ML18106A672

From kanterella
Jump to navigation Jump to search
Startup & Power Ascension Units 1 & 2.
ML18106A672
Person / Time
Site: Salem  PSEG icon.png
Issue date: 06/12/1998
From: Nagy E
Public Service Enterprise Group
To:
Shared Package
ML18106A671 List:
References
NUDOCS 9806290136
Download: ML18106A672 (12)


Text

ATT ACHEMNT 1 LR-N980287 SALEM STARTUP AND POWER ASCENSION UNITS 1and2

&ur-" ~ *fl6&;1 I ~ - J8' Eu~e M. Nagy, Startup Testing Manager 9806290136 980617 PDR ADOCK 05000272 P PDR

Salem Restart Plan Following the Salem Shutdown, the "SALEM RESTART PLAN" was developed to outline a systematic approach for the Integrated Testing associated with the Salem restart effort. The program was been defined in Procedure SC.TE-Tl.ZZ-OOOl(Q), Startup And Power Ascension Program.

The plan established testing in 4 phases to ensure testing was documented and that the testing was sufficient to validate restart readiness. The focus of the test program was in the area where plant modifications were made. The 4 phases were:

  • Phase I - Component Level Testing
  • Phase II - System Level Testing
  • Phase III - Integrated Testing
  • Phase IV - Startup and Power Ascension Testing.

The existing Design Change Process was determined adequate to ensure that testing performed validated the design bases. By using Salem's normal process controls and demonstrating they worked, the overall effort supported the individual Salem Restart Action Plans. The process controls consisted of the present Work Control Process, Design Change Process, Special Tests and Infrequently Performed Evolution Process and the Procedure Development Process.

Packaging these processes under the System Readiness Review Program on a system by system bases was the essence of the Startup and Power Ascension Program.

This concept was presented to the Management Review Committee and approved on November 14, 1995. Subsequently, revision zero of the Startup and Power Ascension Program procedure was completed and- presented to the Management Review Committee for approval on December 7, 1995.

, (

Hold Points and Criteria for Continuing Restart Power ascension for both Unit 2 and Unit 1 used "Hold Points" to evaluate the Units readiness to progress with the startup .. Established plant performance-hold points were placed prior to a plant Mode change and at specific reactor power levels; 25%, 47% and 90%.

There were two types of Hold Points during Startup and Power Ascension. They are Planned Assessment Hold Points and Plant Performance Hold Points. These hold points were controlled in the "Startup and Power Ascension Sequencing" procedures.

Planned Assessment Hold Points permitted a systematic management review and assessment of plant and personnel performance to ensure that the plant and the organization were ready to proceed with the startup plan. Planned Assessment Hold Points include planned assessments by the line organization and independent assessments by the Quality Assessment Department.

These planned assessments were conducted during the ascension to the "Hold Point" and provided input to the department manager's recommendation to the General Manager - Salem Operations to continue with the startup. The assessment criteria were developed from the station self assessment diagnostic performance standards, criteria and attributes.

Plant Performance Hold Points allow time for a deliberate decision to be made by the Shift Plant Manager that the sequence should progress to the next set of activities in the startup. The decision is based on satisfactory plant performance, acceptable test results and effective resolution of open and emergent issues. Plant Performance Hold Points ensure that all information is considered (i.e. material condition, completion of necessary corrective maintenance actions, personnel performance, responsiveness of support activities, etc.)

supporting the decision to continue with the startup.

Lesson learned from Unit 2 startup and a management recommendation changed the way hold points were satisfied on Unit 1. Specifically, to proceed past a hold point on Unit 1 required the testing to be completed and reviewed by the Test Review Board (TRB), or required a SORG presentation of startup test results from the TRB and approval of the General Manager Salem Operations. This change was made to increase management oversight in the startup and power ascension process.

r [

Assessments Assessments were performed to evaluate the plant and the organizations ability to operate Salem in a Safe and Reliable manner. Assessments were performed at designated plant conditions (prior to fuel load, prior to proceeding into Mode 2, at 25%, 4 7% and 90% reactor power and a final assessment after reaching 100% power). The assessments verified that Salem had met it's expectations of effective implementation of policies and directives, management expectations for high standards of station performance and the planning and control of station activities.

