Forwards IE Insp Rept 50-317/79-11 on 790709-13 & Notice of Violation
ML19254E108
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 09/06/1979
From: Grier B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Lundvall A
BALTIMORE GAS & ELECTRIC CO.
Shared Package
ML19254E103 List:
References
NUDOCS 7910310105
Download: ML19254E108 (2)


See also: IR 05000317/1979011

Text

.I

.

UNtTED STATES

,, n gqq

o

NUCLEAR REGULATORY COMMisslON

)W,(/

3 \\

o

REGION I

,

. k

631 PARK AVENUE

$*i

f

KING OF PRUSSI A, PENNSYLVANIA 19406

,w/

+....

Docket No. 50-317

SEP 0 61979

Baltimore Gas and Electric Company

ATTN: Mr. A. E. Lundvall, Jr.

Vice President, Supply

P. O. Box 1475

Baltimore, Maryland 21203

Gentlemen:

Subject:

Inspection 50-317/79-11

This refers to the inspection conducted by Mr. D. Johnson of this office on July

9-13, 1979 at Calvert Cliffs Nuclear Power Plant, Unit 1, Lusby, Maryland, of

activities authorized by NRC License No. DPR-53 and to the discussions of our

findings held by Mr. Johnson with Mr. L. Russell of your staff at the conclusion

of the inspection.

Areas examined during this inspection are described in the Office of Inspection

and Enforcement Inspection Report which is enclosed with this letter.

Within

these areas, the inspection consistec of selective examinations o# procedures

and representative records, interviews with personnel, and observations by the

inspector.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full

omplience with NRC requirements, as set forth in the

Notice of Violation, enclosed herewith as Appendix A.

This item of noncompliance

has been categorized into the levels as described in our correspondence to you

dated December 31, 1974. This notice is sent to you pursuant to the provisions

of Section 2.201, of the NRC's " Rules of Practice", Part 2, Title 10, Code of

Federal Regulations. Section 2.201 requires you to submit to this office,

within twenty (20) days of your receipt of this notice, a written statement or

explanation in reply including:

(1) corrective steps which have been taken by

you and the results achieved; (2) corrective steps which will be taken to avoid

further items of noncompliance; and (3) the date when full compliance will be

achieved.

In addition to the need for corrective action regarding this specific

item of noncompliance, we ara concerned about the implementation of your management

control systems that permitted it to occur.

Consequently, in your reply, you

should describe in particular, those actions taken or planned to improve the

effectiveness of your management control systems.

The item of noncompliance shown in the Notice of Violation enclosed with this

letter, is a recurrent or uncorrected item.

In your response please give this

matter your particular attention.

1243

188

7 910310 f 0 4

.

.

Baltimore Gas & Electric Co.

2

In accordance with Section 2.790 of the NRC's " Rules of Practice", Part 2, Title

10, Code of Neal Regulations, a copy of this letter and the enclosures will

be placed in the NRC's Public Document Room.

If this report contains any

information that you (or your contractue) believe to be proprietary, it is

necessary that you make a written application within 20 days to this office to

withhold such information from public disclosure. Any such application must be

accompanied by an affidavit executed by the owner of the information, which

identifies the document or part sought to be withheld, and which contains a

statement of reasons which addresses with specificity the items which will be

considered by the Commission as listed in subparagraph (b)(4) of Section 2.790.

The information sought to be withheld shall be incorporated as far as possible

into a separate part of the affidavit.

If we do not hear from you in this

regard within the specified period, the report.will be placed in the Public

Document Room.

Should you have any questions concerning this inspecticn, we will be pleased to

discuss them with you.

Sincerely,

f

+

B

H. Grier

Director

Enclosures:

1.

Appendix A, Notice of Violation

2.

Office of Inspection and Enforcement Inspection

Report Number 50-317/79-11

cc w/encls:

R. M. Douglass, Manager, Quality Assurance

L. B. Russell, Chief Engineer

W. Gibson, General Supervisor, Operations QA

R. C. L. Olson, Senior Engineer

K. H. Sebra, Principal Engineer