ML19322A649

From kanterella
Jump to navigation Jump to search
Testing & Startup Insp Repts 50-269/72-02,50-270/72-01 & 50-287/72-01 on 720222-25 & 29.Noncompliance Noted:Gauges Used for Determining Jacking Pressures Not Calibr & Inadequate Review of QA Program
ML19322A649
Person / Time
Site: Oconee  
Issue date: 04/19/1972
From: Moseley N, Murphy C, Warnick R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19322A643 List:
References
50-269-72-02, 50-269-72-2, 50-270-72-01, 50-270-72-1, 50-287-72-01, 50-287-72-1, NUDOCS 7911210712
Download: ML19322A649 (16)


See also: IR 05000269/1972002

Text

e

.

.

4 :e (

e

UNITED STATES

$

~E' [

,*

ATOMIC ENERGY COMMISSION

.

'

oiv SION OF COMPLIANCE

i .j

e'

.

'

REGION ll - Suit E 818

^

g

230 PE AC HT REE ST REET, NORT HWEST

$p

9

AT LANT A. GEORGI A 30303

4r

TESTING AND STARTUP INSPECTION REPORT

C0 Report Nos. 50-269/72-2, 50-270/72-1, and 50-287/72-1

Duke Power Company

Oconee 1, 2, and 3

Docket Nos. 50-269,270 and 287, License Nos. CPPR-33,34 and 35

Category: A3/B1, A2, A2

Type of Licensee: PWR 2452 Mw(e), B&W

Type of Inspection: Routine, Unannounced

Dates of Inspection: February 22-25, 1972

February 29, 1972

Dates of Previous Inspection: January 18-21, 1972 (Unit 1)

December 7-10, 1971 (Units 2 and 3)

Princiral Tec,ector:

~7

/

.3 7k

C. E. Mur'phyi Reactor Inspector (Testing

Dat(

and Startup Unit)

Accompanying Inspectors:

9-/ 9-78

R.' F. Warnick, Reactor Inspector

Date

(Testing and Startup)

Y-?w

F. Jape, React M Inspector

Date

~

(Testing and Startup)

V

l9 7%

s

N. C. Moseley, Senior 3dactor Inspector

Date'

(Testing and Startup)

Other Accompanying Personnel: None

j

Reviewed By;

I//9//2

N.C.Moselef,Seniorkeactor[nspector

Date

(Testing and Startup Unit)

Proprietary Information: None

Nen 22 o Jt7

.-.

.. -

- - - .

.

.--

-

. . - .

.

.

O

.

/]'

C0 Report Nos. 50-269/72-2,270,287/72-1

-2-

SECTION I

Enforcement Action

A.

Noncompliance Items

1.

Contrary to the requirements of Criterion XII of Appendix B

to 10 CFR 50, Section 2621 of ACI-318-63, and Section 5B.2.8.2

of the FSAR gauges used in determining jacking pressures had not

been calibrated.

Calibration of these gauges after completion

of stressing operations indicated that the calibration was not

maintained within specified limits.

(See Section II, Paragraph 4)

2.

Contrary to the requirements of Criterion VI of Appendix B

to 10 CFR 50, stressing of the tendons was performed using

a procedure that had been revised but had not been approved.

,

(See Section II, Paragraph 4)

3.

Contrary to the requirements of Criterion XI of Appendix B

to 10 CFR 50, and the licensee's Stressing Procedure N4, daily

calibration checks were not made of pressure gauges used in

tensioning.

(See Section II, Paragraph 4)

4.

Contrary to the requirements of Criterion XVI of Appendix B

to 10 CFR 50 and to Section 2621 of ACI 318-63 and to Section

5B.2.8.2 of the FSAR the cause of discrepancies between measured

and calculated values of elongation exceeding 5% were not corrected.

(See Section II, Faragraph 4)

5.

Contrary to the requirements of Section 5.4.1.2, of the FSAR

and Section 2606 (a) 1, of ACI-318-63, tendons may have been

stressed in excess of 0.8 f's during stressing operations and were

stressed to values exceeding 0.7 f's for post-tensioning tendons

immediately after anchoring.