The assessments utilized data obtained from self assessment observations submitted by each organization; Startup Organization, Operations, Maintenance, System Engineering, Radiation Protection and Chemistry. The Observations submitted were forwarded to the Salem Self Assessment Coordinator, who compiled the observations into assessment results. The assessment results were then returned to the submitting organization. Each organization reviewed the results and submitted an affirmation to SORC as to the plant and organizations readiness to continue with the startup. SORC made recommendations to the General Manager-Salem Operations as to the plants readiness to continue with the startup. Based on the recommendation, General Manager-Salem Operations authorized proceeding with the plant startup.

UNIT 1 STARTUP -UNIT 2 STARTUP STARTUP

SUMMARY

STARTUP

SUMMARY

No r:iajor test delays were encountered during the Several problems occurred during Unit 2 Unit 1 startup. This was primarily due to better test startup that resulted in testing delays. The planning, better coordination between departments, major testing delay encountered during the experience and knowledge gained from the Unit 2 startup was for installation and testing of the startup and through the lesson learned program Service Water CFCU modification. This instituted as part of the Unit 2 Startup. resulted in an approximate 4 month delay in the startup.

Lessons learned included a contingency plan which identified actions should equipment problems arise The delays that occurred in Mode 3 were during the startup, cause & effect evaluations of caused by 22 Reactor Coolant Pump high installation of test equipment, increased awareness vibration, leaking BIT isolation valves, and the of plant conditions required to perform testing and a inability to pressurize the steam system on rewrite of DCP special test procedure (STP) to pump heat. The Mode 2 delay occurred due to address testing concerns identified during Unit 2 problems with the rod position indication

  • startup. STP's were rewritten to have a consistent system. The Mode 1 delays occurred due to, format and to be more specific on what was tested by Flux map problems with the P-250 computer, each STP. For example on Unit 2 the test procedure NI adjustments, Pressurizer level for the Heater Drain Pumps tested all the pumps instrumentation deviations and with various using 1 procedure and on Unit 1 six procedures were problems with the Steam Generator Feed used to test the heater drain pumps. This resulted in Pumps (SGFP).

more test activities to accomplish the same task but resulted in less problems during the startup. After reaching 100% power on Unit 2, Steam  : .

Generator water chemistry went out of spec on Several equipment problems did occur during the September 30, 1997 and Reactor Power was testing but did not result in significant startup delay. reduced to approximately 55%. Seven plugs The first obstacle was performing Component were repaired in the condenser water boxes and Cooling System (CC) flow balance. System cleanup Chemistry was returned to in spec. Reactor was required prior to completing the testing which Power was returned to 100% on September 30, took approximately 10 days. Heater Drain Pump 1997.

problems and valve problems were encountered during the startup. Testing was delayed for Unit 2 had a manual Reactor Trip from 100%

replacement of the 11 Heater Drain Pump and repair power on October 2, 1997, due to Steam

  • of the 12HD9 valve. This work was performed after Generator Feed Pump Low Suction Pressure.

100% fuel conditioning was completed. During the The cause of the low suction pressure was 25% turbine runback test at 90% reactor power, rods caused by a fault in test equipment installed on did not respond as expected. The test was completed the Digital Feedwater System. In addition, satisfactorily but required investigation into rod post-trip cooldown of the unit went.smoothly, control system. It was determined that rod control and the unit response proved that repairs and functioned as designed and this was verified on May modifications made during the outage were 13, 1998, during performance of the 40% Turbine successful. The unit was restarted on October Load Reject test. The SGFP trip test was completed 6, 1997.

on May 14, 1998 which completed the major testing on Unit 1.

, f

  • UNIT 1 STARTUP 4IN1T 2 STARTUP Mode6 Mode6 Unit 1 startup was officially entered on November Unit 2 plant startup was officially entered on 30,_ 1997, when core reload commenced on Unit 1. December 16, 1996 when core reload Core loading was completed on December 4. commenced on Unit 2. Fuel loading was completed on December 21.

