Letter Sequence Request |
|---|
EPID:L-2018-NEW-0003, Package: Letter to F. Hilbert Request for Supplemental Information for the Review of the Model No. DN30 Package (Approved, Closed) |
Results
Other: ML19088A181, ML19088A182, ML19088A183, ML19088A184, ML19170A222, ML19170A227, ML19170A228, ML19170A229, ML19170A230, ML19170A232, ML19170A233, ML19200A132, ML19200A133, ML19200A134, ML19200A135, ML19200A136, ML19203A265, ML19203A266, ML19249B070, ML19290E730, ML19290E739, ML19290E743, ML19290E745
|
MONTHYEARML19088A1812013-08-18018 August 2013 Criticality Safety of Enriched UF6 Cylinders Project stage: Other ML19088A1822013-08-18018 August 2013 Regulatory Criticality Safety Review of Uranium Hexafluoride Transport Package Applications Project stage: Other ML19088A1842013-08-18018 August 2013 Criticality Analyses of Enriched Uranium-Hexafluoride Containing Impurities Project stage: Other ML19088A1832016-09-18018 September 2016 Hydration of Uranium Residues Contained in Enriched UF6 Cylinders Project stage: Other ML18282A0892018-09-10010 September 2018 Daher - Application for Withholding Proprietary Information from Public Disclosure Project stage: Request ML18282A0882018-09-10010 September 2018 Daher - Supplemental Information for the Review of the Model No. DN30 Package Project stage: Supplement ML18264A1322018-09-20020 September 2018 Package: Letter to F. Hilbert Request for Supplemental Information for the Review of the Model No. DN30 Package Project stage: Request ML18264A1342018-09-20020 September 2018 Letter to F. Hilbert Request for Supplemental Information for the Review of the Model No. DN30 Package Project stage: Approval ML18264A1332018-09-20020 September 2018 Enclosurequest for Supplemental Information (Letter to F. Hilbert Request for Supplemental Information for the Review of the Model No. DN30 Package) Project stage: Approval ML19070A0022019-03-0707 March 2019 Letter to F. Hilbert Request for Additional Information for the Review of the Model No. DN-30 Package (W/Enclosure) Project stage: RAI ML19066A2162019-03-0707 March 2019 Notice of Public Meeting with Daher Nuclear Technologies Gmbh (Daher) to Discuss Proposed Responses to the Request for Additional Information for the Model No. DN-30 Package Project stage: RAI ML19088A1782019-03-29029 March 2019 Application for Withholding Proprietary Information from Public Disclosure Project stage: Request ML19088A1752019-03-29029 March 2019 Daher Nuclear Technologies Gmbh, Request for Additional Information for the Review of the Model No. DN30 Package Project stage: Request ML19088A1762019-03-29029 March 2019 0023-BAR-2019-001 Answers to the Request for Additional Information Project stage: Request ML19120A0292019-04-30030 April 2019 Daher Nuclear Technologies Gmbh - Request for Extension of the Deadline to Provide the Additional Information Requested in Letter Dated March 7, 2019 Project stage: Request ML19123A2082019-05-0303 May 2019 Memorandum to C. Regan Summary of April 16, 2019, Meeting with Daher Nuclear Technologies (W/Enclosure) Project stage: Meeting ML19170A2322019-06-19019 June 2019 Technical Information Sheet - 50/50 Tin Lead Solder Project stage: Other ML19170A2272019-06-19019 June 2019 Proceedings of the 17th International Symposium on the Packaging and Transportation of Radioactive Materials Patram 2013, August 18-23, 2013, San Francisco, CA, USA - Criticality Safety of Enriched UF6 Cylinders Project stage: Other ML19170A2282019-06-19019 June 2019 Proceedings of the 17th International Symposium on the Packaging and Transportation of Radioactive Materials Patram 2013, Aug 18-23San Francisco, CA, USA - Regulatory Criticality Safety Review of Uranium Hexafluoride Transport Package Appli Project stage: Other ML19170A2232019-06-19019 June 2019 0023-BAR-2019-001-Rev1 - Response to Request for Additional Information Project stage: Response to RAI ML19170A2312019-06-19019 June 2019 Daher Nuclear Technologies Gmbh - Response to Request for Additional Information Project stage: Response to RAI ML19170A2292019-06-19019 June 2019 Proceedings of the 18th International Symposium on the Packaging and Transportation of Radioactive Materials Patram 2016 September 18-23, 2016, Kobe, Japan - Hydration of Uranium Residues Contained in Enriched UF6 Cylinders Project stage: Other ML19170A2332019-06-19019 June 2019 Nord-Lock Group - Slides Project stage: Other ML19170A2222019-06-19019 June 2019 Daher Nuclear