IR 05000259/2018012
| ML18276A012 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 10/03/2018 |
| From: | Masters A NRC/RGN-II/DRP/RPB5 |
| To: | James Shea Tennessee Valley Authority |
| References | |
| IR 2018012 | |
| Download: ML18276A012 (13) | |
Text
October 3, 2018
SUBJECT:
BROWNS FERRY NUCLEAR PLANT - NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION REPORT 05000259/2018012, 05000260/2018012 AND 05000296/2018012
Dear Mr. Shea:
On August 23, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed a problem identification and resolution inspection at your Browns Ferry Nuclear Plant, Units 1, 2, and 3.
On that date, the NRC inspectors discussed the results of this inspection with Mr. Lang Hughes and other members of your staff. The results of this inspection are documented in the enclosed inspection report.
The NRC inspection team reviewed the stations corrective action program and the stations implementation of the program to evaluate its effectiveness in identifying, prioritizing, evaluating, and correcting problems, and to confirm that the station was complying with NRC regulations and licensee standards for corrective action programs. Based on the samples reviewed, the team determined that your staffs performance in each of these areas adequately supported nuclear safety.
The team also evaluated the stations processes for use of industry and NRC operating experience information and the effectiveness of the stations audits and self-assessments.
Based on the samples reviewed, the team determined that your staffs performance in each of these areas adequately supported nuclear safety.
Finally, the team reviewed the stations programs to establish and maintain a safety-conscious work environment, and interviewed station personnel to evaluate the effectiveness of these programs. Based on the teams observations and the results of these interviews the team found no evidence of challenges to your organizations safety-conscious work environment. Your employees appeared willing to raise nuclear safety concerns without fear of retaliation through at least one of the several means available.
NRC inspectors documented a finding of very low safety significance (Green) in this report.
This finding involved a violation of NRC requirements. The NRC is treating this violation as non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy. If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis of your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC resident inspector at the Browns Ferry Nuclear Plant.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Anthony D. Masters, Chief Reactor Projects Branch 5 Division of Reactor Projects
Docket Nos.: 50-259, 50-260, 50-296 License Nos.: DPR-33, DPR-52, DPR-68
Enclosure:
IR 05000259/2018012, 05000260/2018012 and 05000296/2018012
REGION II==
Docket Numbers:
50-259, 50-260, and 50-296
License Numbers:
Report Numbers:
05000259/2018012, 05000260/2018012, and 05000296/2018012
Enterprise Identifier: I-2018-012-0017
Licensee:
Tennessee Valley Authority (TVA)
Facility:
Browns Ferry Nuclear Plant, Units 1, 2, and 3
Location:
Corner of Shaw and Nuclear Plant Road
Athens, AL 35611
Inspection Dates:
August 6, 2018 to August 23, 2018
Inspectors:
W. Deschaine, Resident Inspector, Team Lead
T. Stephen, Senior Resident Inspector
N. Hobbs, Resident Inspector
M. Kirk, Resident Inspector
G. Eatmon, Resident Inspector
S. Ninh, Senior Project Engineer
Approved By:
A. Masters, Chief
Reactor Projects Branch 5
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Problem Identification and Resolution Inspection at Browns Ferry Nuclear Plant, Units 1, 2, and 3 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. NRC and self-revealed findings, violations, or additional items are summarized in the table below.
List of Findings and Violations
Failure to correct an inoperable 250V Shutdown Board Battery Charger Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems
Green NCV 05000296/2018-012-01 Closed None 71153
A self-revealed, Green, NCV of Technical Specifications (TS) 3.8.4 was identified when the licensee failed to correct an inoperable 250V Shutdown Board (SDBD) 3EB Battery Charger on Unit 3. Specifically, in 2014 the 250V SDBD 3EB Battery Charger was entered into the Corrective Action Program (CAP) as a Condition Adverse to Quality (CAQ), but no actions were taken to correct the condition, which led to the component being in inoperable for longer than the allowed outage time defined in TS 3.8.4.
Additional Tracking Items
Type Issue Number Title Report Section Status LER 05000296/2018-002-00 Inoperable 250V Shutdown Board Battery Charger Results in Condition Prohibited by Technical Specifications 71153 Closed
INSPECTION SCOPE
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71152 - Problem Identification and Resolution
Biennial Team Inspection (1 Sample)
The inspectors performed a biennial assessment of the licensees corrective action program, use of operating experience, self-assessments and audits, and safety conscious work environment. The assessment is documented below.
