ML18152A085

From kanterella
Jump to navigation Jump to search
Insp Repts 50-280/98-07 & 50-281/98-07 on 980726-0905. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support
ML18152A085
Person / Time
Site: Surry  Dominion icon.png
Issue date: 10/05/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML18152A086 List:
References
50-280-98-07, 50-280-98-7, 50-281-98-07, 50-281-98-7, NUDOCS 9810290251
Download: ML18152A085 (32)


See also: IR 05000280/1998007

Text

Docket Nos . :

License Nos. :

Report Nos . :

Licensee:

Facility:

Location:

Dates:

Inspectors:

Approved by: .

9810290251 981005

PDR

ADOCK 05000280

G

PDR

U.S. NUCLEAR REGULATORY .COMMISSION

REGION II

50-280. 50-281

DPR-32. DPR-37

50-280/98-07, 50-281/98-07

Virginia Electric and Power Company CVEPCO)

Surry Power Station. Units 1 & 2-

5850 Hog Island Road

Surry, VA

23883

July 26 - September 5. 1998

R. Musser. Senior Resident Inspector

K. Poertner. Resident In~pector

G. McCoy, Resident Inspector (In Training)

S. Freeman. Resident Inspector. Oconee (Sections M8.l

and M8.2)

P. Fillion and C. Smith. Reactor Inspectors (Sections

El.l. E3.l and E8.3 through E8.23)

R. Gibbs. Reactor Inspectof (Section E8.1)

D. Jones. Radiation Specialist (Sections Rl.2. Rl.3.

and Rl.4)

R. Haag. Chief. Reactor Projects Branch 5

Division of Reactor Projects

ENCLOSURE 2

EXECUTIVE SUMMARY

Surry Power Station. Units 1 & 2

NRC Integrated Inspection Report Nos. 50-280/98~07. 50-281/98-07

This integrated inspection included aspects of licensee operations.

engineering, maintenance. and plant support.

The report covers a six-week

period of resident inspection; in addition. it includes the results of

announced inspections by five Region II inspectors.

Operations

Licensee actions in preparation for the potential arrival of Hurricane

Bonnie were conservative and station operation was not i-mpacted by the

storm (Section 01.2).

The Unit 1 Auxiliary Feedwater system was properly aligned for standby

operation (Section 02.1).

The Unit 2 charging pump component cooling system was properly aligned

for normal operation.

The valve alignment procedure did not include the

surge tank sight glass isolation valves.

The licensee revised the

procedure to require that the valves be verified open (Section 02.2).

Maintenance

Unit 2 turbine inlet valve freedom testing was accomplished in

accordance with the procedure requirements and the test results were

acceptable (Section Ml.1).

Ventilation damper maintenance activities were properly documented and

procedures were present at the job site during work activities (Section

Ml. 2).

Engineering

A violation was identified for not correcting design problems.

.

conditions adverse to quality, in a timely manner.

In 1992 the licensee

identified that the setpoint for th~ overcurrent protection of the

inside recirculation spray pump motors could result in spurious tripping

upon motor starting, and that there ~as no analysis or test to

demonstrate that the components in the 125 VDC Station Battery

.Distribution System would receive rated voltage for all design basis

scenarios.

However. these conditions were not corrected as of August

1998 (Section El.1).

Violations of 10 CFR 50.71(e) for failure to update the UFSAR and 10 CFR

50.59 for the facility not being as described in UFSAR were identified.

However. the NRC is exercising discretion and refraining from issuing a

Notice of Violation in consideration of the licensee having a good UFSAR

review program in progress (Section El.1) .

2

There was a weakness. acknowledged by the licensee. in the area of

documenting how significant information such. as information notices is

disposed when that disposition involves closure without a detailed

review by an Operating Experience group reviewer (Section E3.l).

The Maintenance Rule periodic assessment met the requirements of

paragraph (a)(3) of the Maintenance Rule (Section E8.l).

An non-cited violation was identified for a condition outside the design

basis as described in Licensee Event Report 50-280. 281/98008-00.

The

cause was an inadequate test procedure (Section E8.23).

An unresolved item was identified related to not reporting the problem

described in Licensee Event Report 50-280. 281/98008-00 within 30 days

(Section E8.23).

Plant Support

Health physics practices were observed to be proper and high radiation

doors were found to be in good condition and locked (Section Rl.l).

The licensee was maintaining radioactive effluent monitoring

instrumentation in an operable condition and performing the required

surveillances to demonstrate their operability (Section Rl.2).

The onsite meteorological measurements* program was implemented in

accordance with the Updated Final Safety Analysis Report (Section Rl.3).

The licensee was maintaining the Control Room Emergency Ventilation

System in an operable condition and performing the required

surveillances to demonstrate operability of the systems (Section Rl.4).

Security and material condition of the protected area perimeter barrier

were acceptable (Section Sl).

Report Details

Summary of Plant Status

Unit 1 and Unit 2 operated at power the entire reporting period.

I. Operations

01

Conduct of Operations

01.1 General Comments (71707. 40500)

The inspectors conducted frequent control room tours to verify proper

staffing. operator attentiveness. and adherence to approved procedures.

The inspectors attended daily plant status meetings to maintain

awareness of overall facility operations and reviewed operator logs to

verify operational safety and compliance with Technical Specifications

(TSs).

Instrumentation and safety system lineups were periodically

reviewed from control room indications to assess operability. Frequent

plant tours were conducted to observe equipment status and housekeeping.

Deviation Reports (DRs) were reviewed to assure that potential safety

concerns were properly reported and resolved.

The inspectors found that

daily operations were generally conducted in accordance with regulatory

requirements and plant procedures .

01.2 Hurricane Preparations

a.

Inspection Scope (71707)

The inspectors monitored licensee actions to prepare for the potential

arrival of hurricane Bonnie.

b.

Observations and. Findings

During the inspection period Hurricane Bonnie approached the North

Carolina coast.

The licensee monitored the storm track and implemented

severe weather preparations in accordance with Operations Checklist (OC)

-21. "Severe Weather." and AP-37.01. "Abnormal Environmental Condition."

The Virginia.Electric Power Company (VEPCO) Hurr.icane Response Plan is

triggered by the predtction of hurricane force winds on-site by the

Virginia Power Weather Center.

Hurricane force winds were not predicted

durjng the approach of Hurricane Bonnie: however. the licensee did

.

implement the plan as a precautionary measure.

The inspectors reviewed

the licensee's preparations. reviewed the status of important systems.

and monitored the storm's progress. Maintenance and surveillance

activities performed by the licensee were minimized during the time

frame that Hurricane Bonnie could impact the Surry station .

2

c.

Conclusions

Licensee actions in preparation for the potential arrival of Hurricane

Bonnie were conservative and station operation was not impacted by the

storm.

02

Operational Status of Facilities and Equipment

02.1 Unit 1 Auxiliary Feedwater System

a.

Inspection Scope (71707)

The inspectors performed a walkdown of the Unit 1 Auxiliary Feedwater

CAFW) system.

b.

Observations and findings

During the inspection period. the inspectors performed a walkdown of the

Unit 1 AFW system.

The inspectors reviewed the associated system

drawings. valve alignment procedure. and inspected accessible portions

of the system to verify proper valve alignment and material condition.

The system was properly aligned for standby operation.

The inspectors

identified one electrical breaker handle which required adjustment. This

problem was identified tti the licensee for resolution.

c.

Conclusions

The Unit 1 Auxiliary Feedwater system was properly aligned for standby

operation.

02.2 Unit 2 Charging Pump Component Cooling Water System

a.

Inspection Scope (71707)

The inspectors performed a walkdown of the Unit 2 Charging Pump

Component Cooling CCHCC) system.

b.

Observations and Findings

During the inspection period the inspectors performed a walkdown of the

Unit 2 CHCC system.

The inspectors reviewed the associated system

drawings. valve alignment procedure. and inspected accessible portions

of the system to verify proper valve alignment and material condition.

The system was properly aligned for normal operation.

During review of

procedure 2-0P-51.SA. "Charging Pump CC and SW Systems Valve Alignment."

the inspectors determined the CHCC surge tank sight glass isoration

valves were not verified open by the valve alignment procedure.* The

valves were verified open by the licensee and the procedure was revised

to require that the valves be verified open during performance of the

3

valve alignment procedure.

The inspectors verified that the Unit 1

procedure required that the surge tank isolation valves be verified

open.

c.

Conclusions

The Unit 2 charging pump component cooling system was properly aligned

for normal operation.

The valve alignment procedure did not include the

surge tank sight glass isolation valves.

The licensee revised the

procedure to.require that the valves be v~rified open.