(See Section II, Paragraph 4)

6.

Contrary to the requirements of Criterion II of Appendix B to

10 CFR 50, ~1nagement- did not regularly review the status and

adequacy or that ps:.c of the quality assurance program associated

with the tendon it.sta11ation.

B.

Nonconformance Items

None

C.

Safety Items

None

s-

!

,

,

.__

.

. _ . .

.

.

.

.

.

'

~

-3-

CO Report No. 50-269/72-2,270,287/72-l

Licensee Action on Previously Identified Enforcement Matters

1.

The licensce's response to the Compliance letter discussing the

inspection conducted-on September 7-10, 1971, was unacceptable.1/

The deficiencies were discussed with Lee and Thies during this

inspection. A supplemental letter will be sent by DPC in an effort

to resolve the deficiencies.

2.

Corrective action has not been completed on items identified in

CO Report Nos. 50-269/71-9, 71-10, 71-11 and 72-1.

Unresolved Items

Correction of hot functional functional tast procedures.

(See Section

III, Paragraph 4)

Status of Previously Reported Unresolved Items

1.

Failure to document corrective action.1/ Action not completed.

2.

Flowmeter error analyses and tests.2/ Action not completed.

3.

Verification of loop backflow analysis.2/ Action not completed.

4.

Effect of rerouting cable on preoperational testing.3/ Action

not completed.

5.

Valve wall measurements.$/ Action not completed.

(See Section II,

Paragraph 6)

Unusual Occurrences

Shrink cracks in stems of instrumentation and drain valves.2/ (gee

Section II, Paragraph 5)

1/ CO Report No. 50-269/71-9

2/ Co Report No. 50-269/71-10

3/ Co Report No. 50-269/71-11

4/ C0 Report No. 50-269/71-7

l

m.

!

l

I

=

_ __

.

,-

CO Report No. 50-269/72-2,270,287/72-1

-4-

Persons Contacted

W. S. Lee - Senior Vice President, Engineering and Construction

A. C. Thies - Senior Vice President, Production and Transmission

R. L. Dick - Vice Presidnet, Construction

J. R. Wells - Quality Assurance Engineer, DPC

J. E. Smith - Plant Superintendent

J. W. Hampton - Assistant Superintendent

L. E. Summerlin - Staff Engineer

K. S. Canady - Nuclear Engineer, DPC Steam Production Department

M. D. McIntosh - Operating Engineer

R. M. Koehler - Technical Support Engineer

E. D. Brown - Maintenance Supervisor

j

D. G. Beam - Project Manager

D. L. Freeze - Principal Field Engineer

l

W. J. Watson - Assistant Field Engineer, Civil

S. B. Hager - Senior Design Engineer, Civil

i

Management Interview

A management interview was held on February 25, 1972, and was attended

by Hampton, Canady, Beam, Freeze, Ansell, Brown, Koehler, McIntosh,

and Summerlin.

A second 2anagement interview was held on February 29, 1972, with

Thies ana Lee.

The following items were discussed during the February 25 meeting:

'

1.

Reactor building tendon installation and tensioning, Unit 2 -

Murphy advised Beam and Freeze that in his review of ;he records

and in discussions with QC and engineering personnel, he had found

numerous deficiencies in the tensioning of the tendons.

He further

stated that in his telecon discussion with Hager, he had been advised

that DPC would issue a report, similar to that issued for Unit 1,

'

that would discuss the effects of all installation deficiencies

on the integrity of the building.

The inspector also-stated that

it was his understanding that stressing procedure N4 would be revised

for Unit 3 to require documentation of the daily pressure gauge

checks.

Beam advised the inspector that these understanding were

correct.

(See Section II, Paragraph 4)

2.

Preoperational Test Guide - The principal inspector stated that it was his

understanding that the " Guide for Conducting the Oconee Preoperational

Test Program" would be revised to reflect Compliance comments.

Hampton agreed that this understanding was correct.

(See Section

II, Paragraph 9)

~

.

._

_

_.

. _ _ _ .