Twenty-three tests activities were completed while in Mode 6. General Manager, Salem Operations Thirty-eight tests activities were completed in authorization was obtained on December 10, 1998, Mode 6. Mode 6 test requirements were for Unit l to proceed to Mode 5. No unexpected completed on December 24, 1996. No delays in startup and power ascension testing were unexpected delays in startup and power noted while in Mode 6 ascension were noted while in Mode 5.

Modes Modes Unit l entered Mode 5 on December 11, 1997. Unit 2 entered Mode 5 on December 26, 1996.

Thirty-eight tests activities were completed while in Forty-seven tests activities were completed Mode 5. One test (lEE-0117-1, Steam Dumps to while in Mode 5. On February 3, 1997, the Condenser) could not be completed in Mode 5 and Unit startup was essentially halted for testing requirements were moved to Mode 4. The implementation of 96-06 modification  : '

test was field complete but required an engineering /integrated testing of Service Water evaluation of the acceptance criteria. On January 5, Containment Fan Coil Units (CFCU) and due 1998, it was identified that RVLIS data collection to problems with Control Area Ventilation.

had not been perforrned prior to establishing a Implementation and testing of 96-06 pressurizer steam bubble as required by the sequence modification took until June 9, 1997. Mode 5

_procedure. An evaluation determined there was no testing requirements were completed on June plant impact for the missed data, due to the data

  • 14, 1997, and Management Review Committee collected is not used to generate new curves and is (MCR) approval was given to proceed to Mode not used for the new EOP setpoints. General 4.

Manager, Salem Operations authorization was obtained on February 18, 1998, for Unit 1 to proceed to Mode 4. No unexpected delays in startup and power ascension testing were noted while in Mode 5.

  • UNIT 1 STARTUP
  • &1T 2 STARTUP Mode4 Mode4 Unit 1enteredMode4on.February18,1998. Unit 2 entered Mode 4 on June 14, 1997.

Sixty-one tests activities were completed while in Eight tests activities were completed while in Mode 4. Three test activities could not be completed Mode 4. While in Mode 4, Steam Generator in Mode 4 and were moved to another Mode. 1EC- Feed Pump (SGFP) testing associated with 3206, STP-001 D & E for testing of the BF 19 and 40 Design Change Package (DCP) 2EC-3306 valves were moved to a Mode 3 test requirement. experienced various problems. SGFP trouble The valves were being reworked by I&C and the shooting was started and resulted in testing valves are not required operable until Mode 2. 1EE- requirements being moved to Mode 2.

0117-1, Steam Dump to Condenser testing, was moved to a Mode 2 test requirement waiting Mode 4 testing requirement were completed on resolution of the acceptance criteria from July 1, 1997, and Management Review engmeermg. Committee approval was given to proceed to Mode 3.

General Manager, Salem Operations authorization was obtained on March 14, for Unit 1 to proceed to Mode 3. No unexpected delays in startup and power ascension testing were noted while in Mode 4.

Mode3 Mode3 Mode 3 was entered on March 17, 1998. Mode 3 was entered on July 3, 1997.

Forty-two tests activities were completed while in Twenty-four tests activities were completed Mode 3. Reactor Coolant Pump high vibrations while in Mode 3. Startup Testing delays in were encountered while in Mode 3. The pumps were Mode 3 were caused primarily due to balanced while performing RVLIS testing at 540° F. equipment issues. On July 4, 1997, Pressurizer On March 25, 1998, Operations experienced Safety Relief Valve, 2PR4 was identified as problems with letdown flow while setting up to leaking. This resulted in having to reduce perform Pressurizer Level tuning. Tuning was primary pressure to approximately 1500 psig, delayed for evaluation of the letdown problem. This on July 7, 1997, to seat 2PR4. On July 5, did not result in a delay in the startup as Pressurizer 1997, 22 Reactor Coolant Pump (RCP) level tuning could be performed at higher power vibration problems were encountered. This levels without impacting the plant. Pressurizer level event resulted in testing delays for Reactor tuning was not completed in Mode 3 arid was moved Vessel Level Indicating System (RVLIS) and to Mode 1. in pressurizing the steam system for trouble shooting per Steam Cycle Monitoring per After department affi~ations and NRC approval, procedure S2.SE-PR.ZZ-0001. The 22 RCP General Manager, Salem Operations authorization vibration problem resulted in the pump being was obtained for Unit 1 to proceed to Mode 2 on removed from service for troubleshooting. On April 7, 1998. No unexpected delays in startup and July 8, 1997, during RVLIS testing 21 RCP lift

  • UNIT 1 STARTUP . &1T 2 STARTUP power ascension testing were noted while in Mode 3. *pump tripped. This resulted in a delay in RVLIS testing until the 21 RCP lift pump was replaced later the same day. Another problem was not being able to pressurize the secondary.

