Text
e
e
- p# "00g'o
UNITED STATES
a
NUCLEAR REGULATO3Y COMMISSIO*J
,,
REGION Il
g
g
.-
.t
101 M ARIETTA STREET. N.W.
ATLANTA, GEORGIA 30303
'% * * * * * #'
FEB 2 01979
In Reply Refer To:
RII:EHG
50-395/79-03
South Carolina Electric and Gas Company
Attn:
Mr. C. C. Johnson, Vice President and Group
Executive - Special Services and Purchasing
Post Office Box 764
Columbia, South Carolina 29218
Gentlemen:
This refers to the inspection conducted by Mr. E. H. Girard of this
office on January 22-25, 1979 of activities authorized by NRC License
No. CPPR-94 for the Virgil C. Summer Nuclear Station facility, and to
the discussion of our findings held with Mr. J. F. Algar at the conclu-
sion of the inspection.
Areas examined during the inspection and our findings are discussed in
the enclosed inspection report. Within these areas, the inspection
consisted of selective examinations of procedures and representative
records, interviews with personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously reported
unresolved items. The status of these items is discussed in the enclosed
report.
One new unresolved item resulted from this inspection and is discussed
in the enclosed report. This item will be examined during subsequent
inspections.
During the inspection, it wcs found that certain activities under your
license appear to be in ncacompliance with NRC requirements. This item
and references to pertinent requirements are listed in the ? )tice of
Violation enclosed herewith as Appendix A.
This notice is sent to you
pursuant to the provisions of Section 2.201 of the NRC's " Rules of
Practice", Part 2, Title 10, Code of Federal Regulations.
Section 2.201
requires you to submit to this office, within 20 days of your receipt of
this notice, a written statement or explanation in reply including:
(1)
corrective steps which have been taken by you, and the results achieved;
(2) corrective steps which will be taken to avoid further noncompliance;
and (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's " Rules of Practice,"
Part 2, Title 10, Code of Federal Regulations, a copy of this letter and
the enclosed inspection report will be placed in the NRC's Public Document
7903280092_
.
FEB 2 01979
.
South Carolina Electric and
Gas Company
-2-
Room.
If this report contains any information that you (or your contrac-
tor) believe to be proprietary, it is necessary that you make a written
application within 20 days to this office to withhold such information
from public disclosure. Any such application must include a full state-
ment of the reasons on the basis of which .it is claimed that the informa-
tion is proprietary, and should be prepared so that proprietary informa-
tion identified in the application is contained in a separate part of
the document.
If we do not hear from you in this regard within the
specified period, the report will be placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincerely,
- -
/
Charles E. Murphy, Chief
Reactor Construction and
,
Engineering Support Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 50-395/79-03
cc w/ enclosures:
Mr. Troy B. Conners, Jr.
Conners, Moore and Corber
1747 Pennsylvania Avenue, N.W.
Washington, D.C.
20006
Mr. H. I. Donnelly, Jr.
Quality Assurance
Post Office Box Eight
Jenkinsville, South Carolina 29065
Mr. O. S. Bradham, Manager
Nuclear Operations
Post Office Box Eight
Jenkinsville, South Carolina 29065