__

)

}

,

4

7)

C0 report no. 50-269/72-270,287/72-1

-5-

-

/

,

3.

Compliance comments on test procedures - The principal inspector advised

Hampton that because tests were being conducted almost as soon as

the approved test procedures were being issued, Compliance would in

many cases give comments by telephone.

In turn, Compliance would

want some type of confirmation of the disposition of the comments.

Hampton stated that this would be done either by. sending a note confirming

'

the comments or by sending a revised copy of the procedure.

4.

The inspector discussed weaknesses noted in a review of preoperational

'

test procedures.

The comments had previously been discussed and

resolved in an earlier discussion with Hampton, McIntosh, and Koehler

but were repeated here for the record.

(See Section IV, Paragraph 1 and 8)

5.

In response to Murphy's questions, Hampton stated that DPC would

incorporate the Compliance comments on the following procedures:

TP 600/4

TP 600/26

TP 600/5

TP 600/22

TP 600/25

(See Section III, Paragraph 4)

Murphy advised Canady that because of the difficulties experienced

. . .

with the main coolant pump vibration and with flow measurement

fluctuations, Compliance would want to review the evaluations made

by DPC of the performance of the reactor coolant pumps.

Compliance

will be interested in one, two and three-pump operation as well

as the four-pump operation.

Canady agreed that the evaluations

would be made available.

(See Section II, Paragraph 5)

7.

Murphy and Moseley met with Lee and Thies on February 29, 1971,

to discuss the changes made by DPC as a result of the November.3,

1

1971, meeting / to improve the implementation of the QA program.

These changes included:

a.

The addition of two additonal construction QC inspectors,

b.

Wells had been transferred to Charlotte and devotes almost full

time to quality assurance.

An engineer reporting directly to W. H. Owen, Vice President,

c.

Engineering, has been given full-time responsibility for the

DPC quality assurance manual.

l

.

If C0 Report No. 50-269/71-9

l

,_,

L

--

-

,

,

CO Report No. 50-2 69/72-2,270,287/72-1

-6-

g

J

d.

On each site visit, Lee audits at least one QA activity.

e.

Most sections of the DPC QA manual are being backfitted to

Oconee.

f.

The Oconee welding procedures have been rewritten and requalified.

Southwest Research Institute was retained to review the procedures

and procedure qualifications.

An outside consultant, Helmut Theilsch,

has been retained to determine the effects of the welding deficiencies

on the integrity of the piping and structural systems.

g.

Thies has held meetings with operating supervisors to get across

to them management's concerns for the test program.

,

h.

Smith has held two working sessions with operating personnel

i

to discuss the conduct of tests, test preparation and audits.

He has used specific problems to 11?ustrate what can go wrong.

1.

A complete review has been made of approved tests.

The Site

Review Committee (SRC) is reviewing all new procedures and revisions.

j. A new test guide has been published.

k.

A new procedure for handling drawings has been implemented.

1.

A steam production department engineer has been assigned to the

plant to assist the operating group in planning and scheduling.

m.

A program for retesting to assure correction of deficiencies

is being instituted.

4

' .'

,

4

'

_ _ - .

'.

.

CO Report No. 50-269/72-2,270,287/72-1

~7-

,~s

.

SECTION II

Prepared by:

C. E. Murphy, Reactor

Inspector

' ADDITIONAL SUBJECTS INSPECTED, NOT IDENTIFIED IN SECTION I, WHERE NO

DEFICIENCIES OR UNRESOLVED ITEMS WERE FOUND

1.

General

Unit 1

The four reactor coolant pumps have been returned from the manufacturer

and reinstalled. Hot functional testing is in progress.

DPC now

expects to load fuel in May 1972.

Unit 2

Installation of the reactor coolant boundary piping is complete,

and all reactor coolant pump motors have been installed. DPC

now expects to load fuel in December 1972.

Unit 3

Installation of the reactor building liner plate is complete.

Installation and fitup of the reactor coolant piping is in progress.

DPC expects to load fuel in December 1973.

2.

Unit 2

The inspector reviewed the records related to the installation of

the reactor coolant boundary piping and made a visual inspection of

a portion of the completed installation. No deficiencies were

observed.

