ML18093B238

From kanterella
Jump to navigation Jump to search
Enforcement Conference Repts 50-272/86-23 & 50-311/86-23 on 880929.Areas Discussed:Significance of Concerns About Environ Qualification of Limitorque Valve Operators W/O Required T-drains & solenoid-operated Valves W/O Seals
ML18093B238
Person / Time
Site: Salem  
Issue date: 10/14/1988
From: Durr J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18093B237 List:
References
50-272-86-23-EC, 50-311-86-23, NUDOCS 8810250417
Download: ML18093B238 (69)


See also: IR 05000272/1986023

Text

'._;;,

. ':.

  • .

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

50-272/86-23, 50-311/86-23

Docket Nos.

50-272 and 50-311

License Nos.

DPR-70 and DPR-75

Licensee:

Public Service Electric and Gas Company

Facility Name:

Salem Units 1 and 2

Conference At:

NRC Region I, King of Prussia, Pennsylvania

Inspection Conducted:

September 29, 1988

Approved by:

//?;A_~~

J. Durr, Chief, Engineering Branch

'date

Conference Summary:

Environmental Qualification (EQ) enforcement conference

held to discuss the significance of concerns about the environmental

qualification of Limitorque Valve operators without required T-drains, Solenoi¢

operated valves without Conax seals, Electric junction boxes not properly

sealed, Limitorque valve operators with brakes electrically disconnected but

not physically removed, Terminal blocks associated with auxiliary feedwater

transmitters.

DETAILS

1.

Public Service Electric and Gas Company

S. Miltenberger, Vice President and Chief Nuclear Officer

R. Burricelli, General Manager of Engineering and Plant Betterment

J. Zupko, General Manager of Quality Assurance

B. Preston, Manager of Licensing and Regulations

C. Lambert, Nuclear Engineering Sciences Manager

A. Blum, Program Analysis Group Supervisor

R. Blum, Engineering Sciences Group

J. Bailey, Engineering Sciences Group

F. Thompson, Nuclear Sciences Supervisor

.

D. Perkins, Manager at Station Quality Assurance

Atlantic Electric

M. Cavalier

NRC

T. Martin, Director of Division of Reactor Safety

N. Dudley, Project Engineer

C. Miller, Reactor Engineer

J. Stone, Sr. Project Manager, NRR

P. Swetland, Project Section Chief

R. Borchardt, Senior Resident Inspector

G. Hubbard, Reactor Engineer, Office of Special Projects

C. Anderson, Chief of Plant Systems Section

2.

Conference Scope

The enforcement conference considered the following potential EQ

violations:

Limitorque Valve operators without required T-drains

Solenoid operated valves without Conax seals

Electric junction boxes not properly sealed

Limitorque valve operators with brakes electrically

disconnected but not physically removed

Terminal blocks associated with auxiliary feedwater transmitters.

The scope of the discussions included:

Safety significance of each violation, number of deficiencies and

number of systems and components affected

3

Specific and underlying cause of each violation *

Actions taken or planned to correct the individual violations to

ensure overall compliance

A discussion of each violation in light of the Modified Enforcement

Policy for EQ Requirements, GL88-07

3.

Licensee Presentation

The licensee presented their position on the EQ issues of concern.

The

licensee presentation is outlined in their handout which is provided ~s

Attachment A to this document.

4.

Conclusion

The NRC staff stated that the licensee input will be considered in

assessing NRC handling of the potential enforcement items.

The licensee

will be notified of appropriate enforcement actions in the future.

~

. .*, ** :__:._...
  • **. -*-*"* *.
  • - -

.

-**

.*

-- *.* **

.

-~: ........ **-

  • - *** ;.. **.* ,_._ .,.,._,..*.::** *. !; -
    • ** * ........ ,_ ....... _.,_ ..... _

.. _ ...... ""~*---* .. **-*"""*'-'*"****** ...... -*-*-"-'--'-- .... *-*-*~* *.*.*.. ~-* ........ _ ........ --* , __

  • --~ -- .

--** - ..

,\\

0

0

0

0

0

PUBLIC SERVICE ELECTRIC AND GAS

J

SALEM UNITS 1 AND 2 GENERATING STATIONS

ENVIRONMENTAL QUALIFICATION PROGRAM

ENFORCEMENT CONFERENCE

SEPTEMBER 29~ 1988

-INTRODUCTION - s. E. MILTENBERGER

BACKGROUND - c. w. LAMBERT

EQ ISSUES - c. w. LAMBERT/B. A. PRESTON

STATUS OF THE ENVIRONMENTAL QUALIFICATION PROGRAM - C. W. LAMBERT

SUMMARY - s. E. MILTENBERGER

. .

"

'

\\

PUBLIC SERVICE ELECTRIC AND GAS

SALEM UNITS 1 AND 2 GENERATING STATIONS

ENVIRONMENTAL QUALIFICATION PROGRAM

ENFORCEMENT CONFERENCE

SEPTEMBER 29, 1988

PRESENTATION MATERIAL

.

_.

'

  • .:.,: .!

.. ~ ,.

.. *_;, * * : *

. '; .. ,,.. , .. ::.;* *'*.: .* '°***"* . ., * ' :. : ** !. .)C,-~ '.f*. L"' ,,:::_.,_'\\.:<>:: **. : .* -\\~ '~* *** -~ .,.. * *

'* ' *** * *, * * ~*, .. * * .*. !, ._ .* * *-. *

  • . _:

BACKGROUND

ENVIRONMENTAL QUALIFICATION PROGRAM

- PRIOR TO NOVEMBER 30, 1985

1-

INITIAL EQ REQUIREMENT 1970-1979

0

BOP - EQ REQUIREMENT INCLUDED WITHIN EQUIPMENT

PROCUREMENT SPECIFICATION

NSSS - VENDOR <WESTINGHOUSE> ESTABLISHED EQ TESTING

PROGRAM FOR SAFETY RELATED EQUIPMENT DOCUMENTED IN

WCAP'S

2-

l&E BULLETIN 79-0lB, 1980-1983

0

0

0

REVIEW OF ALL ELECTRICAL EQUIPMENT LOCATED IN HARSH

ENVI RO NM ENT

SPECIFY REQUIREMENTS FOR AGI~G

SUBMITTAL OF SALEM UNITS 1 AND 2 *ENVIRONMENTAL

QUALIFICATION REVIEW REPORT* - 1980

1980 NRC AUDIT OF SALEM UNIT 2 EQ PROGRAM - ALL OPEN

ITEMS HAVE BEEN RESOLVED

3.

NUREG 0588 ENDORSED BY NRC ON JUNE 25, 1980.

0

PSE&G PROMPTLY RESPONDED AND INITIATED ACTION FOR

UNITS 1&2

-~-.--

  • . '*.--*
      • -.*. -. - -

..* - .. - *.*. -._

.* -,. -.. -

.. :"..-

    • -** * -__ , *. -.-~*, :,.,..-_:.) ........
__._,_-._ --.-
    • - .. _-.,-,,, *

.,.,.,,_-.;~ ........

\\ .... .-.-_.*

  • .,..-

__ ** -:-,,

__ .-=-..l"'/V,...,.,,,.,~--l,,.-".:~

.,._.,..,..~*-*

.... """'~*.~.*...:."""'"'*::.J.-:=,

....

~*.:l.,,,--..

o. * ..:,.-,, --*-"-,,_.,,,,~,,:--7

__ .;'."::'7.~

.** -..,.,-

  • * * *** '."-:-7

... 1 ;_7"'.".',_

    • .._".'7,..._,, ~.:

... .,,:.~*,

    • ~~-

.**** *.-, ------

- --

BACKGROUND

-

UNIT 1 - DOR GUIDELINES

UNIT 2 - CATEGORY II REQUIREMENTS

4.

1981 THROUGH 1983 COMPREHENSIVE CHANGEOUT OF PLANT

EQUIPMENT

Cl

200 TRANSMITTERS

Cl

180 SOLENOID VALVES

Cl

250 LIMIT SWITCHES

Cl

UPGRADE OF LIMITORQUE ACTUATORS

5.

QUALITY ASSURANCE INVOLVEMENT IN DCP REVIEW AND FIELD

VERIFICATION ACTIVITIES

6.

JANUARY 61 1983 lOCFRS0.49 ISSUED AS FINAL RULE

7.

JANUARY 191 1983 NRC SERS AND TER ISSUED

Cl

PSE&G 30 AND 90 DAY RESPONSES TO QUESTIONS

0

ASSESSMENT OF COMPLIANCE TO lOCFRS0.49

0

DEVELOPMENT OF MAINTENANCE/REPLACEMENT PROGRAMS

8.

NRC SER'S FOR FINAL RESOLUTION OF EQ PROGRAM ISSUED

0

DECEMBER1 1984 FOR SALEM UNIT 1

.,__.,:_**.

  • ~-~ *** _ ..... - _, **-. -

.,

0

0

BACKGROUND

JANUARY, 1985 FOR SALEM UNIT 2

NRC CONCLUDED PSE&G'S EQ PROGRAM WAS IN COMPLIANCE

WITH THE REQUIREMENTS OF 10CFR50.49

9.

EQ TASK FORCE EFFORTS REFOCUSED TOWARD PROGRAM

ENHANCEMENT - 1985

0

.