- (1) Corrective Action Program Effectiveness: Problem Identification, Problem Prioritization and Evaluation, and Corrective Actions - The inspection team reviewed the stations corrective action program and the stations implementation of the program to evaluate its effectiveness in identifying, prioritizing, evaluating, and correcting problems, and to confirm that the station was complying with NRC regulations and licensee standards for corrective action programs.
- (2) Operating Experience and Self-Assessments and Audits - The team evaluated the stations processes for use of industry and NRC operating experience information and the effectiveness of the stations audits and self-assessments.
- (3) Safety Conscious Work Environment - The team reviewed the stations programs to establish and maintain a safety-conscious work environment, and interviewed station personnel to evaluate the effectiveness of these programs.
71153 - Follow-up of Events and Notices of Enforcement Discretion Licensee Event Reports
The inspectors evaluated the following licensee event reports (LER) which can be accessed at https://lersearch.inl.gov/LERSearchCriteria.aspx:
- (1) LER 05000296/2018-002-00, Inoperable 250V Shutdown Board Battery Charger Results in Condition Prohibited by Technical Specifications
INSPECTION RESULTS
Corrective Action Program Effectiveness Assessment 71152Problem Identification and Resolution
Based on the samples reviewed, the team determined that the licensees corrective action program (CAP) complied with regulatory requirements and self-imposed standards. The licensees implementation of the corrective action program adequately supported nuclear safety.
Problem Identification: The inspectors determined that the licensee was effective in identifying problems and entering them into the corrective action program and there was a low threshold for entering issues into the corrective action program. This conclusion was based on a review of the requirements for initiating Condition Reports (CRs) as described in licensee procedure NPG-SPP-22.300, Corrective Action Program, and managements expectation that employees were encouraged to initiate condition reports for any reason. Additionally, site management was actively involved in the corrective action program and focused appropriate attention on significant plant issues. Based on reviews and walkdowns of accessible portions of selected systems, the inspectors determined that deficiencies were being identified and placed in the CAP.
Problem Prioritization and Evaluation: Based on the review of CRs sampled by the inspection team during the onsite period, the inspectors concluded that problems were generally prioritized and evaluated in accordance with the CR significance determination guidance in procedure NPG-SPP-22.300. The inspectors determined that in general, adequate consideration was given to system or component operability and associated plant risk.
The inspectors determined that plant personnel had conducted root cause and apparent cause analyses in compliance with the licensees CAP procedures and cause determinations were appropriate, and considered the significance of the issues being evaluated. A variety of formal causal-analysis techniques were used to evaluate CRs depending on the type and complexity of the issue consistent with the applicable cause evaluation procedures.
Corrective Actions: Based on a review of corrective action documents, interviews with licensee staff, and verification of completed corrective actions, the inspectors determined that overall, corrective actions were timely, commensurate with the safety significance of the issues, and effective, in that conditions adverse to quality were corrected. For significant conditions adverse to quality, the corrective actions directly addressed the cause and effectively prevented recurrence. The team reviewed performance indicators, CRs, and effectiveness reviews, as applicable, to verify that the significant conditions adverse to quality had not recurred. Effectiveness reviews for corrective actions to prevent recurrence (CAPRs)were sufficient to ensure corrective actions were properly implemented and were effective.
Operating Experience, Self-Assessments, and Audits Assessment 71152Problem Identification and Resolution
Based on the samples reviewed, the team determined that the stations processes for the use of industry and NRC operating experience information and for the performance of audits and self-assessments were effective and complied with all regulatory requirements and licensee standards. The implementation of these programs adequately supported nuclear safety.
Overall, the team concluded that operating experience was adequately evaluated for applicability and that appropriate actions were implemented to address lessons learned as needed. In general, the inspectors determined that the licensee was effective at performing self-assessments and audits to identify issues at a low level, properly evaluated those issues, and resolved them commensurate with their safety significance.
