Forwards IE Insp Rept 50-302/79-52 on 791126-29 & Notice of Deviation
ML19305B444
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 12/31/1979
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Hancock J
FLORIDA POWER CORP.
Shared Package
ML19305B439 List:
References
NUDOCS 8003190664
Download: ML19305B444 (2)


See also: IR 05000302/1979052

Text

'

,

.

e

[O #

UNITED STATES

o,'n

'v?

)

NUCLEAR REGULATORY COMMISSION

s

$

E

REGION il

o

101 MAR!ETTA ST

N.W.. SUITE 3100

kg . 48#

'

o

ATLANTA. GEORGIA 30303

...

In Reply Refer To:

DEC3 11979

RII:SAE

50-302/79-52

Florida Power Corporation

ATTN:

J. A. Hancock, Director

Nuclear Operations

P. O. Box 14042, Mail Stop C-4

St. Petersburg, FL 33733

Gentlemen:

This refers to the inspection conducted by S. A. Elrod of this office on

November 26-29, 1979, of activities authorized by NRC Operating License No.

DPR-72 for the Crystal River 3 facility, and to the discussion of our findings

held with D. C. Poole at the conclusion of the ir;pection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspector.

During the inspection it was found that certain activities under your license

appear to deviate from the applicable guides, codes or standards which are

approved by the Commission and have safety significance. This item is identified

in the Notice of Deviation enclosed herewith as Appendix A.

Please provide us

in writing within 20 days of your receipt of this letter your commetts including

a description of corrective actions that have been or will be taken. corrective

actions which will be taken to avoid further deviations, and the date corrective

actions were or will be completed.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20 days

to this office to withhold such information from public disclosure. Any such

application must include a full statement of the reasons on the basis of which

it is claimed that the information is proprietary, and should be prepared so

that proprietary information identified in the application is contained in a

separate part of the document.

If we do not hear from you in this regard within

'

the specified period, the report will be placed in the Public Document Room.

,

8 0 0319 0 M

<

_

_J

.

-

.

.

.

DECI I Ib $

Florida Power Corporation

-2-

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

.

Sincergly,

()? p{$. ' -

-

R. C. Lewis, Acting hief

,

Reactor Operations and Nuclear

.

Support Branch

Enclosures:

1.

Appendix A, Notice of Deviation

2.

Inspection Report No. 50-302/79-52

cc w/ enc 1:

D. C. Poole

Nuclear Plant Manager

P. o. Box 1240

Crystal River, FL 32629