Technologies Gmbh - Affidavit Project stage: Other ML19170A2302019-06-19019 June 2019 Proceedings of the 17th International Symposium on the Packaging and Transportation of Radioactive Materials Patram 2013 August 18-23, 2013, San Francisco, CA, USA - Criticality Analyses of Enriched Uranium-Hexafluoride Containing Impuritie Project stage: Other ML19200A1332019-07-12012 July 2019 0023-PA-2015-016, Rev. 3, Safety Analysis Report DN30 Package Project stage: Other ML19200A1362019-07-19019 July 2019 0023-PA-2015-016, Rev. 3, Inspection Criteria for Regular and Periodical Inspections of the DN30 Package Project stage: Other ML19200A1342019-07-19019 July 2019 0023-HA-2015-001, Rev. 4, Use and Handling of the DN30 Package Project stage: Other ML19200A1322019-07-19019 July 2019 Daher Nuclear Technologies Gmbh - Submittal of Final SAR for the Review of the Model No. DN30 Package Project stage: Other ML19200A1352019-07-19019 July 2019 0023-PA-2015-015, Rev. 3, Periodical Inspections of the DN30 Psp Project stage: Other ML19203A2662019-07-25025 July 2019 Enclosure 1: CoC No. 9362, Rev. No. 0 (Letter to F. Hilbert Certificate of Compliance No. 9362, Revision No. 0, for the Model No. DN30 Package (W/Enclosure 2)) Project stage: Other ML19203A2642019-07-25025 July 2019 Package: Certificate of Compliance No. 9362, Revision No. 0, for the Model No. DN30 Package Project stage: Request ML19203A2652019-07-25025 July 2019 Letter to F. Hilbert Certificate of Compliance No. 9362, Revision No. 0, for the Model No. DN30 Package (W/Enclosure 2) Project stage: Other ML19249B0702019-08-26026 August 2019 Daher Nuclear Technologies Gmbh - 0023-HA-2015-001-Rev 5, Use and Handling of the DN30 Package Project stage: Other ML19290E7452019-10-10010 October 2019 Daher Nuclear Technologies Gmbh, 0023-PA-2015-016, Rev. 4, Inspection Criteria for Regular and Periodical in, Inspections of the DN30 Package Project stage: Other ML19290E7392019-10-10010 October 2019 Daher Nuclear Technologies Gmbh, 0023-HA-2015-001, Rev. 6, Use and Handling of the DN30 Package Project stage: Other ML19290E7432019-10-11011 October 2019 Daher Nuclear Technologies Gmbh, 0023-PA-2015-015, Rev. 4, Periodical Inspections of the DN30 Psp Project stage: Other ML19290E7322019-10-17017 October 2019 Daher Nuclear Technologies Gmbh, Application for Withholding Proprietary Information from Public Disclosure Submittal of Document: Design Change of the DN30 Package Project stage: Request ML19290E7302019-10-17017 October 2019 Daher Nuclear Technologies Gmbh, Securing Bolt of the Closure Devices of the DN30 PSP Project stage: Other 2019-03-29
[Table View] |
Text
- *oAHER DAHER NUCLEAR TECHNOLOGIES GmbH, Postbox 1365, 63514 Rodenbach Mr. Pierre M. Saverot Project Manager, Spent Fuel Licensing Branch Division of Spent Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Two White Flint North - Mail Stop T 4-834 11545 Rockville Pike Rockville, MD 20852-2738 USA lhre Zelchen / Nachrlcht vom Your ref. I message Unser Zelchen / Nachrlcht vom Our ref. I message 0023-SVK-2019-007 Telefon/Fax/E-Mall
- Hanau, April 30, 2019 Docket No. 71-9362 EPID No. L-2018-NEW-0003
+49 (0)6181 501 353
+49 (0)6181 501 266 y.vanwijk@daher.com
Subject:
Request for extension of the deadline to provide the additional information requested in your letter dated March 7, 2019
Dear Mr. Saverot,
This letter is to request an extension of the deadline to respond to your request for additional infor-mation (RAI, reference Docket No. 71-9362, EPID No. L-2018-NEW-0003) to June 28, 2019.
We require this extension to include the preliminary answers provided to the NRC with our letter dated March 29, 2019 into the SAR and to answer the last questions raised during the meeting be-tween the NRC and ONT of April 16, 2019.
We kindly ask you for a confirmation of the extension.
Sincerely, DAHER NUCLEAR TECHNOLOGIES GmbH DAHER NUCLEAR TECHNOLOGIES GmbH, Margarete-von-Wrangell-Stralle 7, 63457 Hanau, Germany Telefon* +49 (0)6181 501-0, Telefax* +49 (0)6181 57 36 92. E-Mail. info.nuclear-technologies@daher.com, Internet www daher com Sitz Hanau RG Hanau HR B 4428, USt-ld*Nr DE11357 4961, Genchtsstand Hanau, Geschaftsfuhrer Olaf Old1ges Bankverb1ndung Soc,ete Generale Frankfurt (BLZ 512108 00), Konto 1095013031, SWIFT SOGEDEFF, IBAN DE 45 512108001095 0130 3 Auftrage warden aufgrund unserer Allgeme,nen Geschaftsbed,ngungen ubemommen Dlese stehen Ihnen auf Wunsch zur Verfugung SV-0432105-F 1/1