08

Miscellaneous Operations Issues (92901)

08.1

(Closed) Inspection Followup Item (IFI) 50-280. 281/97002-01:

Long term

corrective actions to resolve potential TDAFW pump overspeed trips. The

licensee has initiated a modification package to provide a seal-in

circuit in the turbine driven auxiliary feedwater start circuitry to

prevent the pump from receiving an automatic stop signal based on steam

generator level after an automatic start signal is received.

The*

licensee plans to implement the modification during the next Unit 1 and

Unit 2 refueling outages.

08.2 (Closed) Violation (VIO) 50-280/97003-01:

Loss of containment

integrity.

The inspectors reviewed the licensee's corrective actions

associated with this event and found them acceptable.

The inspectors

verified during the subsequent Unit 2 refueling outage that the specific

deficiencies identified by the violation had been corrected prior to

establishing containment integrity.

I I. Mai ntena nee

Ml

Conduct of Maintenance

Ml.1 Turbine Inlet Valve Freedom Test

a.

Inspection Scope (61726)

b:

The inspectors observed portions of the Unit 2 turbine Inlet Valve

Freedom Test.

Observations and Findings

On September 2. 1998. the inspectors observed the performance of

procedure 2-0SP-TM-001. Revision 10. "Turbine Inlet Valve Freedom Test."

The inspectors observed activities locally at the turbine throttles. in

the emergency switchgear room and in the control room.

During the test.

the number 1 governor valve failed to shut in the maintenance mode and

the D intercept valve shut when the C reheat stop and intercept valves

were tested.

Neither of these problems invalidated the testing in

progress. and both were identified in DR S-98-2142 for further

investigation.

The number 1 governor valve was subsequently repaired.

4

The testing was performed in accordance with the procedural

requirements. and the test results were acceptable.

c.

Conclusions

Unit 2 turbine inlet valve freedom testing was accomplished in

accordance with the procedure requirements and the test results were

acceptable.

Ml.2 Ventilation Damper Maintenance

a.

Inspection Scope (62707)

The inspectors ob~erved portions of the work activity associated with

Work Order (WO) 00375779 and reviewed the completed work package.

b.

Observations and Findings

On September 3. 1998. the inspectors reviewed maintenance activities

associated with WO 00375779.

The WO was generated as a preventive

maintenance activity to lubricate the converter for the valve actuator

assbciated with ventilation damper 2-VS-MOD-200A.

The work activity was

performed in accordance with procedure O-MCM-0504-02. "Ventilation

Damper Actuator Overhaul ... Revision 2-P3.

The work activity consisted

of replacing the existing valve actuator with a new actuator.

The

licensee replaced the actuator to reduce the out of service time

associated with performing the maintenance activity. The licensee plans

to refurbish the actuator that was removed.

The inspectors noted that

the procedure was present at the job site during wotk activities

observed and that the component was properly isolated to allow the work *

activity to commence.

c.

Canel usi ans

Ventilation damper maintenance activities were properly documented and

procedures were present at the job site during work activities observed.

MS

Miscellaneous Maintenance Issues (92700, 92902)

M8.1

(Closed) Licensee Event Report (LER) 50-280/97001-00 and -01:

Shutdown

due to steam drain line weld leak. The events described in this LER

were previously discussed in Inspection Reports (IRs) 50-280. 281/96-13

and 50-280. 281/97-03.

The inspectors reviewed Revisions O and one of

the LER and proposed corrective action plan to prevent recurrence and

found them adequate.

The corrective actions included changing the

procedure for main turbine trip block assembly corrective maintenance to

add pull force testing of the trip solenoid coil. changing the turbine

trip signal functional test to include testing of the trip solenoid

prior to startup. and to replace the source range detectors every third

cycle.

The inspectors verified these actions had indeed been

implemented.

5

M8.2

(Closed) LER 50-280. 281/97002-00 and -01:

One train of auxiliary

ventilation system inoperable outside TS.

This LER and the events

leading to it were previously discussed in IR 50-280. 281/97-02.

Non-

cited Violation CNCV) 50-280. 281/97002-02 was identified for failure to

maintain two trains of Auxiliary Ventilation operable as required by TS.

The inspectors reviewed Revisions O and 1 of the LER and corrective

actions to prevent recurrence and found them adequate.

Revision 1 of

the LER stated that given the state of damper 1-VS-MOD-588. if an

automatic start signal occurred when fan 58A was operating, reverse

rotation of fan 588 could have been enough to cause fan 588 to fail to

start or continue to run.

The corrective actions for Revision 1

included revising the ventilation filter train test to address reverse

rotation considerations on fan operability. including checking for

reverse rotation with the opposite fan running.

The inspectors verified

these actions had indeed been implemented.

M8.3

(Closed) VIO 50-280/97003-02:

Failure to follow maintenance procedures.

M8.4

This violation involved the failure to properly install the cavity seal

ring in preparation for refueling. Corrective actions included the

modification of procedure O-MCM-1150-01. Reactor Disassembly and

Reassembly, to specify a sign-off step for the installation of RTV 3145

sealant along the inner J-seal.

The licensee also committed to form a

task team to review this violation and other maintenance procedural

compliance issues and implement management-approved recommendations.

Revision 6 of procedure O-MCM-1150-01 has been modified such that there

are individual sign-offs for each step of the cavity seal ring

procedure.

The step for sealant application now specifically requires

application along the entire circumference of the inner and outer J-

seals.

The accompanying figure. Figure 13 has also been modified to

clearly indicate where the sealant is to be applied.

A maintenance task team reviewed the maintenance procedural compliance

issues and identified four recommendations which were all accepted by

management.

These recommendations emphasized the role of first-line and

second-line management's monitoring of maintenance field work.

These

recommendations were tracked by the licensee's Commitment Tracking

System (CTS) (CTS Item 3844) and have been completed*.

(Closed) IFI 50-280. 281/97007-02: Alternate Alternating Current CAAC)

diesel coolant temperature concerns and long term actions to resolve the

issue. This item was opened for followup of inspectors* concerns about

the elevated operating temperature of the AAC diesel in certain specific

meteorological conditions.

When the AAC diesel is operated while wind

is from the northwest. the exhaust was blown back into the suction of

the rooftop radiators. resulting in elevated operating temperatures.

As a result of the temperature concerns. the licensee initiated Design

Change Package CDCP)92-052 and modified the diesel exhaust piping such

that the exhaust is released to the atmosphere vertically, at

approximately the same elevation as the exhaust of the radiators. This

will cause the hot exhaust gasses to be carried up and away from the

6

diesel building along with the radiator exhaust and reduce the

overheating problems previously noted.

Although the winds were not out

of the northwest, the AAC di ese_l has been subsequently opera ti ona lly

tested after the installation of the

modification.

M8.5

(Closed) VIO 50-280. 281/97002-03:

Procedures not appropriate to the

circumstances.

The inspectors reviewed the licensee's response to NRC

Inspection Report 50-280, 281/97-02, dated May 6, 1997. which describes

the corrective actions for the above listed violation. This violation

involved two instances where the licensee had failed to prescribe

adequate instructions for activities affecting quality.

Based on the

inspectors* review of the violation response letter and the related

corrective actions. it was concluded that the licensee had completed the

required actions for this violation.

III. Engineering

El

Conduct of Engineering

El.1 Followup to Surry Plant Design Inspection

a . Inspection Scope (37551. 92903)

In February and March 1998, the NRC, Office of Nuclear Reactor

Regulation CNRR), Events Assessments. Generic Communications and Special

Inspection Branch. performed a design inspection of the Safety Injection

and Recirculation Spray systems.

The results of this inspection were

recorded in the design inspection report (NRC Inspection Report Nos. 50-

280, 281/98-201) issued May 11. 1998.

The report transmittal letter and

Executive Summary communicate the following conclusions:

Discrepancies were identified regarding adherence of the systems

to their design and licensing basis.

The team found examples of inadequate corrective action for

potential problems identified by the 1992 Electrical Distribution

System Functional Assessment Can internal assessment).

The team identified a number of UFSAR discrepancies.

The.design inspection report transmittal letter states that any

. enforcement action resulting from that inspection will be handled by NRC

Region II via separate correspondence.

During the week of August 24 -

28, 1998. two Region II inspectors conducted an inspectiori at the VEPCO

corporate offic~ in Richmond. VA. to evaluate the findings of the design

inspection to determine whether they represent violations of NRC

requirements.

Each IFI and Unresolved Item (URI) are discussed in

Section ES, Miscellaneous Engineering Issues .

7

b.

Observations and Findings

Observations and findings regarding the issues of corrective action and

UFSAR discrepancies are discussed below.

Resolution of Design Problems Identified by the Licensee

In December 1992. the licensee completed a calculation which reviewed

and documented the overcurrent protection and coordination for the 480 V

safety-related load centers for Units 1 and 2 (refer to IFI 98201-06).

