MONTHYEARCNL-18-042, Proposed Technical Specifications Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus, Supplement 12018-03-0707 March 2018 Proposed Technical Specifications Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus, Supplement 1 Project stage: Supplement ML18101A1012018-04-13013 April 2018 Summary of March 16, 2018, Meeting with Tennessee Valley Authority Regarding a License Amendment Request to Implement Maximum Extended Load Line Limit Analysis Plus for Browns Ferry Nuclear Plant Project stage: Meeting CNL-18-099, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 2, Operator Training Results2018-07-23023 July 2018 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 2, Operator Training Results Project stage: Supplement ML18268A0212018-09-27027 September 2018 Regulatory Audit Plan in Support of Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Other ML18317A1642018-11-20020 November 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - Non-Proprietary Project stage: RAI ML18331A5442018-12-0606 December 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - (Non-Proprietary) Project stage: RAI CNL-18-140, Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 42018-12-13013 December 2018 Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 4 Project stage: Supplement CNL-18-139, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information2018-12-14014 December 2018 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information Project stage: Request CNL-19-011, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results2019-01-16016 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results Project stage: Supplement CNL-19-007, Supplement 5, Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus2019-01-16016 January 2019 Supplement 5, Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus Project stage: Supplement CNL-19-017, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information2019-01-25025 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information Project stage: Supplement ML19067A0262019-03-0707 March 2019 Notice of Forthcoming Closed Meeting with Tennessee Valley Authority (TVA) and General Electric-Hitachi (Geh), Regarding Maximum Extended Load Line Limit Analysis Plus (Mella+) License Amendment Request (LAR) for Browns Ferry Nuclear Plant, Project stage: Meeting CNL-19-032, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information2019-03-13013 March 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information Project stage: Supplement CNL-19-045, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 9, Additional Information Regarding Anticipate Transient Without Scram with ...2019-04-24024 April 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 9, Additional Information Regarding Anticipate Transient Without Scram with ... Project stage: Supplement ML19121A2242019-06-0606 June 2019 Non-Proprietary - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Summary Report for the Audits in Support of License Amendment Request for Operation in the Expand Maximum Extended Load Line Limit Analysis Plus Operating Domain Project stage: Other ML19120A2882019-06-0606 June 2019 Summary of March 19, 2019, Closed Meeting with Tennessee Valley Authority a License Amendment Request to Implement Maximum Extended Line Limit Analysis Plus Project stage: Meeting ML19163A0802019-07-22022 July 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A3282019-07-22022 July 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A1342019-07-22022 July 2019 Request for Additional Information from Public Disclosure Project stage: RAI ML19163A1652019-08-0505 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A2782019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A2542019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19135A5572019-08-26026 August 2019 Request for Withholding Information from Public Disclosure (EPID L-2018-LLA-00488) Project stage: Withholding Request Acceptance ML19133A1192019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A0582019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance CNL-19-125, Proposed Technical Specifications (TS) Change 510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 12, Additional License Condition2019-12-19019 December 2019 Proposed Technical Specifications (TS) Change 510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 12, Additional License Condition Project stage: Supplement 2019-01-16
