LER 78-162/03L-0:on 771212,containment Airlock Not Pressure Tested for 771212 Entry.Caused by Failure to Follow Prescribed procedures.SP-443 Revised,Requiring Daily Airlock Pressure Test Regardless of Entry
ML19317G140
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 01/18/1978
From: Stewart W
FLORIDA POWER CORP.
To:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
Shared Package
ML19317G138 List:
References
LER-78-162-03L, LER-78-162-3L, NUDOCS 8002270846
Download: ML19317G140 (2)


Text

- . . - -

j.

-l .

'O

  • penc Fon M 364 gy,y g g

. .t .*

U.S. NUCLCAR aCcutAtoRY CoMMISS80N LICENSEE EVENT REPORT EXHIBIT A coarmot stoco 1 I 11 I I .IQ tet: Ass mur on tves att nacuiano i~,oamaries .

l 1(1 ;1 gg g -; g g laTO lF 1 LI Q Rl P13 Igl0 t 01- l 0 l ..ca Or 0m -; 0;0 l ;0 ; O ggg _4 g j

.. . .m. wo. .. u ... a .. 6,ci%.. ... . , . . , . ,

com 7 1o1 1 C &@l oi.a 5;01Doca.r%bv98 -;0
3;0 12 gl 1; 2,1 27e. ed 444*f0.Tg

! i 7 g!O i 111817t8l@

i. it 1

.g.C rC.t8 sJ 3 4 6a aveur otscairvies ano paes4sta ecuscqusNers g ,Upon review of completed survei ance Procedure SP-430, Containment Entry, ,

, it was discovered that contrary to Tech Spec Surveillance 4.6.1.3.a, the ,

. g , Contm4mant airlock was not pressure tested for an entry on 12 Dec.1977. ;

m , Redundancy NA. No safety implications as results of Airlock Pressure Test ,

,, g , , on 15 Decent:er 1977 was satisfactory. .econd S occurrence as reported by ,

t

. ,,,,,,1ER~77-119. l I

. rTTT1 1

'US" *lo's sNc'M ecwas.s? =st i s!NYCs IS I D[@ (AJ@ l A l@ l ZlZ l Z jZ l ZI j@ s's5'E*:[Zj@ [Zj @ .

I

[f_L.]

,, , . .. u

. . . . . .. ece,.. a . . . ,

. . . ..o, u

O ,ay.;;; .. .v I yI9 I L-j 1 1..i %'I'2 i 1-1 I6 I L'_J u L,, 8 L9.J u

_,, u u  :. .. ,, ., .,

@ Wne ERi , ' Sir' , S *2.%;if .U.n', ..h"i ,2C:?R' ,. -

LGjg Q.Jg l>Zl@ L,Zj@ ,1 01 010 P0J [YJ@ l N !g i Z(@ [ Zl 919 l 9[Q u . . . .a .s ., ., ., -

cause cascaterien amo ccanacn.e ac tess The cause of this event was to the failure to perform prescribed ,

gg

, , , , , , procedures, in that the Master Surveillance Plan,- SP-443, requires an ,

, Airlock Pressure Test upon each Containment entry. SP-443 has been revised,

,,,,, , to require a Daily Airlock Pressure Test regardless of entry. ,

f ii i i

's.'W.7  % :ws. er-i.searus @ Essi=**  : s-:7.i , :in...es @

ITT's 1 [Ej@ l 014 I 6 l@l NA I I r s ,j,,,,, ,ga.,,, i: >> L.i -A_J@l Coreliance review se

..s ., , .. .- soc m.,s .. ..am @

W, .

'J @. :...a mL.Z.J@l NA @ I L.,_.. i ,,

I NA i

-- . ow tuwot.s as.oes..s tvet it s. .* *,'QN NA (

i 1010 3 Ol@L_J@l" a

,....m ,,,

L1.1. ! l 0 I e di.  ! O!@l a' s'!issese.='es@ NA l

(y,s. :.,=," .,.,e[o m.a. g FT71 L1J@l10 n to i

7 8 9

.,;. , 'i.';...... s @ sac.u w f fI Ifff tt8 tt i I:..I .aI. [3[6l ..

NA s.4..sc...g.iata

  • > a e._--. g "an. " m _.9,.c.;g (813) 866-4159 (SEE ATTACHED SUPPLEMENTARY INFORMATION SHEET)

} ,

. 80.02 270 l

s SUPPLEMENTA13 INIURMATION

r. Report No.: 50-302/77-1C2/03L-0
2. Facility: Crystal River Unit #3 *
3. Report Date: 18 January 1978
4. Occurrence Date: 12 December 1977 (discovered 29 December 1977)
5. Identification of occurrecca:

The failure to demonstrate the operability of both Conts'=nt airlocks contrary to Technical Specification Surveillance 4.6.1.3.a.

6. Conditions Prior to occurrence:

Mode 1 operation.

7. Description of Occurrence:

While reviewing the complaced Containment Entry Surveillance Procedure SP-430, ',

it was discovered that the Data Sheet #1 (Airlock Pressure Test) had not been .

completed for a Containment entry on 12 December 1977. Further review indicated that the Containment was entered on 15 December 1977 and the Airlock Pressure Test was satisfactorily performed.

Designation of Apparent Carse:

The cause of this occurrence was the failure to follow prescribed procedures, in that SP-433 requires Airlock Pressure Test be performed daily in Modes 1-4 if the Containment has been entered.

9. Analysis of occurrence:

There were no safety implications as the results of the complaced Airlock Pressure Test on 15 December 1977 were satisfactory.

10. Corrective Action:

A revision to the Master Surveillance Plan, SP-433, requiring an Airlock Pressure Test be performed daily regardless of Containment entry, has been entered.

11. Failure Data:

This is the second occurrence of missed Airlock Pressure Test as reported by LER 77-119.