Safety Conscious Work Environment Assessment 71152Problem Identification and Resolution
Based on a sample size of approximately 30 people interviewed from a cross-section of plant employees, the team found no evidence of challenges to a safety-conscious work environment. Employees interviewed appeared willing to raise nuclear safety concerns through at least one of the several means available.
However, the team does recognize that the licensee during a 2017 Nuclear Safety Culture (NSC) Self-Assessment in the RP department determined that the NSC was unhealthy resulting in a chilled environment in the RP department. The licensee identified Areas for Improvement (AFIs) and entered them into their CAP. The NRC was unable to determine, at this time, if the corrective actions by the licensee have been effective. The NRC will conduct a follow-up inspection in this area after the licensee has completed their effectiveness reviews.
71153 - Follow-up of Events and Notices of Enforcement Discretion
Failure to correct an inoperable 250V Shutdown Board Battery Charger Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems
Green NCV 05000296/2018-012-01 Closed None 71153
Introduction:
A self-revealed, Green, NCV of Technical Specifications (TS) 3.8.4 was identified when the licensee failed to correct an inoperable 250V Shutdown Board (SDBD)3EB Battery Charger on Unit 3. Specifically, in 2014 the 250V SDBD 3EB Battery Charger was entered into the CAP as a CAQ, but no actions were taken to correct the condition, which led to the component being in inoperable for longer than the allowed outage time as defined in TS 3.8.4.
Description:
The Licensee Event Report (LER) was associated with the Unit 3 250V SDBD 3EB Battery Charger failing its TS required surveillance test on December 22, 2017.
Operations personnel from the licensee placed the spare battery charger in service and exited TS Limiting Conditions for Operation (LCOs) for DC Sources 3.8.4. The licensee determined that a failed firing card in 250V SDBD 3EB Battery Charger was the cause of the failed TS surveillance test. Based on the results from their troubleshooting, a Past Operability Evaluation (POE) was requested on February 5, 2018. The violation of TS was first recognized on February 28, 2018, when the POE determined that the 250V SDBD 3EB Battery Charger, was functional but inoperable from April 3, 2014, until December 22, 2017, which is longer than allowed by TS, thus requiring an LER.
The apparent cause of this event was no Preventive Maintenance (PM) strategy exists to replace or refurbish subcomponents of the SDBD Battery Chargers that are vulnerable to age degradation failures. A lack of precise and rigorous communication between Operations and Engineering personnel in regards to the operability determination of the 3EB Battery Charger in 2014 was a contributing cause.
The inspectors reviewed the licensee event report and determined that the report adequately documented the summary of the event including the cause of the event and potential safety consequences.
Corrective Action(s): As an immediate corrective action, the licensee replaced the firing card in the 250V SDBD 3EB Battery Charger. The licensee also plans to create a PM strategy to replace or refurbish subcomponents of the SDBD Battery Chargers that are vulnerable to similar age degradation failures.
Corrective Action Reference(s): CR 1383682
Performance Assessment:
Performance Deficiency: The failure to correct a condition adverse to quality was a performance deficiency (PD). Specifically, in 2014 the 250V Shutdown Board Battery Charger was entered into the CAP as a CAQ, but no actions were taken to correct the condition until December 22, 2017.
Screening: This performance deficiency was more than minor because it was associated with the mitigating systems cornerstone attribute of equipment performance and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. With the 3EB Battery Charger inoperable the availability and reliability was adversely affected. An evaluation was completed and the Shutdown Board subsystem was considered functional, but inoperable.
Significance: The team used IMC 0609, Attachment 4, Initial Characterization of Findings, issued October 7, 2016, for mitigating systems, and IMC 0609, Appendix A, The Significance Determination Process (SDP) for Findings At-Power, issued June 19, 2012, and determined the finding to be of very low safety significance (Green) because the finding was a deficiency that did not represent a loss of safety function. While the charger did not meet the TS Surveillance Requirement to supply the minimum current of 50A at greater than or equal to 210V DC, the charger was capable of fully charging the battery in less than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> because it could provide a current above 27.92A, which was the required current limit for functionality.
Cross-cutting Aspect: No cross-cutting was assigned because it is not indicative of current licensee performance.
