Forwards IE Circular 80-05, Emergency Diesel Generator Lubricating Oil Addition & Onsite Supply. No Written Response Required
ML19309C610
Person / Time
Site: 05000516, 05000517, Shoreham  File:Long Island Lighting Company icon.png
Issue date: 04/01/1980
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Wofford A
LONG ISLAND LIGHTING CO.
References
NUDOCS 8004090063
Download: ML19309C610 (1)


Text

0

~

~

~ ~~

~^~

~

g.

yg E(

'o,,

UNITED STATES NUCLEAR REGULATORY COMMISSION o

c e

REGION 1

%(.' W 3....,e#

631 PARK AVENUE xtwo oP PnusstA, PENNSYLVANIA 19406 4cril 1, 1980 Docket Nos. 50-322 50-516 50-517 Long Island Lighting Company ATTN:

Mr. Andrew W. Wofford Vice President 175 East Old Country Road Hicksville, New York 11801 Gentlemen:

The enclosed IE Circular No. 80-05, " Emergency Diesel-Generator Lubricating 011 Addition and Onsite Supply," is forwarded to you for information.

No written response is required.

If you desire additional information regarding this matter, please contact this office.

Sincerely, L

Boyce H. Grier

" Director

Enclosures:

1.

IE Circular No. 80-05 2.

List of Recently Issued Circulars CONTACT:

D. L. Caphton (215-337-5254) cc w/encls:

J. P. Novarro, Project Manager Edward M. Barrett, Esquire Edward J. Walsh, Esquire T. F. Gerecke, Manager, Engineering QA Department 80 0 4.0 90 C6'S

4 ENCLOSURE 1 SSINS No.: 6830 Accession No.:

UNITED STATES 7912190691 NdCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 IE Circular No. 80-05 Date:

April 1, 1980 Page 1 of 3 EMERGENCY DIESEL-GENERATOR LUBRICATING OIL ADDITION AND ONSITE SUPPLY Description of Circumstances:

On January 17, 1980, the Kewaunee Nuclear Power Plant experienced a partial loss of offsite power which resulted 10 a turbine trip, reactor trip, and one emergency diesel engine driven generator (diesel generator or D/G) supplying power to one engineered safeguards bus.

Offsite power continued to supply the other engineered safeguards bus.

During the day before, on 1-16-80, this diese' generator had successfully completed a 24-hour loaded test run but had a low lube oil alarm condition with oil level 1/2-inch low.

The D/G was fully operational in this condition.

Before oil could be added on 1/17/80, the D/G was required for emergency power following the failure of the reserve auxiliary transformer.

The normal oil fill location could not be used while the D/G was operating.

The D/G fechnical Manual (TM) indicated that oil could be added with the engine running, but did not describe the method to be used.

Lube oil was added by pumping into the engine through a pipe that was assumed to be a lube oil line; this line was color coded in the TM and painted with the lube oil system color code.

Three barrels of oil were added via this line while the D/G was operating. After transferring the emergency bus to off site power through the tertiary auxiliary transformer the D/G was shut down. With the D/G shut down two more barrels of oil were added through this line without increasing the sump level.

Then two more barrels of oil were added through a.

different addition point and the 1e/e1 was restored to normal.

The following day a factory representative determined that the first five barrels of oil had been added to the engine air box through a mismarked (should I

have been color coded as an air line) drain connection.

Four and a half barrels of oil were drained out after which the diesel generator was satis-factorily test operated.

It is believed that the diesel engine could have -

been damaged had an engine start been attempted while the five barrels of oil were in the air box.

Further, it is noted tnat procedures for adding oil to the operating diesel engine were not available and that the personnel perform-ing the addition were not familiar with, nor trained on, how to add oil to a i

running engine or how to verify that oil had been properly added, l

IE Circular No. 80-05 Date:

April 1, 1980 Page 2 of 3 This event brought to light an additional problem which may be generic.

During the previous day's test run of the diesel generator lube oil consump-tion was approximately 3 gal /hr.

During the loss of power event, the licensee had three barrels (165 gallons) of lube oil available onsite.