0

0

0

MAINTENANCE REQUIREMENTS

ASSURANCE OF COMPLIANCE WITH lOCFRS0.49

QA AUDIT OF PROGRAMMATIC CONTROLS DURING JUNE, 1985

ISSUANCE OF CONSOLIDATED EQ PROCEDURE GM8-EMP-022 IN

OCTOBER~ 1985

  • ,

.4

ISSUE 1

LIMITORQUE T-DRAINS

DESCRIPTION OF CONDITION

19 OF 24 LIMITORQUE ACTUATORS Cll IN SALEM 11 8 IN SALEM 2>

INSIDE CONTAINMENT WITHOUT I-DRAINS DISCOVERED DURING

WALKDOWN.

SYSTEMS AND COMPONENTS AFFECTED

-

ACCUMULATOR OUTLET VALVES - SAFETY INJECTION SYSTEM

-

RHR PUMP INLET VALVES FROM RCS HOT LEG - RHR SYSTEM

-

PORV BLOCK VALVES - REACTOR COOLANT SYSTEM

-

RHR PUMP DISCHARGE VALVES TO HOT LEGS ~ RHR SYSTEM

-

CO.NTAINMENT ISOLATION VALVES - COMPONENT COOLING WATER

CCCW> RETURN FROM RCP MOTOR

COOLERS

- CCW RETURN FROM RCP THERMAL

BARRIER COOLERS

- RCP SEAL WATER RETURN VALVE

CCVCS>

CAUSE

LACK OF SPECIFIC DETAIL IN DCP/VENDOR MANUAL INSTALLATION

I NSTl{UCTIONS

. .

...

ISSUE 1

CORRECTIVE ACTIONS TAKEN

T-DRAINS INSTALLED IN SALEM UNIT 1 PRIOR TO RESTART FROM

MARCH 1986 REFUELING OUTAGE.

T-DRAINS INSTALLED IN SALEM

UNIT 2 PRIOR TO RESTART FROM VOLUNTARY SHUTDOWN IN MAY 1986.

NEW PROCEDURE ESTABLISHED TO CLARIFY INSTRUCTIONS WITH REGARD

TO INSTALLATION OF T-DRAINS <FIELD DIRECTIVE

S-C-A910-MFD-342).

PROCEDURE ESTABLISHED CGM8-EMP-009 ISSUED 12/85) REQUIRING

FIELD WALKDOWN BY PROJECT TEAM MEMBER IN ORDER TO CLOSE OUT A

DCP.

SAFETY SIGNIFICANCE

-

DEFICIENCIES NOT SAFETY SIGNIFICANT DUE TO QUALIFIABILITY

OF EXISTING CONFIGURATION.

  • ORIGINAL LIMITORQUE ACTUATORS CERTIFIED TO TEST REPORT.

600198 ESTABLISHED QUALIFICATION OF RELIANCE RAD-H TYPE

"OTOR WITHOUT T-DRAINS.

UPGRADED VALVE ACTUATOR MOTORS TO CLASS H1 TYPE RH IN

1984.

NEW RELIANCE MOTORS CERTIFIED TO TEST REPORT

600456.

SIMILARITY ANALYSIS DEMONSTRATES THAT UPGRADED RELIANCE

TYPE RH MOTOR WAS QUALIFIABLE WITHOUT T-DRAIN.

  • ,

...

  • *~- ... * .... _._ .... **-,*~****-*- _,_, *" -*

.*.',. ***--* *****'"'-** ~ ....*.

--"-'*-~**-****""*'-'*--~** .. -............. ,, ___ ................ ,.-........... ** ............. .

ISSUE 2

CONAX CONNECTORS FOR SOLENOID VALVES

DESCRIPTION OF CONDITION

8 OF 248 SOLENOID OPERATED VALVES WITHOUT REQUIRED CONAX

CONNECTORS DISCOVERED DURING WALKDOWN.

SYSTEMS AFFECTED

-

POST ACCIDENT SAMPLING SYSTEM - SALEM UNIT 1-

-

REACTOR VESSEL HEAD VENT VALVES - CONAX SEALS ARE NOT

REQUIRED FOR THE QUALIFICATION OF THESE VALVES.

CAUSE

ISOLATED OCCURRENCE OF NON-ADHERENCE TO INSTALLATION

INSTRUCTIONS.

ONLY 8 OUT OF 754 CONAX CONNECTORS NOT INSTALLED AS REQUIRED.

CORRECTIVE ACTIONS TAKEN

CONAX CONNECTORS INSTALLED PRIOR TO RESTART FROM SALEM 1

"ARCH 1986 REFUELING OUTAGE.

PROCEDURES ADOPTED REGARDING EQ REVIEW OF DCPS.

FIELD WALKDOWN PROCEDURE ALREADY IMPLEMENTED <DECEMBER 1985).

.I

ISSUE 2

CONAX CONNECTORS FOR SOLENOID VALVES

SAFETY SIGNIFICANCE

NOT SAFETY SIGNIFICANT.

-

PASS NOT REQUIRED FOR ACCIDENT MITIGATION.

-

QUALIFIABLE BY TEST FOR AT LEAST 12 DAYS*

-

REACTOR VESSEL HEAD VENTS DO NOT REQUIRE THE CONAX

SEALS, AND ARE NOT REQUIRED FOR MITIGATION OF DESIGN

BASIS ACCIDENTS.

-

NORMALLY DE-ENERGIZED, KEY LOCKED CLOSED DURING

OPERATION.

-

REDUNDANT MEANS OF NON-CONDENSIBLE GAS REMOVAL

DURING RECOVERY AS IDENTIFIED IN EOP'S.

-

VALVES ARE FAIL-CLOSED.

..

ISSUE 3

ELECTRIC JUNCTfON BOX SEALS

DESCRIPTION OF CONDITION

16 OUT 'OF 138 JUNCTION BOXES C7 IN SALEM l AND 9 IN SALEM 2)

WERE NOT PROPERLY SEALED IN ACCORDANCE WITH DCP INSTRUCTIONS.

SYSTEMS AND COMPONENTS AFFECTED

-

MSIV INDICATION LIMIT SWITCHES

-

CONTAINMENT PRESSURE VACUUM RELIEF -ISOLATION SYSTEM SOVs

-

UNIT 2 LIQUID RADWASTE SYSTEM CONTAINMENT ISOLATION VALVE

LIMIT SWITCHES.

CAUSE

CONFUSION OVER 'GENERIC INSTALLATION REQUIREMENTS, WHICH LED

-TO MISINTERPRETATION.

OVERSfGHT BY EQ SPONSOR IN NOT INCLUDING ALL JUNCTION BOXES

IN EQML.

CORRECTIVE ACTIONS TAKEN

0

JUNCTION BOXES WERE EITHER PROPERLY SEALED OR EVALUATED

AND FOUND ACCEPTABLE BASED ON THEIR CONFfGURATION PRIOR TO

RESTART FROM SALEM l MARCH, 1986 REFUELING OUT~GE AND MAY

1986 VOLUNTARY SHUTDOWN OF SALEM UNIT 2.

ISSUE 3

ELECTRICAL JUNCTION BOX SEALS

0

EQML AND DESfGN DOCUMENTS WERE UPDATED.

ADMINISTRATIVE CHANGES WERE MADE <PROCEDURE 'GMB-EMP-009

ISSUED 12/BS>*To ENSURE EQ SECTION REVIEW OF DCPs AND

EQ-RELATED DRAWINGS1 AND VERIFICATION OF FIELD WALKDOWN

PERFORMED BY PROJECT TEAM MEMBERS TO CLOSE OUT DCP.

FIELD DIRECTIVE <NO. S-C-A910-NFD-0405) FOR INSTALLATION

SEALING REQUIREMENTS WAS ISSUED IN AUGUST 1986.

SAFETY SfGNIFICANCE

-

DEFICIENCY NOT SAFETY SfGNIFICANT:

INDIVIDUAL CONFfGURATIONS WERE QUALIFIABLE.

AFFECTED COMPONENTS WOULD COMPLETE THEIR INTENDED

FUNCTION.

  • MSIV LIMIT SWITCHES PROVIDE POSITION INDICATION FOR

WHICH ALTERNATE POSITION INDICATION WAS AVAILABLE.

~ CPVRIV AND LIQUID RADWASTE VALVES '60 TO FAIL-SAFE

. POSITIQN.

.
***, ..

ISSUE 4

REMOVAL OF LIMITORQUE OPERATOR MOTOR BRAKES

7 C4 IN SALEM 11 3 IN SALEM 2> OF 136 CONLY 51 ORfGINALLY

SUPPLIED WITH MOTOR BRAKES> LIMITORQUE MOTOR OPERATORS WITH

MOTOR BRAKES FOUND OUTSIDE OF CONTAINMENT WITH BRAKES

ELECTRICALLY DISCONNECTED. BUT NOT PHYSICALLY REMOVED.

SYSTEMS AND COMPONENTS AFFECTED

-

COMPONENT COOLING WATER OUTLET OF RHR HEAT EXCHANGERS

-

SALEM 1 SAFETY INJECTION PUMP SUCTION

-

SALEM 2 RHR PUMP SUCTION.

CAUSE

MISUNDERSTANDING AS TO WHAT CONSTITUTED COMPLETE REMOVAL OF

THE BRAKES.

