NRR E-mail Capture - Acceptance of Shearon Harris Nuclear Power Plant, Unit 1 LAR to Change Emergency Plan EAL Scheme
ML18250A312
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 09/04/2018
From: Martha Barillas
Plant Licensing Branch II
To: Hamilton T
Duke Energy Carolinas
References
L-2018-LLA-0216
Download: ML18250A312 (3)


Text

NRR-DMPSPEm Resource From: Barillas, Martha Sent: Tuesday, September 4, 2018 3:40 PM To: Tanya.Hamilton@duke-energy.com; McDaniel, Sarah A; Robertson, Jeffrey N Cc: Barillas, Martha; Venkataraman, Booma

Subject:

Acceptance of Shearon Harris Nuclear Power Plant, Unit 1 LAR to Change Emergency Plan EAL Scheme

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1- ACCEPTANCE OF LICENSE AMENDMENT REQUEST TO CHANGE EMERGENCY PLAN EMERGENCY ACTION LEVEL SCHEME (EPID L-2018-LLA-0216)

Ms. Hamilton, By letter dated August 13, 2018 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML18226A022), Duke Energy Progress, LLC (Duke Energy) submitted a license amendment request for Shearon Harris Nuclear Power Plant, Unit 1. The proposed changes to the Emergency Plan Emergency Action Level (EAL) scheme will correct deficiencies identified and bring the site into alignment with the approved EAL methodology, Nuclear Energy Institute (NEI) 99-01 Revision 6, Development of Emergency Action Levels for Non-Passive Reactors. The purpose of this e-mail is to provide the results of the U.S.

Nuclear Regulatory Commission (NRC) staffs acceptance review of this license amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this license amendment request will take approximately 280 hours11.667 days <br />1.667 weeks <br />0.384 months <br /> to complete. The NRC staff expects to complete this review in September 2019. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me at Martha.Barillas@nrc.gov or at (301) 415-2760.

Martha Barillas Project Manager NRR/DORL/Licensing Branch II-2 1

US Nuclear Regulatory Commission 301-415-2760 DOCKET 50-400 2

Hearing Identifier: NRR_DMPS Email Number: 550 Mail Envelope Properties (BN6PR09MB123331049F04BC745FEE215CF2030)

Subject:

Acceptance of Shearon Harris Nuclear Power Plant, Unit 1 LAR to Change Emergency Plan EAL Scheme Sent Date: 9/4/2018 3:40:28 PM Received Date: 9/4/2018 3:40:37 PM From: Barillas, Martha Created By: Martha.Barillas@nrc.gov Recipients:

"Barillas, Martha" <Martha.Barillas@nrc.gov>

Tracking Status: None "Venkataraman, Booma" <Booma.Venkataraman@nrc.gov>

Tracking Status: None "Tanya.Hamilton@duke-energy.com" <Tanya.Hamilton@duke-energy.com>

Tracking Status: None "McDaniel, Sarah A" <Sarah.McDaniel@duke-energy.com>

Tracking Status: None "Robertson, Jeffrey N" <Jeffrey.Robertson@duke-energy.com>

Tracking Status: None Post Office: BN6PR09MB1233.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3316 9/4/2018 3:40:37 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: