ML19260A237
| ML19260A237 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 09/24/1979 |
| From: | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML19260A233 | List: |
| References | |
| 50-302-79-29, NUDOCS 7911080216 | |
| Download: ML19260A237 (5) | |
Text
t 1
APPENDIX A NOTICE OF VIOLATION Florida Power Corporation License No. DPR-72 Crystal River, Unit 3 Based on the NRC inspection July 24 through August 5, 1979, certain of your activities were apparently not conducted in full compliance with NRC requirements as indicated below. These items have been categorized as described in correspondence to you dated December 31, 1974.
A.
As required by Technical Specification 6.8.2, procedures for surveil-lance and test activities of safety-related equipment, and changes thereto shall be reviewed by the PRC and approved by the Nuclear Plant Manager prior to implementation.
Contrary to the above, on July 26, 1979, procedure SP-102, "Contr.ol Rod Drop Time Tests" (October 1978) was revised and implemented without the required review and approval.
This is an infraction.
B.
As required by Technical Specification 6.8.1(c), written procedures shall be established, implemented, and maintained covering surveil-lance and test activities of safety-related equipment.
Contrary to the above, on July 26, 1979, step 6.9 of procedure SP-102, " Control Rod Drop Time Tests" was incorrectly implemented, resulting in erroneous measurement of control rod drop times.
This is a deficiency.
}29b 7011080 2l5
.