Forwards IE Insp Repts 50-460/79-06 & 50-513/79-06 on 790424-27 & Notice of Deviation
ML19207A932
Person / Time
Site: Washington Public Power Supply System
Issue date: 06/22/1979
From: Spencer G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Strand N
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML19207A933 List:
References
NUDOCS 7908230053
Download: ML19207A932 (2)


See also: IR 05000460/1979006

Text

f

'o

S

'

UNITED STATES

.

E] ,

/ g

' NUCLEAR REGULATORY COMMISSION

"

REGION V

g

c [s

7

1990 N. CALIFORNI A BOULEVARD

o

"g'.

SUITE 202, WALNUT CREEK PLAZA

%*

'

%>

,,,,,

WALNUT CREE K, CALIFORNI A 9459u

JUN 2 2 B79

Docket Nos. 50-460

50-513

Washington Public Power Supply System

P. O. Box 968

Richland, Washington 99352

Attention: Mr. N. 0. Strand

Managing Director

Gentlemen:

Subject:

NRC Inspection - WNP 1 and 4

This refers to the inspection conducted by Messrs. W. G. Albert, J. H. Eckhardt,

and J. O. Elin of this office on April 24-27, 1979, of activities authorized by

NRC Construction Permit Nos. CPPR-134 and CPPR-174, and to the discussion of

our findings held with Mr. Hultgren and other members of your staff at the

conclusion of the inspection.

Areas examined durmg this inspection are described in the enclosed inspection

report.

Within these areas, the inspection consisted of f. elective examinations

of procedures and representative records, interviews with personnel, and obser-

vations by the inspectors.

Based on the results of this inspection, it appears that one of your activities

was not conducted in full compliance with your commitments in the PSAR as set

forth in the Notice of Deviation enclosed herewith as Appendix A.

You are requested to submit to this office within thirty (30) days of your

receipt of this notice, a written statement or explanation in reply including:

(1) corrective steps which have been taken by you and the results achieved;

(2) corrective steps which will be taken to avoid further deviations; and (3)

the date when full compliance will be achieved.

In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,

Title 10, Code of Federal Regulat#ons, a copy of this letter and the enclosed

inspection repart will be placed in the NRC's Public Document Room.

If this

report contains any infonnation that you believe to be proprietary, it is

786150

7908230053;

.

Washington Public Power Supply System

2-

JtJN 2 2 B79

necessary that you submit a written application to this effice, within 30 days

of the date of this letter, requesting that such information be withheld frora

public disclosure. The application must include c full statement of the reasons

why it is claimed that the information is proprietary.

The application should

be prepared so that any proprietary infonnation identified is contained in an

enclosure to the application, since the application without the enclosure will

also be placed in the Public Document Room.

If we do not hear from you in this

regard within the specified period, the report will be placed in the Public

Document Room

Should you have any questions concerning this inspection, we will be glad to

discuss them with you.

Sincerely,

W

,/ J

G. S. Spencer, Chief

Reactor Construction and

Engineering Support Branch

Enclosures:

1.

Appendix A - Notice of Deviation

2.

IE Inspectic Report

Nos.50-46L,79-06

50-513/79-06

cc w/o enclosure 2:

M. E. Witherspoon, Division Manager

Quality Assurance, WPPSS

J. P. Thomas, Project Manager, WPPSS

.