Enforcement:
Violation: Browns Ferry Nuclear Plant, Unit 3 TS Subsection 3.8.4, DC Sources - Operating, Condition A requires that with the 3EB Shutdown Board DC electrical power subsystem inoperable, restoration of the 3EB Shutdown Board DC electrical power subsystem is required within 7 days. Condition B requires that if the required action and associated completion time of condition A could not be met then the unit shall be placed in Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and Mode 4 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
Contrary to the above, the 3EB Shutdown Board DC electrical power subsystem was inoperable from April 3, 2014, to December 22, 2017, and the unit did not enter mode 3 as required in 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after exceeding the allowed outage time.
Enforcement Action(s): This violation is being treated as a NCV consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors confirmed that proprietary information was controlled to protect from public disclosure. No proprietary information was documented in this report.
- On August 23, 2018, the inspectors presented the problem identification and resolution inspection results to Mr. Lang Hughes and other members of the licensee staff.
DOCUMENTS REVIEWED
Procedures
BFN-ODM-4.16, Operator Workarounds/Burdens/Challenges, Rev. 0005
COO-SPP-22.305, Level 2 Evaluations (Apparent Cause Evaluation), Rev. 0000
OPDP-1, Conduct of Operations, Rev. 0040
OPDP-8, Operability Determination Process and Limiting Conditions for Operation Tracking,
Rev. 0024
NEDP-22, Operability Determinations and Functional Evaluations, Rev. 0018
NPG-SPP-07.1.4, Work Management Prioritization - On Line, Rev. 0008
NPG-SPP-09.16.1, Component and Program Health, Rev. 0011 System
NPG-SPP-22.000, Performance Improvement Program, Rev. 0008
NPG-SPP-22.001, Effectiveness Reviews, Rev. 0001
NPG-SPP-22.102, NPG Self-Assessment and Benchmarking Programs, Rev. 0005
NPG-SPP-22.300, Corrective Action Program, Rev. 0010
NPG-SPP-22.500, Operating Experience Program, Rev. 0007
0-TI-444(Bases), AIST Program Bases Document, Revision 0006
0-TI-444, Augmented In-service Testing Program, Revision 001
TRN-30, Radiological Emergency Preparedness Training, Revision 38
ECI-0-000-BKR008, Testing and Troubleshooting of Molded Case Circuit Breakers and Motor
Starter Overload Relays, Revision 107
EPIP-5, General Emergency, Revision 54
CAP Training Manual, Revision 5
NPG-SPP-01.7.1, Employee Concerns Program, Revision 3
NPG-SPP-22.600, Issue Resolution, Revision 4
NPG-SPP-07.3.4, Protected Equipment, Revision 4
Condition Reports
1017294
1146001
1146363
1150455
1169573
1119892
1153826
1157981
1158463
1160702
1168726
1170980
1176706
1176922
1195081
201196
204730
212034
219043
21265
21273
28557
249802
298080
249717
249723
253350
268051
281537
286193
233084
294760
1303737
1312984
22394
29543
1331462
1332866
1333906
1336241
1336242
1336246
1340855
1340872
1346131
1347792
1350086
1352009
1354876
1389131
1393879
1402739
1403761
1413619
1413619
1413620
1413621
1413623
20413
23322
23322
27962
1431238
1433902
1436281
1147778
1157182
1157862
1158643
1165935
1170124
258736
266308
267323
284073
285600
28204
29024
1379565
1384056
1384057
1392134
1407222
1419921
20973
1336830
1337825
28204
1337825
1413039
1170978
1189508
237382
268177
1395402
1161179
1161926
1172128
1348588
1385434
1393879
1409305
272790
1153853
1166017
1189404
292179
1353663
1354876
1353667
1354886
233049
1175751
1186857
29794
252195
1336349
1374607
1382275
1389480
1414608
23044
233079
294294
1161911
204735
1159943
1192000
1170978
1131140
1133821
1112692
1170971
1115172
1179483
28065
1385280
260619
1413623
1143588
1143590
1170970
260580
233076
1170968
1179696
1142006
1158499
1163243
1181071
1189810
