Forwards Insp Repts 50-317/78-34 & 50-318/78-31 on 781114-17 & Notice of Violation
ML19269C023
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 11/30/1978
From: Brunner E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
Shared Package
ML19269C009 List:
References
NUDOCS 7901190214
Download: ML19269C023 (2)


See also: IR 05000317/1978034

Text

.

.

%

UNITED STATES

4g

4

NUCLEAR REGULATORY COMMISSION

f

., h

REGION l

'C

631 PARK AVENUE

KING OF PRUSSIA, PENNSYLVANI A 19406

Docket Nos. 50-317

3 D NOV 1978

50-318

Baltimore Gas and Electric Company

ATTN:

Mr. A. E. Lundvall, Jr.

Vice President, Supply

P. O. Box 1475

Baltimore, Maryland 21203

Gentlemen:

Subject:

Combined Inspections 78-34; 78-31

This refers to the inspection conducted by Mr. W. Baunack of this office

on November 14-17, 1978 at Calvert Cliffs Nuclear Power Plant, Units 1

and 2 of activities authorized by NRC License Nos. DPR-53 and DPR-69 and

to the discussions of our findings held by Mr. Baunack with Mr. L.

Russell and other members of your staff at the conclusion of the inspection.

Areas examined during this inspection are described in the Office of

Inspection and Entorcement Inspection Report which is enclosed with this

letter.

Within these areas, the inspection consisted of selective

examinations of procedures ana representative records, interviews with

personnel, and observations by the inspector.

Based on the results of this inspection, it appears that one of your

activities was not conducted in full compliance with NRC requirements,

as set forth in the Notice of Violation, enclosed herewith as Appendix

A.

This item of noncompliance has been categorized into the levels as

described in our correspondence to you dated December 31, 1974.

This

notice is sent to you pursuant to the provisions of Section 2.201 of the

NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.

Section 2.201 mquires you to submit to this office, within twenty (20)

days of your receipt of this notice, a written statement or explanation

in reply including:

(1) corrective steps which have been taken by you

and the results achieved; (2) corrective steps which will be taken to

avoid further items of noncompliance; and (3) the date when full compli-

ance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part

2, Title 10, Code of Federal Regulations, a copy of this letter and the

enclosures will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to

be proprietary, it is necessary that you make a written application

within 20 days to this office to withhold such information from public

7 9 0119 0M

.

.

Baltimore Gas .and Electric Company

2

3 ONOV 197a

disclosure. Any such application must be accompanied by an affidavit

executed by the owner of the information, which identifies the document

or part sought to be withheld, and which contains a statement of reasons

which addresses with specificity the items which will be considered by

the Commission as listed in subparagraph (b) (4) of Section 2.790.

The

information sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in

this regard within the specified period, the report will be placed in

the Public Document Room.

Should you have any ques' .cns concerning this inspection, we will be

.

pleased to discuss them with you.

Sincerely,

=xx

1

n W. Brunner, Chief

Reyctor Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection

Combined Report Number 50-317/78-34; 50-318/78-31

cc w/encls:

R. M. Douglass, Manager, Quality Assurance

L. B. Russell, Chief Engineer

W. Gibson, General Supervisor, Operations QA

R. C. L. Olson, Senior Engineer