Forwards IE Circular 79-25, Shock Arrestor Strut Assembly Interference. No Written Response Required
ML19262B496
Person / Time
Site: Perkins, Cherokee  Duke Energy icon.png
Issue date: 12/20/1979
From: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Dail L
DUKE POWER CO.
References
NUDOCS 7912280124
Download: ML19262B496 (4)


Text

.

rge UNITED STATES k

8 s,., g,T NUCLEAR REGULATORY COMMISSION r

TIEGION II

  • ['p ' k'#

I o

101 MARIETTA ST., N.W., SUITE 3100 g

ATLANTA, GEORGIA 30303 DEC 2 01979 In Reply Refer To:

RII:JPO 6 0-489)

C50-490T,)50-491 50-492, 50-493 Duke Power Company Attn:

L. C. Dail, Vice President Design Engineering Post Office Box 33189 Charlotte, North Carolina 28242 Gentlemen:

The enclosed Circular No. 79-25, is forwarded to you for information.

No written response to this Circular is required.

If you require additional information regarding this subject, please contact this office.

Sincerely, s.

n

~ ls 1

~2,.,,#

James P. O'Reilly Director

Enclosures:

1.

IE Circular No. 79-25 2.

List of IE Circulars Recently Issued

, #p O

7912280/2p 9

DEC 2 01979 g

Duke r ier Company cc w/ encl:

J. T. Moore, Project Manager Post Office Box 422 Gaffney, South Carolina 29340

~

-5

.1.648 182

SSINS:

6830

{

Accession No: 7910250514 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.

20555 December 20, 1979 IE Circular No. 79-25 SHOCK ARRESTOR STRUT ASSEMBLY INTERFERENCE The Bergen Paterson Pipesupport Corporation reported to the NRC a potential problem with their mechanical shock arrestor

" Strut Assembly." The Bergen Paterson, Part 2540 Strut Assembly, is being used as a rear bracket for different sizes of Pacific Scientific Company (PSCO) mechanical shock arrestors. Some of these shock arrestor sizes may not function as intended due to insufficient clearances. The following problems were identified:

For PSCO shock arrestors sizes 15 and 50, the Bergen Paterson Part 2540 Strut Assembly does not provide sufficient clearance for the shock arrestor to function fre21y, when installed at an off a :is angle greater than 83*.

For PSCO shock arrestor size 120 there is insufficient clearance throughout the 180 installation angle.

For PSCO shock arrestor sizes 50 and 120 with Bergen Paterson Adaptor Part 2108 the shock arrestor unit may sustain functional damage when the adaptor unit comes in contact with the rear of the snubber, causing distortion of the end dust cover.

PSCO shock arrestors sizes

.35,

.65, 1.5 and 6 do not have this interference condition and therefore are not part of the potential problem of this circular.

Bergen Paterson stopped shipment as of October 1979 of all Part 2540-15, 2540-50 and 2540-120 Strut Assemblies and is reviewing all applicable design detail drawings, to identify all affected items and the facilities to which th::e items have been delivered.

Licensees and holders of construction permits are advised to proceed with the inspection of Pacific Scientific Mechanical Shock Arrestor installations with Bergen Paterson Part 2540-15, 2540-50 and 2540-120 Strut Assemblies and deter-mine whether any uJ the following conditions are applicable:

1.

The shock arrestor installation orientation presents a possible interference problem.

2. - Inspection of shock arrestors 50 and 120 with adaptor show damaged or

~ deformed snubber.

Corrective action should be coordinated with the Strut Assembly supplier } h? O

} O (Bergen Paterson) and appropriate resolutions promptly implemented.

o m -.

e e

4, IE Circular No. 79-25 Enclosure December 20, 1979 RECENTLY ISSUED IE CIRCULARS Circular Subject Date of Issued to No.

Issue 79-25 Shock Arrestor Strut 12-20-79 All Holders of a Assembly Interference Powar Reactor OL or CP 79-24 Proper Installation and 11/26/79 All Holders of a Calibration of Core Spray Power Reactor OL or Pipe Break Detection CP Equipment on BWRs.

79-23 Motor Starters and 11/26/79 All Power Reactor and Contactors Failed Operating Facilities to Operate and Holders of Reactor cps 79-22 Stroke Times for Power 11/16/79 All Power Reactor Operated Relief Valves Operating Facilities and all Utilities having a CP 79-21 Prevention of Unplanned 10/19/79 All holders of Power Releases of Radioactivity Reactor OLs and cps 79-20 Failure of GTE Sylvania 9/24/79 All holders of Power Relay, Type PM Bulletin Reactor OLs and cps 7305, Catalog SU12-11-AC with a 12V AC Coil 79-19 Loose Locking Devices 9/13/79 All Holders of Power on Ingersoll-Rand Pumps Reactor OLs and cps 79-18 Proper Installation of 9/10/79 All Holders of Power Target Rock Safety-Relief Reactor CLs and cps 79-17 Contact Problem in SB-12 8/14/79 All Power Reactor Switches on General Electric Licensees with a CP Company Metalclad Circuit and/or OL Breakers

~

79-1,6 Excessive Radiation Exposures 8/16/79 All Radiography To Members Of The General Public Licensees And A Radiographer 79-15 Bursting of High Pressure Hose 8/8/79 All Materials Priority I, and Malfunction of Relief Fuel Cycle and Operating Valve "0" Ring in Certain Self-Power Reactor Licensees Contained Breathing Apparatus