SUBSEQUENT LICENSE RENEWAL GUIDANCE AND PROCESS Bennett Brady NRR/DMLR/MRPB May 17, 2018 1
Overview
- SLR Regulatory and Technical Developments
- Significant Technical Changes from Initial License Renewal
- Review Process Changes 2
SLR Regulatory and Technical Developments
- 2008 and 2011 o International workshops on long-term operations defined major issues for SLR:
reactor pressure vessel neutron embrittlement at high fluence; irradiation-assisted stress corrosion cracking of reactor internals and primary system components; concrete and containment degradation, and electrical cable qualification and condition assessment 3
SLR Regulatory and Technical Developments (cont.)
- 2011 - 2014 NRC defines potential regulatory changes o Working group of program managers, technical experts, and senior level advisors o Public meetings to solicit stakeholder input 4
SLR Regulatory and Technical Developments (cont.)
- SECY 14-0016 - proposed a rule change for a more efficient process
- SRM to SECY 14-0016 - Did not approve the staffs recommendation oRevise guidance oKeep the Commission informed on the progress in resolving the major technical issues 5
SLR Regulatory and Technical Developments (cont.)
- 2011-2014 - Collected proposed changes to technical guidance o Aging Management Program (AMP) Effectiveness Audits o Review of the draft Expanded Materials Degradation Assessment o Input from industry and staff on needed changes
- 2014 - Began expert panel meetings to disposition proposed changes
- 2015 - Draft guidance documents published for public comment 6
SLR Regulatory and Technical Developments (cont.)
- February 2017 - Engaged ACRS on draft guidance documents
- July 2017 - Final GALL-SLR (NUREG-2191, Vols. 1 and 2) and SRP-SLR (NUREG-2192) published
- December 2017 - Published companion documents o NUREG-2221 (Technical Bases for Changes in the Subsequent License Renewal Guidance Documents, NUREG-2191 and NUREG-2192), and o NUREG-2222 (Disposition of Public Comments on the Draft Subsequent License Renewal Guidance Documents, NUREG-2191 and NUREG-2192) 7
SLR Regulatory and Technical Developments (cont.)
- December 2017 - NRC issues interim endorsement letter for NEI guidance o NEI 17-01, Industry Guidance for Implementing the Requirements of 10 CFR Part 54 for Subsequent License Renewal, Rev. 0 o NEI 17-04, Model SLR New and Significant Assessment Approach for SAMA, Rev. 0
- NRC currently revising regulatory guidance to endorse NEI guidance o RG 1.188 to endorse NEI 17-01 o RG 4.2 to endorse NEI 17-04 8
Significant Technical Changes
- New GALL-SLR AMPs
- Fluence Monitoring
- High Voltage Insulators
- Deleted AMPs
- Feedwater nozzle and control rod drive return line nozzle
- Withdrawal and testing of at least one reactor vessel surveillance capsule addressing the subsequent PEO (if specified criteria not already met) 9
Significant Technical Changes (cont.)
- A plant-specific data gap analysis for inspection of PWR reactor vessel o to address differences from first license renewal period to subsequent license renewal period
- Expanded Electrical Insulation of Cables AMP from one AMP to three AMPs o to address aging of submerged cables at different voltages
- Aging management of concrete o Updated for alkali-silica reaction o Added further evaluation for irradiation of concrete
- Added over 1035 new items to GALL-SLR tables 1 0
Review Process Changes
- Piloted on River Bend license renewal review
- Pre-Submittal Meetings o Environmental at least 12 months prior to submittal o Safety at least 6 months prior to submittal
- SLRA acceptance review performed by technical staff assigned to review v. tiger team approach
- 18 month schedule begins upon SLRA acceptance for docketing 1 1
Review Process Changes
- Applicant provides access to electronic portal (no later than acceptance of the SLRA in order to support the review schedule)
- Aging Management Audits (Safety) o Offsite Aging Management Program Operating Experience Audit o In-Office Aging Management Audit via telecom/webinar breakout sessions o On-Site Aging Management Audit with regional participation to walk down specific material conditions and plant configurations 1
2
Review Process Changes