Steam cycle monitoring per S2.SE-PR.ZZ-OOO 1, was performed to identify the leak.age path to the main condenser. Various steam paths to the condenser were identified but the secondary could only be pressurized to approximately 740 psig without cooling off the primary. On July 23, 1997, Unit 2 commenced a cooldown to Mode 5 for troubleshooting leaking BIT isolation valves and for trouble shooting steam dumps.

The testing delays while in Mode 3 were with the Steam Generator Feedwater Pump testing, Steam Dump control loop functional testing, Atmospheric Relief Valve (MS 10) dynamic testing and with Letdown control loop functional testing. SGFP's experienced problems with the governor and with the ability to latch, which extended some testing for approximately one month. Soine of the SGFP testing was originally scheduled to be completed in Mode 4 butwas moved to Mode

2. Steam Dump and MS 10 testing was delayed due to problems with the test procedure, problems with installation of test equipment and the inability to pressurize the main steam system on pump heat. Letdown temperature and pressure functional testing was required to be repeated due to the acceptance criteria not being satisfied. Mode 3 testing requirement were completed on August 7, 1997.

Mode2 Mode2 Unit 1 entered Mode 2 on April 7, 1998. A delay in the startup was encountered on August 7, 1997 during rod pulls due to Fifteen tests activities were completed while in deviations in IRPI rod position indications.

Mode 2. Reactor power was increased to 3% on Trouble shooting of the rod position indication April 11, 1998. General Manager, Salem Operations problems and corrective actions were not authorization was obtaiiled on April 12, 1998, for completed until August 17, 1997. This Unit 1 to proceed to Mode 1. No unexpected delays resulted in a delay in Hot Zero Power testing.

in startup and power ascension testing were noted

- UNIT 1 STARTUP &1T 2 STARTUP while in Mode 2. Mode 2 was entered on August 17, 1997, and Hot Zero testing was started.

Four tests activities were completed while in Mode 2. On August 18, 1997, 2 rods on D Control Bank drifted > 12 steps out of alignment. Unit 2 entered Mode 3 on August 19, 1997, as required by Technical Specifications due to the rod deviation problem. Rod deviation corrective actions were completed and Unit 2 entered Mode 2 August 22, 1997. Hot Zero Power Testing was completed on August 24, 1997. Unit 2 increased Reactor Power to 2% on August 24, 1997.

Mode 1 Mode 1 Unit 1 entered Mode 1 on April 13, 1998. Reactor Mode 1 was entered on August 26, 1997.

power was.increased to 9% on April 13, 1998 and he.Id at that power until April 17, 1998 when the Twenty-two tests activities were completed turbine was synchronized to the grid. Power was while in Mode 1. ADFCS testing experienced then increased to 24%. After department testing problems at the 7 - 10% Reactor Power affirmations and NRC approval, General Manager, level and could not be performed due to low Salem Operations authorization was obtained feedwater flow conditions at that power level.

allowing reactor power to be increased to the 47% The ADFCS testing was rescheduled. Unit 2 plateau, on April 18, 1998. synchronized to the grid on August 30, 1997, were power was held at 20 % for Digital A Reactor power of 47% was achieved on April 19, Feedwater testing. Power was increased to the

  • 1998. The 4 7% fuel conditioning was completed on 25% on August 30, 1997. Delays at the 25%