The number and title of that calculation are EE-0497. Safety-Related 480

V Load Center Coordination.

The Summary of Results section of EE-0497

discusses the Inside Recirculation Spray (IRS) pump motors. and states:

The nominal instantaneous setting is greater than 173

percent of the locked-rotor current. accounting for

the maximum possible DC offset.

Based on the

tolerance of the type OD trip device instantaneous

units (+/- 20%). 173 percent is not maintained.

This statement meant that theoretically the circuit breakers protecting

the IRS motors could trip on motor starting. The relevant design

criterion. as stated on sheet 40 of the calculation. was to have the

instantaneous trip device set above 173 percent of locked-rotor current

as a minimum. with 200 percent being preferred. Actually, the 173

percent setpoints was in terms of locked-rotor amperes at 460 V.

The

inspectors estimated what the voltage at the terminals of the motor

would be upon starting assuming 480 Vat the bus and 300 feet of cable.

The estimate was 446 V.

The setpoint in terms of locked-rotor current

at 446 V was nominal 181 percent. with an uncertainty band of 144 to 199 *

percent. Therefore. the inspectors agreed with the calculation

conclusion that theoretically the motor could trip upon starting. as the

transient starting current could be above the minimum trip point.

The

setpoints have not been re~ised as recommehded by the calculation.

No

DR was written for this problem at the time the calculation was issued.

In March 1997. the breaker for the Unit 1 lA IRS pump spuriously tripped

upon starting. and DR S-97-0943 was initiated. It was reasonable to

assume that there has not been repeated spurious tripping of the IRS

motor circuit breakers upon starting in the past. otherwise problem.

reports would have been written by the operators. This concept was used

by the inspectors to conclude that there was no immediate operability

concern.

Nevertheless. the inspector's position was that the setpoiht

should be brought within the design criteria at the earliest

opportunity. *

In about June 1992. the licensee performed an Electrical Distribution

System Functional Assessment CEDSFA) on Surry. That assessment

.

identified th~t there was no analysis or test to demonstrate that the

components on the 125 VDC Station Battery Distribution System would

receive rated voltage for all de~ign basis scenarios.

Rated voltage is

given as a range. i.e .. minimum and maximum.

EDSFA Item A-105 addressed

the issue of low voltage and Item A-185 addressed the issue of high

8

voltage.

The inspectors were not able to ascertain the official status

of these items.

However. it was clear from discussions with the

cognizant engineers that nothing had been done on these items.

During the period of the design inspection. the licensee performed some

voltage analysis on components selected by the design inspection team

(inspection questions S-98-130 and 131).

These questions were reviewed

by the inspectors during the current inspection. and the inspectors

agreed that the question responses gave some measure of confidence that

there was no immediate operability concern with low voltage.

Both the breaker setpoint issue and the DC voltage analysis issue

represent condition adverse to quality identified by the licensee in the

past for which no DR was written and no corrective action was taken

until intervention by the design inspection team.

These circumstances

represent a violation of 10 CFR 50. Appendix B. Criterion XVI.

"Corrective Action." which requires that conditions adverse to quality

be corrected in a timely manner.

Subsequent to the design inspection.

the licensee has committed to implement corrective actions for these

problems.

In the inspection report response letter. dated July 9. 1998.

on Attachment 1. pages 34 and 35. the licensee states: "The development

of a new DC System transient model and calculation encompassing end

components will be completed by December 16. 1999." The inspectors

examined Commitment Tracking System (CTS) Item No. 4211. and observed

that the action plan included an item to develop a new DC System *

transient model and calculation encompassing end components by December

1. 1999.

The inspection response letter Attachment 1. page 21. states:

"Virginia Power will provide additional tripping margins. as required.

between the individual motor feeders [breaker setpoint] and the locked

rotor curr~nt." Furthermore. it states on page 21 that this will be

accomplished by revising calculation EE-0497 and preparing a DCP to

implement the setpoint changes.

During the inspection the licensee

indicated that the IRS breaker setpoint change will be implemented in a

timely manner.

The inspectors examined CTS Item Nos. 4210 and 4290. and

observed that they were tracking the resolution of problems with

Calculation EE-0497 and specifically the IRS pump breaker problem.

In

addition. the inspection response letter Attachment 2. pages 1 and 2.

discusses the corrective action problem identified by the design

inspection team (and discussed in this section). Attachment 2 proposes

to p~rform a root cause analysis on the poor disposition of the EDSFA

findings and to take programmatic type corrective actions if needed.

The *circumstances described above. i.e .. failure to take corrective

action for identified design type problems. constitute a violation of 10

  • CFR 50. Appendix B. Criterion XVId and will be identified as Violation

50-280. 281/98007-01. Failure to Take Corrective Action for Identified

Design Problems.

UFSAR Discrepancies

The design inspection report identified eighteen UFSAR discrepancies..

inaccuracies. inconsistencies etc. These are listed in Section El.4.2

C.

9

of the report. along with some Design Basis Document COBO)

discrepancies.

During the current inspection. the inspectors evaluated

each of the UFSAR items for significance.

Each of the items fell into

one of three categories:

A.

A clarification of original or old wording would enhance the

document

B.

50.71(e) issue

C.

50.59 issue

Based on these evaluations. the inspectors concluded that items in A

above were not violations of NRC requirements.

Items in Band C above

were violations of 10 CFR 50.71(e) for failure to update the UFSAR and

violations of 10 CFR 50.59 for the facility not being as described in

UFSAR. respectively.

However. according to NUREG 1600. "General

Statement of Policy and Procedures for NRC Enforcement Actions." (the

Enforcement Policy) as revised on May 13. 1998. the NRC may refrain from

issuing a Notice of Violation when certain criteria are met for issues

considered old design issues. Discretion may be considered if. in the

Staff's view. the licensee would have identified the violation in light

of the defined scope. thoroughness. and schedule of the licensee's

initiative CUFSAR review program).

The scope of the licensee's UFSAR

review program is defined in a letter from VEPCO to the NRC dated May

23. 1997. on the*subject of an integrated configuration management

program.

The inspectors saw documentation that nine of the eighteen items in the

report were already resolved by the licensee in that the necessary

evaluations had been performed and the revised wording had been

prepared.

The inspectors examined a sample of these changes. and found

that the evaluations and revised wording were correct.

The inspectors

also examined the methodology and data bases utilized in the UFSAR

review program. and found that documentation was detailed and extensive.

The inspectors concluded the licensee had a good UFSAR review program.

The inspectors *also noted that the UFSAR review program had not.*

completed any system at the time of the design inspection.

In summary. the UFSAR discrepancies identified by the design inspection

team did represent a violation of the requirement to update the UFSAR. *

However. the NRC is exercising discretion in accordance Section VII.B.3

of the Enforcement Policy and refraining from issuing a citation for

this Severity Level IV violation.

Conclusions

A violation was identified for not correcting design problems.

conditions adverse to quality. in a timely manner.

In 1992 the licensee

identified that the setpoint for the overcurrent protection of the

inside recirculation spray pump motors could result in spurious tripping

upon motor starting. and that there was no analysis or test to

10

demonstrate that the components in the 125 VDC Station Battery

Distribution System would re~eive rated voltage for all design basis

scenarios.

However. these conditions were not corrected as of August

1998.

.

Violations of 10 CFR 50.71(e) for failure to update the UFSAR and 10 CFR

50.59 for the facility not being as described in UFSAR were identified.

However. the NRC is exercising discretion and refraining from issuing a

Notice of Violation in consideration of the licensee having a good UFSAR

review program in progress.

E3

Engineering Procedures and Documentation ..

E3.1 Conduct of Operating Experience Review Program

a.

Inspection Scope (92903)

The inspectors reviewed the licensee's evaluation for NRC Information

Notice IN 98-22. Deficiencies Identified During NRC Design Inspections.

b.

Observations and Findings

C .

The Significant Information Focus Team. which is the second level of

screening for INs. disposed IN 98-22 as follows: "Close to the North

Anna architect/engineer inspection preparation team review.

Information

copies sent to Configuration Management. Nuclear Training and two

supervisors at the Surry plant." North Anna did not receive an

architect/engineer inspection and the preparation team was dissolved

before it reviewed the subject IN.

The Corporate Operating Experience Coordinator. who chairs the

Significant Information Focus Team meetings, stated that. even though

not documented. the IN was not recommended for detailed review by the

Operating Experience group because each of the items had already been

received via separate communication.

He also stated that the IN was

included in technical staff training.

The inspectors did not

independently confirm these statements.

Apparently as a result of NRC inquiry into the handling of IN 98-22. the

IN has been reopened. and will receive a detailed review by an Operating

Experience reviewer.

