Letter Sequence Meeting |
|---|
EPID:L-2018-LLA-0048, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information (Open) |
Initiation
- Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting
|
MONTHYEARML18079B1402018-02-23023 February 2018 Browns Ferry Nuclear Plant, Units 1, 2, and 3: Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus Project stage: Request CNL-18-042, Proposed Technical Specifications Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus, Supplement 12018-03-0707 March 2018 Proposed Technical Specifications Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus, Supplement 1 Project stage: Supplement ML18059A1072018-03-16016 March 2018 Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Request ML18088A0252018-04-0606 April 2018 Acceptance Review Regarding Proposed Expanded Maximum Extended Load Line Limit Analysis Plus (Mellla+) Project stage: Acceptance Review ML18101A1012018-04-13013 April 2018 Summary of March 16, 2018, Meeting with Tennessee Valley Authority Regarding a License Amendment Request to Implement Maximum Extended Load Line Limit Analysis Plus for Browns Ferry Nuclear Plant Project stage: Meeting CNL-18-099, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 2, Operator Training Results2018-07-23023 July 2018 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 2, Operator Training Results Project stage: Supplement ML18268A0212018-09-27027 September 2018 Regulatory Audit Plan in Support of Maximum Extended Load Line Limit Analysis Plus License Amendment Request Project stage: Other ML18317A1642018-11-20020 November 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - Non-Proprietary Project stage: RAI ML18331A5442018-12-0606 December 2018 Request for Additional Information Regarding Maximum Extended Load Line Limit Plus License Amendment Request (EPID L-2018-LLA-0048) - (Non-Proprietary) Project stage: RAI CNL-18-140, Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 42018-12-13013 December 2018 Response to Request for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 4 Project stage: Supplement CNL-18-111, Triennial Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis)2018-12-13013 December 2018 Triennial Decommissioning Funding Plans for Independent Spent Fuel Storage Installations (Isfsis) Project stage: Request CNL-18-139, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information2018-12-14014 December 2018 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Information Project stage: Request CNL-19-007, Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus2019-01-16016 January 2019 Response to Requests for Additional Information Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus Project stage: Response to RAI CNL-19-011, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results2019-01-16016 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 6, Additional Operator Training Results Project stage: Supplement CNL-19-017, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information2019-01-25025 January 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 7, Response to Requests for Additional Information Project stage: Supplement ML19067A0262019-03-0707 March 2019 Notice of Forthcoming Closed Meeting with Tennessee Valley Authority (TVA) and General Electric-Hitachi (Geh), Regarding Maximum Extended Load Line Limit Analysis Plus (Mella+) License Amendment Request (LAR) for Browns Ferry Nuclear Plant, Project stage: Meeting CNL-19-032, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information2019-03-13013 March 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 8, Additional Operator Training Information Project stage: Supplement CNL-19-045, Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 9, Additional Information Regarding Anticipate Transient Without Scram with .2019-04-24024 April 2019 Proposed Technical Specifications (TS) Change TS-510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 9, Additional Information Regarding Anticipate Transient Without Scram with . Project stage: Supplement ML19121A2242019-06-0606 June 2019 Non-Proprietary - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Summary Report for the Audits in Support of License Amendment Request for Operation in the Expand Maximum Extended Load Line Limit Analysis Plus Operating Domain Project stage: Other ML19120A2882019-06-0606 June 2019 Summary of March 19, 2019, Closed Meeting with Tennessee Valley Authority a License Amendment Request to Implement Maximum Extended Line Limit Analysis Plus Project stage: Meeting ML19136A3282019-07-22022 July 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A1342019-07-22022 July 2019 Request for Additional Information from Public Disclosure Project stage: RAI ML19163A0802019-07-22022 July 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19163A1652019-08-0505 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19135A5572019-08-26026 August 2019 Request for Withholding Information from Public Disclosure (EPID L-2018-LLA-00488) Project stage: Withholding Request Acceptance ML19133A1192019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A0582019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A2542019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML19136A2782019-08-26026 August 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance CNL-19-125, Proposed Technical Specifications (TS) Change 510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 12, Additional License Condition2019-12-19019 December 2019 Proposed Technical Specifications (TS) Change 510 - Request for License Amendments - Maximum Extended Load Line Limit Analysis Plus - Supplement 12, Additional License Condition Project stage: Supplement 05000260/LER-2019-001-01, Traversing In-core Probe Purge Header Check Valve Leak Rate in Excess of Technical Specifications Limits2019-12-19019 December 2019 Traversing In-core Probe Purge Header Check Valve Leak Rate in Excess of Technical Specifications Limits Project stage: Request ML19210C3082019-12-26026 December 2019 Redacted - Browns Ferry Nuclear Plant, Units 1, 2, and 3 - Issuance of Amendment Nos. 310, 333, and 293 Regarding Maximum Extended Load Line Limit Analysis Plus Project stage: Approval ML19360A0442019-12-30030 December 2019 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance 2019-01-16
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 6, 2019 LICENSEE:
Tennessee Valley Authority FACILITY:
Browns Ferry Nuclear Plant, Units 1, 2, and 3
SUBJECT:
SUMMARY
OF MARCH 19, 2019, CLOSED MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING A LICENSE AMENDMENT REQUEST TO IMPLEMENT MAXIMUM EXTENDED LOAD LINE LIMIT ANALYSIS PLUS FOR BROWNS FERRY NUCLEAR PLANT (EPID L-2018-LLA-0048)
By letter dated February 23, 2018 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML180798140), Tennessee Valley Authority (TVA) submitted a license amendment request (LAR) for the Browns Ferry Nuclear Plant, Units 1, 2, and 3 (Browns Ferry).