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML24269A0062024-10-0303 October 2024 Correction to Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the TVA Nuclear Quality Assurance Plan ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24221A0132024-08-19019 August 2024 July 10, 2024, Summary of Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24176A1252024-06-28028 June 2024 Summary of Partially Closed Meeting with Tennessee Valley Authority to Discuss a Proposed License Amendment Request Regarding the Hydrologic Analysis Updates ML24155A0422024-06-13013 June 2024 Meeting Summary: Public Scoping Webinars for the Environmental Review of the Subsequent License Renewal Application for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML24142A5152024-05-28028 May 2024 April 22, 2024, Summary of Public Mtg with Tennessee Valley Authority to Discuss Use of Risk-Informed Process Evaluation for a Proposed License Amendment Request Elimination of Limiting Condition for Operation Actions for the Rod Worth Mini ML24155A0432024-04-18018 April 2024 Meeting Summary ML24089A0712024-04-0101 April 2024 3/20/24 & 3/27/24 2023 TVA Public Annual Assessment Meeting Summary ML24057A0402024-02-27027 February 2024 Summary of February 7, 2024, Public Meeting with Tennessee Valley Authority to Preliminarily Discuss the Planned Approach for the Browns Ferry Nuclear Plant Hydrologic Analysis ML24043A0462024-02-16016 February 2024 Summary of Meeting with TVA to Discuss Use of Risk-Informed Process Evaluation (RIPE) for a Proposed LAR Regarding Elimination of Limiting Condition for Operation Actions for Rod Worth Minimizers ML24008A1592024-01-18018 January 2024 Summary of December 13, 2023, Meeting with Tennessee Valley Authority Regarding a Proposed Change to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML23270A0702023-09-26026 September 2023 SLRA Pre-Application Meeting Summary 09-13-2023 ML23157A1272023-06-13013 June 2023 Meeting Summary for Environmental Pre-Submittal Meeting for Subsequent License Renewal Application on May 11, 2023 ML23142A2132023-05-22022 May 2023 Public Meeting Summary - 2022 Annual Assessment Meetings for Browns Ferry, Sequoyah and Watts Bar Nuclear Plants ML22319A1952022-12-0202 December 2022 Summary of October 13, 2022, Meeting with Tennessee Valley Authority to Discuss Planned Alternative Requests for the Fifth 10-Year Inservice Testing Program Interval for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML22298A1612022-11-17017 November 2022 Summary of Public Meeting on SAMA with TVA ML22266A2742022-09-28028 September 2022 Summary of September 22, 2022, Public Meeting with Tennessee Valley Authority to Discuss a Request to Use a Later Edition of the ASME OM Code ML22108A1842022-04-18018 April 2022 TVA 2021 Annual Assessment Public Meeting Summary ML22103A2472022-04-14014 April 2022 Summary of April 12, 2022, Closed Meeting with Tennessee Valley Authority to Discuss Recently Identified Errors Potentially Affecting the Browns Ferry Revised Criticality Analysis License Amendment Request ML22094A1112022-04-0404 April 2022 Public Meeting Summary 2021 Annual Assessment Meeting Catawba Dockets Nos. 50-413 and 50-414; McGuire No. 50-369 and 50-370; Oconee. 50-269, 50-270, and 50-287 ML22083A0762022-03-24024 March 2022 Summary of March 17, 2022, Closed Meeting with Tennessee Valley Authority to Discuss Recently Identified Errors Potentially Affecting the Browns Ferry Atrium 11 License Amendment Request (EPID L-2021-LLA-0132 ML21291A0092021-11-0303 November 2021 Tennessee Valley Authority Fleet - Summary of October 13, 2021, Teleconference with Tennessee Valley Authority to Discuss Planned License Amendment Requests Related to the Emergency Action Level Scheme ML21266A0532021-10-20020 October 2021 Summary of September 22, 2021, Meeting with Tennessee Valley Authority Regarding Planned License Amendment Request to Adopt Technical Specifications Task Force (TSTF)-205 and TSTF-563 ML21273A1922021-10-12012 October 2021 September 27, 2021, Summary of Meeting with Browns Ferry Nuclear Plant, Units 1 & 2 Related to a Planned Alternative Request Per American Society of Mechanical Engineers (Asmee) Code Case N-526, Alternative Requirements for Successive Sect ML21251A1122021-09-14014 September 2021 Summary of September 7, 2021, Teleconference with Tennessee Valley Authority to Discuss a Planned License Amendment ML21165A1482021-06-30030 June 2021 Summary of Closed Meeting with Tennessee