SPONSOR ENGINEER STATES THAT HE OBTAINED CONCURRENCE FROM

LIMITORQUE REPRESENTATIVE THAT ELECTRICAL.DISCONNECTION OF

BRAKES WAS SATISFACTORY.

CORRECTIVE ACTIONS TAKEN

MOTOR BRAKES WERE PHYSICALLY REMOVED PRIOR TO RESTART FROM

SALEM UNIT 1 MARCH1 1986 REFUELING OUT<<GE AND MAY 1986

VOLUNTARY SHUTDOWN OF SALEM UNIT 2.

WALKDOWN VERIFIED NO

OTHER EXAMPLES OF THIS DEFICIENCY.

....,.,.=

...... -.. --* . ! -_._.--.--

__ .,"!""'!!

.... ! -._ ........ ""!"".,

........ -

......... ""!""_. ---**----"**~*-

.. --

.... ~.---~--**-~,"""!""

.... ,.,.,...

.. .,.,.,,.,

.. ,, .. =.,

.. _,.,.,...,.,.~=

.. -.. =

...... ,.,..,,.,.._,,.,.,,,,,,_,,,.,,,,.,.,,,.,.,,_

.. _.,..,,.

... .,,,.,,

... .,.,,,,,-:

...... =*

...... ,.,,,..,.

.. , ..

,,.,...-., '""""*

... ,,,.....,.

....

,..-::;-

... =::

...... ,,.-,.:'.-.. .,,.,-;

. .,.~

... ~

... ~

..... ~~

........ -.

,-_ ..... ~ *****

'.

ISSUE 4

REMOVAL OF LIMITORQUE OPERATOR MOTOR BRAKES

REEMPHASIS OF ADHERENCE TO INSTRUCTIONS AS PART OF EQ

TRAINING PROGKAM OF STATION PERSONNEL.

SAFETY SIGNIFICANCE

-

DEFICIENCIES NOT SAFETY-SIGNIFICANT DUE TO QUALIFIABILITY .

OF EXISTING CONFIGURATION.

LIMITORQUE TEST REPORTS 600198 AND FC2485-l QUALIFY THE

OPERATORS WITH BRAKES <REPORT WAS FILED IN BACKUP

FI LES>.

MAXIMUM RADIATION EXPOSURE WOULD NOT DEGRADE BRAKE OR

COIL MATERIAL TO THE POINT OF IMPAIRING OPERABILITY.

INSERVICE STROKE TESTS HAVE CONFIRMED THAT THE PRESENCE

OF THE DEENERGIZED BRAKES DID NOT IMPAIR SAFETY

FUNCTION.

AFFECTED VALVES WOULD BE POSITIONED IN THEIR REQUIRED

RECIRC LINEUP BEFORE THEY WOULD BE EXPOSED TO

SIGNIFICANT RADIATION DOSES.

  • SIMILARITY ANALYSIS DEMONSTRATES THAT AS-FOUND

CONFIGURATION WAS QUALIFIABLE WITH MOTOR BRAKES.

  • .., .. ~ ... ** ..... * .. : ... : .

-

  • ... -** ...

. *. *

... *: ... : ... ' , _ _,.,. "", .. ,. -* #.~.** *..

.'* * .. * * ;,.._. J

  • * ** :
  • :. *.- i .: .:.' .**' :. :_ _, *, ':"..:. '- * ** ;- ... , .:.::.. *~-.-,;r.-: .. :.. ... , . . v ** _ .. _

-'-*

~ ~. *

  • _

ISSUE 5

AUXILIARY FEEDWATER FLOW TRANSMITTER CONNECTIONS

DESCRIPTION OF CONDITION

MARCH, 1986 WALKDOWN IDENTIFIED 8 C4 IN EACH UNIT> AUXILIARY

FEEDWATER FLOW TRANSMITTERS COUT OF 200 QUALIFIED

TRANSMITTERS> THAT WERE TERMINATED WITHIN JUNCTION BOXES ON

TERMINAL BLOCKS RATHER THAN QUALIFIED SPLICES.

SYSTEMS AND COMPONENTS AFFECTED

-

AUXILIARY FEEDWATER SYSTEM FLOW TRANSMITTERS

CAUSE

ISOLATED CASE OF USE OF TERMINAL BLOCKS IN A TRANSMITTER

CIRCUIT WHICH WAS NOT DISCOVERED BY THE REVIEWERS DURING

REVIEW OF IN 84-47.

CORRECTIVE ACTIONS TAKEN

THE TRANSMITTER TERMINATIONS WERE MODIFIED TO USE QUALIFIED

RAYCHEM SPLICES..

SPLICES WERE INSTALLED_ PRIOR TO RESTART

FROM SALEM 1 MARCH, 1986 REFUELING OUTAGE AND MAY, 1986

VOLUNTARY SHUTDOWN OF SALEM 2.

.. *- . . ";

-~-....

ISSUE 5

AUXILIARY FEEDWATER FLOW TRANSMITTER CONNECTIONS

ADMINISTRATIVE CHANGES MADE <PROCEDURE GM8-EMP-009 ISSUED

12/85) TO ENSURE EQ SECTION REVIEW OF DCPs AND EQ-RELATED

DRAWINGS1 AND VERIFICATION OF FIELD WALKDOWN PERFORMED BY

PROJECT TEAM MEMBER TO CLOSE-OUT DCP.

SAFETY SIGNIFICANCE

-

DEFICIENCY WAS NOT SAFETY SIGNIFICANT:

  • CONFIGURATION WAS QUALIFIABLE
  • - TRANSMITTERS HAVE NO ACCIDENT MITIGATION FUNCTION.

AFW FLOW VERIFICATION WILL OCC*UR LESS THAN TWO MINUTES

INTO ACCIDENT1 BEFORE ADVERSE CONDITIONS COULD AFFECT

THE TERMINATIONS.

THE INDICATED FLOW.

    • """~: :.: *.. __ ., ~-.. --*--*** .- *' .'

~*-- -.

-* *. - - *. . : . "-*. *, -:**

-** -

- -- .* *.. .:: *.... ,. , .... ' - * **' -** .* -* ** **. -- -

  • '. ': -~.:.-

~-....... ,.{~ _;_ ,_.,. __ ;...,,.!"~':.::.,..: .>".'. ::.-..:.'.* .. ::.~~-~*:.:..1;.:_ ... ..::;,.:. ** J

    • ~-*:.. .. _.-,~*~:.~;..~*~;,,i;..;. . .-.~ .. ~-..:-.::. *'-'-******- ....... :-*. ---.'"'" .... . * ,

. --

.... ,, .*.. _, .... -.:: .

..

GENERIC LETTER 88-07 APPLICATION

EVALUATE EACH ISSUE AGAINST GENERIC LETTER 88-07 CRITERIA FOR

APPLICATION OF THE MODIFIED ENFORCEMENT POLICY:

1.

PRIOR TO NOVEMBER 30J 1985 DEADLINE

2'.

"CLEARLY KNEW OR CLEARLY SHOULD HAVE*KNOWN" TEST

-

AVAILABILITY OF VENDOR-SUPPLIED QUALIFICATION DOCUMENTATION

-

EQUIPMENT CONFIGURATION VERIFICATION MEASURES

-

PRIOR KNOWLEDGE OF POTENTIAL EQ DEFICIENCY.

-

IDENTIFICATION AND CORRECTION OF SIMILAR PROBLEMS BY OTHER-

LICENSEES PRIOR TO DEADLINE

GENERIC LETTER 88-07 ENFORCEMENT POLICY ASSESSMENT

IF APPLICATION OF ENFORCEMENT POLICY IS CONSIDERED, DETERMINE

"SIGNIFICANCE" OF EACH ISSUE?

1.

IS THE EQUIPMENT "QUALIFIABLE"?

2.

IF NOT SINGULARLY "SIGNIFICANT", ARE THE PROBLEMS, IN THE

  • AGGREGATE, PROGRAMMATIC?

3.

IF "SIGNIFICANT", CLASSIFY PROBLEM AS "ISOLATED", "MODERATE",

OR "EXTENSIVE" PURSUANT TO THE EXPLANATION PROVIDED IN GENERIC

LETTER 88-07.

.


~- .... , ... -

'

... ;-._ *..

--*

_,.,.~_,_ ..... , __ .****---~-'****-*-**---

        • -**-**** ..... ,...--.-., .... ~ .. ,. .. -...: .. -.... ~ .... ---"*"-*"-*** ... ~---*"*'~-----*-*-******- ....

--~

    • -*---*--------*--**------------~--..--

. *-- --.- - ..

MODIFIED POLICY vs 5 DEFICIENCIES

  • 1.

LIMITORQUE T-DRAINS

2.

CONAX CONNECTORS FOR SOLENOID VALVES

3.

ELECTRIC JUNCTION BOX SEALS

4.

REMOVAL OF LIMITORQUE OPERATOR MOTOR BRAKES

5.

AUXILIARY FEEDWATER FLOW TRANSMITTER CONNECTIONS

° CLEARLY SHOULD HAVE KNOWN ?

