ML19261B892
| ML19261B892 | |
| Person / Time | |
|---|---|
| Site: | Hatch |
| Issue date: | 02/14/1979 |
| From: | Sutherland J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | John Miller GEORGIA POWER CO. |
| Shared Package | |
| ML19261B893 | List: |
| References | |
| NUDOCS 7903070509 | |
| Download: ML19261B892 (1) | |
See also: IR 05000321/1978040
Text
. . ,
s*
{
kmntGu
UNITED STATES
,(
jo,,
NUCLEAR REGUL.* TORY COMMISSION
J
y
)7 .
g
GEGION il
h -p/
g
e
101 M ARIETTA STREET, N.W.
g
a
o
ATLANTA, GEORGIA 30303
%,**U***g
FEB 141979
In Reply Refer To:
RII:ALC
50-321/78-40 and
50-366/78-49
Georgia Power Company
ATTN:
Mr. J. H. Miller, Jr.
Executive Vice President
270 Peachtree Street, N.W.
Atlanta, Georgia 30303
Gentlemen:
Thank you for your letter of January 26, 1979, informing us of steps
you have taken to correct the items of noncompliance concerning
activities under NRC License Nos. DPR-57 and NPF-5 brought to your
attention in our letter of January 4, 1979. We will examine your
corrective actions and plans Auring subsequent inspections.
We appreciate your cooperation with us.
Sincerely,
f
Nb
Jf
Jack T. Sutherland, Chief
Fuel Facility and Materials
Safety Branch
cc:
Mr. C. E. Belflower
Site QA Supervisor
Plant E. I. Hatch
P. O. Box 442
Baxley, Georgia 31513
Mr. M. Manry, Plant Manager
Plant E. I. Hatch
P. O. Box 442
Baxley, Georgia 31513
7903 070 fo9
-
.
.
.
.
RII Rpt. Nos. 50-321/78-40
I-l
and 50-366/78-49
,,,
-
-
/
',/
DETAlLS I
Prepared by: -/. . ,
,
A.'L. 'Cunnin}gham, Engatal'
~
///J//yp'
~j jir.1 r, W
x,z,,, f
'Date
Scientist, Environmental and
Special Projects Section
Fuel Facility and Materials Safety
Branch
I
Dates of Inspection: December 4-8, 1978
Reviewed by
M \\
11
i 1
, <nw;
J. W. Hufhad Chi f "_
Date
Em
ronmental
nd Special Projects
>ction
Fuel Facility and aterials Safety
Branch
All information in the following DETAILS I applies equally to Units 1 and 2.
1.
Individuals Contacted
W. R. Woodhall, Coordinator of Environmental Affairs
M. Manry, Plant Manager
- J. H. Motz, Jr., Engineer
W. II. Rogers, Healtn Physicist
H. Nix, Assistant Plant Manager
D. Smith, Laboratory Supervisor
S. X. Baxley, Operations Superintendent
- B. L. Maulsby, Senior Design Engineer
R. F. Rogers, NFC Resident Inspector
- R. W. Staf fa, Manager Quality Assurance
- D. R. Savage, Quality Assurance Engineer
- F. L. Willis, Laboratory Foreman
M. L. Link, Laboratory Foreman
- C. W. Hayes, Quality Assurance Engineer
J. D. Peregoy, Quality Assurance Engineer
L. Collins, Laboratory Supervisor
- Denotes those present at the exit interview.
2.
Licensee Action on Previous Inspection Findings
(Closed) Noncompliance (50-321/78-19-01) Deficiency:
Procedures.
Licensee failed to implement procedures HNP-1-7306 and HNP-1-7305 for
calibration of plant cooling water intake / discharge temperature and pH
monitors respectively.
Inspection disclosed that the above procedures
were deleted and supplemented by procedure RNP-7604.
Inspection included
a review of the subject procedure and records of quarterly calibrations
,,
-
.
.
,
RII Rpt. Nos. 50-32:./78-40
1-2
and 50-366/78-49
~
-
6f the above cited monitors. The procedure was implemented as required.
There were no questions regarding this item.
(Closed) Noncompliance (50-321/77-19-02) Deficiency:
Records Retention.
The licensee failed to implement Appendix B ETS-5.7.1.
The specifica-
tion required that operational information, concerning limiting conditions
for operation, be kept by Georgia Power Company Production Department in
a manner convenient for review including plant data, records and logs.
Inspection disclosed that subject records were appropriately filed and
readily retrievable.
There were no further questions regarding this
item.
3.
Unresolved Item
No unresolved items were disclosed during inspection.
4.