Valley Authority to Discuss Planned Requests for Exemption from Certain Requirements of 10 CFR Part 37 ML21155A0212021-06-0808 June 2021 Summary of Teleconference with Tennessee Valley Authority to Discuss a Planned License Amendment ML21137A0022021-05-17017 May 2021 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plants, Docket Nos. 50-259, 50-260, 50-296, 50-327, 50-328, 50-390, and 50-391, Meeting Number 20210392 ML20357A0092021-01-19019 January 2021 Summary of December 17, 2020, Teleconference with Tennessee Valley Authority Regarding Planned License Amendment Request Related to Use of Alternate Probability of Detection at Watts Bar Nuclear Plant, Unit 2 ML20175A8012020-08-11011 August 2020 Summary of June 23, 2020, Public Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20162A1532020-06-25025 June 2020 Summary of June 8, 2020, Partially Closed Meeting with Tennessee Valley Authority to Discuss a Planned License Amendment ML20127H8412020-05-0606 May 2020 Public Meeting Summary - Browns Ferry, Sequoyah and Watts Bar Nuclear Plant, Meeting No. 20200384 ML20094M9012020-04-13013 April 2020 Summary of April 2, 2020 Public Meeting with Tennessee Valley Authority Regarding the Future Submittal of a License Amendment Request Adoption of 10 CFR 50.69 ML19120A2882019-06-0606 June 2019 Summary of March 19, 2019, Closed Meeting with Tennessee Valley Authority a License Amendment Request to Implement Maximum Extended Line Limit Analysis Plus ML19120A3692019-04-30030 April 2019 Public Meeting Summary - Browns Nuclear Plant, Docket No. 50-259, 50-260, and 50-296 ML18242A4882018-09-24024 September 2018 Summary of Pre-Application Conference Call with Tennessee Valley Authority to Discuss Proposed Changes to Modifications Associated with Approved NFPA 805 for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML18101A1012018-04-13013 April 2018 Summary of March 16, 2018, Meeting with Tennessee Valley Authority Regarding a License Amendment Request to Implement Maximum Extended Load Line Limit Analysis Plus for Browns Ferry Nuclear Plant ML18068A0792018-03-15015 March 2018 Summary of Pre-Application Meeting with Tennessee Valley Authority Regarding a Planned License Amendment Request Associated with Modifications to the Control Bay Chillersystems at Browns Ferry Units 1, 2 and 3 ML18053A5362018-03-0101 March 2018 Summary of February 7, 2018, Pre-Application Conference Call with TVA a Planned License Amendment Request to Change the Emergency Response Organization Staffing ML17278A8972017-10-17017 October 2017 Summary of Meeting with TVA Regarding Hydrology-Related Licensing Actions, Browns Ferry, Units 1, 2, and 3, Sequoyah Nuclear, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2(EPID L2016-TOP-0011; CAC Nos. MF8391-MF8397 ML17227A5142017-09-0101 September 2017 Summary of August 1, 2017, Pre-Submittal Public Meeting with TVA Regarding a Class 1E Unbalanced Voltage Relay Licensing Amendment Request for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant ML17131A2512017-05-11011 May 2017 Summary of Public Meeting Concerning Annual Assessment of Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML17061A6722017-04-0606 April 2017 Summary of February 15, 2017, Meeting with Tennessee Valley Authority on Updates to the Transmission System Regarding Extended Power Uprate for Browns Ferry Nuclear Plant, Units 1, 2, and 3 ML17017A4552017-02-0303 February 2017 Summary of Meeting with Tennessee Valley Authority Regarding Maximum Extended Load Line Limit Plus Pre-Application Meeting for Browns Ferry Nuclear Plant ML16350A2962016-12-14014 December 2016 Enclosure 3- Reactor Oversight Process Task Force FAQ Log- November 16, 2016 ML16280A2912016-10-31031 October 2016 September 23, 2016, Summary of Public Meeting with TVA Regarding Hydrology-Related Licensing Actions, Browns Ferry Nuclear Plant, Units 1, 2, and 3, Sequoyah Nuclear Plant, Units 1 & 2 and Watts Bar Nuclear Plant, Units 1 & 2 (CAC Nos. MF83 ML16279A2332016-10-0505 October 2016 Summary of Closed Pre-Decisional Enforcement Conference with Tennessee Valley Authority Regarding Browns Ferry Nuclear Plant ML16210A4532016-08-16016 August 2016 07/19/2016 Summary of Meeting with Tennessee Valley Authority Regarding Extended Power Uprate License Amendment Request for Browns Ferry Nuclear Plant (CAC Nos. MF6741, MF6742, and MF6743) ML16193A4602016-07-21021 July 2016 June 23, 2016, Summary of Closed Meeting with Tennessee Valley Authority Regarding the Structural Adequacy of Steam Dryers for Extended Power Uprate License Amendment Request for Browns Ferry Nuclear Plant, Units 1, 2, and 3 (MF6741, MF6742 ML16153A1982016-06-0101 June 2016 2015 EOC Meeting Summary 2024-09-23
