ML19263E467
| ML19263E467 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 03/23/1979 |
| From: | Robert Lewis NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Stewart W FLORIDA POWER CORP. |
| Shared Package | |
| ML19263E463 | List: |
| References | |
| NUDOCS 7906180372 | |
| Download: ML19263E467 (2) | |
See also: IR 05000302/1979008
Text
-t
.
.
UNITED STATES
- g #R800
NUCLEAR REGULATORY COMMISSION
o,,
4
[
REGloN il
o
5
g
101 M ARIETT A STRE ET, N.W.
8
ATLANTA. GEORGI A 30303
o,s...../
MAR 2 31979
In Reply Refer To:
RII:DRQ
50-302/79-08
Florida Power Corporation
ATTN:
W. P. Stewart, Director
Power Production
P. O. Box 14042, Mail Stop C-4
St. Petersburg, FL 33733
Gentlemen:
This refers to the inspection conducted by D. R. Quick of this office on
February 12-16, 1979, of activities authorized by NRC Operating Licence
DPR-72 for the Crystal River 3 facility, and to the discussion of our
findings held with G. P. Beatty, Jr. at the conclusion of the inspection.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews
witn personnel, and observations by the inspectors.
We have examined actions you have taken with regard to previousl, identified
enforcement matters and unresolved items. The status of these items is
discussed in the enclosed report.
One new unresolved item resulted from this inspection and is discussed in the
enclosed report. This item will be examined during subsequent inspections.
During the inspection it was found that certain activities under your license
appear to deviate from commitments to the Commission and have safety signifi-
cance. This item is identified in the Notice of Deviation enclosed herewith
as Appendix A.
Please provide us in wr' ting within 20 days of your receipt
of this letter your comments including u description of corrective actions
that have been or will be taken, corrective actions which will be taken to
avoid further deviations, and the date corrective actions were or will be
completed.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room.
If this
report contains any information that you (or your contractor) believe to be
79061807/{
2355 028
.
-
~
. . . . .
.
.
e
MAR 2 31979
Florida Power Corporation
-2-
proprietary, it is necessary that you make a written application within 20Any
days to this office to withhold such information from public disclosure.
such application must include a full statement of the reasons on the basis of
which it is claimed that the information is proprietary, and should be prepared
so that proprietary information identified in the application is contained in
If we do not hear from you in this regard
a separate part of the document.
within the specified period, the report will be placed in the Public Document
Room.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
}l C &c-
R. C. Lewis, Acting Chief
Reactor Operations and Nuclear
Support Branch
Enclosures:
1.
Appendix A, Notice of Deviation
2.
Inspection Report No. 50-302/79-08
cc w/ enc 1:
G. P. Beatty, Jr.
Plant Superintendent
2355 029
P. O. Box 1228
Crystal River, FL 32629