0

QUALIFIABILITY

- GENERAL ENFORCEMENT POLICY SHOULD APPLY -

MITIGATION/ESCALATION FACTOR ASSESSMENT

IF A CIVIL PENALTY IS PROPOSED UNDER GENERIC LETTER 88-07 FULL

MITIGATION IS WARRANTED:

-

ALL DEFICIENCIES WERE IDENTIFIED BY PSE&G AS A RESULT OF SELF-

INITIATED WALKDOWNS AND PROMPTLY REPORTED TO NRC

-

PROMPT AND EXTENSIVE CORRECTIVE ACTIONS TAKEN~ INCLUDING EXTENSION

OF SALEM l OUTAGE~ VOLUNTARY SHUTDOWN OF SALEM 2~ PHYSICAL

MODIFICATIONS AND ADMINISTRATIVE IMPROVEMENTS

-

LIMITED NUMBER OF COMPONENTS AND SYSTEMS AFFECTED

-

PSE&G APPLIED BEST EFFORTS TO COMPLETE EQ PROGRAM WITHIN DEADLINE

0

MAJOR REPLACEMENT EFFORT UNDER NUREG-0588~ CAT. II (1981-83)

0

QA INVOLVEMENT (1981+)

0

EQ TASK FORCE EFFORTS (1984-1985)

° FINAL SERS AND APPROVED PROGRAM (1984-1985)

0

PROGRAM ENHANCEMENTS Cl985)

    • -* ' .. **, --~-....:~*-.*---~-'-*-** *-**** .. -..
  • ":

-

-

  • ----

""-**'*' ***

-

........

, ... -.*::._.~,_ __ ..... :- .. ~**** _, .. -1. ... :::.*1"~: .. *-** ... -.;- ... -* .. .: ...* ; *. : ..

~--*--*---*-** .:. ** *.- ... --~-----.. ----~"-~-'-'** ...... _.:..

...

.* ... :;.

  • <

ASSESSMENT UNDER GENERAL ENFORCEMENT POLICY

ClOCFR PART 2~ APPENDIX C>

THE FOLLOWING POINTS SHOULD BE CONSIDERED IN APPLYING lOCFR

PART 2~ APPENDIX C

1.

THE EQ DEFICIENCIES IN QUESTION WERE IDENTIFIED BY PSE&G

2.

THE DEFICIENCIES WERE REPORTED IN LER 86-007

3.

EACH DEFICIENCY IS NO MORE THAN SEVERITY LEVEL V .

4.

APPROPRIATE CORRECTIVE ACTIONS HAVE BEEN TAKEN TO RESOLVE

THE DEFICIENCIES AND PRECLUDE RECURRENCE

..

5.

THE FINDINGS COULD NOT HAVE BEEN PREVENTED BY CORRECTIVE ACTIONS

RESULTING FROM A PREVIOUS VIOLATION

6.

THE EQ DEFICIENCIES IN QUESTION ARE NOT SAFETY SIGNIFICANT

- EXERCISE OF DISCRETION IS WARRANTED -

  • ---****"* ....... -_ -* _,_.

-:-... -- ,.,, __ - * .. *.

~ ** ***. --**** ~,,.; ;>;-~ ~J..,." * , ;, ***. ' ***** -~ ;.* *** -'-'*' .* ,, ... *.: *-;,: * ..;; .*

  • * .i':: *
  • . ,...,...,,; * .- -..~ .* . .,*,: .-* .._~,,_.,_~_.._,._,,.:;,.-.:..: * .n:.;<< * .:oo.: ** ,, *** _...... -~..:. ... ...: .~r~ ....... ,..'.l, .* >W "* *~ ~ * ., **

-'"*'; - ***

  • -
  • -** .;..

-

~*

  • *...
    • * .,,, ._ **

PROGRAM STATUS

ENVIRONMENTAL QUALIFICATION PROGRAM AFTER NOVEMBER 30, 1985

1.

MILESTONE EVENTS

0

0

0

EQ WALKDOWN FOR MAINTENANCE BASELINE OF SALEM UNIT I

- MARCH 22, 1986 *

0

PLAN INITIATED IN EARLY 1985

0

VERIFY EQUIPMENT SERIAL NO. AND INSTALLATION DATE

TO ESTABLISH START OF QUALIFIED LIFE

.

0

J)ETERMINE SPECIFIC EQUIPMENT LOCATION <ELEVATION

AND COLUMN LINE>

0

VERIFY MOUNTING ORIENTATION, MOISTURE SEAL, SPLICE

OR TERMINAL BLOCKS

SHUTDOWN OF SALEM UNIT 2 TO PERFORM COMPREHENSIVE

WALKDOWN - MAY l, 1986

0

SAME ACTIVITIES AS SALEM UNIT 1

0

ISSUE LER #86-007 - MAY 8, 1986

SHUTDOWN OF SALEM UNITS 1&2 - AUGUST 6, 1986

0

REPLACE QUESTIONABLE WIRE IN LIMITORQUE ACTUATORS

- IN RESPONSE TO INFORMATION NOTICE #86-03

0

PROGRAM STATUS

0

100% WALKDOWN OF LIMITORQUE ACTUATORS IN EQ

PROGRAM

-

0

100% REPLACEMENT OF SUSPECT WIRE WITH QUALIFIED

ROCK8ESTOS FIREWALL III WIRE

NRC EQ INSPECTION - AUGUST 11-15, 1986

0

ALL ISSUES ADEQUATELY RESOLVED

2-

ORGANIZATION ENHANCEMENTS

0

(l

ENGINEERING & PLANT BETTERMENT CE&PB> REORGANIZATION

TO MATRIX ORGANIZATION - OCTOBER, 1987

FORMED THE PROGRAM ANALYSIS GROUP CPAG> - OCTOBER,

1987

0

PROGRAMMATIC SPONSOR FOR EQ

° CENTRALIZED DEDICATED GROUP TO SUPPORT SALEM AND

HOPE CREEK STATIONS

0

ESTABLISH COMMONALITY, CONSISTENCY BETWEEN SALEM

AND HOPE CREEK STATIONS

3.

PROGRAMMATIC ENHANCEMENT

0

DEVELOPMENT OF PROGRAMMATIC STANDARDS

.o

RESTRUCTURE OF SALEM EQ FILES

0

PROGRAM STATUS

CONVERSION OF HOPE CREEK EQ FILES FROM PURCHASE ORDER

BASIS TO EQUif'lENT TYPE BASIS

4.

INDUSTRY ENVOLVEMENT

0

0

-

Cl

0

MEMBER OF NUCLEAR UTILITY GROUP ON EQUIPMENT

QUALIFICATION CNUGEQ)

MEMBER OF EPRI

MEMBER OF SEISMIC QUALIFICATION UTILITY GROUP CSQUGl

MEMBER OF SEISMIC OWNERS GROUP

\\.

PUBLIC SERVICE ELECTRIC AND GAS

SALEM UNITS 1 AND 2 GENERATING STATIONS

ENVIRONMENTAL QUALIFICATION PROGRAM

ENFORCEMENT CONFERENCE

SEPTEMBER 29, 1988

DETAIL HANDOUT MATERIAL

  • t

INTRODUCTION

PUBLIC SERVICE ELECTRIC AND GAS

SALEM GENERATING STATION UNITS 1&2

NRC EQ ENFORCEMENT CONFERENCE

SEPTEMBER 29, 1988

The material provided in this package supplements PSE&G's verbal

presentation in response to the NRC letter of August 19, 1988

with regard to PSE&G's identified deficiencies in the Salem Units

l and 2 concerning the Environmental Qualification of Electrical

Equipment as addressed in LER No.86-007, dated May 8, 1986.

BACKGROUND

The following is a discussion which chronlogically presents the

various milestones encountered during the development of the

Salem Units 1 and 2 Environmental Qualification Program.

The environmental qualification of electric equipment has been an

item of primary importance throughout the licensing and

operational stages of both Salem Unit 1 and Salem Unit 2.

At

Salem Unit 1, guidance for the design and installation of

safety-related electrical equipment was initially {i.e., in the

early 1970s) based on existing engineering codes and standards

and was indicated within the specific design and procurement

specifications for the individual components.

For the NSSS

equipment, qualification assessments were made by the vendor

(Westinghouse) to assure the operation of appropriate

safety~related equipment in a post-accident environment.

At the

site, all of this equipm-ent was installed under the purview of an

effective Quality Assurance program established under the

requirements of 10CFR50, Appendix B.

While initial environmental qualif ic~tion efforts were similar

for Salem Unit 1 and Unit 2, the actions taken to comply with EQ

guidelines were magnified by Salem Unit 2's status as a post-TM!

near OL plant.

In 1978 and 1979, PSE&G responded to a number of

Salem Unit 2 SER Open Items with regard to the qualification of

terminal blocks, limit switches, solenoid valves, pressure

transmitters, instrument panels, motor operated valves and

cables *.

On January 14, 1980, the N.RC Office of Inspection and Enforcement

issued the DOR guidelines and I&E Bulletin 79-0lB.

In response*

to Bulletin 79-018 and its associated supplements, PSE&G

conducted an EQ review of electrical and control equipment

located in a {post-accident) harsh environment.

Equipment

Al 88/ba

"

Background (Cont.)

2

qualification was based on IEEE 323-1971 with the additional

requirements for aging noted in Bulletin 79~01B.

This review

effort resulted in the submittal of the original Salem Units 1

and 2 Environmental Qualification Review Report to NRC on

December 1, 1980.

On June 25, 1980, the NRC issued a Generic Letter endorsing the

EQ guidelines provided in NUREG-0588.