3.

Unit 3

The inspector reviewed records related to the installation of the

reactor building liner plate and made a visual inspection of portions

of the completed installation.

No deficiencies were observed.

DETAILS OF SUBJECTS DISCUSSED IN SECTION I

4.

Reactor Building Tendon Installation and Tensioning - Unit 2

The inspector reviewed the quality assurance records relating to

,

l

the installation of the reactor building tendons.

These included

!

l

l

r - -

..

.

gs

CO Report No. 50-269/72-2,270,287/72-1

-8-

the tendon pulling. cards, tendon.buttonheading cards, tendon stressing

cards, pressure gauge calibration test records and the stressing

procedure, N4.

The inspector also discussed'the installation with

the Quality Control Engineer, Watson.

No deficiencies were noted

in the tendon pulling and buttonheading records.

The review of the other records and the discussions with Watson,

however, revealed the following deficiencies in the stressing operations:

a.

The FSAR, Section 5.B.2.8.2, states, in part, "The gauge.(for

measuring jacking forces) indicates the preosure within the jack

within plus or minus two percent.

Force-jack pressure gauge

or dynamometer combinations are calibrated against precise

standards before application of prestressing force."

"The presence of two gauges, one gauge on the pump and one

gauge on the jack, provides a means to maintain a constant

check on the calibration of the gauges. . . . During stressing,

records are made of elongations as well as pressures obtained.

Jack-dynamometer or gauge combinations are checked against

elongations of the tendons and the cause of any discrepancy

exceeding plus or minus 5 percent of that corrected, and if

caused by differences in load elongations from averages, it is

so documented. Calibration of the' jack-dynamometer or pressure

gauge combinations are maintained accurate within the above

limits and, if requested by Duke Power, recalibrated or newly

calibrated combinations substituted during and at the end of the

tensioning operations."

Section 5.1.2 of the FSAR states, in part, "The structure is designed

and constructed in accordance with design criteria based upon

ACS 318-63."

The calibration test data for the pressure gauges used in

the stressing operations are summarized in the following table:

Gauge

Initial

As Left

Final Test'

As Found

No.

Test Date

Error *

Date

Error *

G223

1/17/72

-200 psi


G224

7/10/71

0

1/18/72

0

G225

7/12/71

0

1/18/72

0

G227

7/10/71

0


-

G228

7/10/71

0

1/18/72

-500

G230

1/17/72

+300


-

G231

--

1/18/72

0

G236

7/26/71

50

-=

G238

1/18/72

0


G239

7/26/71

0

1/18/72

-200

G240

7/10/71

0

1/17/72

0

G242

7/26/71

0

--==

i

.-

--

.

.

S

7~

CO Report No. 50-269/72-2,270,287/72-1

-9-

  • Error at 7500 psig. Allowed error is +150 psig

Contrary to the requirements of the FSAR,. Appendix B to 10 CFR 50, and to ACI 318-63, the above data indicates that seven of

the gauges did not receive either the inital test or the final

calibration test.

Also contrary to the requirements of the

FSAR, four the the gauges did not meet the calibration requirements

at the conclusion of the stressing operations. The stressing

procedure, N4, requires in Section C that the readings of the

two pressure gauges. associated with each jack be compared

once each morning and once each afternoon and that the readings

should coincide within 100 psi.

There was no documantation,

however, to confirm that these checks had been made.

Also,

no records were maintained as to which gauges were used with

each jack.

The final calibration checks would indicate, however,

that the required daily checks had not been made.

Watson could

not verify with any certainty that the stressing crews had made

the checks.

b.

Section 5.4.1.2 of the FSAR states, in part, "The procedure

required the measured temporary jacking force, for a single

tendon to approach, but not exceed, 850 kips (0.8f's).

Thus

the limits set by ACI-318-63 2606 (a) 1, and of the prestressing

system supplier were observed." The requirements of ACI 318-63

2606 (a) 2 states that fs (tendon stress) should not exceed 0.7

f's for posttensioning tendons i= mediately after anchoring."