Administrative Controls
Inspection included a detailed review and audit of written procedures
a.
for selected activities involved in implementing the Environmental
Technical Specifications (ETS).
Inspection disclosed that the
Environmental Programs Description Document defined in ETS-5.6.1
and describing the monitoring programs required by ETS Sections 3.1
and 4.1, appeared consistent with such requirements.
Inspection
also disclosed, however, that the licensee failed to provide
procedures to assure quality assurance of program results required
by ETS-5.6.2.
This specification required, in part, provision of
procedures assuring the quality of ETS program results, including
analytical measurements.
In addition, the procedures were required
to provide systems to identify and correct deficiencies in monitoring
programs, to investigate anomalous or suspect results, and to
review and evaluate program results.
The inspector informed licensee
representatives that failure to provide the subject procedures, as
required, constituted an item of noncompliance (50-321/78-40-1 and
50-366/78-49-1).
b.
The inspector reviewed annual audit requirements defined in
ETS-5.3.2.
Inspection disclosed that an audit of activities of the
Plant Manager related to compliance with the ETS was performed
July 14 through July 18 (QA Audit 78-ETS-1-1).
Inspection also
disclosed that the required annual audit of activities of the
Manager of Environmental Affairs regarding compliance with the ETS
had not yet been performed.
There were no questions regarding this
item.
The inspector reviewed the Annual Environmental Report for the
c.
period ending December 31, 1977.
The subject report is required by
.
..
-
-
,.
RII Rpt. Nos. 50-321/78-40
I-3
and 50-366/78-49
ETS 5.7.1 entitled Routine Reports. There were no questions
regarding this item.
5.
Environmental Monitoring
Review and inspection of environmental monitoring was confined to aquatic,
abiotic parameters defined in ETS-3.1.1.1, 3.1.1.2 and 3.1.1.3 ; viz. ,
plant intake and discharge cooling water temperature, pH and residual
chlorine respectively.
Inspection of monitoring data, records and logs
disclosed that the subject requirements were implemented as assigned.
6.
Special Surveillance
The inspector reviewed the special surveillance requirements defined in
ETS-4.1.
The subject specification required semi-annual aerial surveys
of the transmission lines rights-of-way from HNP to the Bonaire Sub-
station for evidence of significant erosion.
Inspection disclosed that
the licensee failed to implement the survey as required. A survey was
conducted on August 22, 1978.
The previous survey was conducted
October 14, 1977. The inspector informed licensee representatives that
failure to conduct the surveys at the specified frequency constituted an
item of noncompliance (50-321/78-40-2 and 50-366/78-49-02).
7.
Terrestrial Surveillance
Inspection included review and discussion of monitoring of vegetative
communities within the site and its environs.
Inspection disclosed that
the annual aerial photographic survey to detect and assess the signifi-
cance of damage related to deposition of cooling tower drift was
implemented as required.
The survey indicated no perceptible damage.
There were no questions regarding this item.
8.
Licensee Event Reports
The inspector reviewed License Event Report No. 78-05 concerning
excursion of the plant cooling water discharge pH above the assigned
limit.
Inspection disclosed that corrective actions were implemented as
assigned. This event was formally closed out.
9.
Exit Interview
The inspector met with licensee representatives (denoted in paragraph 1)
at the conclusion of the inspection on December 8, 1978.
The inspector
reviewed the scope of the inspection and discussed the findings listed
herein.
JAN 041979
-
-
.
-2-
In sccordance with Section 2.790 of the NRC's " Rules of Practice",
Part 2, Title 10, Code of Federal Regulations, a copy of this letter
and the enclosed inspection report will be placed in the NRC's Public
Document Room.
If this report contains any information that you (or
your contractor) believe to be proprietary, it is necessary that you
make a written application within 20 days to this office to withhold
such information from public disclosure. Any such application must
include a full statement of the reasons on the basis of which it is
claimed that the information is proprietary, and should be prepared
so that proprietary information identified in the application is
contained in a separate part of the document.
If we do not hear from
you in this regard within the spccified period, the report will be
placed in the Public Document Room.
Should you have any questions concerning this letter, we will be glad
to discuss them with you.
Sincerely,
,
c~
, ,
,
gf}JackT.Sutherland, Chief
Fuel Facility and Materials
Safety Branch
J
Enclosures:
1.
Inspection Report Nos.
50-321/78-40 and
50-366/78-49
2.
Appendix A, Notice of Violation
cc.
Mr. M. Manry, Plant Manager
Plant E.
I. Hatch
P. O. Box 442
Baxley, Georgia 31513
Mr. C. E. Belflower
Site QA Supervisor
Plant E.
I. Hatch
P. O. Box 442
Baxley, Georgia 31513