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 13, 2018 LICENSEE: Tennessee Valley Authority FACILITY: Browns Ferry Nuclear Plant, Units 1, 2, and 3
SUBJECT:
SUMMARY
OF MARCH 16, 2018, MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING A LICENSE AMENDMENT REQUEST TO IMPLEMENT MAXIMUM EXTENDED LOAD LINE LIMIT ANALYSIS PLUS FOR BROWNS FERRY NUCLEAR PLANT (EPID: L-2018-LLA-0048)
On March 16, 2018, a Category 1 public meeting was held among the U.S. Nuclear Regulatory Commission (NRC) staff, representatives of Tennessee Valley Authority (TVA, the licensee),
and TVA's contractors (General Electric Hitachi (GEH) and AREVA (now Framatome)) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. By letter dated February 23, 2018 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML180798140), as supplemented by letter dated March 7, 2018 (ADAMS Accession No. ML18067A495), TVA submitted a license amendment request (LAR) for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Browns Ferry or BFN). The proposed amendment would allow operation in the expanded Maximum Extended Load Line Limit Analysis Plus (MELLLA+) operating domain. The purpose of the meeting was for TVA to present to the NRC staff its submitted LAR to implement MELLLA+. The meeting notice and agenda dated February 26, 2018, are available in ADAMS under Accession No. ML18057A200.
A list of attendees is provided in the enclosure to this meeting summary.
The licensee's presentation slides, copies of which were provided prior to the meeting and attached to the meeting notice, are available under ADAMS Accession No. ML18059A107.
During the meeting, the licensee presented a background of MELLLA+ and its benefits for Browns Ferry. The licensee explained that the MELLLA+ licensed flow window would be between 85 percent and 105 percent core flow at the approved extended power uprate (EPU) power levels.
The licensee presented a list of benefits of implementing MELLLA+ for Browns Ferry including (see Slide No. 4) reduction in the number of end of cycle down-powers, fewer control rod manipulations, improved core instability detection algorithm, and increased station capacity factor during the operating cycle. TVA presented its current schedule for the proposed MELLLA+ LAR (see Slide No. 5) that shows completion of this LAR by April of 2020, which is 26 months from the LAR submittal. During the meeting TVA stated that this completion date is based on the comments TVA received during the pre-application meeting. However, the licensee stated that if the review could be completed quickly, it could be possible to implement MELLLA+ at Unit 3 in August 2019. This would require an 18-month review from the submittal date of February 23, 2018.
TVA's presentation included a detailed discussion on the overview of the LAR, information associated with Browns Ferry MELLLA+ LAR Electronic Reading Room and a comparison between Browns Ferry MELLLA+ analyses and Brunswick MELLLA+ analyses, which is currently under review by the NRC staff. The licensee discussed details associated with the following (see Slides 6 to 9):
Changes in the Browns Ferry Technical Specifications and renewed Facility Operating license GEH MELLLA+ Safety Analysis Report (M+SAR)
AREVA MELLLA+ Safety Analysis Report (AMSAR)
AREVA fuel related reports In addition, TVA compared MELLLA+ analyses used for Browns Ferry to analyses that were used for Brunswick (see Slides 15 to 18):
High energy linebreak Containment accident pressure (CAP) credit GEH use of thermal hydraulic data that is provided by AREVA Use of a minimum core flow value for loss of coolant accident analyses Use of statistical data for safety relief valves that support use of a 3 percent setpoint drift value for anticipated transient without scram calculations The licensee also clarified that no new methodologies are used for MELLLA+ and that the methodologies approved for use in the EPU safety evaluation are only expanded to the MELLLA+ operating domain. Additionally, the licensee noted that CAP credit was not required for this LAR, as it was addressed under EPU. Also the licensee clarified that no fresh AREVA ATRIUM-10 fuel or fresh blended low-enriched uranium fuel will be used when MELLLA+ is implemented.
