05/17/2018 Workshop Subsequent License Renewal Guidance and Process
ML18137A136
Person / Time
Issue date: 05/17/2018
From: Bennett Brady
NRC/NRR/DMLR/MRPB
To:
Brady B, NRR-DMLR 415-2981
Shared Package
ML18137A131 List:
References
Download: ML18137A136 (12)


Text

SUBSEQUENT LICENSE RENEWAL GUIDANCE AND PROCESS Bennett Brady NRR/DMLR/MRPB May 17, 2018 1

SLR Regulatory and Technical Development

  • 2008 and 2011 o International workshops on long-term operations defined major issues for SLR:

reactor pressure vessel neutron embrittlement at high fluence; irradiation-assisted stress corrosion cracking of reactor internals and primary system components; concrete and containment degradation, and electrical cable qualification and condition 2

assessment

SLR Regulatory and Technical Development (cont)

  • 2011 - 2014 NRC begins defining potential regulatory changes o Working group of program managers, technical experts and senior level advisors o Public meetings to solicit stakeholder input
  • SECY 14-0016 -proposed a rule change for a more efficient process 3

SLR Regulatory and Technical Development (cont)

  • SECY 14-0016 -proposed a rule change for a more efficient process
  • SRM to SECY 14-0016 - Did not approve the staffs recommendation o Revise guidance o Keep the Commission informed on the progress in resolving the major technical issues 4

SLR Technical Development

  • 2011-2014 -Collected proposed changes to technical guidance o Aging Management Program (AMP) Effectiveness Audits o Review of the draft Expanded Materials Degradation Assessment o Input from industry and staff on needed changes
  • 2014 -Began expert panel meetings to disposition proposed changes
  • 2015 - Draft guidance documents published for public comment 5

SLR Technical Development (cont)

  • February 2017 - Engaged ACRS on draft guidance documents

Subsequent License Renewal Guidance Documents, NUREG-

Regulatory Guides

Significant Changes in the Guidance Documents

  • Fluence Monitoring
  • High Voltage Insulators
  • Withdrawal and testing of at least one capsule addressing the subsequent PEO (if specified criteria not already met) 8

Significant Changes in the Guidance Documents (cont)

  • A plant-specific data gap analysis for inspection of PWR reactor vessel
  • Expanded Electrical Insulation of Cables AMP from one AMP to three AMPs

- to address aging of submerged cables at different voltages

- Updated for alkali-silica reaction

- Added further evaluation for irradiation of concrete

  • Added over 1035 new items to GALL-SLR tables 9

SLR Review Optimization Efforts

  • Pre-Submittal Meetings
  • Environmental at least 12 months prior
  • Safety at least 6 months prior
  • Schedule initiates on acceptance of the SLRA (18 months) 1 0

SLR Review Optimization

  • Applicant provides access to electronic portal (no later than acceptance of the SLRA in order to support the review schedule)

SLR Review Optimization

2