Contrary to these requirements, calculations by the inspector

using the maximum pressure, which could have been applied for

gauges that were not within the required calibration, indicate

that the jacking. force could have exceeded 0.80 f's and the fs

could have exceeded 0.7f's after anchoring.

In. response to the

inspector's questions, Watson stated that no records were main-

tained of the jack-pressure gauge combinations and, therefore, he

could not correlate the tendon elongation deviations with pressure

i

gauge calibrations.

The results of the stressing operations are summarized in the

table below.

One hundred fifty-three, or 16% of the tendons

had elongations which deviated from the calculated elongations

by more than the five percent required by the FSAR, Section

5.B.2.8.2 and by ACI 318-63-2621 (a) .

This discrepancy was not

documented in the Engineering Quality Assurance Problem list.

l

_

-,

.

'

.

CO Report No. 50-269/72-2,270,287/72-1

-10-

, . ~ ,

)

Deviations.from Calibrated Values (%)

No. of Tendons

4

Negative Devistions greater than 5%

-9.52 to -8.00

13

.

-7.99 to -7.00

7

-6.99 to -6.00

9

-5.99 to -5.01

13

Subtotal of - deviations

42

Positive Deviation greater than 5%

5.01 to 5.99

38

6.00 to 6.99

37

7.00 to 7.99

9

8.00 to 8.99

6

9.00 to 9.99

3

10.00 to 14.99

13

15.00 to 19.99

3

22.05

_1_

Subtotal of + deviations

110

Unknown Deviations-

1

Deviations between +5% and -5%

817

c.

In discussing the deviations with Watson, the inspector was

advised by Watson that he did not consider the number of deviations

significant since only 17 tendons.were involved.

When the

inspector questioned Watson about the basis for this aumber,

Watson stated that only the deviations exceeding 10% of

calculated were considered significant.

Watson showed the

inspector a copy of procedure N4 that gave this figure as the

acceptable limit. When the inspector examined the procedure,

he found that it was an unapproved revision.

Watson ca7.2ed

Hager by telephone for clarification and was told that th-

,

10% value was incorrect.

In discussions with Freeze and Beam,

the inspector determined that they were unaware of the number

of deficiencies involved in the tendon tensioning or that

unapproved. procedure had been used. The inspector advised them

that the use of an unapproved procedure appeared to be contrary

to the requirements of Appendix B to 10 CFR 50.

i

o

.

r

.

.

'

.

i

g-)

C0 Report No. 50-269/72-2,270l287/72-1

-11-

The inspector discussed the deficiencies observed in the tendon

tensioning program.in the exit interview and advised Beam that

the matter would be discussed in.the Compliance. letter to

DFC discussing the results of the inspection.

The inspector

also discussed.the deficiencies by telecon-with.Hager.. . Eager

advised the inspector that DPC planned to issue.a report similar

to that issued for Unit 1, discussing the effects of the

deficiencies _upon containment integrity.

5.

Reactor Coolant Pumps

Smith advised the inspector that the problem of excessive vibration

of the main coolant pumps appeared to be resolved.

In response

to the inspector's questions, he stated that vibrations were greater

when only one pump was in operation.

The addition of each pump

brought about a reduction in vibration of the operating pumps.

He

also stated that apparent fluctuations in coolant flow could be

due to measurement difficulties rather than actual flow fluctuations.

He stated that the fluctuations were greater with single pump

operation than with multiple pumps.

He stated that evaluations

of both problems were continuing and that DPC would advise the

inspector of the results of these evaluations.

6.

Valve Walls

l

Lee and Thies advised the inspectors that the walls of 51 valves

had been examined.

This included all the Crane-Chapman valves larger

than one inch in the Unit 1 reactor coolant and emergency core

cooling systems. All valves met the thickness. requirements specified

in the tables in B16.5.

Seventy-five valves fabricated by other

manufacturers have not been measured. Lee stated.that he planned

no further action without direction from Compliance. Moseley advised

Lee that the information relating to the wall measurements would be

sent to headquarters with a request for clarification as to what

would be required.

7.