The licensee's Technical Specifications require a seven day su> ply of fuel oil for one diesel gen-erator be available onsite.

To meet the intent af the Technical Specifications, a seven day supply of lube oil should also be available onsite.

The diesel engines are model 999-20 manufactured by the Electro-Motive Division of General Motors Corporation.

These diesel engiras use a 2 stroke cycle and lube oil consumption is normally higher than for the 4-stroke cycle diesel engines.

Vendor representatives and NRC consultants indicate that lube oil consumption rate varies with engine condition and load.

Further, the 3 gal /hr consumption rate is considered to be in the normal range.

Recommended Action for Licensee's Consideration:

All holders of operating licenses for nuclear power reactor facilities should be aware of the potential problems described above.

Because of the generic nature of these matters, it is recommended that the considerations identified above be reviewed at your facility in the following respects:

1.

Verify the existence and adequacy of procedures or instructions for adding lubricating oil to safety related equipment.

This should include the following:

a)

Whether or not, how and where lube oil can be added while the equipment is in operation, b)

Particular assurance that the wrong kind of oil is not inadvertently added to the lubricating oil system, and c)

That the expected rise in level occurs for each unit of lube oil added.

These operating procedures or instructions should be available locally in the area of the affected equipment.

2.

Verify that personnel are trained in such appros9d procedures and demon-strate an ability for using these procedures to adi oil while the D/G is operating and that they understand how to verify thct the proper amount of oil has been added.

3.

Verify that the color coded, or otherwise marked, lines associated with the diesel generator are correct and that the line or point for adding lube oil has been clearly identified.

i

IE Circular No. 80-05 Date:

April 1, 1980 Page 3 of 3 4.

Verify that appropriate procedures or instructions exist, and personnel are trained, on the proper addition of lube oil and the performance of maintenance during operation of other similar vital equipment.

5.

Determine the lube oil usage rate for each diesel engine under full load conditions including the rates considered to be excessive.

Provide adequate inventory of lubricating oil of the proper grade consistent with the highest usage emergency diesel generator (s) operating for the time period specified in the plant Technical Specifications for fuel oil supply.

When lube oil consumption rates become excessive, provisions should be included for overhaul of the diesel engine.

All holders of construction permits for nuclear power reactor facilities should be aware of the potential problems identified above and initiate appro-priate procedures prior to initial fuel loading.

No written response to this Circular is required.

If you require additional information regarding these matters, contact the Director of the appropriate NRC Regional Office.

4 l

ENCLOSURE 2 IE Circular No. 80-05 Date:

April 1, 1980 Page 1 of 1 RECENTLY ISSUED IE CIRCULARS Circular Subject First Date Issued To No.

of Issue 79-19 Loose Locking Devices 9/13/79 All Power Reactor Licensees on Ingersoll-Rand Pumps with an Operating License (OL) or Construction Permit (CP) 79-20 Failure of GTE Sylvania 9/24/79 All Power Reactor Licensees Relay, Type PM Bulletin with an OL or CP 7305, Catalog SU12-11-AC with a 120V AC Coil 79-21 Prevention of Unplanned 10/19/79 All Power Reactar Licensees Releases of Radioactivity with an OL cr CP 79-22 Stroke Times for Power 11/16/79 All Power Reactor Licensees Operated Relief Valves with an OL nr CP 79-23 Motor Starters and Con-11/26/79 All Power Reactor Licensees tactors Failed to Op-with an OL or CP erate 79-24 Proper. Installation and 11/26/79 All Power Reactor Calibration of Core Facilities with an OL or Spray Pipe Break CP Detection Equipment on BWRs 80-01 Service Advice for GE 1/17/80 All Power Reactor Faci-Induction Disc Relays lities with an OL or CP 80-02 Nuclear Power Plant 2/1/80 All Power and Research Staff Work Hours Reactors with an OL or CP 80-03 Protection from Toxic 3/6/80 All Power Reactor Facil-Gas Hazards ities with an OL 80-04 Securing Threaded Lack-3/14/80 All Power Reactor Facil-ing Devices on Safety-ities with an OL or CP Related Equipment.