Forwards IE Insp Repts 50-324/79-17 & 50-325/79-17 on 790416-20,notice of Violation & Notice of Deviation
ML19225B271
Person / Time
Site: Brunswick  Duke Energy icon.png
Issue date: 05/14/1979
From: Murphy C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Jackie Jones
CAROLINA POWER & LIGHT CO.
Shared Package
ML19225B269 List:
References
NUDOCS 7907240420
Download: ML19225B271 (2)


See also: IR 05000324/1979017

Text

_

lT L

'

e

UNITED STATES

g8R800

NUCLEAR REGULATORY COMMISSION

g

,o

REGloN Il

O

3c -

o

$

101 M ARIETTA STREET, N.W.

7

M'

3

4 )h !

ATLANTA. GEORGI A 30303

o9

%.%. . . . ,5

4

MAY 141979

In Reply Refer To:

RII:WHM

50-324/79-17

50-325/79-17

Carolina Power and Light Company

Attn:

J. A. Jones, Executive Vice President

at.d Chief Operating Officer

411 Fayetteville Street

Raleigh, North Carolina 27602

Gentlemen:

This refers to the inspection conducted by W. H. Miller, Jr. of this

office on April 16-20, 1979 of activities authorized by h3C License Nos.

DPR-71 and DPR-62 for the Brunswick Steam Electric Plant facility,

Units 1 and 2, and to the discussion of our findings held with A. C. Tollison,

Jr. at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in

the enclosed inspection report. Within these areas, the inspection

consisted of selective examinations of procedures and representative

records, interviews with per onnel, and observations by the inspector.

Two new unresolved items resulted from this inspection and are discussed

in the enclosed report. These items will be examined during subsequent

inspections.

During the inspection, it was found that certain activities under your

license appear to be in noncompliance with h3C requirements.

Two items

and references to pertinent requirements are listed in the Notice of

Violation enclosed herewith as Appendix A.

This notice is sent to you

pursuant to the provisions of Section 2.201 of the NRC's " Rules of

Practice", Part 2, Title 10, Code of Federal Regulations.

Section 2.20]

requires you to submit to this office, within 20 days of your receipt of

this notice, a written statement or explanation in reply including:

(1)

corrective steps which have been taken by you, and the results achieved;

(2) corrective steps which will be taken to avoid further nor. compliance;

and (3) the date when full compliance will be achieved.

f

During the inspection it was found that certain activities under your

license appear to deviate f rom co::mitments to the Cocaission and have

.

safety significance. This item is identified in the Notice of Deviation

ene'losed herewith as Appendix B.

Please provide us in writing within 20

days of your receipt of this letter your comments including a description

of corrective actions that have been or will be taken, corrective actions

which will be taken to avoid further deviations, and the date corrective

actions were or vill be completed.

368

239

790724& b

-

,

-

,

,

MAY 141979

.

Carolina Power and

Light Company

-2-

In accordance with Section 2.790 of the NRC's " Pules of Practice,"

Part 2, Title 10, Code of Federal Regulations,

copy of this letter and

the enclosed inspection report will be placed in the NRC's Public Document

Room.

If this report contains any information that yvu (or your contractor)

believe to be proprietary, it is necessary that you make a written

application within 20 days to this office to withhold such information

from public disclosure. Any such application must include a full state-

ment of the reasons on the basis of which it is claimed that the informa-

tion is proprietary, and should be prepared so that proprietary information

ideutified in the application is contained in a separate part of the

document.

If we do not hear from you in this regard within the specified

period, the report will be placed in the Public Document Room.

Should you have any questions concerning this letter, we will be glad to

discuss them with you.

Sincerely,

/

<

Ch irles E. Murphy, Chief

Reactor Construction and

-

Engineering Support Branch

Enclosures:

1.

Appendix A, Notice of Violation

2.

Appendix B, Notice of Deviation

3.

Inspection Report Nos. 50-324/79-17

and 50-325/79-17

cc w/ enclosures:

A. C. Tollison, Jr.

Plant Manager

Box 458

Southport, North Carolina 28461

.

.

.

363

240

.

~

-g