The inspectors commented that there appeared to be a weakness in

documenting the reason for closeout of the IN.

The Corporate Operating

Experience Coordinator agreed with that comment.

He indicated that they

were in the process of improving the documentation of reasons for items

closed without detail evaluation by an Operating Experience reviewer~

Conclusions

There was a weakness. acknowledged *by the licensee. in the area of

documenting how significant information such as INs are disposed when

11

  • that disposition involves closure without a detailed review by an

Operating Experience group reviewer.

EB

Miscellaneous Engineering Issues

E8.l Maintenance Rule Periodic Assessment

a.

Inspection Scope (37551. 62706. and 92902)

Paragraph (a)(3) of the Maintenance Rule requires that performance and

condition monitoring activities and associated goals and preventive

maintenance activities be evaluated taking into account. where

practical. industry-wide operating experience. This assessment is

required to be performed at least one time during each refueling cycle.

not to exceed 24 months between evaluations.

The inspectors discussed

the requirements .with the corporate Maintenance Rule coordinator who is

responsible for this activity. The inspectors also reviewed the

completed assessment which was issued in March 1998.

b.

Observations and Findings

The inspectors verified that the completed assessment was in accordance

with the guidance contained in NUMARC 93-01. "Nuclear Energy Institute

Industry Guidelines for Monitoring the Effectiveness of Maintenance at

Nuclear Power Plants." Revision 2. which included review of: goals and

monitoring, performance criteria. effectiveness of corrective actions.

balancing of availability and reliability, the use of industry operating

experience. and effectiveness of a preventive maintenance program.

C.

Conclusions

The Maintenance Rule periodic assessment met the requirements of

paragraph (a)(3) of the Maintenance Rule.

E8.2 (Closed) VIO 50-280. 281/97002-04:

Failure to meet the requirements of

10 CFR 50.9(a) for LER 50-280/97002-00. and

(Closed) VIO 50-280/97003-03:

Failure to meet the requi~ements of 10

CFR 50.9(a) for LER 50-280/97001-00.

  • The inspectors reviewed the licensee's response to NRC Inspection Report

50-280. 281/97-02. dated May 6. 1997. which describes corrective actions

for the violations listed above.

These violations involved reporting

inaccurate information to the NRC in Licensee Event Reports.

Based on

the inspector's review of the violation response letter and the related

corrective actions. it was concluded that the licensee.had completed the

required actions for these violations.

E8.3

(Open) IFI 50-280. 281/98201-01:

Low Head Safety Injection (LHSI) pump

Net Positive Suction Head (NPSH).

This item involves the method of

calculation of the available NPSH for the LHSI. Inside Recirculation

Spray (IRS) and Outside Recirculation Spray (ORS) pumps.

The issue is

12 -

the same as the issue of Generic Letter 97-04. "Assurance of Sufficient

Net Positive Suction Head for Emergency Core Cooling and Containment

Heat Removal ... issued October 7. 1997.

The NRC is reviewing information

on this issue supplied by the licensee in response to the design

inspection report. in response to the generic letter and in response to

a request for additional information.

The IFI remains open pending

review by the NRC.

E8.4 (Closed) IFI 50-280. 281/98201-02:

Error in Calculatjon SM-104. Reactor

Cavity Water Holdup.

The IFI was opened because calculation SM-104.

Revision 1. failed to account for some of the water volume lost over a

period of time from the containment floor.

The calculation was revised

by the licensee to address this concern.

The inspectors reviewed

revision 2 of the calculation which determined the available Net

Positive Suction Head (NPSH) for safeguard pumps following a design

basis Loss of Coolant Accident (LOCA) based on the effects of the

following:

Holdup of spray water in the reactor cavity

Recirculation spray piping fill volume

Draining condensate films on passive heat sinks in containment

Suspended spray droplets in the containment atmosphere.

Based on the results of the above analysis the following penalties were

applied to currently reported available NPSH values in order to reflect

the integrated effects of these uncertainties:

Outside recirculation spray pumps; -0.15 foot

Inside recirculation spray pumps~ -0.16 foot

Low head safety injection pumps; -0.17 foot.

The licensee prepared UFSAR change request number FS-98-021 to revise

UFSAR sections 6.2 and 6.3.

The basis for this change was Westinghouse

Nuclear Safety Advisory Letter (NSAL)97-009. Containment Sump Issues.

The licensee's review of the issues listed in NSAL 97-009 led to the

conclusion that the penalties documented in calculation SM-104. Revision

2. should be subtracted from ~urrently reported NPSH for the spray

.

pumps.

The inspectors reviewed the 50.59 evaluation. performed for the

UFSAR change, and verified that the UFSAR change request was in the

licensee's commitment tracking system with a schedule completion date of

August 31. 1998.

This item was being tracked by Task Item No. 682.

Based on objective evidence reviewed this item is closed.

EB.5

(Open) URI 50-281/98201-03: -Unit 2 LHSI pump minimum flow.

The design

inspection team identified that one of the Unit 2 Low Head Safety

Injection (LHSI) pumps could be subjected to less than rated minimum

13

flow for certain design basis scenarios. The susceptibility of the LHSI

pumps to interact during recirculation at close to shut off head

conditions was documented by the licensee on DR S-98-0660.

Additionally. in response to DR S-98-0660 the licensee prepared

calculation number ME-0558 in order to evaluate a proposed plant

modification to the Unit 2 LHSI pump recirculation piping.

The

inspectors reviewed calculation ME-0558 and determined the scope of the

plant modification to include relocating each LHSI pump recirculation

line from downstream of the pump discharge check valve to upstream of

the discharge check valve.

The calculation* concluded that with

implementation of the plant modification the LHSI pumps discharge flow

rates during parallel operation will result in flows of* approximately

132 gpm for pump 2-SI-P-lA and 185 gpm for pump 2-SI-P-lB.

As discussed

in NRC Inspection Report Nos. 50-280. 281/201. paragraph E.1.2.1.2(g).

the Unit 2 LHSI pumps .were considered operable based on 18 gpm

recirculation flow and operator action within 30 minutes to secure one

LHSI pump.

Consequently, the post modification flow rate of 132 gpm and

185 gpm were considered adequate to maintain the Unit 2 LHSI pumps

operable.

The licensee in their response letter to the design inspection. dated

July 9. 1998. committed to implement a plant modification during the

1999 Refueling Outage (RFO) for Unit 2 and the 2000 RFO for Unit 1 in

order to resolve this issue. The licensee also committed to review

their response to NRC IEB 88-04 to ensure that there are no other

invalid assumptions regarding pumps that are susceptible to potentially

harmful interactions. * The review will be completed by October 1. 1998.

and a revised response submitted if necessary.

The URI remains open pending evaluation of other potential design basis

issues.

E8.6

(Open) IFI 50-280/98201-04:

Motor thermal overload for 1-SI-P-lB.

In

the licensee's response to the design inspection report. dated July 9.

1998. the licensee committed to provide overcurrent protection for the

1-SI-P-lB motor by adjusting the setpoint of the trip devi.ce or

replacing the trip device if necessary.

The inspectors observed that

this item was tracked by CTS No. 4288.

Also. the licensee has been

requested to furnished additional details of the equipment in a

telephone conversation on July 28. 1998.

The IFI remains open pending

review by the NRC.

E8.7

(Open) IFI 50-280. 281/98201-05:

Adequacy of 4160 VAC electrical cables

to withstand fault current.

Reference to IEEE standards indicates that.

given the available short-circuit current magnitude. the breaker

operating time and the type of cable (aluminum conductor), a minimum

size of 250 KCM would be required to ensure that the 250 °C momentary

temperature rating is not exceeded.

The problem is that several

circuits have smaller conductors. for example the charging pump motors

are fed with No 1 AWG size cable.

The fact that some cables are

undersized from a short-circuit viewpoint means that. if a short-circuit

were to occur on one of those cables. the protecting circuit breaker

14

could not possibly operate fast enough to prevent severe damage along

the whole length of the cable. This situation raises questions about

whether the installation meets Appendix R requirements.

One specific

question is whether a fire induced short-circuit on a circuit not

required for safe shutdown could result in significant damage to a safe

shutdown required circuit given the fact that the two circuits could be

in close proximity in a cable tray.

As stated in the licensee's response to the design inspection report.

dated July 9. 1998. and as confirmed during the inspection. the

licensee's approach to resolving this issue is to attempt to obtain test

reports that will show that a cable damaged by short-circuit could *not

result in damaging an adjacent cable to the extent that it could not

perform its intended functi.on.

The licensee stated they had knowledge

that tests had already been conducted for use at another plant that

would apply to the Surry situation.

The inspectors* position was that the licensee's approach was

reasonable. and they should be given a* reasonable period of time to

pursue that approach.