PSE&G promptly responded

and initiatea action to review the Salem Units ) and 2 EQ program

based on the Category II requirement~ of NUREG-0588 (Salem Unit 1

is a DOR plant).

On September 8-9, 1980, and December 9-10, 1980, NRC conducted a

pre-license audits of Salem Unit 2 EQ Program at the corporate

headquarters in Newark~ NJ.* Issues raised by the NRC during the

Septemb~r audit-were adequately addressed prior to the December

audit.

In 1981, PSE&G initiated utilization of the EPRI ~Q Data Bank

(EQDB) in order to obtain additional information concerning

equipment qualification.

This data base provided support to the

Salem EQ program and also allowed PSE&G access to a data base of

other utility EQ-related activities.

From 1981 through 1983 PSE&G initiated and completed whole. scale

-changeout of plant equipment with new environmentally qualified

equipment.

This effort included replacement of approximately 200

transmitters, 180 solenoid valves, and 250 limit switches in

Units 1 and 2.

During 1984 and early 1985, 24 Limitorque

actuator's motors were upgraded from class B to class RH

insulation in Salem Units 1 and 2.-

QA's involvement in the EQ program, in particular verification of

design changes Covering replacement of the above noted equipment

was significant.

In 1981, prior to the start of the EQ equipment

changeouts, surveillance plans were executed to provide

verification of pre-assembly operations as well as field

installation surveillances covering component model verification,

installation of splices and seal assemblies torquing

requirements, and various other attributes.

Review of the design

change packages content was also done by QA for procedural

compliance, specific details and appropriate engineering

instructions.

The reviews by QA resulted in favorable results in

each of the above areas.

The Salem Units 1 and 2 Environmental Qualification Review Report

was reviewed for the NRC by the Franklin Research Center.

The

NRC Safety-Evaluation Reports (SERs) for Salem Units 1 and 2

along with the associated Franklin Technical Evaluation Reports

Al88/ba

Background (Cont.)

3

(TERs) were issued in January, 1983, shortly after the issuance

of the final EQ rule, lOCFRS0.49 on January 6, 1983.

Following

the required 30-day and 90-day responses to the SERs, the

development of the Salem EQ program was defined by four (4)

distinct efforts:

1.

The resolution of any remaining concerns ~ith regard to the

NRC SERs and the ~ranklin TERs,

2.

The assessment of compliance with lOCFRS0.49, particularly

with regard to the 3ppl:cation of the more stringnt

requirements of IEEE 323-1974 to replacements and spare

parts,

3.

The development of a maintenance/replacement program for

equipment with less than a 40-year qualified life, and

4.

The categorizing and disposition of all safety-related

electrical components into functional maintenance,

surveillance and test plans.

These efforts resulted in the formation of a task force in early

1984 to keep track on the progress of responses to NRC open items

as well as the overall development of the EQ program.

This task

force was headed by Engineering and Plant Betterment (E&PB),

Systems Analysis Group (SAG) who, with plant engineering, were

primarily responsible for the development of the program and its

related documentation.

On April 24, 1984, a meeting was held in Bethesda, MD to discuss

NRC's remaining EQ concerns and PSE&G compliance with

lOCFRS0.49.

NRC's primary concerns were:

1.

The finalization of the EQ Master List,

2.

The response to the two generic deficiencies noted in the

Franklin TER with regard to submergence and chemical spray,

and

3.

The confirmation that all design basis events which could

result in a potentially harsh environment (including flooding

outside containment) were addressed in the identification of

safety-related electrical equipment which was to be

environmentally qualified.

PSE&G's responses to these concerns were documented in a letter

dated June 8, 1984.

The NRC SERs for Final Resolution of the EQ

Program were issued in December 1984 for Salem Unit 1 and January

19~5 for Salem Unit 2.

?\\188/ba

  • '

.... -*** .. _;_ *.

-~** **- -

.* ... -*

  • ~ .. *-***--***. ~*-***""'-"""""'****---.... ~.-*-**-*- - --***-**

Background (Cont.)

4

The NRC concluded that Public Service Electrical and Gas

Company's Equipment Qualification Program was in compliance with

the requirements of 10CFR50.49.

QA verification continued during this period on EQ related design

changes.

In line surveillances were supplemented in 1984 with

follow-up desiqn change package and EQ report reviews as

committed to the NRC during the April, 1984 meeting.

EQ Task Force efforts were refocused at this time toward program

enhancement regarding maintenance and control and assurance of

continued compliance with 10CFR50.49.

Several QA walkdowns of

randomly selected components were initiated at the direction of

the task force.

In conjunction with the task force, SAG

initiated an effort to review-all qualification documents and to

assure establishment of the programmatic controls necessary to

maintain appropriately qualified electrical equipment.

A QA

audit of the programmatic control of EQ at Salem Units l and 2

was performed, at the recommendation of the EQ Task Force, from

June 17-25, 1985.

The QA audit did not reveal any obvious

programmatic flaws but did result in the initiation of several

recommendations with regard to procedures, documentation and

training which were incorporated accordingly.

On October 16, 1985, PSE&G procedure GM8-EMP-022 was issued to

consolidate and provide a more comprehensive description and

guide to the EQ requirement& established for Salem.

This

procedure centralized all phases of the EQ program so that its

implementation could proceed more effectively.

Further enhancement of the program by SAG in 1985 included

reviewing all of the EQ file binders to assure compliance with

the above noted procedure.

In addition, new field directives

regarding installation and maintenance requirements were issued

providing more explicit information for Station personnel usage.

The above summary represents those actions taken by PSE&G prior

to the November 30, 1985 mandatory EQ deadline to establish and

maintain the qualification of safety-related electrical equipment

at Salem Units 1 and 2.

PSE&G feels that the results of these

efforts represent a firmly established EQ program and that the

efforts themselves represent a substantial commitment on our-part

to comply with the EQ deadline.

Al88/ba

PUBLIC SERVICE ELECTRIC AND GAS

TECHNICAL ASSESSMENT

ISSUE 1

LIMITORQUE T-DRAINS

I.

STATEMENT OF CONDITION

As described in LER 86-007, PSE&G identified (during a

self-initiated walkdown) eleven (11) Unit 1 and eight

(8) Unit 2 Limitorque actuators inside containment for

which T-drains had not been installed in the motor bell

  • housings.

These actuators were located inside

containment and involve the safety injection system,

residual heat removal system, reactor coolant system,

component cooling water system and the chemical and

  • volume control system.

II *. ROOT CAUSE

These omissions were isolated instances.

PSE&G

nevertheless considers the underlying cause of the

omission to be a lack of explicit instructions

that detailed the T-drain requirement.

III. CORRECTIVE ACTIONS TAKEN

PSE&G took prompt corrective actions to address fully

the deficiency as well as the root cause.

Specifically,

PSE&G installed T-drains in Salem Unit 1 prior to

-

restart from the March, 1986 ~efueling outage.

T-drains

w~re aiso installed in Salem Unit 2 prior to restart

from a voluntary shutdown in May, 1986.

PSE&G further

established a new procedure (S-C-A910-MFD-0342, dated

December 2, 1985) to provide added as~rnrance that future

DCPs include sufficient instructions with respect to

T-drains and other EQ requirements.

In addition, PSE&G

had previously implemented a new engineering procedure,

GM8-EMP-009 dated December, 1985, to close-out DCPs with

a field walkdown performed by the project team members.

These actions provided assurance that PSE&G was in full

compliance prior to restart and that this type of

condition should not recur.

IV.

SAFETY SIGNIFICANCE

1.

There was no safety significance regarding the

installed configuration in that:

Al88/l

..

Issue 1 (Cont.)

2

(a)

On a case specific basis, PSE&G analysis

con~luded that Salem Station containment

Lirritorque actuators do not require T-drains to

assure qualification.

The actuators were

qualifiable without T-drains based on

Limitorque Test Report 600198, which was the

original basis for qualification of Limitorque

actuators inside containment.

(b)

Report 600198 tested a size SMB-0-15 actuator

without T-drains to a maximum temperature of

328°F, 105 psig, and 100% saturated steam

environment.

Radiation qualification was

achieved by utilizing Report 600376A plus

analyses.

(c)

Qualification upgrading program consisted of

installing superior quality components (DCR's

1788 and 1789).

New class H, type RH motors

were ordered to replace existing RAD H

containment motors.

(d)

Motor similarity analysis demonstrates

qualif iability of class H, type RH motor to

original motor qualification report, 600198.

(See Appendix A for qualifiability bases)

V.

STATUS

Al88/l

Full compliance with respect to the T-drain.

condition was achieved by April 30, 1986 for Unit 1,

and May 3, 1986 for Unit 2.

-:... ..... *.:*:. .. ~, : .. ~,;;_,,, .. *-- .* .:. --

. .* ... ~ . '* . -

'

  • ...

~ .. -' * ~-. , ** , - * ,..:-.~ ... ,, *. -* ** *.:. * .* .:.. .. ,.. .,, ;. .. :-_,* ,; ... * *.*:-. ...:, ;: * *;..,. ;;~ *. :... .. *-~;.::. .-:.. , .:* .*. _ *. .- :-J.-.!>.! *. . "" ,..,_ . _ ........ * ;.,,_ .. __ .. ,. ~-

.L*
_.~. "-'-****** ***- .__;.:,. *-:-..