Pipe and Fitting Traceability

Lee advised Nbseley and Murphy that 16 sections of pipe and pipe

fittings have been identified in the Unit 1 reactor coolant system

boundary and the makeup systems that do not have complete traceability.

The failure of these components would cause a loss of coolant in

excess of the makeup capability. Moseley told Lee that Compliance

would review the information presented and advise Lee of Compliance's

position on traceability requirements.

'

l

~

1

i

l

I

,

_

.

.

.

i

CO Report No. 50-269/72-2,270,287/72-1

-12-

[_,)

.

l

8.

Valve Stem Failure

Smith advised Murphy that the testing program had revealed cracking

in the valve stems of. instrumentation and drain valves supplied by

the Velan Company. All the stems of the affected valves (approximately

3000 valves for the 3 units) will be replaced.1/

9.

Review of Test Guide

The principal inspector discussed his review of the " Guide for

Conducting the Oconee Preoperational Test Program" with Smith.

Smith agreed that, because of the deficiencie that had been observed

in implementation of the licensee's test program, the guide would

be revised to require that the test coordinator reference FSAR re-

quirements in the acceptance criteria of the appropriate test

procedures.

The section heads also would be required to verify

that the FSAR requirements had been met when they reviewed the

test results.

1/

Inquiry Reports. 50-269/72-1, 270/72-1, 287/72-1

.

d

.

.

.

/ 'N,

CO Report No. 50-269/72-2,270,287/72-1

-13-

- . _ _ .

1

SECTION III

Prepared By:

R. F. Warnick, Reactor

Inspector

ADDITIONAL SUBJECTS INSPECTED, NOT IDENTTFIED IN SECTION I, WHERE NO

DEFICIENCIES OR UNRESOLVED ITEMS WERE FOUND

1.

General

,

Summerlin prepared a summary of the preoperational and startup test

programs.

The status as of February 22, 1972, is as follows:

Total

Approved

Tests

Results Approved

Number

Procedures

Completed

Tests Signed Off

Tests Before Hct

Functionals

380

380 (100%)

380 (100%)

380 (100%)

Tests During Hot

,Functionals

173

159 (92%)

61

(35%)

48 (28%)

Tests Prior To

Core Loading

131

88 (67%)

58

(44%)

44 (34%)

^

Total Precperational

Tests

684

627 (92%)

499 (73%)

472 (69%)

2.

Preoperational Test. Program - Procedure Review

TP-1B-600-1, Revision 2, Controlling Procedure For Hot Functional

Testing.

TP-1B-600-8, Revision 2, Component Cooling System Operational Test.

1

TP-1A-600-15, Revision 2, Control Rod Drive System Operational Test.

TP-1B-600-21, Revision 4, Reactor Coolant System Hydrogen Addition

Test.

3.

Preoperational Test Program - Evaluation of Test Results

IP-1A-150-2, Revision 5, Reactor Building Structural Integrity

Test.

TP-1A-160-2, Revision 1, Reactor Building Coolers Functional

Test.

i

..J

.-

. _ _

_

. _ _ _ _ _

.

.

(

C0 Report No. 50-269/72-2,2707287/72-1

-14-

,

TP-1A-200-ll, Reactor Coolant Flow Instrument Calibration.

TP-1B-200-17, Reactor Coolant System Pressurizer Level

'

Verification Test.

TP-1A-200-27, Reactor Level Instrumentation and Calibration

TP-1A-330-313, Control Rod Drive System DC Breaker Trip Test.

DETAILS OF SUBJECTS DISCUSSED IN SECTION I

4.

Comments on Preoperational Test Procedures

The inspector reviewed nine hot functional test procedures, which

are part of the preoperational test program, and discussed comments

on five of them with Hampton, McIntosh, and Koehler.

The procedures,

the inspector's comments, and DPC's responses are as follows:

TP-1B-600-4, Revision 2, Chemical Addition and Sampling System

a.

Operational Test.

One of the test criteria states, " Boron concentration A ppm < 500 ppm."

The inspector questioned what was intended to be proved by tEis

part of the test. He told Hampton.that it would be necessary

to control boron concentration to much lower tolerances.

