ML19246B445
| ML19246B445 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 03/16/1979 |
| From: | Sutherland J NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Stewart W FLORIDA POWER CORP. |
| Shared Package | |
| ML19246B412 | List: |
| References | |
| NUDOCS 7907130500 | |
| Download: ML19246B445 (2) | |
See also: IR 05000302/1979007
Text
.
9
e' 8800
UNITED STATES
9
[g
jo,,
NUCLEAR REGULATORY COMMISSION
,
REGloN il
h
) .r;
g
0g
101 M ARIETT A sTRE ET. N.W.
9 E
N
ATLANTA. GEORGIA 30303
o,s,..../
MAR 161979
In Reply Refer To:
RII:GTG
50-302/79-7
Florida Power Corporation
Attn: Mr. W. P. Stewart, Director
Power Production
Post Of fice Box 14042, Mail Stop C-4
St Petersburg, Florida 33733
Gentlemen:
This refers to the inspection conducted by Mr. G. T. G: i;on of this of fice on
January 22-26, 1979, of activities authorized by hTC
4 cense No. DPR-72 for
the Crystal River facility, Unit 3, and to the discus: on of our finaings
held with Mr. G. Beatty at the conclusion of the inspectica.
Areas examined during the inspection and our findings are discussed in the
enclosed inspection report. Within these areas, the inspection consisted of
selective examinations of procedures and representative records, interviews
with personnel, and observations by the inspector.
We have examined actions you have taken with regard to previously reported
unresolved items. The status of these items is discussed in the enclosed
report.
One new unresolved item resulted from this inspection and is discussed in the
enclosed report. This item will be examined during subsequent inspections.
During the inspection, it was found that certain activities under your license
appear to be in noncompliance with NRC requirements. These items and references
to pertinent requirements are listed in the Notice of Violation enclosed here-
with as Appendix A.
This notice is sent to you pursuant to the provisions of
Section 2.201 of the NRC's " Rules of Practice", Part 2, Title 10, Code of
Federal Regulations.
Section 2.201 requires you to submit to this office,
within 20 days of your receipt of this notice, a written statement or expla-
nation in reply to item 302-79-7-3, including:
(1) corrective steps which
have been taken by you, and the results achieved; (2) corrective steps which
will be taken to avoid further noncompliance; and (3) the date when full
compliance will be achieved. With regard to item 302-79-7-01, as discussed
in Section 5 of the enclosed report, corrective action and commitments for
implementation of the corrective action have been received during the inspection;
therefore, a response to this item is not required.
360
147
goo
G
7 9 071,a g
.
..
.
3
MAR 161979
.
Florida Power Corporation
-2-
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Ccde of Federal Regulations, a copy of this letter and the enclosed
inspection report will be placed in the NRC's Public Document Room. If this
report contains any information that you (or your contractor) believe to be
proprietary, it is necessary that you make a written application within 20
days to this office to withhold such information from public disclosure. Any
such application must include a full statement of the reasons on the basis of
which it is claimed that the information is proprietary, and should be prepared
so that proprietary information identified in the application is contained in
a separate part of the document. If we do not hear from you in this regard
within the specified period, the report will be placed in the Public Document
Room.
Should you have any questions concerning this letter, we will be glad to
discuss them with you.
Sincer ly,
')
~
Jack T. Sutherland, Chief
Fuel Facility and Materials
Safety Branch
Enclosures:
1.
Appendix A, Notice of Violation
2.
Inspection Report No. 70-824/79-1
cc w/ enc 1:
Mr. G. P. Beatty, Jr.
Nuclear Plant Superintendent
Post Office Box 1228
Crystal River, Florida 32629