,.

LIMITORQUE T-DRAINS

APPENDIX A

BASES FOR QUALIFIABILITY

Limitorque designed the actuator with the philosophy th~t the

environmental ambient conditions be permitted to enter the

actuator with minimal restrictions, while ensuring the

capability of the actuator to perform their safety function

during the accident scenario.

The Ankorite gaskets, used between the actuator housing and

.the limit switch compartment cover, will seal against the

entry of fluids sprayed on the actuator, but are not designed

to seal against vapor entry as would be experienced during an

accident (as a result of differential pressure).

Qualif icatio~ testing was performed at extremely high

pressure and temperature conditions.

This philosophy was

designed to incorporate a significant safety margin.

Motor

T-drains were installed on the test units to drain away

potential acctirnulation of fluids that could result from the

extremely high test pressure, combined with the saturated

steam environment.

In order to serve their principal purpose, which is to

function as drainage pathways, the T-drains should be

installed at actuator low points.

Limitorque recommends that whe~ T-drains are requir~d, that

they be installed on the motor bell, regardless of the

orientation of the as-fnstalled actuator, to represent the

tested configuration.

Motor orientation, which would preclude moisture accumulation

in the motor bell, does not necessitate the use of T-drains

as drainage ports, as the function of the T-drain, to

eliminate moisture from the low point of the unit, would not

be performed.*

Due to the un~ealed actuator design, internal to external

actuator pressure equalization will be achieved without the

need of T-drains.

Salem Station Limitorque actuators inside containment are*

oriented *such that the motor and limit switch compartment are

horizontal.

The limit switch compartment cover is mounted in

Al88/l

.,

  • . -* .... _. ~-.,, .

.

'

Appendix A (Cont.)

2

a vertical position, thus the bottom of the limit switch

compartment is the low point of the ~ctuator.

In this

orientation, it is unlikely that moisture will accumulate in

the moto~ bell housing.

The original Reliance RAD H motors were certified to

Limitorque Qualification Report 600198, which was the basis

for qualif ic3tion of Limito~que actuators for use inside

containment at Salem Station.

Testing and qualification to

this report was done without the uie of T-drains.

This

report is currently maintained in the Salem EQ backup files.

For actuators tested without T-drains, as is the case of

Report 600198, T-drains are not required to support the

qualification of the actuators.

The replacement Reliance*

type RH motors, are supplied with certification to more

recent qualification testing (Report 600456), that had

T-drains installed on the motor bell.

When upgrading the

actuators inside containment, qualification changed from

Report 600198 to 600456.

Since the .RH type of motor

insulating system is considered superior to the RAD H system,

an analysis has been generated that supports the gualif ied

configuration of the original installation without the. use of

motor T-drains.

In this case, the absence of T-drains is

readily justified and will not.prevent proper motor operation

or violate environmental qualification.

To support the issue of operability of the installed

. configuration without T-drains, motor orientation, which

would preclude moisture accumulation in the motor bell,

should not necessitate the use of T-drains (as drainage

ports}.

Salem Station Limitorque actuators inside

containment are oriented such that the motor and limit switch

compartment are horizontal.

In this configuration, it is

unlikely that moisture will accumulate in the motor bell

housing, as the motor bell is not at the low point of the

actuator unit.

Since the actuators installed at Salem Station are not in the

worst possible~test orientation position, the functionality

of the T-drains on the motor bell is not essential for

moisture elimination.

Also, due to the results of Limitorque

test 600198, and the unsealed actuator design, internal to

external pressure equalization will be achieved without the

need *of T-drains.

Thus, Salem Station Limitorque actuators

inside containment are qualif iable in their installed

Al88/l

._ .... : . .- . *--- :.

..

. -* . . . --*

~*

. - - *..* : *..

~ .*. *-*:

.~ .,.. ..... * ~*. -** *:~* .. --~---.: *.. _;:;_.: *. _:*.~.:c.:.::...J - ""-'"-""-*-'** ;_ ---* ._ .*. ; ____ .... -4.. : .. ..... ' ~; * '* **.*** *,. -.-**** -'*-* .,,

PUBLIC SERVICE ELECTRIC AND GAS

TECHNICAL ASSESSMENT

ISSUE 2

. SOLENOID OPERATED VALVES -

CONAX SEALS

I.

STATEMENT OF CONDITION

As.described in LER 86-007, PSE&G identified during

self-initiated walkdowns of Salem Units 1 and 2

instances in which Conax connectors had not been

installed in solenoid operated valves, contrary to the

requirements of PSE&G's EQ requirements.

The solenoid operated ~alves involved were on the Unit.!

Post Accident Sampling System and the Unit 1 and Unit 2

Reactor Head Vent valves.

A total of 16 valves were

identified in the LER as not utilizing seal connectors.

Subsequent evaluation has shown that the Reactor Head

Vent valves do not require seal connectors, therefore,

only 8 of 248 solenoid operated valves were installed

without the required seal connectors.

I I.

ROOT CAUSE

The DCP's for the ASCO PASS solenoid valves specifically

directed that Conax connectors be installed.

The

required connectors for the PASS valves involved are

located within a single panel (801-lA) in Unit 1.

Other

ASCO solenoid valve installations.in Unit 1 pnd Unit 2

  • properly addressed s.imilar DCP seal requirement

instructions.

Accordingly, this appears to be an

isolated instance of overlooking explicit directions, as

these are the only eight, out of 754 Conax connectors,

that were not installed as required.

With respect to the Target Rock Reactor Head Vent

solenoid valves, no DCP requirement was necessary as the

seals are not required.

III. CORRECTIVE ACTIONS TAKEN

PSE&G promptly corrected the identified deficiencies by

installing the required Conax connectors prior t6

restart from the Unit 1 refueling outage which commenced

in March, 1986, and instituting corrective measures to

address the root cause of the deficiency.

Specifically,

in response to the findings discussed in LER 86-007,

PSE&G instituted a procedure to require a formal review

Al88/2

  • .

Appendix A (Cont.)

3

  • configuration by the original basis supplied in Report

600198.

Detailed analysis have been performed by Engineering

and are on file at PSE&G.

Al88/l

..

,'--,

.. *.: ...... --..-.. .: .~. : .. : __ , ___ ~ __ ._,;*_,._,_,. ... : ... :.*: ... ~* ...... -~. * .. -.. * .... *~-~-- -*---: _*.: .. :_ .. :.* .. -......... *,_ . -*-~--~ ..... __ ,,_, __ _.*, .. *

Issue 2 (Cont.)

2

of DCP's by the EQ Engineers.

In addition, another

procedure had previously been implemented (December,

1985) to require a post-installation walkdown by the

lead engineer for each DCP.

IV.

SAFETY SIGNIFICANCE

The identified deficiencies were not safety significant.

Al88/2

Unit 1 Post Accident Sampling System Valves -

Post

Accident Monitoring System

Evaluation of these solenoid valves has shown that

they are qualifiable, by vendor testing perf0rmed,

for a minimum of 12 days.

Inoperability of the valve solenoids could preclude

the ability to sample the containment atmosphere and

the Reactor Coolant System to assess cor& damage.

(NUREG 0737,Section II.B.3.)

Although this

sampling is not required for mitigation of an

accident, it is employed for emergency planning

purposes such as providing protective action

recommendations.

There is no condition which would

re$ult in inadvertent opening of the valves.

A

short due to moisture would result in the valves

failing closed.

In addition, in series with each

valve in question is-a second valvE (located outside

containment) in a mild envir_onment.

The switches.located in the control room for the

PASS valves provide control power only.

The valves

are operated from the PASS sampling panel.

This

panel contains adequate inform2tion to ascertain

valve position and flow.

Once the operator

energizes the control power he has no further

interface with the operation of these valves.

Therefore there is no potential for the operator to

be misled or confused by conflicting information

from valve position.

Unit l and Unit 2 Reactor Head Vent Valves

Evaluation of these solenoid valves has shown that

seal connectors are not required to ensure proper

operation of the valves.

._._. .... ,.

<'

"

Issue 2 (Cont.)

3

These valves are normally key-locked closed during

operation, and are used only as a last resort to

remove a non-condensible gas bubble from the reac_tor

head in the event that no other means is available

(EOP-FRCI-3).

However, these valves are not

required to mitigate accidents analyzed in the

FSAR.

Additionally, there is no condition which

would result in inadvertent opening of the valves;

i.e., a short due to moisture would result in the

valves failing closed.

If moisture intrusion were to occur, the resultant

short circuit would trip the 125VDC breaker

supplying power to the valves.

This breaker also

provides power for the limit switches which provide

position indication.

Therefore position indication

would be lost the same time the valves

failed-closed, eliminating the possibility for

conflicting information being presented to the

operator regarding actual position of the valves.

In summary, the affected valves do not perform functions

necessary for the prevention or mitigation of design

basis accidents.

Thus, there is no safety significance

to the stated deficiency.

V.

STATUS

Al88/2

Full compliance with respect to the PASS valves and

Reactor Head Vent valves was completed on May 6,

198 6.

Regarding corrective actions to address the

root cause, the DCP process was supplemented by

procedure GM8-EMP-009, issued December, 1985.

The

post-installation walkdown procedure had already

been issued and implemented.

