s
wh
UNITED STATES
h" "' G%
t
NUCLEAR REGULATORY COMMISSION
og
REGION ll
{
c(
g
101 M ARIETT A STREET N W.
"
r
-
[
ATLA *7 4. GEORGIA 30303
p,
.e
(
g,
NOV 171978
'
....'
In Reply Refer To:
RII:WBS
50-424/78-8
50-425/78-8
Georgia Power Company
Attn:
Sk. J. H. Miller, Jr.
Executive Vice President
270 Peachtree Street, N. W.
Atlanta, Georgia
30303
Gentlemen:
This refers to the inspection conducted by Mr. W. B. Swan of this office
on October 18-20, 1978, of activities authorized by NRC Conrtruction
Permit Nos. CPPR-108 and CPPR-109 f or the Alvin W. Vogtle Nuclear Plant
Units 1 and 2 facilities, and to the discussion of our findings held
with Mr. L. L. Gray, Jr. at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection
consisted of selective examinations of procedures and representative
records, interviews with personnel, and observations by the inspectors.
During the inspection, it was found that certain activities under your
This ice-
license appear to be in noncompliance with NRC requirements.
and references to pertinent requirements are listed in the Notice of
Violation enclosed herewith as Appendix A.
This notice is sent to you
pursuant to the provisions of Section 2.201 of the NRC's " Rules of
Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201
requires you to submit to this office, within 20 days of your receipt of
this notice, a written statement or explanation in reply including:
(1)
corrective steps which have been taken by you and the results achieved;
(2) corrective steps which will be taken to avoid further noncompliance;
.;nd (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter and
the enclosed inspection report _ sill be placed in the SRC's Public Document
From.
If this report contains any information that you (or your contractor)
believe to be proprietary, it is necessary that you rake a writter.
781228007c)
.
.
Georgia Power Company
-2-
application within 20 days to this of fice to withhold such information
from public disclosure.
Any such application must include a full statement
of the reasons on the basis of which it is claimed that the inf ormation
is proprietary, and should be prepared so that proprietary information
identified in the application is contained in a separate part of the
document.
If we do not hear f rom you in this regard within the specified
period, the report will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
/
'
$.
r'.,.
- /
/'a ,
- f >
.
C. E. Murphy, Chief
Reactor Construction and
Engineering Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report Nos.
50-424/78-8 and 50-425/78-8
cc w/ enc 1:
Mr. K. M. Gillespie
Construction Project Fbnager
Vogtle Nuclear Plant
P. O. Box 282
Waynesboro, Georgia 30830
Mr. E. D. Groover
QA Site Supervisor
Vogtle Nuclear Plant
P. O. Box 282
Waynesboro, Georgia 30830