-3.
Wall 8 concrete filled blockouts; Aux. b1dg., central part, El. -19'3";
Attachments: None, Proximity: pipes - 10"-SI-60lR, 8"-AC-60l R-4, 10"-AC-60lR-3.
Wall 39 - 21"Thk blockout to floor; 2 wythe thick; Aux. Bldg., central part, El. 8'-0"; Attachments: Lead shield housing radioactive non-safety related pipes, Proximity: pipes - 6"-AC-152N-ll, cable tray - JJ17.
~
Wall 40 - 21"Thk blockout to floor; 2 wythe thick; Aux bldg., central part, El. 8"-0"; Attachments: None, Proximity: pipes - 6"-AC-152N-ll.
Wall 5 21" & 24" Thk blockouts to floor: 2 wythes thick; Aux. Bldg.,
central part, El. 8'-0"; Attachments: None, Proximity: pipes - 14"-AC-152N-7,14"-AC-152N-3, 3/8" stainless RHR instrument lines.
Wall 5 21" & 24" Thk blackouts to floor; 2 wythes thick; Aux. Bldg.,
central part, El. 8'-0"; Attachments: None, Proximity: pipes -
14" AC-152N-3,14"-AC-152N-ll, 6"-AC-60l R-6,10"-S;-151 R-4, 3/8" stainless RHR instrument lines.
Wall 5 block filled blockouts; Aux. bldg., central part, El. 8'-0";
Attachments: None, Proximity: pipes - 6"-AC 601R.
Wall 30 - brick & block filled blockouts; Aux. b1dg., central part, El. 8'-0";
Attachments: None, Proximity: pipes - 24"-HB-19, 3"-EB-8, 3" EB-10, 20"-JB-2, conduit - CL-2, 2Pil A & B, cable trays - FWO3, FV07, PT03, PUO4.
Wall 5 21"Thk alockout, to floor; 2 wythes thick; Aux. bldg., central part, El. 8'-0"; Attachments: None, Proximity: pipes - 6"-AC-152, 14"-SI 30lR-3, 2-1/2" Component Cooling Water lines, (CCW) lines, 6"-AC-60lR, conduit F085.
j Wall 5 block filled blockouts; Aux bldg., central part, El.
8'-0"; Attachments: None, Proximity: pipes - 4"-SI-150C-3 Conduit - IP11 Al, IPil A2, IP1182, cable trays - FYO7, FN04, FJ04, FP06, i
FK03, FM04, FR04, pumps: IPilA,1PilB.
Wall 24 - 25"Thk blockout to floor; 2 wythe thick; Aux. bldg., central part, El. 8'-0"; Attachments: lateral supports for instrument rack for waste evaporator (non safety), Proximity: H & V duct 8' x 14" (non safety), pipes - 3"-SC-152-N12, 1"-AC-152-N12, 14"-AC-152-N7, 14"-AC-152-N3.
, f
..-.....n.
-c
Wall 26 - 24"Thk blockwall; 2 wythe thick; Aux. bldg., central part, El. 8'-0"; Attachments: None, Proximity: cable tray - RC04.
Wall 157 - 22"Thk blockout' to floor; 2 wythe thick; Aux. bldg., central part El. 8'-0"; Attachments: None, Proximity: pipes - 10"-AC-152N.6, 6"-AC-152N-10, 2"-AC-152N-13.
Wall 5 brick filled blockout; Aux. bldg., c entral part, El. 8'-0";
Attachments: None, Proximity: pipes - 14"-AC-15 2N3, 4"-SI-151 R-6.
Wall 5 block filled blockout; Aux. bldg., i:entral part, El. 8'-0";
Attachments: Proximity: pipe - 3"-CH-151 R.
Wall 14 - brick filled blockout; Aux. b1dg., south wing, El. 8'-0";
Attachnunts: None, Proximity: pipes - 4"-SI-150lR-2, 4"-SI-1501-3.
1 i
Wall 45 - block & brick filled blockouts; Aux. bldg., north wing El. 8'-0"; Attachments: None, Proximity: cable trays - YB12-YB15 YA2, JWO2, conduit - 2I124C, pipes - 4"-SI-150lR-2, 4"-SI-150lR-3.
Wall 12 - 8" blockwall; single wythe thick: Turbine bldg., electrical j
shop El. 8'-0"; Attachments: non-safety tool rack, Proximity: cable trays - 1 AA04, conduit - F70Bl.
l Wall 19 - 8" blockwall; single wythe thick; Control b1dg., Battery Room El. 8"-0"; Attachments: safety related circuit board panels D01 &
D02, Proximity: cable trays - FL01, GF01, GA01, GB01, Elect panel -
D09 Equipment: Emergency Batteries, 006, 005.
Wall 20 - 8" blockwall; single wythe thick; control bldg., Battery Room El. 8'-0"; Attachments: None, Proximity: pipes - 24"-RB-19, 20"-JB-2 (both pipes are in sleeves), Equipment: Emergency Batteries, 006, D05.