SOLENOID OPERATED VALVES -

CONAX SEALS

APPENDIX A

BASIS FOR QUALIFIABILITY

ASCO solenoid valves a~e mounted inside of Panel 801-lA,

which will shield the SOV's from direct impingement of water

spray and steam.

Because.of the installed configuration, the only way moisture

can enter into Panel 801-lA is through the pressure

equalization vent in the lower left corner of the enclostire

door.

Qualification testing of the ASCO SOV's was performed at

extremely high temperatures and pressures-.

The 30 day LOCA

test performed more than encompasses the Salem LOCA profile,

where the severe accident pressure condition decays (to 5

psig) within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

One anomaly occurred during the LOCA test when the SOV coil

shorted due to moisture intrusion.

This occurred on the 12th

day of the LOCA exposure, when the test pressure was at 68

psig.

(Note:

pressure is the parameter that will force

moisture into the SOV housing, which could then possibly

cause the coil to short.)

After 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, the Salem accident

pressure has decayed to 5 psig, and remains there throughout

the completion of the accident scenario.

The tested SOV coil

shorted only_ after exposure to two transients, 10 days of

exposure to extreme pressure conditions (i.e., above 30

psig)*, and one full day of exposure at 68 psig.

Therefore,

the SOV's are shown to be qualifiable for a minimum of 12

days.

It is postulated that the PASS SOV's would operate well

beyond the 12th day failure point experienced in the ASCO

test report.

At Salem, the accident pressure rapidly decays

to a low value, rather than fluctuating between extreme

values.

This "equilibrium" effect provides a less severe

environment, and therefore, will have less ability to drive

moisture into the SOV hou~ing.

As a result of the anomaly, ASCO recommended that the SOV

installation utilize a sealed vented conduit/junction box

GOnfiguration to prevent moisture intrusion.

Essentially,

the as-installed configuration meets this criteria.

ASCO did

not specifically recommend the use of seal connectors.

Al88/2

..

Appendix A (Cont.)

2

ASCO's recommendation of using a sealed vented conduit/

junction box configuration was not subsequently tested.

Therefore, no firm evidence exists that utilization of this

configuration will prevent coil-related failure of the SOV

from moisture intrusion at extreme pressure conditions.

To date, there is no known methodology to extrapolate

p1:essure/humidity test results pcist the actuc.l t.:steC: time

period.

To prove that ASCO's "sealed" system is qualified

for 100 days post-accident, it would have been necessary to

test the unit for 100 days.

Since this testing was not

performed, there is no evidence that the sovrs will survive

for 100 days, anymore than there is evidence that they will

fail after 12 days.

Al88/l

..

        • -:. *** **** *'Y<>-\\; *** : ...... ,_,-;..-...... ~---**~
  • .
    • '~*,

--*~-: ....

o,.:. .***. *_*_ ** '.-~---~*:_.;.*.:...:-~->-*";....__.,~:,:*: .* :,.* ........ *.--**** ***--... --~__,__;_._"_,.__,

PUBLIC SERVICE ELECTRIC AND GAS

TECHNICAL ASSESSMENT

ISS.UE 3

ELECTRIC JUNCTION BOX SEALS

I.

STATEMENT OF CONDITION

As described in LER 86-007, PSE&G identified seven (7)

junction boxes in Unit 1 and nine (9) in Unit 2 that

were not sealed out of a total of 138 EQ junction boxes,

in accordance with the instructions provided in original

installation and design change packages (DCP's).

Systems and *components affected by this deficiency

include the Main Steam System; Main Steam Isolation

Valve (MSIV) indication limit switches for Units 1 and

2; Containment Pressure Vacuum Relief (CPVR) Isolation

System solenoid valves for Units 1 and 2; and Liquid

Radwaste Management (LRM) System Containment isolation

valve limit switches for Unit 2.

I I.

ROOT CAUSE

The root cause of the above deficiencies is (1)

confusion generic installation requirements which led to

misiriterpretation, and (2) an oversight by the

responsible EQ sponsor in not including all EQ

identified junction boxes in the updated (most current

issue in 1985) EQML.

The four junction boxes which were

not included on the EQML were on the original master

1 is t~.

III. CORRECTIVE ACTIONS TAKEN

The junction boxes were either proper iy sealed or

evaluated and found acceptable prior to restart

following the Salem Unit 1 March, 1986 refueling outage

and a volunta~y shutdown of Salem Unit 2 in May, 1986.

PSE&G had taken corrective actions prior to the

discovery of the deficiencies that would likely have

precluded its occurrence in that procedures had 'been

modified io reqtiire that a field walkdown by the project

team members be performed.prior to DCP closeout

(Engineering Procedure GM8-EMP-009, Revision 0,

December, 1985).

The procedure also ensures that all DCPs receive a

review by the EQ section to ensure EQ compliance.

Therefore, any EQ-related drawings which are contained

Al88/3

...... -. .:. *~-* : .. ,* ..

      • !
  • ** *

'*.

.

-

  • *
    • -~* * , ....

Issue 3 (Cont.)

2

within the DCP are required to be reviewed by the

responsible EQ engineer to ensure that all EQ junction

boxes are designated as such to avoid misinter-

pretation.

A field directive was also issued (FD No.

s-C-A910-NFD-0.405) on August 1, 1986 concerning EQ

requiremerits for junction box iristallation and

maintenance.

IV.

SAFETY SIGNIFICANCE

1.

The deficiencies were not safety significant in that

affected components (a).were qualifiable *in their

individual configuration, (b) provided valve

position indication, for which alternate position

verification was available, (c) would fail such that

associated valves would go to a fail-safe position,

and (d) components would operate prior to failure of

the junction box/terminal block.

Al88/3

Specifically, for each item listed above:

(a) QualifiabLlity of the existing configuration is

addressed in Appendix A.

(b) Limit switches for 12MS167 and 14MS167 for Unit

1 and, 22MS167 and

24MS167 for Unit 2, in the

Main Steam System MSIVs only provide indication

for verification of containment isolation.

Alternate indication, (which is required by EOPs

to be checked when MSIV position indication is

lost) is available from steam flow

instrumentation.

The CPVR Isolation Valves (lVCS and 2VC5) are in

series with a second normally closed valve (1VC6

  • and 2VC6) which also receives a containment

isolation Phase A signal to provide redundant

isolat..i.on.

The ~RM system containment isolation valve

limit switches, 2WL13, 2WL17, 2WL97, 2WL99 and

2WL108 only provide position indication and a

seal-in function from the open limit switch to

maintain the valves open.

These valves are

closed upon initiation of the accident and are

verified early in the EOP.

........ :*-* .... ~*:-: .... *. -

..

-*-

  • .*
    • *** * *
            • ,,._.._ .. * * ** -*, *
  • .:. : .*,. ,:. ,;~ ....... :. ' ****' .C.* .' *
  • -~** **. *,

- .:.** .;_ ** *._ *. ;

-

Issue 3 (Cont. )

3

(c) The*CPVR Isolation Valves (lVCS and 2VC5), are

normally closed, fail closed valves and would

not be opened during an accident.

In addition,

should associated solenoid valves SV928 and

SV1025 fail, lVCS and 2VC5 will fail-closed.

The LRM system containment isolation valves are

all fail closed valves.

Failure of the

associated limit switch will only result in a

spurious indication signal on the control room

panel.

All valves will be closed at the

~

initiation of the accident and are verified

early in the EOP, before the loss of position

indication would occur.

V.

STATUS

Al88/3

Full compliance regarding junction box seal

deficiencies was achieved on April 30, 1986 (Unit 1)

and May 3, 1986 (Unit 2).

Corrective actions regarding the DCP process have

been previously noted as being completed by

December, 198 5.

.

......, .. ~~ :. :-.. : .. -*. : ..*

UNSEALED JUNCTION BOXES

APPENDIX A

BASES FOR QUALIFIABILITY

The basis for sealing the conduit entrances to junction boxes

is to prevent the possibility of a

~tream of water from

flowing through tne rigid conduit into the top of the box

resulting in the terminal block being flooded and shorting

out.

Plant walkdown inspections demonstrate that the installed

configuration eliminates the possibility of the junction box

being flooded.

This is accomplished through (1) sealed rigid

conduit, (2) horizontal or bottom conduit entrances where

sealing is not required, (3) physical barries protecting open

conduit and (4) the actual location of the open conduit not

being closed enough to a HELB/MELC area where the steam/spray

mixture could enter the conduit opening.

The junction boxes installed in Salem Units 1 and 2 are

designed and tested in, accordance with PSE&G specifications.

Junction box cover plates are installed on all junction boxes

to protect the. terminal blocks from direct spray

impingement.

However, there are no cover gaskets provided.

Therefore, if high pressure spray or moisture enters into the

box through the gaps created by the'metal-to-metal interface

between the junction box cover plate and junction box edges,

or through condensation it will drip out through these same

gaps.

The test report used to establish qualifiability tested a

junction box/terminal block configuration similar to the

configuration installed in Salem.

Additionally, the plant

installed configuration is considered to be superior in

design due to the utilization of Raychem splices or Conax

connectors installed at the specific component which provides

a water-tight seal.

The junction boxes are located in the Mechanical Penetration

Area and the Outboard Penetration Area where they could be

exposed to a HELB or MELC.

The pressure and spray conditions

during the HELB tests were more severe in magnitude and

duration than the expected plant conditions.

