o
.
.
UNITED STATES
ffpm alcOg(o
NUCLEAR REGULATORY COMMISSION
g
REGloN 11
&
) y,( g g
101 M ARIETT A sTRE ET, N.W.
5
" '
C
'
[,
ATL ANTA, GEORGI A 30303
o, ,
,
%*% f
DEC 4
1978
In Reply Refer To:
RII:AKH
50-348/78-32
Alabama Power Company
Atta: Mr. A. R. Barton
,
Executive Vice President
Post Office Box 2641
Birmingham, Alabama
35291
Gentlemen:
This refers to the inspection conducted by Mr. A. K. Hardin of this office on
November 6-9, 1978, of activities authorized by NRC License No. NPF-2 for the
Farley Unit 1 facility, and to the discussion of our findings held with
Mr. W. G. Hairston at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews
with personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously identified
enforcement matters and unresolved items.
The status of these items is
discussed in the enclosed report.
One new unresolved item resulted from this inspection and is discussed in the
enclosed report. This item will be examined during subsequent inspections.
During the inspection, it was found that certain acMvities under your license
appear to be in noncompliance with NRC requirements. This item and references
to pertinent requirements are listed in the Notice of Violation enclosed here-
with as Appendix A.
This notice is sent to you pursuant to the provisions
of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of
Federal Regulations.
Section 2.201 requires you to submit to this office,
within 20 days of your receipt of this notice, a written statement or expla-
naticn in reply including:
(1) corrective steps which have been taken by you
and .he results achieved; (2) corrective steps which will be taken to avoid
furt ser roncompliance; and (3) the date when full compliance will be achieved.
In acurdance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room. If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20
7901120% % 7
.
.
Alabama Power Company
-2-
DEC 4
1978
days to this office to withhold such information from public disclosure.
Any such application must include a full statement of the reasons or the
basis of which it is claimed that the information is proprietary, and should
be prepared so that proprietary information identified in the application is
contained in a separate part of the document. If we do not hear from you in
this regard within the specified period, the report will be placed in the
Public Document Room.
.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
F. J. Long, Chi f
Reactor Operations and
Nuclear Support Branch
Enclcsures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-348/78-32
cc w/ enc 1:
Mr. O. D. Kingsley, Jr. , QA Supervisor
Drawer 470