The NRC staff asked clarifying questions throughout the presentation and provided observations on key issues. The NRC staff and the licensee discussed issues related to the use of GEH Detect and Suppress Solution - Confirmation Density (DSS-CD) for Browns Ferry.
The NRC staff asked the licensee to clarify what the basis is for changing the period based detection algorithm's lower period limit (T min) from that in the approved DSS-CD topical report.
Also the staff asked the licensee to compare the TVA approach regarding penalties on the safety limit minimum critical power ratio to the approach that was used for Brunswick. Further, the NRC staff and TVA staff discussed holding regulatory audits including a simulator audit at the site and a regulatory audits in Rockville, Maryland.
The following action items were developed during the meeting:
Item Action
- 1. TVA will review specific differences between the Brunswick Reload Analysis Report approach and the BFN Representative Reload Analysis Report approach. TVA will provide review results to NRC.
Item Action
- 2. TVA will determine the basis of Period Based Algorithm Time Period Lower Limit (Tmin).
TVA will determine if the T min value associated with the current Browns Ferry Option Ill stability solution is equivalent to the proposed DSS-CD T min value. TVA will also review DSS-CD Licensing Topical Report basis discussion for T min- In addition, TVA will obtain information from Brunswick personnel with respect to recent NRC conference call regarding T min- TVA will provide review results to NRC.
- 3. NRC will review the M+SAR tables of containment analysis input parameters to determine if values for additional input parameters are needed. NRC will inform TVA of the results.
- 4. With respect to operator action times assumed in the anticipated transient without scram
- instability (ATWS-1) analysis, the NRC requested TVA review these times and determine whether BFN had sufficient margin to reduce these times. NRC stated that reducing these times could help to resolve concerns related to the A TWS-1 analyses.
No regulatory decisions were made at the meeting. No members of the public attended the meeting and no Public Meeting Feedback forms were received.
Please direct any inquiries to me at 301-415-1447 or Farideh.Saba@nrc.gov.
Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-259, 50-260, 50-296
Enclosure:
List of Attendees cc: Listserv
LIST OF ATTENDEES MARCH 16, 2018, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 REGARDING MAXIMUM EXTENDED LOAD LINE LIMIT ANALYSIS PLUS LICENSE AMENDMENT REQUEST Name Organization Farideh Saba Nuclear Regulatory Commission (NRC)
Andrew Hon NRC Ahsan Sallman NRC Mathew Panicker NRC Brian Tindell NRC Joshua Borromeo NRC Joe Giitter NRC Jennifer Whitman NRC William Ruatzen NRC Charapani Basavaraju NRC Matthew Hamm NRC Todd Hilsmeier* NRC Kathy Gibson* NRC John Hughey* NRC Natreon Jordan* NRC Gerard Doyle Tennessee Valley Authority (TVA)
Pete Donahue TVA Dan Green TVA Gordon Williams TVA Greq Storey TVA William Baker TVA Michael Dick TVA Larry King General Electric Hitachi (GEH)
Mike Cook* GEH J. D. Kvaall* GEH James Harrison* GEH Lander Ibarra* GEH Alan Meginnis Framatome (AREVA)
Scott Tylinski* Framatome Earl Riley* Framatome Jordan Harvey* Framatome Dan Tinkler* Framatome
- Participated by phone Enclosure
ML 181101A101
OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DSS/SRXB/BC(A)* DORL/LPL2-2/PM BC(A)
NAME FSaba BClayton JWhitman BTindell FSaba DATE 4/12/18 4/12/18 04/11/2018 4/13/18 4/13/18