ML19225B206
| ML19225B206 | |
| Person / Time | |
|---|---|
| Site: | Vogtle |
| Issue date: | 05/17/1979 |
| From: | Gouge M, Herdt A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML19225B182 | List: |
| References | |
| 50-424-79-07, 50-424-79-7, 50-425-79-07, 50-425-79-7, NUDOCS 7907240285 | |
| Download: ML19225B206 (5) | |
See also: IR 05000424/1979007
Text
UNITE D STATES
/g* R80 9'o
NUCLEAR REGULATORY COMMISSION
0
,g
REGION il
$
p
g
101 M ARIETT A STRE ET. N.W.
5
..g
' *
ATLANT A, GEORGI A 3o303
o
%...../
Report Nos. 50-424/79-7 and 50-425/79-7
Licensee: Georgi 3 Power Company
270 Peachtree Street, N. W.
Atlanta, Georgia 30302
Facility Name: Alvin W. Vogtle Nuclear Plant, Units 1 and 2
Docket Nos.
50-424 and 50-425
License Nos.
CPPR-108 and CPPR-109
Inspection at Vogtle Nuclear lant near Waynesbaro, Georgia
E!/
Inspector:
M. J. Gouge
]
Date Signed
f
[/
JJJ[
Approved by:
'
A. R. Herdt, Section Chief, RCES Branch
D4te ighed
SLTiARY
Inspection on April 25-27, 1979
Areas Inspected
This routine, unannounced inspection involved 21 inspector-hours onsite in
the areas of concrete placement, preventive maintenance, and reactor cavity
liner plate welding (Unit 2).
Results
Of the three areas inspected, no apparent items of noncompliance or devia-
tions were identified in one area; one apparent item of concompliance was
found in one area (Infraction - Electrical Preventive Maintenance - Details
paragraph 5.b.) one apparent deviation was found in one area (Concrete Design
Commitments - Details paragraph 5.a).
AIS
162
790724o285
T
.
DETAILS
1.
Persons Contacted
Licensee Employees
H. H. Gregory, III, Assistant Construction Project Manager
- D. M. Fiquett, Manager, Field Operations
- C.
R. Miles, Jr.
QA Field Supervisor
i
- E. D. Groover, QA Site Supervisor
- J. F. D'Amico, Senior QA Field Representative
- C. Sarver, Senior QA lield Representative
- B. C. Harbin, Civil QC Supervisor
L. J. James, Civil QC Supervisor
W. L. Kent, Soils and Concrete Inspector, Laboratory
- R. R. Allen, QC Manager
C. D. Mauldin, Associate Mechanical Engineer
R. D. Osbourne, Mechanical QC Inspector
!!. Ahluwali, Electrical Engineer
F. Warren, Electrical QC Inspector
Other licensee employees contacted included various construction
craftsmen and office personnel.
Other Organizations
Chicago Bridge and Iron Company
- D. F. Wilkerson, QA Superintendent
R. A. Franz, Welding Engineer
G. E. Rowe, QA Engineer
Walsh Construction Company (WCC)
415
i63
- G. S. Wisen, QC Coordinator
- Attended exit interview.
2.
Exit Interview
The inspection scope and findings were summarized on April 27, 1979 with
The licensee acknowledged
those persons indicated in Paragraph I above.
the item of noncompliance and the deviation discussed in this report.
424-425/79-07-01,
The licensee stated that, pending resolution of deviation
no Category I toncrete would be placed with a 91-day design strength
where the PSAR specified a 28-day design strength requirement.
.
-2-
3.
Licensee Action on Previous Inspection Findings
Not inspected.
4.
Unresolved Items
Unresolved items were not identified during this inspection.
5.
Independent Inspection Effort
a.
Observation of Concrete Placement (Units I and 2)
The inspector observed placement of Category I concrete pour
1-01D-]08B in Unit 1 tendon gallery wall.
Acceptance criteria
examined by the inspector appear in the following documents:
(1) Section 3.8 of the Vogtle PSAR
(2) GPC Construction Procedure CD-T-02, Concrete Quality Control
(3) Bechtel Specification X2AP01, Section 3.6, Material Testing
Se rvices
Forms were tight and clean and preplacement inspection was
indicated by the signed pour card. Areas inspected included
delivery, testing, conveying, placement and consolidation of
concrete.
The following concrete records were reviewed:
(1) Concrete Pour Card (Form CD-T-02-36)
(2) Batch Record Summary (Form CD-T-02-37)
(3) Summary of Concrete Placed (Form CD-T-02-39)
Concrete operations were continuously monitored by civil QC
personnel.