Hampton agreed to clarify procedural steps in Section 12.0, correct

mistakes in the acceptance criteria, and clarify the acceptance

criteria limits for changes in boron concentration.

b.

TP-1B-600-5, Revision 3, Reactor Coolant System Chemistry Test.

Some of the acceptance criteria are not sufficiently definitive.

The test method does not agree with the test procedure.

Some

of the procedural steps refer to acceptance criteria that have

not been specified.

Hampton agreed to revise this procedure and to rewrite the

acceptance criteria in language that a reactor operator can

understand and easily follow.

c.

TP-1B-600,22, -Revision 3, Degassification Test

This procedure does not specify whether or not the pressurizer

will be degassed.

Hampton indicated this would be clarified.

'

-

k

-

.

.

.

. ,

(]

CO Report No. 50-269/72-2,270,287/72-1

-15-

i

d.

TP-1C-600-25, OTSG Shell Surface Temperature Test

,

There are no acceptance criteria in the test procedure.

Koehler and McIntosh indicated B&W would evaluate the test

results.

In addition, they stated the test would not be run

on Unit 2.

They felt acceptance criteria were not needed.

The inspector indicated that any test important enough to be

included in the hot functional tests required acceptance criteria

to be complete.

e.

TP-1A-600-26, 1500 PSIG High Pressure Injection Engineered

Safeguard Test

"The inspector found this test deficient in that not all of the

engineered safeguards functions in high pressure injection system

are being tested.

4

Hampton indicated that he ' thought all high pressure injection

engineered safeguards functions were being tested. Warnick

enumerated the deficient items. Not all have been satisfactorily

resolved.

_

.

.

L

_

_

.

.

.

.

CO Report No. 50-26 9/72-2,270,287/R2-L

-16-

,3

i

SECTION IV

Prepared By:

F. Jape, Reactor Inspector

ADDITIONAL SUBJECTS INSPECTED, NOT IDENTIFIED IN SECTION I, WHERE NO

DEFICIENCIES OR UNRESOLVED ITEMS WERE FOUND

1.

Preoperational Testing

Preoperational test procedures were reviewed to evaluate the adequacy

of the program. The following seven tests were reviewed and either

minor comment or no comment was noted:

1.

TP-1A-600-10, RCS Hot Leakage. Test.

2.

TP-1A-600-11, Emergency Feed System and Steaa Generator Control Test

3.

TP-1B-600-12, Pressurizer Operational Test

4.

TP-1B-600-13, RCS Instrument Hot Operation Functional Test

5.

TP-1A-600-23, Emergency Operation of Nuclear Steam Supply System

6.

TP-lC-600-24, First-of-a-Kind Test Reactor Vessel and OTSG Support

Flange Temperatures, Oconee Unit 1

7.

TP-1B-270-33, Main Steam Relief Valve Test

i

2.

Evaluation of Test Results

'

The results of ten preoperational tests were reviewed. Minor comments

,

(i

were noted on four of these. The comments were discussed r?*h Duke

personnel and'all were resolved satisfactorily.

The ter,ta that sorn

reviewed are:

1.

TP-1A-150-4, RB Hatch Leak Testa

2.

TP-1A-150-3, RB Integrated Leak Eate Test

3.

TP-1B-230-7D, Gaseous Waste. Disposal System Functional Test

4.

TP-1A-620-9, Keowee Functional Tests of Auto-Emergancy Startup

of Keowee from Oconee

5.

TP-1B-340-8, Control Rod Drive System Dilute Contral Adjustment

6.

TP-1B-250-5, HPSW System Functional and Operational Test

7.

IP-1B-202-2A, HPI Letdown Line Hydro (Red Section}

8.

TP-1B-202-2C, HP Letdown Line Hydro

9.

TP-1B-202-2, HP System Hydro Test (Fuel Return - C range, Red,

Green,, Blue, and Yellow Sections)

10.

IP-1B-200-6, Pressurizer Heater and Controls Elect:rical Test

DETAILS OF SUBJECTS DISCUSSED IN SECTION I

None

4

4

.N-

, _ .