Wall 22 - brick, block & concrete filled blockouts; Control b1dg.,
Switchgear room - El. 8'-0"; Attachments: None, Proximity: conduit 15006,14000,154000, lET04, 009-SWI, Dll6, D115. cable trays -
FR01, FL101, EK02, 2AQO3, pipes - 10"-JB-2, 24"-HB-19., equipment -
H & V ducts and H & V units W46A & HX66A.
Wall 22A - 8" blockwall; single wythe thick; Control bldg., Switch gear room El. 8'-0"; Attachments: None, Proximity: equipment, H & V unit W46A.
Wall 23 - block filled blockouts; Control bldg., Pump room El. 8'-0";
Attachments: None, Proximity: pipes - 10"-JG-4-22, 6"-HB-19, M0V2817.
Wall 161 - brick facing on steel column; Control bldg., Diesel rooms El. 8'-0"; Attachments: None, Proximity: conduit - 3922C, pipes -
1"-HB-22 (fuel oil), equipment - diesel gen. exhaust silencers.
Wall 162 - brick facing on steel column; Control bldg., Pump room El. 8'-0"; Attachments: None Proximity: pipes - 3"-EB-10, 8"-HB-15, 3"-EB-8, conduit 4000,1-4001, P38A2, CU-2, CV4002, C4002, 2-4001, 2-4000, 2-4006, CJ2, YB5, 2P292, 4020, 4021, 4019-2, P38A, cable trays -
FM03, FR04, motor operated valves: M0V l-4000,1-4006, 2-4001, 2-4000, 2-4006, 4020, 4021, 468 Equipment: pumps - 1P29, P38A, 2P39. _. - - _ _ _...
_ j
Wall 3 brick and Dioci filled blockouts; Control bldg., Pump room El. 8'-0"; Attachments: None, Proximity: pipes - 3"-EB-10, 3"-EB-8, 8"-HB-15, 4" HB-19, 6" HB-19, conduit - 2Pil A2, 2P11 Al, 2PilB1, 2PilB2, CJ2,1P11 A1,1P11 A2, IP11 A2, IPllB1,1P1182,1-4001,1-4000, 2P3882 cable trays - FJ04, FK06, FP06, FR04, FM03, FT03, QUO 4, FWO3, FV07, motor operated valves; M0V 2817, 4001, 4000.
Wall 3 block filled blockout; Control b1dg., Pump room El. 8'-0";
Attachments: None, Froximity: pipes - 3"-EB-10, 3"EB-8-3 Wall 3 block & brick filled blockout; Control bldg., Pump room El. 8'-0"; Attachments: None, Proximity: pipes - 3"EB-10, 3"EB-3, conduit - 4022.
Wall 3 concrete filled blockout; Control bldg., Diesel generator rooms El. 8'-0"; Attachments: None, Proximity: pipes - 8"-HB-19, 10"-JB-2, cable tray - GJ05, Equipment: starting air compressor, K4A.
Wall 3 concrete filled blockout; Control Bldg., Diesel generator rooms. El. 8'-0"; Attachments: None, Proximity: pipes - 6"-HB-19, 10"-JB-2, 8"-HB-19, cable tray - GJ05, equipment: starting air compressor K4A.
Wall 86 - 30" blockwall; 3 wythes thick; Aux. bldg., central part, El. 26'-0"; Attachments: new safety related conduit added by WEPCo (No number).
Wall 151 - 18" blockwall; 2 wythes thick; Aux. bldg., central part El. 26'-0"; attachments: None, Proximity: pipes - 10"-HB-19, motor operated valve M0V 2930.
Wall 152 - 6" blockwall; single wythe thick; Aux. b1dg., central part,
)
El. 26-0; Attachments: None, Proximity: conduit - new safety related conduit added by WEPCo (No number).
Wall 72 - 32" blockwall; 3 wythe thick; Aux. bldg., central part, El. 26; Attachments: None, Proximity: boric acid transfer system (Piping & instrumentation.)
Wall 5 brick filled blockouts; Aux. bldg., - central part El. 26'-0"; Attachments: None, Proximity: conduit - YG04, YD04, KR06, CV02, CA02.
Wall 64 - 40" blockwall; 4 wythe thick; Aux. bldg., south wing, El. 26'-0"; Attachments: None, Proximity: cable trays XA09, XB07, conduit IPVCR, INISR, IT949, IPVCB.
Wall 65 12" blockout to floor; Aux. bldg., south wing, El. 26'-0";
Attachments: None, Proximity: cable tray - CT01.
Wall 68 - 8" blockwall; single wythe thick; control bldg., elect.
equipment room, El. 26'-0"; Attachments: None, Proximity: intake for diesel generators, pipes - 10"-JG-4, 6"-JG-4, tanks - T24A & B conduit YUl6, YU15. - _..
~ ~......~,._
F Wall 69 8" blockwall; single wythe thick; control bldg., condensate storage tank room, El. 26'-0"; Attachments: None, Proximity: pipes -
10"-JG-4, 6"-JG-4.
