ML19290C187
| ML19290C187 | |
| Person / Time | |
|---|---|
| Site: | Point Beach |
| Issue date: | 12/13/1979 |
| From: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Burstein S WISCONSIN ELECTRIC POWER CO. |
| References | |
| NUDOCS 8001100286 | |
| Download: ML19290C187 (1) | |
Text
s ?. ' (i
'o UNITED STATES l )
/,
NUCLEAR REGULATORY COMMISSION 3
5..nE REGION 111 o,
799 ROOSEVELT ROAD
%.....o GLEN ELLYN, ILLINOIS 6o137 DEC 131979 Docket No. 50-266 Docket No. 50-301 Wisconsin Electric Power Company ATTN:
Mr. Sol Burstein Executive Vice President Power Plants 231 West Michigan Milwaukee, WI 53201 Gentlemen:
This Information Notice is provided as an early notification of a possibly significant matter.
It is expected that recipients will review the informa-tion for possible applicability to their facilities. No specific action or response is requested at this time. If further NRC evaluations so indicate, an IE Circular or Bulletin will be issued to recommend or request specific licensee actions.
If you have questions regarding this matter, please contact the Director of the appropriate NRC Regional Office.
Sincerely,
%.b3 h = ^
=
(/ James G. KeppW r Director
Enclosure:
IE Information Notice No. 79-31 cc w/ encl:
Mr. G. A. Reed, Plant Manager Central Files Director, NRR/DPM 1728 143 Director, NRR/ DOR C. M. Trammell, ORB /NRR PDR Local PDR NSIC TIC Sandra A. Bast, Lakeshore Citizens for Safe Energy 80011002576
., \\
SSINS: 6870 4
Accession No.:
UNITED STATES 7910250507 NUCLEAR REGULATORY C0tHISSION c,
OFFICE OF INSPECTION AND ENFORCEMENT T,
.)D.
g WASHINGTON, D.C.
20555
,ej_d December 13, 1979 IE Information Notice No. 79-31 USE OF INCORRECT AMPLIFIED RESPONSE SPECTRA (ARS)
Description of Circumstances:
Recently, the NRC was informed that, during a review of valve weights in conjunction with the as-built review for IE Bulletin 79-14 at North Anna Unit 1, it was discovered that incorrect amplified response spectra (ARS) had been used as input to the analyses of some piping on both units 1 and 2.
The reanalyses are being perfomed by Stone & Webster (S&W), the Architect Engineer for the Virginia Electric & Power Company's facilities.
Similarly, Public Service Company of New Hampshire informed the NRC that the wrong ARS were used for the design of some containment supports at their Seabrook units. The Architect Engineer for these plants is United Engineers & Constructors (UE&C).
The NRC is currently pursuing this issue in detail with S&W and UE&C to determine the extent of the problem and the generic implications for other facilities.
This Information Notice is provided as an early notification of a possible significant matter.
It is expected that recipients will review the informa-tion for possible applicability to their facilities.
Specific action has been requested by IE Bulletin 79-14.
This bulletin requires that input to seismic analyses of piping, which includes the use of the correct ARS, be verified against the as-built condition of the plant. No specific actions are requested in response to this Information Notice.
If NRC evaluations so indicate, further licensee actions may be requested or required.
If you have ar.y ques-tions regarding this matter, please contact the Director of the appropriate NRC Regional Office.
No written response to this IE Information Notice is required.
Enclosure:
List of IE Information Notices Recently Issued 1728.146
.'s IE Information Notice No. 79-31 Enclosure December 13, 1979 RECENTLY ISSUED IE INFORMATI0H NOTICES Information Subject Date Issued To Notice No.
Issued 79-30 Reporting of Defects and 12/6/79 All power reactor facilities Noncompliances, 10 CFR holding OLs and cps and Part 21 vendors inspected by LCVIP 79-29 Loss of NonSafety-Related 11/16n9 All power reactor facilities Reactor Coolant System holding OLs or cps Instrumentation During Operation 79-28 Overloading nf Structural 11/16D9 All power reactor facilities Elements Due to Pipe Support with an OL or CP Loads 79-27 Steam Generator Tube 11/16/79 All powee reactor facilities Ruptures At Two Fek holding JLs and cps Facilities79-12A Attempted Damage To New 11/9n9 All Fuel Facilities, Fuel Assemblies research rerttors, and power reactors with an OL or CP 79-26 Breach of Containment 11/5n9 All power reactor facilities Integrity holding OLs and cps 79-25 Reactor Trips At Turkey 10/in9 All power facilities with Point Units 3 And 4 an OL or a CP 79-24 Overpressurization Of 10/in9 All power reactor facilities Containment Of A PWR Plant with a CP After A Main Steam Line Break 79-23 Emergency Diesel Generator 9/26n9 All power reactor Lube Oil Coolers facilities holding OLs and cps 79-22 Qualification of Control 9/14n9 All power reactor Systems facilities with operati,ng licenses and construction permits.
79-21 Transportation and Commercial 9n/79 All power and research Burial of Radioactive Material reactors with OLs 1728 147
.