Should the licensee use a test report to show

that the existing installation is acceptable. the NRC would want to

review that report.

In addition. the NRC would want to verify by on-

site inspection that configurations assumed in the report are consistent

with the actual installation. If the test report cannot be obtained or

cannot be used to show acceptability of the existing installation. then

compliance with Appendix R would be in question. and the NRC would

monitor that situation.

For the reasons stated herein. the IFI remains

open.

E8.8

(Closed) IFI 50-280. 281/98201-06:

Breaker-to-breaker and breaker-to-

fuse analysis. This issue involves problems discussed in the Summary of

Results and Conclusions sections of -Calculation EE-0497.

This

calculation was Completed in December 1992. and its purpose was to

determine the setpoints of the overcurrent trip devices at the safety-

related 480 V load centers of both units.

It was a re-constitution type

calculation generated because the basis for the original setpoints was

lost. The IFI does not involve breaker to fuse coordination as that is

not covered by Calculation EE-0497.

The Summary of Results section states that several problems (with the

existing setpoints) were identified in the calculation. but that none of

thes~ were safety significant. The inspectors reviewed each problem

discussed in the Conclusions section of the calculation.

The inspectors

agreed that the problems were not safety significant. except for* one

case. That case is the setpoint for the IRS pump motors. which is

discussed in Section El.1 of this report under the heading: Resolution

of Design Problems Identified by the Licensee.

In the response letter

to the design inspection report. dated July 9. 1998. the licensee

committed to resolve all issues discussed in the EE-0497 calculation by

making setpoint changes if necessary.

The inspectors noted that CTS

Items 4210 and 4290 were tracking this item.

The IFI was closed.

15 *

E8.9

(Closed) IFI 50-280. 281/98201-07:

Breaker replacement.

In their

response to the design inspection report. the licensee committed to

replace circuit breakers as necessary at the next refueling outages to

make the enhancements recommended. or implied by, the analysis of

penetration protection.

The analysis is contained in Technical Report

EE-0094. Containment Electrical Protections - Electrical Protection

Devices - Power Circuits Surry Unit 1. and EE-0095 for Unit 2.

The

inspectors reviewed these technical reports. and agreed with the

licensee's position that the technical report conclusions did not

represent any operability concerns.

The inspectors observed that CTS

Item No. 4291 was tracking this work scope.

E8.10 (Open) URI 50-280, 281/98201-08:

Emergency Diesel Generator (EOG)

battery transfer switch.

The design inspection team identified that

there was no analysis to demonstrate the capacity of number 3 EOG

battery to supply two sets of EOG loads.

The lack of analysis raised

questions about a possible common mode failure. because the breaker

which could connect the second set of loads did not have sufficient

administrative controls.

In response to the NRC's concern the licensee prepared Potential Problem

Report (PPR) No.98-021. dated March 2. 1998, which described the desigh

adequacy of the transfer switches used to allow 125 VDC control power

for the number 1 and/or 2 EDGs to be supplied from number 3 EOG battery .

This PPR documented an evaluation of the applicable design criteria for

the original plant design and the licensing basis for the use of these

switches.

The PPR stated that because use of the throw over switches

were permitted by procedure and no analysis of their use was found. it

was recommended that a station DR be written in order to initiate

corrective action.

The PPR also recommended that (1) operation of the

switches be prevented by pulling their respective fuses and locking them

in the position where each battery is powering its associated EOG 125

voe load; and (2) revising plant procedures O-AP-17.04 and O-FCA-12.00

to remove the requirement for use of the switches.

In the response to the design inspectioh report. dated July 9. 1998. the

licensee stated the switch has been disabled by locking them in the

"open" position. -The inspectors reviewed station DR S-98-0605 and

verified that the recommendations of PPR-98-021 had been incorporated

for disabling the transfer switches and revising the procedures to

delete the steps detailing operation of the switches. This item has

been incorporated in the licensee's commitment tracking system and

assigned CTS No. 4202 to ensure completion of this commitment by June

30. 1999. Additionally, a Request for Engineering Assistance (REA) has

been submitted for preparation of a design change package to either

physically remove or physically secure the throw over switches to

prevent their use in the future.

Although these corrective actions were

adequate to address the issue. the URI will remain open pending review

by the NRC to determine whether an unreviewed safety question was

involved during past operation.

16

E8.11 (Open) URI 50-280. 281/98201-09:

DC tie breaker. This item was

identified in connection with a concern of whether closing the DC tie

breaker with both batteries connected to the DC busses constituted an

Unreviewed Safety Question (USQ).

The licensee wrote station DR S-98-

0719 to document that the interim configuration of two batteries and

four chargers was not covered by a calculation of record and would

likely exceed the fault interrupting current of the bus.

The inspectors

reviewed DR S-98-0719 and determined that the licensee's developed

corrective actions for this item included the following:

Station engineering to provide guidance for revising procedures on

how to perform removal and return to service of the station

batteries by July 31. 1998.

Procedures department to revise procedures 1/2-MOP-EP-30 and 31;

and l/2-MOP-EP-204 thru 207 by September 15. 1998.

The above corrective actions have been incorporated in the licensee's ,

commitment tracking system. Additionally, CTS No. 4292 has been

assigned to monitor completion of the corrective actions which has been

scheduled for October 1. 1998. in the commitment tracking system. This

i tern. remains open pending review by the NRC to determine whether an

unreviewed safety question exists or existed in the past.

Also. the design inspection team identified a issue as to whether the

molded case switch used to cross connect the station batteries met

applicable regulatory requirements (IFI 50-280. 281/98201-10).

Station

DR S-98-0661 was written to document this plant condition and to

initiate corrective action. The inspectors reviewed DR S-98-0661 a~d

verified that corrective actions had been developed for resolution and

recurrence control of this item. *The corrective action plan involved

preparation of a Type 1 report. "Evaluation of DC Cross-Tie Surry

Station." dated July 31. 1998. This report concluded that the existing

molded-case switch which serves as the DC cross-tie does not meet Safety

Guide 6 requirements of having at least one interlock to prevent

operator error that could parallel their standby sources.

It also

recommended that the existing DC system be modified by supplementing the

existing molded-case switch or replacing the single molded-case switch

with two devices. A Request for Engineering Assistance (REA) was

prepared for development of the plant modification in support of

implementation by the end of Unit 2 year 2000 RFO and by the end of Unit

1 year 2001 RFO.

In the response to the design inspection report. dated July 9. 1998.

licensee committed to perform an evaluation to determine whether

modifications were required to comply with Safety Guide 6.

The licensee

also committed to develop design change packages to support

implementation by the end of Unit 2 2000 RFO and by the end of Unit 1

2001 RFO.

The inspectors verified that this item had been incorporated

in the licensee's commitment tracking system and CTS No. 4262 had been

assigned for monitoring closure of all corrective actions.

However.

final disposition of this manner is pending evaluation cif the USQ.

17

E8.12 (Closed) IFI 50-280. 281/98201-10:

DC bus tie interlock. This issue*

has been combined with URI 50-280. 281/98201-09.

Thus. the IFI is

considered closed.

E8.13 (Closed) IFI 50-280. 281/98201-11:

Battery calculation discrepancies.

The inspectors reviewed Calculation No. EE-0046. "125 VDC Loading

Analysis-Unit 1 Batteries: Analysis of New Annunciator Loading,"

Revision 1. Addendum OlB which was prepared by the licensee to address

concerns identified by the NRC.

The calculation evaluated station batteries lA and lB new loading for

the replacement annunciators and incorporated changes to battery lA and

1B load model based on the February 1998 Surry A/E inspection.

The

revision addressed the two-hour accident duty cycle for battery lA and

lB and the four-hour Station Blackout (SBO) duty cycle for battery lA.

Based on the above review the inspectors verified that the changes in

the load model in response to the findings of the A/E inspection

included:

Inverter load based on the accident loading of the vital busses in

lieu of inverter full load rating.

Switchgear manufacturer recommendation for using switchgear spring

charging motor current of 6.5 times rated current of 10 Amps.

Inclusion of an additional breaker operation in the first minute

of the duty cycle for additional conservatism.

Inclusion of a random load for an additional breaker operation

during the duty cycle for additional conservatism.

The licensee in their- response to the design inspection report. *dated

July 9. 1998. committed to revise calculation EE-0046 by March 30. 1999.

to incorporate all A/E inspection findings.

The inspectors verified

that CTS No. 4211 had been assigned to Corporate Engineering for

completion of this item.

Based on objective evidence reviewed this item

is closed.

E8.14 (Closed) IFI 50-280. 281/98201-12:

Battery design margin.

