Forwards IE Insp Rept 50-369/79-29 on 790816-23 & Notice of Violation
ML19260A957
Person / Time
Site: McGuire Duke Energy icon.png
Issue date: 10/19/1979
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
Shared Package
ML19260A948 List:
References
NUDOCS 7912060192
Download: ML19260A957 (2)


See also: IR 05000369/1979029

Text

.

.

/

o,

UNITED STATES

8

7,

NUCLEAR REGULATORY COMMISSION

g

-r

REGION il

'#

o

101 MARIETTA ST

M.W.. SUITE 3100

ATLANTA, GEC.RGIA 30303

.....

In Reply Refer To:

007 .1 9 1979

RII:HLW

50-369/79-29

Duke Power Company

ATTN:

W. O. Parker, Jr.

Vice President, Steam Production

P. O. Box 2178

Charlotte, NC 28242

Gentlemen:

This refers to the inspection conducted by H. L. Whitener of this office on

August 16-23, 1979, of activities authorized by NRC Construction Permit No.

CPPR-83 for the McGuire facility, and to the discussion of our findings held

with M. Sample at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report.

Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews with

personnel, and observations by the inspectors.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation enclosed herewith

as Appendix A.

This notice is sent tc you pursuant to the provisions of Section

2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regula-

tions. Section 2.201 requires you to submit to this office, within 20 days of

your receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you and the results achieved; (2)

corrective steps which will be taken to avoid further noncompliance; and (3) the

date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2, Title

10, Code of Federal Regulations, a copy of this letter and the enclosed inspection

report will be placed in the NRC's Public Document Room. If this report contains

any information that you (or your contractor) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must

include a full atatement of the reasons on the basis of which it is claimed that

the information is proprietary, and should be prepared so that proprietary

information identified in the application is contained in a separate part of the

document. If we do not hear from you in this regard within the specified period,

the report will be placed in the Public Document Room.

1510

302

7 912 0 6 0 / h

.

.

.

Duke Power Company

-2-

OCT 191979

Should you have any questions concerning this letter, we will be glad to discuss

them with you.

Sincerely,

,

{o

}

s

R. C. L

is, Acting Chief

Reactor Operations and Nuclear

Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-369/79-29

cc w/ enc 1:

M. D. McIntosh, Plant Manager

P. O. Box 488

Cornelius, NC 28031

J. C. Rogers, Project Manager

P. O. Box 33189

Charlotte, NC 28242

1510