April 23, 1998. After department affirmations and Hold Point were caused by Gland Seal Steam NRC approval, General Manager, Salem OperatiOns Testing and problems with the P-250 authorization was obtained allowing reactor power computer. The Gland Seal Steam Test could to be increased to the 90% plateau, on April 23, not be completed due to inoperable equipment 1998. Power was then increased to the 60% on in the GS system and the test was rescheduled April 23, 1998 for heater drain pump testing and to be completed with the Unit at 100% Reactor then to 75% plateau on April 23, 1998 for Reactor Power. The problem with the P-250 computer Engineering testing. On April 29, 1998, a power resulted in a 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> delay in plant startup due increase was started to the 90% plateau. The power to problems with obtaining data for the flux increase was performed prior to signoff of the map, on September 1, 1997. This problem was Refueling Test Sequence Procedure by Reactor resolved, which completed the required testing Engineering, A review to determine the impact of necessary for exceeding 25 % power. The performing the steps out of sequence was performed NRC granted permission to increase power to and it was determined that the missed step did not the next hold point of 47 % on September l,

. UNIT 1 STARTUP &1T2STARTUP result in any safety issues. The step intent had been 1997 .Power was increased to 4 7% on satisfi~d and a verbal step compliance had been September 2, 1997 .

obtained prior to the increase. A CR was initiated to document the missed step, 980429228. The first test problem at 47% was with Digital Feedwater testing not transferring to the high Forty-five tests activities were completed while in power mode of operation during the power Mode l. Four tests placed transients on the Unit; increase to the 4 7% Hold Point. No testing l 0% load swings for Advanced Digital Feedwater was performed from September 6, 1997 Control System (ADFCS) at 47%, 25% Main through the 8th due to I&C adjusting Nuclear Turbine runback at 90%, 40% Main Turbine Instrumentation and for performance of Runback Test at 90% and SGFP Trip test at 90%. maintenance activities. The Digital Feedwater The Heater Drain Pump testing per DCP 1EC-3692 Control System 10% load swing was could not be completed as scheduled in the performed satisfactorily on September 11, sequencing procedure due to problems with the 1997. The major maintenance activities heater drain pumps and 12HD9. Heater Drain Pump performed during this power plateau were to testing was a Mode 1 test and could be completed at troubleshoot Pressurizer level channel a later time. The sequence procedure did not require deviations, SGFP work due to high vibrations the testing to be completed prior to performing the and to clean up the heater drain system water load reject testing and it was determined to complete chemistry. The 4 7% power plateau the testing at a later date. The testing was moved to requirements were completed and NRC the Post Startup testing procedure to allow closure of permission was granted to proceed to the 90%

this procedure. power plateau on September 11, 1997.

After department affirmations and NRC approval, . Reactor power was increased to 54% on General Manager, Salem Operations authorization September 12, 1997, and stabilized for SGFP was obtained allowing reactor power to be increased Speed Control tuning and Heater Drain Pump greater than 95% on May 1, 1998. 100% Reactor system testing. 21 Heater Drain Pump power was achieved at 0133 hours0.00154 days <br />0.0369 hours <br />2.199074e-4 weeks <br />5.06065e-5 months <br /> on May 2, 1998, problems prevented completion of the testing where power remained until the fuel was and it was determined that the testing could be conditioned at the 100% power level. On May 5, completed later when power was returned to 1998, Reactor power was reduced to 90% for Heater less than 60% for the Digital Feedwater 40%

Drain Pump testing and repair. load reject. Power increase was started on September 17, 1997, but due to problems with The 40 % Main Turbine load reject was performed SGFP pressure transmitters and with 24 loop on May 13, 1998 and the SGFP Trip and Main Delta T, was suspended for trouble shooting.

Turbine auto runback was completed on May 14, These problems were resolved and power was 1998. This completed the major testing required at increased to the 90% plateau on September 19, the 100% power plateau. 1997. The 25% load reject was performed satisfactorily on September 21, 1997 and the Unit was returned to 90% power. The 90%

power plateau requirements were completed and NRC permission was granted to proceed to 100% power on September 22, 1997.

100% Power was achieved on September 23, 1997 at 0040 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br />. The 40 % Main Turbine

lJNIT 1 STARTUP

-UNIT 2 STARTUP

, 'n, load reject was performed on September 27-,

1997 and the SGFP Trip and Main Turbine auto runback were completed on September 29, 1997. This completed the major testing required at the l 00% power plateau.