The design

inspection report identified the following concerns with calculation

14937.28. Verification of Lead Storage Battery Size for Emergency Diesel

Generator. Revision 2:

Calculation should provide worst case battery loading by assuming

at least two unsuccessful starts in the first minute.

The starting currents for some DC motors in the EOG starting

circuit may be partially concurrent with the current drawn by the

EOG field flashing circuitry.

18

The second start attempt in the first minute invokes two redundant

starting circuits thereby almost doubling the load demand.

In response to the above concerns the licensee wrote station DR S-98-

0677 to document deficiencies and initiate corrective actions.

Additionally, the licensee in their response to the design inspection

report. dated July 9, 1998. stated that an operability review had been

performed for the issues listed on station DR S-98-0677 and concluded

that the Emergency Diesel Generator (EOG) battery had adequate margin

such that the documented deficiencies do not present an operability

concern.

The license also committed to revise calculation 14937.28 for

the EOG battery two hour load profile to incorporate the concerns listed

above.

Calculation 14937.75. Verification of Lead Storage Battery Size

for Emergency Diesel Generator Under Station Blackout Conditions.

Revision 1. will also be reviewed and revised if similar discrepancies*

are identified.

The inspectors reviewed calculation 14937.28 Revision 2. and verified

that there was a battery margin of 88.8% with its present duty cycle.

The inspectors concurred with the licensee's conclusion that adequate

margins exist and there is not an operability concern for the EOG

battery. Corrective actions documented on station DR S-98-0677 were

reviewed to verify agreement with the licensee's commitment in their

response to the design inspection report. dated July 9, 1998.

The

inspectors verified that these corrective actions had been incorporated

in the licensee's commitment tracking system and CTS No. 4223 had been

assigned to monitor closure of this item scheduled for December 16.

1998.

This item is closed based on objective evidence reviewed.

E8.15 (Closed) IFI 50-280. 281/98201-13:

DC fault contribution.

The design

inspection report documented a concern where a calculation for

determining the EOG batteries short-circuit current had not been

prepared.

The inspectors were informed by the licensee that a station

DR had not been prepared for this item because a condition was never

identifted in which available fault currents exceeded component design ..

The licensee in their response to the design inspection report. dated

July 9. 1998. committed to prepare a EOG battery _short-circuit

calculation by December 1. 1998.

The inspectors verified that CTS No.

4298 had been assigned to this item and responsibility for closure had

been assigned to the Corporate Engineering Group.

This item is closed

based on objective evidence reviewed.

E8.16 (Closed) IFI 50-280. 281/98201-14:

DC load flow/voltage drop.

This

issue is discussed in Section El.l of this report under the heading:

Resolution of Design Problems Identified by the Licensee.

The issue

represents an example of a violation of NRC requirements in the area of

corrective action.

The IFI is closed because satisfactory corrective

actions have been put in place.

19

E8.17 (Closed) IFI 50-280. 281/98201-15: Adequate DC component voltage. This

issue is essentially the same as the issue of IFI 98201-14 except that

IFI 98201-14 dealt with the Station Battery Distribution System and

98201-15 dealt with the Diesel Generator Batteries Distribution Systems.

The issue is that the licensee did not have a calculation demonstrating

that the components would receive rated voltage for all design basis

scenarios.

The inspectors found that the situation with the diesel

generator batteries was not as significant as the situation with the

station batteries for two reasons. First, the loss-of-offsite-power

test conducted each outage very nearly duplicated the design basis

scenario for the diesel generator batteries. Therefore the test went a

long way in demonstrating the system could perform its design basis

function.

Second. the inspectors observed that the diesel generator

battery (Exide EI-5) is capable of supplying 210 Amperes for one minute

and 97 Amperes for one hour.

The calculated load for the first minute

was 83 Amperes.

Therefore. there was a good deal of design margin to

cover any design basis loads that may not appear in the loss-of-offsite-

power_test.

In their response letter to the design inspection. the

licensee committed to develop a new analysis for voltage drop for diesel

generator battery loads.

The inspectors observed that CTS Item No. 4299

was tracking this scope of work.

E8.18 (Closed) IFI 50-280. 281/98201-16:

DC load control.

In thei~ response

to the design inspection report. the licensee committed to revise the

relevant procedures to strengthen the control over adding of loads to

the DC busses.

The specific procedures to be revised were mentioned in

the response.

In addition. the licensee committed to provide training

on the revised procedures.

The inspectors observed that CTS Items 4179

and 4297 are tracking these commitments.

E8.19 (Closed) IFI 50-280. 281/98201-17: Battery surveillance test.

In their

response to the design inspection report. the licensee committed to

revise the procedure for the battery performance test to make the test

consistent with the test described in industry standards (IEEE 450).

The change would continue a performance test until final design end .

voltage was reached thereby determining the true battery capacity.

Previously the test was terminated at the duty cycle time which had

been showing a capacity less than the true capacity.

The inspectors

confirmed that the procedure for emergency diesel No 1 battery was

revised as described above and made effective May 21. 1998.

The

inspectors observed that CTS Item No. 4355 was tracking this commitment.

E8.20 (Closed) IFI 50-280. 281/98201-18:

Fuse control.

In their response to

the design inspection report. the licensee clarified certain statements

in the design inspection report.

The licensee stated that their item

equivalency evaluation procedure was adequate as written.

They

determined that certain individuals were not always using the procedure

when making substitutions of non-safety-related fuses.

Therefore. the

corrective action will be to review the maintenance work management

process to determine whether enhancements are required.

As a minimum.

training will be provided as to how fuse substitutions shall be

20

controlled.

The inspectors observed that CTS Item Nos 4300 and 4301

were tracking these commitments.

E8.21 (Open) IFI 50-280. 281/98201-19:

RS System flow.

The inspectors

reviewed the licensee's corrective actions for resolution of the

deficiencies identified with calculation ME-405 which did not account

for flow diversions from Units 1 and 2 inside recirculation spray (IRS)

and outside recirculation spray (ORS) pumps.

The licensee in response

to the NRC concerns prepared station DR S-98-0673 to initiate corrective

actions including alternatives to minimize flow through the unidentified

flow paths.

The corrective actions developed as*a result of DR S-98-

0673 were tracked under CTS No. 4129 and resulted in initiation of a

Recirculation Spray System Margin Improvement Project.

This project was intended to address the short term and long term

corrective actions identified in the response to station DR S-98-0673

for improving the flow paths from the IRS and ORS systems.

Mechanical

Engineering Technical Report ME-0116. Revision 0. Recommendations for

Recovery of RS System Delivered Spray Flow Losses. described the long

term and short term corrective actions developed by this project. The

short term corrective actions were identified as elimination of the

recirculation flow paths that do not directly contribute to the spray

flows or to the net positive suction head (NPSH) improvements of the

recirculation spray pumps.

The long term corrective actions recommended

remodeling the IRS system and ORS system to include the effects of EOG

frequency variations: voltage variations: and instrument uncertainties.

The long term corrective actions also recommended evaluating the size of

the ORS pump discharge flow restricting orifice and the IRS bleed flow

orifice.

The licensee in their response to the design inspection report. dated

July 9, 1998. committed to implement design changes to eliminate non-

needed -flow paths.for the recirculation spray system by the end of 1998

refueling outage (RFD) for Unit 1 and 1999 RFD for Unit 2.

System flow

calculations were also required to be updated at the time the design

change packages were implemented in order to include those flow paths

that could not *be eliminated.

At the time of the inspection the.

licensee was in the process of developing Design Change Number (DCN) 98-

040. Recovery of RS System Delivered Spray Flow/Surry Unit 1.

The

purpose of this plant modification was to implement the short term*

corrective actions to recover the shortfalls in recirculation flows

doc~mented in CME-98-0013 by closing the valves identified within the

scope of DCN 98-040.

The inspectors observed that table 4 of this

document listed spray flow margins that would be achieved after

implementation of the plant modification. Section 4. "References" of

the DCN. however. did not identify the calculation of record which

supported the values of spray flow margins documented in table 4.

The

inspectors were inform~d by the licensee that a formal calculation had

not yet been prepared to demonstrate the margins that would be available

after implementation of the plant modification. Station DR S-98-0673

identified CTS No. 4129 as the tracking mechanism for ensuring that

required corrective actions are completed by the end of the next RFD for

21

each unit. This item is left open until plant modification DCN 98-040

and the associated system flow calculations have been approved and

issued for use.

E8.22 (Closed) IFI 50-280. 281/98201-20:

Unqualified coatings.

In their

response to the design inspection report, the licensee outlined their

program for resolving the issue of whether debris from unqualified

coatings and other debris could clog the containment sump screens .. The

inspectors discussed the program with the cognizant engineers.

They

presented a detailed program flow chart which depicted 22 specific

activities arranged in three*phases.

