. . . - . .._ .- . - li: .L.
- .L
-
i.
ur
Q
4,,
UNITED STATES
NUCLEAR REGULATORY COMMISSION
o
$
E
REGION 11
'
'#
o
101 MARIETTA ST., N.W SUITE 3100
l
ATLANTA, GEORGIA 30303
.....
MAR 2 81980
In Reply Refer To:
RII:DRQ
50-302/79-55
Flori a Power Corporation
ATTN:
J. A. Hancock, Director
Nuclear Operations
P. O. Box 14042, Mail Stop C-4
St. Petersburg, FL 33733
Gentlemen:
This refers to the inspection conducted by D. R. Quick of this office on December 10
through 14, 1979 of activities authorized by NRC Operating License No. DPR-72 for the
!
Crystal River facility, and to the discussion of our findings held with D. C. Poole
at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the enclosed
inspection report. Within these areas, the inspection consisted of selective exam-
inations of procedures and representative records, interviews with personnel, and
observations by the inspector.
We have examined actions you have taken with regard to previously reported unre-
solved items.
The status of these items is diseassed in the enclosed report.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements. This item and references
to pertinent requirements are listed in the Notice of Violation enclosed herewith
as Appendix A.
This notice is sent to you pursuant to the provisions of Section
2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-
tions.
Section 2.201 requires you to submit to this office, within 20 days of
your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you and the results achieved; (2)
corrective steps which will be taken to avoid further noncompliacce; and (3) the
date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title
10, Code of Federal Regulations, a copy of this letter end the enclosed inspection
report will be placed in the NRC's Public Document Room. If this report contains
any information that you (or your contractor) believe to be proprietary, it is
necessary that you make a written application within 20 days to this office to
withhold such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is claimed that
the information is proprietary, and should be prepared so that proprietary
information identified in the app 1! cation is contained in a separate part of the
document.
If we do not hear from you in this regard within the specified period,
the report will be placed in the Public Document Room.
8006060 d
G
5
-
- - ~ . - - - - . . . - . . - - - . . . .
. .
..
-
'
.
.
)
j
Florida Power Corporation
-2-
MAR 2 81980
Should you have any questions concerning this letter, we will be glad to discuss
them with you.
Sincerely,
g. C.
R. C. L wis, Acting Chief
Reactor Operations and Nuclear
Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-302/79-55
cc w/ enc 1:
D. C. Poole
Nuclect Plant Manager
P. O. Box 1240
Crystal River, FL 32629
.