The proposed amendment would allow operation in the expanded Maximum Extended Load Line Limit Analysis Plus (MELLLA+) operating domain. The purpose of the meeting was for TVA to present to the U.S. Nuclear Regulatory Commission (NRC) staff its submitted LAR to implement MELLLA+. The meeting notice and agenda dated March 7, 2019, are available in ADAMS under Accession No. ML19067A026. A list of attendees is enclosed.
On March 19, 2019, a Category 1 closed meeting was held between the NRC staff, representatives of TVA, and TVA's contractor (General Electric Hitachi) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The discussion was focused on the differences between the NRC Office of Research confirmatory calculation limiting results and the limiting results provided by TVA in its LAR. This meeting was closed to the public due to discussion of proprietary information.
During the meeting, TVA representatives discussed the Anticipated Transient Without Scram with Instability (ATWS-1) analyses performed to support the Browns Ferry MELLLA+ LAR. By letter dated April 24, 2019 (ADAMS Accession No. ML19115A099), TVA submitted Supplement 9 to the LAR, which provided additional information regarding A TWS-1 analyses.
No regulatory decisions were made at the meeting.
Please direct any inquiries to me at 301-415-1447 or Farideh.Saba@nrc.gov.
Docket Nos. 50-259, 50-260, and 50-296
Enclosure:
List of Attendees cc: Listserv Farideh E. Saba, Senior Project Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
LIST OF ATTENDEES MARCH 19, 2019, CLOSED MEETING WITH TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 REGARDING MAXIMUM EXTENDED LOAD LINE LIMIT ANALYSIS PLUS LICENSE AMENDMENT REQUEST Name Organization Farideh Saba U.S. Nuclear Regulatory Commission (NRC)
Joshua Borromeo NRC Undine Shoop NRC Chris Hoxie NRC Peter Yarsky NRC Andrew Bielen NRC Nathanael Hudson NRC Ian Porter NRC Aaron Wysocki NRC Consultant Pete Donahue TVA Dan Green Tennessee Valley Authority (TVA)
Barry Myers TVA Michael Dick TVA Larry King.
General Electric Hitachi (GEH)
Mike Cook GEH Enclosure
SUBJECT:
SUMMARY
OF MARCH 19, 2019, CLOSED MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING A LICENSE AMENDMENT REQUEST TO IMPLEMENT MAXIMUM EXTENDED LOAD LINE LIMIT ANALYSIS PLUS FOR BROWNS FERRY NUCLEAR PLANT (EPID L-2018-LLA-0048)
DATED MAY 6, 2019 DISTRIBUTION:
PUBLIC PM File Copy RidsRgn2MailCenter Resource RidsNrrPMBrownsFerry Resource RidsNrrDorlLpl2-2 Resource RidsNrrDssSnpb Resource RidsNrrDra Resource RidsNrrDssSrxb Resource JJohnston, NRR AHon, NRR JQuichocho, OEDO CHoxie, RES
!Porter, RES MPanicker, NRR ADAMS A ccess1on N ML19120A288 o.:
RidsNrrLABClayton Resource RidsACRS_MailCTR Resource RidsNrrDss Resource RidsNrrDorl Resource RidsNrrDssStsb Resource RidsNrrDe Resource MMcCoppin, OEDO JBorromeo, NRR DWoodyatt, NRR PYarsky, RES NHudson, RES ABielen, RES
- b 1y e-ma1 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LA DSS/SRXB/BC(A)*
DORL/LPL2-2/BC NAME FSaba LRonewicz JWhitman UShoop DATE 05/16/2019 05/15/2019 05/08/2019 06/05/2019 OFFICIAL RECORD COPY DORL/LPL2-2/PM FSaba 06/06/2019