They also presented the purchase

order with specification showing that Phase 1 work had been awarded to

an outside engineering firm.

The inspectors concluded that

implementation of the coatings/debris program should resolve this issue:

E8.23 (Closed) LER 50-280. 281/98008-00: Auxiliary ventilation fans in a

condition outside design basis for certain accidents. Auxiliary

ventilation fans l-VS-F-58A and -58B are components in the Emergency

Ventilation Filtration System which provides a method for control of

airborne isotopes and provides cooling for the charging pumps.

The fans

are safety-related and they are shared between the two units.

Normally,

the 58A fan is aligned to the lH bus and the 58B fan is aligned to the

2H bus.

The design provided for the capability to align the 58A fan to

the 2J bus by physically disconnecting and reconnecting power cables in

splice boxes.

Similarly, the 58B fan could be aligned to the lJ bus.

The auxiliary ventilation fans receive safety injection start signals

and loss-of-power load shed signals. Surveillance test OPT-ZZ-001 which

is basically a logic test of safety injection and load shed signals

included these fans in the test.

One of the power supply .realignments

described above (depending on which unit was in the refueling outage)

was made during the test. because it was thought necessary to actually

make the realignment to test all the logic. Specifically, it was

thought that realignment was necessary to verify load shedding upon a

loss of voltage .. When in the test alignment. the Emergency Ventilation

Filtration System was outside the design basis.

For example. a test

condition could be Unit 1 on-line and Unit 2 in an outage.

A typical

surveillance test alignment was the 58A fan aligned to the 2J bus and

the 58B fan aligned to the 2H bus.

Then. if a Unit 1 LOCA were to occur

coincident with loss-of-offsite-power (this means on both units). and

the No. 2 emergency diesel generator failed to start. power would be

lost to both .the fans.

The 58B fan would loose power due to failure* of

the No.2 emergency diesel generator. and the 58A fan would loose power

due to the loss-of-offsite-power. Apparently, the licensee did not *

recognize in the past that the design basis was not met while in the

test configuration.

The licensee identified this problem while they

were discussing the concept of whether the design bqsis is a loss-of~

offsite power *on one unit or on both units.

Review of outage history

data from 1994 by the licensee showed that the test alignment was

maintained for extended periods of time following completion of the OPT-

ZZ-001 test. The three longest durations in the test alignment were 142 *

days, 42 days and 25 days.

22

The cause of this problem was that the test procedure OPT-ZZ-001 did not

adequately control the test in that it did not specify restoring the

normal alignment immediately following the test. nor did it initiate an

Limiting Condition for Operation (LCD) clock when the test alignment was

entered. These circumstances represent a violation of 10 CFR 50.

Appendix B. Criterion XI. "Test Control." which requires that testing be

performed in accordance with written test procedures which incorporate

. the requirements and acceptance limits contained in applicable design

  • documents .

The licensee's corrective action to preclude recurrence of this problem

has already been developed and initiated. The basic resolution is to

leave the 58A and 58B fans in their normal alignment during the logic

testing. This solution became apparent once it was realized that the

load shed function could be tested while in the normal configuration.

The inspectors reviewed the concept of this change to the test

procedure. along with the safety evaluation for the change. and

concluded that it was a valid resolution to the problem.

Since the violation was non-repetitive. licensee identified and the

corrective action was developed and close to implementation. it will be

treated as a Non-Cited Violation. consistent with Section VII.B.l of the

NRC Enforcement Policy. It is identified as Non-Cited Violation 50-280.

281/98007-02. Emergency Ventilation Filtration System Outside Design

Basis for Certain Scenarios for Certain Periods of Time.

While reviewing LER 98-08 the inspectors observed that the LER was not

submitted within 30 days of discovery of the event.

The inspectors

considered. the discovery date to be the initiation date of the

underlying DR.

Deviation Report S-98-0503 describes the deviation as

follows:

The alternate power supplies for l-VS-F-58A and l-VS-

F-58B are the 2J and lJ power supplies respectively.

Due to the #3 EOG being.the swing diesel generator.

when the'58 fans are powered by the alternate power.

source. a loss of offsite power would result in the

loss of power to the fan if the #3 EOG transferred to

the other unit.

  • The DR indicates the date of discovery was February 20. 1998.

The LER

report date was May 22. 1998. which was 91 days after the date of

discovery.

The licensee stated the interpretation that 10 CFR

50.73(a)(l) which requires that LERs be submitted within 30 days after

discovery of the event allows for evaluation time in the case of design

basis issues. Their practice has been to start the 30 day clock upon

final determination that the condition is in fact reportable.

The NRC

will review this interpretation further before making a final

determination as to whether this practice violates NRC requirements .

The matter is identified as URI 50-280. 281/98007-03. Failure to Submit

LER Withtn 30 Days.

23

IV. Plant Support

Rl

Radiological Protection and Chemistry Controls

Rl.l General Comments (71750)

On numerous occasions during the inspection period, the inspectors

reviewed Radiation Protection (RP) practices including radiation control

area entry and exit, survey results. and radiological area material

conditions.

In addition. the inspectors reviewed the status of numerous

locked high radiation doors and found them to be.in good condition and

locked. Overall, no discrepancies were noted. and the inspectors

determined that RP practices were proper.

Rl.2 Radioactive Effluent Monitoring Instrumentation

a.

Inspection Scope (84750)

The inspectors reviewed procedures and records pertaining to

surveillances and alarm setpoints for selected radioactive effluent

monitors.

The surveillance procedures and established alarm setpoints

were evaluated for consistency with the operational and surveillance

requirements for demonstrating the operability of the monitors.

Those

requirements were specified in sections 6.2.2 and 6.3.2 and Attachments

3 and 12 of VPAP-2103, "Offsite Dose Calculation Manual (ODCM)."

b.

Observations and Findings

The inspectors toured the Control Room and relevant areas of the plant

with a licensee representative to determine the operational status for

the following effluent monitors.

RM-RRM-131 .

l-SW-RM-120

l-GW-RM-130-1

l-VG-RM-104

Radwaste Facility Liquid Effluent Line

Circulating Water Discharge Line

Process Vent Noble Gas Activity Monitor

  • Ventilation Vent Noble Gas Activity Monitor

The above monitors were .found to be well maintained and operable at the

time of the tours.

The irispectors reviewed 14 procedures related to channel checks. source

checks. channel calibrations. channel functional tests. and alarm

setpoints for the above listed monitors.

The inspectors determined that

the procedures included provisions for performing the required

surveillances in accordance with the relevant sections of the ODCM and

at the specified frequencies.

The inspectors also reviewed recently

completed surveillances for the above listed monitors.

Those records

indicated that the surveillances were being kept current and *performed

in accordance with their applicable procedures.

The inspectors also

verified that the current alarm setpoints for three of the above listed

monitors were determined in accordance with the licensee's .procedure for

24

establishing effluent setpoints and were more conservative than required

by the ODCM.

The licensee indicated that effluent monitor percent availability was

not routinely tabulated. therefore. the inspectors reviewed the

licensee's records of DRs pertaining to the four selected monitors.

During the period January 1997 through July 1998 no DRs were issued for

monitors RR-RRM-131 and 1-SW-RM 120. five were issued for monitor 1-GW-

RM-130-1. and eighteen were issued for monitor 1-VG-RM-104.

Most of the

DRs issued for monitor 1-GW-RM-130-1 were initiated when it was found.

during periodic testing, that the setpoints had reverted to more

conservative default values. apparently due to sporadic electrical

spikes.

The licensee has addressed reliability problems of monitor 1-

VG-RM-104 as evidenced by a decreasing trend in the number of DRs. i.e ..

most of the DRs issued for monitor 1-VG-RM~104 occurred in early 1997

with only three in 1998.

From the items reviewed and discussions with

the cognizant system engineer. the inspectors determined that the

selected monitors were seldom out of service for extended periods except

for scheduled preventive maintenance and surveillance testing.

c.

Cone l us i ans

The licensee was maintaining radioactive effluent monitoring

instrumentation in an operable condition and performing the requited

surveillances to demonstrate their operability.

Rl.3 Meteorological Monitoring Program

a.

Inspection Scope (84750)

b.

The inspectors evaluated implementation of the licensee*~ onsite

meteorological measurements program for consistency with the program

description contained in Section 2.2.1.2 of the Updated Final Safety

Analysis Report CUFSAR).

Observations and Findings

The inspectors reviewed meteorological surveillance procedures and

determined that they included provisions for performing daily channel

checks and semiannual channel calibrations. The inspectors also

reviewed the licensee's records for calibration of the instrumentation

used to monitor wind speed. wind direction. and air temperature. Those

records indicated that the most recent instrument calibrations. which

had been performed during May 1998. were current and had been performed

in accordance with the applicable procedures.