Concrete placement, testing and inspection were
conducted in accordance with applicable procedures.
The inspector noted that the pour card and applicable civil drawing
specified a 521(D-2) mix.
Bechtel Specification X2AP01, Division
C3, Section 3.6 describes the D-2 mix in Table II as a concrete mix
containing flyash designed for a strength of 5000 psi at 91-days.
Note 4 to T.ible II states that the design strength for all 5000 psi
and 6000 psi concrete is at 91-days. Discussions with site personnel
indicated all of the Category I concrete in the containment and
415
164
.
.
.-
3-
-
.
,
.
-3-
tendon gallery structures is either 5000 or 6000 psi with a 91-day
Section 3.8.1.6.1 of the Vogtle PSAR
design strength requirement.
specifies a 28-day compressive strength for containment concrete as
follows:
(a) Base mat and gallery - 5,000 psi at 28 days
(b) Cylinder and dome - 6,000 psi at 28 days
results for contain-
A review of concrete compressive strength test
ment structures and the auxiliary building indicated the 91-day,
5,000 psi, Category I concrete mix had a number of 28-day
Ali of the 91-day strengths
compressive strengths below 500" psi.iailure of the licensee to conform
reviewed were above 5000 psi. e ign strength requirement specified
to his commitment to a 28-day
in Section 3.8.1.6.1 of the PSAM is identified as Deviation
424-425/79-07-01, Concrete Design Commitments.
Preventive Maintenance System (Units 1 and 2)
b.
The inspector examined the preventive haintenance system as imple-
mented for mechanical and electrical equipment in storage on site.
The following documents provide guidance in this area:
Procedure MD-T-06, Inspection of Mechanical Equipment
(1)
Procedure MD-A-01, Receipt and Storage of Hechanical Equipment
(2)
Procedure ED-T-06, Electrical Material / Equipment Receipt,
(3)
Storage and Handling
(4) Specification X3AR01, Section E2, Station Service Equipment
The IE inspector reviewed maintenance records for various safety
related heat exchangers, valves and pumps in storage on site.
Preventive maintenance on these mechanical components had been
performed at the specified intervals in accordance with applicable
procedures.
The preventive maintenance records for the fellowing safety-related
electrical components were reviewed:
Containment Spray Pump Motor 1-206-P6-001
Containment Spray Pump Motor 1-206-P6-002
415
165
.
,
.
-4-
Safety Injection Pucp Motor 1-1204-P6-003
Safety Injection Pump Motor 1-1204-P6-004
Rod Drive MG Set 2-1606-M6-001
Rod Drive hG Set 2-1606-M6-002
2 specifies a monthly check of insulation
Procedure ED-T-06, Rev.
Nc record of
resistance for safety related motors and generators.
an insulation resistance check for either of the two Rod Drive
Motor-Generator Sets identified above existed for the month of
O dated
Specification X3AR01, Section E2, Rev.
March, 1979.
3-9-79 specifies in Section E2.10.1.C a weekly shaft rotation for
Records for the two
all safety related motors above 50 horsepower.
containment spray motors and the two safety injection pump motors
(all greater than 50 horsepower) indicate tnat no shaft rotation
Failure to
was performed from March 6, 1979 to April 3, 1979.
follow preventive maintenance procedures for safety related
electrical components is contrary to Criterion V of Appendix B to
424-425/79-07-02,
10 CFR 50 and is identified as Infraction
Electrical Preventive Maintenance.
Reactor Cavity Liner Welding (Unit 2)
c.
Chicago Bridge and Iron Company (CBI) is the contractor responsible
Fabrication
for fabrication of the reactor cavity liner plate.
will be in accordance with the CBI QA Manual for ASMI Sectio
The inspector examined the production and
Products, Issue 6.
repair veld procedures for the reactor cavity liner plate welds,
welder qualification to these procedures, 'nd in process documenta-
Certified Material Test
tion of reactor cavity liner welding.
Reports for welding electrode heat numbers 422A7571, 412E7191 an
411X1461 were examined for compliance to Part C of Section II of
Storage and control of 6010 and 7018 welding
the ASME Code.
electrode were inspected. The Region II inspector observed in
process welding of the F-1 carbon steel reactor cavity liner plates
Welding was in accordance with welding procedure "PS
(Unit 2).
E6010(SKA) by qualifie welders.
No items of nonconpliance or deviation were identifttd in the above stea
inspected.
415
166
-
g
.-