Wall 71 - block with brick filled blockouts; Control bldg. - Cable Spreding Room, El. 26'-0"; Attachments: None, Proximity: conduit -
2Y06, 2XYO6, YX4, YX3, YX2, YX1, 2N25Y,1N1SW, 2NISB, 2N15R, 2XY051, 2Y061, 2XY06, cable trays - YB02-01, YA02-02.
Wall 146 - brick f;cing on steel column; Control bldg., Cable Spreading Room El. 26'-0"; Attachments: None, Proximity: junction box JB 1Y03, control panel Reactor Protection System (RPS) IC165, Equipment: H&V ducts and fans.
Wall 147 - brick facing on steel column; Control bldg. Cable Spreading Room. El. 26'-0"; Attachments: None, Proximity: pipe-4"-HB-19, control panel RPS-2C-K1, junction box - JB2Y03.
Wall 3 brick filled blockout; Control bldg., Cable Spreading Room I
El. 26'-0"; Attachments: None, Proximity: RPS conduit - IC1548, 1Cll64B.
Wall 104 - 33" blockout to floor; 3 wythes thick; Aux. bldg., central part, El. 46'-0"; Attachments: CCW flow indicator rack, Proximity:
flow meters IFI 645, IFI 643, TI-1034, TI-1029, 2T1025, Pipes - cross connection lines between the spent fuel pool heat exchanger (safety-related) and pump P13 (non safety-related).
Wall 109 - brick & concrete filled blockouts; Aux. bldg., central part El. 46'-0"; Attachments: None, Proximity: tanks - boric acid tank T6A, B, C elect. panel, MOV1831-2, pipes - 3"-EB-8, 3"-EB-10.
i Wall 143 - 6" blockwall; single wythe thick; Aux. b1dg., central part El. 46'-0'f; Attachments: None, Proximity: pipes - cross connection lines between the spent fuel pool demineralizer which is nct safety-related and the spent fuel pool heat exchanger which is safety related.
Wall 128 - 6" blockwall; single wythe thick; Control bldg. HVAC Room El. 60'-0"; Attachments: None, Proximity: 3"-HB-19, 4"-JB-2 H & V ducts & fans (S.E.) HX 38Al.
Wall 133 - 8" blockwall; single wythe thick; Unit 2 Turbine b1dg.
Elect. Equipment Room & HVAC Rooms El. 44'-0"; Attachments: 6" 9 pipe to moisture separator (not safety-related) Proximity: conduit -
2B432, 2B41CA, 2C75A, 2C75C1, 2C75C2, 2C75B, 2C75C3, DC3, 22042-B, 22042-A, 2C75A, 2C75A3, elect. panel 2Y21.
Unit 1 Facade Stairwell - 6" blockwall; single wythe thick; Unit 1 i
Facade, El. 6'-6" to El. 74'-8"; Attachments: None, Proximity:
1-32008,1-3200A,1-HX104,1T466,1T4678, LI 4164, cable trays - RA3, RC12, RA73, JD01, JC01, RA37 equipment: radiation monitors: REll, RE12 pipes: 16"-E8-9 (feedwater) 3"EB-10, valves: 1CV2042, 1CV1045.
. = = = =
= - -
Unit 2 Facade Stairwell -
6" blockwall; single wythe thick; Unit 2 Facade, 6'-6" to El. 74'-8"; Attachments: None, Proximity: conduit: 232002, 2RE97, 232001, 5X21, pipes: 2"-RE-11P, feedwater lines: 16"-EB-9, junction boxes: JBHH-22, JBSH6.
Note on Stairwells - Other safety related targets may lie within the proximity of the stairwell, but due to congestion and difficulty of access, they have not specifically been identified.
Control Room Partitions - 6" blockwall; single wythe; Control Bldg.,
Control Room El. 44'-0"
Attachment:
Fire Base (non-safety) Proximity:
conduit - EY7, LEY 6, LEYS,1EYl,1EYO3C, lY01-3, lY01-2, lY02-3, lY02-2, lYO3-3, lY03-2, lY04-2, 2E12, breaker boxes: D19, 018, D22, 2-YOS, 2-Y04, 2-Y03, 2-Y02, 2-Y01, 2-Y05,1-Y05,1-Y01,1-Y02,1-Y03, 1-Y04,1-Y05, Dl6, D17, cable trays - 2M4, 2M4.
Note: Safety-Related conduits were identified by either the conduit number or by the cables routed in the conduit. The conduit number in most cases is identified by the equipment it services.
(Ex:
Pump 2Pil - conduit 2PilAl; 1M0V850 - conduit ^l-850).
When a conduit number was not identifiable by the equipment it serviced, the conduit number was identi-fied in the raceway schedule (Dwg. E-33) which indi-cates cables routed in the conduit. These cables were then identified as safety-related or non-safety related. All unidentifiable conduits were considered to be safety - related. Piping systems were identified from the NRC Bulletin 79-14 Program.
-..