The inspectors reviewed

recently completed Control Room Logs and Operating Records and

determined that channel checks of the meteorological monitoring

instruments had been performed on a daily basis.

During a tour of the

Control Room the inspectors noted that the meteorological monitoring

instrumentation was operable.

  • \\

25

The UFSAR indicated that a microprocessor-based data acquisition system

was used for collection of meteorological monitoring data and that the

data were edited for validity each month before being transferred to the

historical database.

The inspectors reviewed licensee records for the

valid data capture rate from the various monitoring instruments.

Those

data indicated that the year-to-date valid data capture rate for the

first six months of 1998 was greater than 99 percent which was

consistent with industry guidelines.

The inspectors determined that the meteorological monitoring

surveillance requirements were met and the instruments were maintained

operable.

c.

Conclusions

The inspectors concluded that the onsite meteorological measurements

program was implemented in accordance with the UFSAR.

Rl.4 Control Room Emergency Ventilation System

a.

b.

Inspection Scope (84750)

The inspectors reviewed the licensee's procedures and records for the

surveillances required to demonstrate operability of the Control Room

Emergency Ventilation System (CREVS).

Those procedures and records were

evaluated for consistency with the operational and surveillance

requirements delineated in TS 3.19. 3.23. 4.1 and 4.20.

Observations and Findings

The inspectors toured the Turbine Building. Control Room. Emergency

Switchgear and Relay Room~ and Mechanical Equipment Rooms in which the

Control Room ventilation systems were located. The licensee's cognizant

system engineer accompanied the inspectors on the tours. during which

the major components of the systems were located-and identified. The

emergency ventilation systems included redundant bottled air supply

systems for pressurizing the Control Room for one hour under accident

conditions and four independent air filtration units consisting of fans.

dampers. pre-filters. High Efficiency Particulate Air (HEPA) filters.

and charcoal adsorber filter beds.

The inspectors verified that the air

  • flow paths and arrangement of the system components within those *paths

were consistent with the system diagram (Figure 9.13-3) referenced in

Section 9.13.2 of the UFSAR .. The inspectors observed that the

components and associated ductwork were well maintained structurally and

that there was no physical deterioration of the equipment or ductwork

sealants.

The inspectors reviewed selected ventilation system surveillance

procedures and determined the they included provisions for performing

functional tests. filter leak tests. air flow measurements. differential

pressure measurements. and charcoal adsorption efficiency testing .. The

surveillance frequency and acceptance criteria for the test results

26 .

specified in those procedures were consistent with the TS requirements.

Review of selected records of those tests. generally the most recently

completed. indicated that they had been performed in accordance with the

testing procedures and that the acceptance criteria had been met.

The

inspectors noted that the filter leak tests were most recently performed

during January 1997. which exceeded the 18 month surveillance frequency

required by TS 4.20 but did not exceed the plus or minus 25 percent

adjustment to surveillance time intervals allowed by TS 4.0.2.

c . * Cone l us i ons

The inspectors concluded that the licensee was maintaining the CREVS in

an operable condition and performing the required surveillances to

demonstrate operability of the systems.

Sl

Conduct of Security and Safeguards Activities

On numerous occasions during the inspection period. the inspectors

performed walkdowns of the protected area perimeter to assess security

and general barrier conditions.

No deficiencies were noted and the

inspectors concluded that security posts were prop~rly manned and that

the perimeter barrier's material condition was properly maintained.

V. Management Meetings

Xl

Exit Meeting Summarj

The inspectors presented the inspection results to members of licensee

management at the conclusion of the inspection on September 18. 1998.

The

licensee acknowledged the findings presented.

The inspectors asked the licensee whether any materials examined during the

inspection should be considered proprietary.* No proprietary information was

identified.

27

PARTIAL LIST OF PERSONS CONTACTED

M. Adams. Superintendent. Engineering

R. Allen. Superintendent. Maintenance

R. Blount. Manager. Nuclear Safety & Licensing

M. Crist. Superintendent. Operations

E. Collins. Director. Nuclear Oversight

E. Grecheck. Site Vice President

L. Hartz. V. P. Nuclear Engineering

J. Martin. Corporate Maintenance Rule Coordinator*

B. Shriver. Manager. Operations & Maintenance

T. Sowers. Superintendent. Training

B.*stanley, Supervisor. Licensing

W. Thornton. Superintendent. Radiological Protection

IP 37551:

IP 40500:

IP 61726:

IP 62706:

IP 62707:

IP 71707:

IP 71750:

IP 84750:

IP 92901:

IP 92902:

IP 92903:

Opened

INSPECTION PROCEDURES USED

Onsite Engineering

Effectiveness of Licensee Controls in Identifying, Resolving, and

Preventing Problems

Surveillance Observation

Maintenance Rule

Maintenance Observation

Plant Operations

Plant Support Activities

Radioactive Waste Treatment. and Effluent and Environmental

Monitoring

Followup - Plant Operations

Followup - Maintenance

Followup - Engineering

ITEMS OPENED, CLOSED, AND DISCUSSED

50-280. 281/98007-01

VIO

Failure to take corrective action for

identified design problems (Section El.1).

No response required for violation.

50-280. 281/98007-02

NCV

50-280. 281/98007-03

URI

Emergency Ventilation Filtration System

outside design basis for certain scenarios

for certain periods of time (Section

E8. 23).

Failure to submit LER within 30 days

C Sect i on E8 . 23) .

'1

28

Closed

50-280. 281/97002-01

IFI

Long term corrective actions to

resolve potential TDAFW pump

overspeed trips (Section 08.1).

50-280/97003-01

VIO

Loss of containment integrity

(Section 08.2).

50-280/97001-00. -01

LER

Shutdown due to steam drain line

weld leak (Section M8.1).

50-280. 281/97002-00, -01

LER

One train of auxiliary ventilation

system inoperable outside T.S.

(Section M8.2).

50-280/97003~02

VIO

Failure to follow maintenance

procedures (Section M8.3).

50-280. 281/97007-02

IFI

Alternate alternating current CAAC)

diesel coolant temperature concerns

and long term actions to resolve the

issue (Section M8.4).

50-280. 281/97002-03

VIO

Procedures not appropriate to the

circumstances (Section M8.5).

50-280, 281/97002-04

VIO

Failure to meet the requirements of

10 CFR 50.9(a) for LER 50~280/97002-

00 (Section E8.2).

50-280/97003-03

VIO

Failure to meet the requirements of

10 CFR 50.9(a) for LER 50-280/97001-

00 (Section E8.2).

50-280. 281/98201-02

IFI

Error in Calculation SM-1047.

"Reactor Cavity Water Holdup"

(Section EB A).

50-280. 281/98201-06

IFI

Breaker-to-breaker and fuse-to-fuse

analysis (Section E8.8).

50-280. 281/98201-07

IFI

Breaker replacement (Section E8.9).

50-280. 281/98201-10

IFI

DC bus tie interlock (Section

EB.12).

50-280. 281/98201-11

IFI

Battery calculation discrepancies

(Section EB.13).

50-280, 281/98201-12

IFI

Battery design margin (Section

EB.14).

!jlal

"

I_

29

50-280. 281/98201-13

IFI

DC fault contribution (Section

E8 .15).

50-280. 281/98201-14

IFI

DC load flow/voltage drop (Section

EB.16).

50-280. 281/98201-15

IFI

Adequate DC component voltage*

(Section EB.17).

50-280. 281/98201-16

IFI

DC load control (Section E8.18).

50-280, 281/98201-17

IFI

Battery surveillance test (Section

EB.19).

50-280. 281/98201-18

IFI

Fuse control (Section E8.20).

50-280, 281/98201-20

IFI

Unqualified coatings (Section

E8. 22).

50-280. 281/98008-00

LER

Auxiliary ventilation fans in a

condition outside design basis for

certain accidents (Section E8.23).

50-280, 281/98007-03

NCV

Emergency Ventilation Filtration

System outside design basis for

certain scenarios for certain

periods of time (Section EB.23).

Discussed

50-280. 281/98201-01

IFI

LHSI pump NPSH (Section E8. 3).

50-281/98201-03

URI

Uni-t 2 LHSI pump minimum flow

C Sect i on EB . 5) .

50-280/98201-04

IFI

Motor thermal overload for 1-SI-P-lB

(Section EB. 6).

50-280. 281/98201-05

IFI

Adequacy of 4160 VAC electrical

cables to withstand fault current

(Section EB. 7).

50-280. 281/98201-08

URI

EOG battery transfer switch (Sect1on

EB.10).

50-280, 281/98201-09

URI

DC tie breaker (Section EB .11).

50-280, 281/98201-19

IFI

RS System fl ow C Section EB. 21) .