Responds to Request for Addl Info Re Proposed Tech Spec Changes Concerning Snubber Surveillance Requirements. Revised Request Re Deletion of Snubber Tables in Accordance W/Generic Ltr 84-13.Proposal Will Be Completed by 851231
ML18144A027
Person / Time
Site: Surry  Dominion icon.png
Issue date: 11/19/1985
From: Stewart W
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To: Harold Denton, Varga S
Office of Nuclear Reactor Regulation
References
85-751, GL-84-13, TAC-59466, TAC-59467, NUDOCS 8511250095
Download: ML18144A027 (2)


Text

. '..

e e

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 November 19, 1985

w. L. STEWA..BT VICE PRESIDENT NUCLEAR OPERATIONS Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation Attn:

Mr. Steven A. Varga, Chief Operating Reactors Branch_No. 1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNIT NOS. 1 AND 2 REVISED TECHNICAL SPECIFICATION CHANGE EEQUEST Serial No.85-751 NO/ETS/JDH/vlh Docket Nos.

50-280 50-281 _

License Nos. DPR-32 DPR-37 On August 9, 1985 (Serial No.85-556), we proposed technical specification changes regarding the snubber surveillance requirements.

On October 11,

1985, you requested additional information regarding our - proposed changes.

In developing our response, it became apparent to us that current developments in a related area - the NRC's proposed revision to General Design Criterion 4 - would have a significant impact on Surry' s snubber surveillance program.

We_ understand that publication of the revised criterion is expected in-the near term.

Therefore, rather than expand resources on the two issues independently, we defer any major changes to the existing program until the revised criterion is published.

So, we plan to supercede our August 9, 1985 request with a request to delete the snubber tables (and associated references) in accordance with NRC Generic Letter 84-13, dated May 3, 1984. This change was discussed with the NRC Surry Project Manager on November 12, 1985.

We also informed him that we

  • would only respond to your October 11, 1985 request to the extent it was applicable to the revised request.

Our response to your October 11, 1985 request for additional information and the revised Technical Specification proposal will be submitted to your office by December 31, 1985.

Very truly yours, W. L. Stewart

VIRGINIA. Rl.:ECTRIC AND PoWER COMPANY TO

/1 cc:

Dr. J. Nelson Grace Regional Administrator NRG Region II Mr. Donald J. Burke NRG Resident Inspector Surry Power Station

~r. Charles Price Department of Health 109 Governor Street Richmond, Virginia 23219 Mr. Terence t. Chan NRG Surry Project Manager*

Operating Reactors Branch No. 1 Division of Licensing e