242311
258637
276753
1314615
1331793
1345723
1145799
1393423
28030
241805
1354876
868804
1383682
Self-Assessments, Audits, and Trend Reports
QA-BF-17-008, Assessment of Security Performance, Browns Ferry Nuclear Plant, March 2-5,
2017
QA-BF-18-001, Security, Browns Ferry Nuclear Plant, June 19, 2018
BFN-OTH-FSA-17-001, Nuclear Safety Culture with Emphasis on Safety Conscious Work
Environment (Rad -Protection), 9/11/2017
BFN-OTH-FSA-17-002, Nuclear Safety Culture with Emphasis on Safety Conscious Work
Environment (Security) 9/11/2017
Site Audit Report SSA1706 Operations Browns Ferry Nuclear Plant (BFN), April 17 - 28, 2017
SSA1804, Site Audit Report Maintenance BFN, April 30 - May 11, 2018
SSA1801, Site Audit Report Materials Management & Procurement Engineering BFN,
January 22 - February 2, 2018
SSA1708, Site Audit Report Radiation Protection BFN, July 31 - August 11, 2017
BFN-PI-FSA-17-001, Nuclear Safety Culture assessment, May 30 - June 12, 2017
BFN-OTH-FSA-17-001, Nuclear Safety Culture with Emphasis on SCWE (Rad-Protection),
August 28 - August 29, 2017
QA-BF-18-006, Unit 3 Refueling Outage BFN, February 17 - April 6, 2018
QA-BF-18-001, BFN-Quality Assurance December Site Report, January 18, 2018
QA-BF-16-018, Unit 1 Outage Assessment (1R11) BFN, October 1, 2016 - November 6, 2016
QA-BF-16-017, Winter Readiness BFN, November 7, 2016 - November 10, 2016
QA-BF-16-003, BFN Operations Fleet Assessment, February 16 - February 19, 2016
Work Orders (WOs)
117339825
117760950
117764640
117821415
117861528
117877268
118304355
118393397
119186157
119371766
119524773
119594233
119639339
119639366
119639704
119676900
119259118
115707718
117595795
117962593
118372021
118433481
118557418
118880286
118880287
118662022
118680184
118680351
118842853
119099221
119259118
119462580
119531837
113729018
117217900
117877268
117638828
117675541
117692872
117770137
117822991
118014100
119408126
119539861
Cancelled Work Orders (WOs)
117977191
117968137
117966837
117967265
117952469
117910853
117822890
117966856
119685837
119130053
118288229
117698103
118152936
118077890
117968137
117888235
117838767
117839581
118330690
117651167
119130053
118660656
118578729
118493283
118237511
118122113
118091807
118061119
119158148
119158087
117648294
117663684
118456896
118225189
118169216
117724905
118027573
117938363
117907703
117907705
Other
System 571 Monitoring Plan
System 82 Health System Report April 2018
General Design Criteria Document, No. BFN-50-7082, Standby Diesel Generators
Outage Control Room Deficiencies, April 7, 2018
BFN Outage and Non-Outage Control Room Deficiencies, June 18, 2018
All Active OWAs Browns Ferry Nuclear, July 10, 2018
OWA Focus Codes: W1, W2, W3, June 18, 2018
Standing Order: OS-201, Rev 0, Interim Guidance on Verifying TS 3.8.6 Specific Gravity Limits,
8/3/2018
Air Conditioning System 031 (a)(1) Plan, Revision 6, Effective 8/18/2016
Air Conditioning System 031 (a)(1) Plan, Revision 7, Effective 5/30/2017
Air Conditioning System 031 (a)(1) Plan, Revision 8, Effective 8/23/2017
Heating and Ventilating Air Flow Diagram, Powerhouse - Turbine Building Unit 2,
Figure 10.12-1, Amendment 25
System Health Report, Unit 0, A/C Heating CREV for date range 10/1/2015-1/31/2016
System Health Report, Unit 0, A/C Heating CREV for date range 2/1/2016-5/31/2016
System Health Report, Unit 0, A/C Heating CREV for date range 6/1/2016-9/30/2016
Management Review Committee (MRC) package for August 23, 2018
Plant Screening Committee (PSC) package for August 20, 2018
Level of Effort Screening for CR 1439272
LER 50-296/2018-002-00, Inoperable 250V Shutdown Board Battery Charger Results in
Condition Prohibited by Technical Specifications, dated April 30, 2018
BFN-Unit 3 Technical Specifications 3.8.4 DC Sources - Operating, Amendment No. 212