Forwards IE Insp Rept 50-269/79-15 on 790627-29 & Notice of Violation
ML19249C957
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 07/24/1979
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Parker W
DUKE POWER CO.
Shared Package
ML19249C952 List:
References
NUDOCS 7909190344
Download: ML19249C957 (2)


See also: IR 05000269/1979015

Text

>= neco

.

.[

UNITED STATES

o

l'

/,j

NUCLEAR REGULATORY COMMISSION

, , .

FIEGION 11

o, k '-' ' 'f

g ,f

'

s

,

101 MARIETTA ST.. N.W., sulTE 3100

ATLANTA, GEORGIA 30303

. ' . . . . '

%p

j

E2 4 E

In Reply Refer To:

RII:EHB

50-269/79-15

Duke Power Company

ATTN:

W. O. Parker, Jr.

Vice President, Steam Production

P. O. Box 33189

Charlotte, N C 28242

Gentlemen:

This refers to the inspection conducted by E. H. Brooks of this office on

June 27-29, 1979, of activities authorized by NRC Operating License No. DPR-38

for the Oconee Unit 1 facility, and to the discussion of our findings held

with J. E. Smith at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the

enclosed inspection report. Within these areas, the inspection consisted of

selective examinations of procedures and representative records, interviews

with personnel, and observations by the inspector.

We have examined actions you have taken with regard to previously reported

unresolved items.

The status of these items is discussed in the enclosed

report.

During the inspection, it was found that certain activities under your license

appear to be in noncompliance with NRC requirements. This item and references

to pertinent requirements are listed in the Notice of Violation enclosed

herewith as Appendix A.

This notice is sent to you pursuant to the provisions

of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 1C, Code of

Federal Regulations.

Section 2.201 requires you to submit to this office,

within 20 days of your receipt of this notice, a written statement or

explanation in reply including:

(1) corrective steps which have been taken by

you and the results achieved; (2) corrective steps which will be taken to

avoid further noncompliance; and (3) the date when full compliance will be

achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulations, a copy of this letter and the enclosed

inspection report will be placed in the NRC's Public Document Room.

If this

report contains any information that you (or your contractor) believe to be

proprietary, it is necessary that you make a written application within 20

days to this office to withhold such information from public disclosure. Any

such application must include a full statement of the reasons on the basis of

which it is claimed that the information is proprietary, and should be prepared

so that proprietary information identified in the application is contained in

a separate part of the document.

If we do not hear from you in this regard

within the specified period, the report will be placed in the Public Document

Room.

.

'i $

7909190

.

JUL 2 4 l973

.

Duke Power Company

-2-

,

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

[. C.

R. C.

ewis, Acting Chief

Reactor Operations and Nuclear

Support Branch

Enclosure:

1.

Appendix A, Notice of Violation

2.

Inspection Report No. 50-269/79-15