ML19326D990

From kanterella
Jump to navigation Jump to search

Notifies That Equipment Being Added to Reactor Protection Sys Cabinets Is of Sufficient Mass as to Require New Seismic Analysis of Cabinets.Analysis Requires Approx 20 Wks.Info Will Be Provided in Time to Allow for Final Design Approval
ML19326D990
Person / Time
Site: Rancho Seco
Issue date: 07/21/1980
From: Walbridge W
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To: Reid R
Office of Nuclear Reactor Regulation
Shared Package
ML19326D988 List:
References
TASK-2.K.2.10, TASK-TM TAC-45188, NUDOCS 8007250348
Download: ML19326D990 (1)


Text

_

  • w.y WUD SACRAMENTO MUNICIPAL UTILITY DISTRICT O 6201 S Street, Box 15830, sacramento, California 95813; (916) 452 3211 July 21,1980 C/

Director of Nuclear Reactor Regulation Attentiorf:

Mr. Robert W. Reid, Chief Operating Reactors, Branch 4 U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Docket No. 50-312 Rancho Seco Nuclear Generating Station, Unit No. 1

Dear Mr. Reid:

On October 5,1979, the Sacramento Municipal U?.ility District provided you with information concerning the safety grade anticipatory reactor trip to be installed at Rancho Seco Unit No.1.

In that letter we indicated that we felt this trip could be installed within 26 weeks of design approval. Your letter of December 20, 1979, provided approval of our preliminary design.

It has been determined that the equipment being added to the

~

re, actor protection system cabinets is of sufficient mass to require a new seismic analysis of these cabinets. We presently estimate 20 wee _ks for the. completion of this seismic analysis and will, therefore, be unable to install this equipment until that time.

We still intend to install this modification during the first outage of sufficient duration following completion of this analysis.

As requested in your letter of December 20, 1979, the District will provide the additional information required in sufficient time to allow staff approval of the final design prior to system operation.

If you have any further questions on this matter, please advise.