Temperature, in

this case, is not an environmental parameter of any concern

with respect.to leakage current associated with the terminal

block circuit.

Al88/3

.** .~ .. :; , ..

"

-****'* *. , *. *********'*'"***-** **

.r~* *--*-* ** _...,._.r ... *:.*- -****-**** * ., * .._.~ ... ***-----**--*~--* *****--**.--*****,.**-* * **-*****- -**-******

Appendix A (Cont.)

2

Leakage current was monitored during the HELB tests as a

basis for acceptance criteria.

The worst case leakage

current recorded is not sufficient enough to energize any of

the affected components.

A more detailed engineering analysis has been performed by

engineering and is on file at PSE&G.

Al88/3

... J' . *.-* __ -. ...:. *. ~,:_,_ - - .:.:_., _ _.. -~ . , - . ~

. -...

. .. *, ... -.

. - --- *- . . . . . *. ~.-: :. . .".*.-= -*-- ... , __ :~ .... :. :... ,* *. ::._. .:.~ __ : -.-:_.;.,...:..:...: .. _._,_ . __ ... ; ___ _, -~*"-'"'-**~*---* .* ~--- ........ -...... __ ..

-:.~:..',_, ... ~- , .*.. -... -. - .. --* . -.. -

PUBLIC SERVICE ELECTRIC AND GAS

TECHNICAL ASSESSMENT

ISSUE 4

FAILURE TO REMOVE LIMITORQUE MOTOR BRAKES

I.

STATEMENT OF CONDITION

As described in LER 86-007, PSE&G identified four (4)

Limitorque motor-operated valves (MOVs)

outsid~ of Unit

1 containment in which brake assemblies had been

electrically disconnected but had not been physically

removed from the valve operators.

A subsequent

inspection of Unit 2 discov~red three (3) Limitorque

actuators outside containment also contained brake

assemblies that were electronically disconnected but not

physically removed.

The affected Limitorque operators

were found in the component cooling water outlet of the

residual heat removal heat exchanger, the Unit 1 safety

injection pump suction, and the Unit 2 residual heat

removal pump.

I I.

ROOT CAUSE

The ~oot cause of the motor brakes, not being removed

was an apparent misunderstanding of what.constituted

complete removal of the motor brake assembly.

Also, the

EQ sponsor engineer had been given verbal information

from Limitorque which indicated that physical removal of

the brakes was not necessary.

A Limitorque motor brake removal drawing was

unavailable, and instructions by the EQ sponsor engineer

in response to a Field Questionnaire ~nly stated the

brake is to be removed in a manner that the minimum

. number of parts are removed and the associated wiring is

disconnected so the brake is render~d inoperable.

The

Field Questionnaire answer did not correctly clarify the

issue.

III. CORRECTIVE ACTIONS

PSE&G took prompt corrective actions to address fully

the deficiency as well as the root cause.

PSE&G promptly conducted a total walkdown of all

safety-related electrical equipment .and confirmed that

there were no additional examples of the deficiency.

Al88/4

.. ~_. ...... *.; ..

Issue 4 (Cont.)

2

The brakes were removed from Salem Unit 1 prior to

restart from the March, 1986 refueling outage, and from

Unit 2 during the voluntary shutdown during May, 1986.

Corrective actions are ongoing.

Salem Station personnel

are instructed during EQ training that procedural

adherence is a must.

PSE&G further established a new procedure

(S-C-A910-MFD-0342, dated December 2, 1985) to provide

added assurance that future DCPs include sufficient

instructions with respect to motor brakes and other EQ

requirements.

In addition, PSE&G had previously

implemented a new engineering procedure, GM8-EMP-009

dated December, 1985, to close-out DCPs with a field

walkdown performed by the project team members.

These

actions provide assurance that PSE&G was in full

compliance prior to restart and that this type of

condition should not recur.

IV.

SAFETY SIGNIFICANCE

i.

There was no safety significance regarding the

presence of the motor brakes in that:

A188/4

(a) The motor operators had been qualified by

Limitorque test report F-C2485-l, which was the

original basis for Limitorque operator

qualification outside containment (See Appendix

A for qualifiability bases).

(b) The maximum exposure of the brake assemb1y and

brake coil to the outside containment radiation

environment is 106R, which would not degrade the

brake or coil component material to a degree

that would cause binding of the motor.

This is

supported by WCAP-7410-L.

{c) Post maintenance in-service valve stroke test

times confirmed that the presence of

de-energized brakes did not prevent the

actuators from performing their intended safety

function.

This is supported by 4.0.5-V tests.

. * *

' :., ** * .* "*.' : '

_.. * .._ *.*. *. ::l',.'. : *_..._ ...... _.,_,; .,;,.._ *** ** "... .* .--1 '~*** I .:.":,. *. J_,; ** * ** *, 'i...< *- .:_

'~ ..._ .* _.._-.._ ,.:; * .. , *I~---**'* .I._,_.._, ~ - ~ ** * *

~'. ,_ * '- ** *~ .". *'

Issue 4 (Cont.)

3

(d) All affected valves would be positioned in their

required recirculation lineup before they would

be exposed to any significant radiation doses.

VI.

STATUS

The Limitorque actuator motor brakes were removed and

the work W3S completed by April 30, 1986 for Unit 1, and

M~y 3, 1986 for Unit 2.

Al88/4

..

FAILURE TO REMOVE

LIMITORQUE MOTOR BRAKES

APPENDIX A

BASES FOR QUALIFIABILITY

The use of motor brakes is a qualifiable configuration.

The

original basis for ~ualificrition cf Limitorque operators with

class B motors outside contaJnment at Salem Station (File

EQ-29), used Limitorque test report F-C2485-0l to qualify the

operator with brakes installed.

This report is titled,

  • "Tests of a Limi torque Valve Operator and Motor-Brake

Assembly, Both With Class B Insulation

Under Simulated

Reactor Containment Post-Accident Steam and Chemical

Environments."

Other reports were used to support specific

para~eters, of which 600198, F-C2232-01 and WCAP-7410-L were

referenced~ These reports are currently maintained in the

Salem EQ backup files.

In conjunction with upgrading Limitorque actuators outside

and inside of containment at Salem Station to DCP's 1788 arid

1789 (in 1984 and 1985), the EQ files were also upgraded to

more recent qualification test reports (B0058 and 600461).

These new reports did not support motor brake assembly

qualification.

However, the original class B motors

qualified to report F-C2485-01 outside containment were not

replaced.

Since the brake~ were originally qualified by testing, the

disconnection of the brakes at Salem could be deemed a

conservative step, which need not have been made if the

original reports had been used, and a ~aterial composition

~nalysis had been performed.

The existence of the brake~,

whether connected or disconnected, did not substantially

differ from the mechanical configuration that was qualified

in the original Limitorque test reports.

The primary

difference .is that de-energized brakes may create surface

drag between the discs, whereas energized brakes maintain a

preset gap between the stationary and rotating frictiori

discs.

Since the disconnected brakes are no longer

functional, qualification is no longer appropriate, but motor

operability is necessary.

Qualification tests, along with

radiation analysis of brake disc materials, show that class B

or RH brake materials do not change after being exposed-up to

2 x 108 rads gamma radiation.

Also, since the valves were

stroked within their specified time period following brake

disablement in a normal in-service stroke test and

Al88/4

.::. .... - : ... ; ...... :. ..: ~-

- _,, -*~",. -. . .. ~** -.-* *- *. - * - -: .. -:... '* .. ** --.:* **. ~ .,.,; .: *'.~.*- *.* , .* :. :, *. ,_,::., .. *:_, *,.:-... ~._ .... : ... :.:.-..;.;;.:..o:..*:~:~ ....... .:..:..""'*:-..:. .... .: .* - *-* _. ** - -

Appendix A (Cont.)

2

periodically thereafter, it is a reasonable conclusion that

they would stroke under the accident condition of 1 x 106

rads of gamma radiation.

Post-maintenance inservice stroke-time tests SP(0)4.0.5-V-CC

3nd SP(O) 4.0.5-V-SJ, confirmed th~t t~e pre~ence of

de-energized motor brakes did not adversely affect valve or

a.:tuator operability.

Since the presence of dG**snergized

motor brakes did not adversely affect MOV operability, as

confirmed by the post-maintenance stroke-time tests, there

was no safety significance regarding the presence of the

de-energized brakes.

LER 86-007 discusses the possi~ility that the brakes could

bind the valve as a result of radiation exposure.

Subsequent

evaluation of this claim concludes that radiation induc~d

binding of the valve stem, as a result of brake exposure to 1

x 106. rads gamma radiatl.on; is highly unlikely.

The capability of the motor brake assembly and brake coil to

withstand radiation was supported by WCAP-7410-L, "Topical

Report Environmental Testing of Engineered Safety Features

.Related Equipment," December 1970.

The purpose of this

program was to determine the effects of steam, pressure,

temperature and radiation on valve operators with both class

H and class B insulation on .the motor and motor-brake

assembly.

Page 5-4 documents that class B insulation was

irradiated to.a level of 2 x 108 rads with no apparent

degradation of the insulation.

Although failure of. the coil

portion of the assembly did occur during the testing, this

.was attributed to steam and chemistry solution entering into

the assembly through the cutouts for the leads, causing coil

failure.

Since the motor brakes in our analyses were

electrically disconnected from the coil, and the brake disc

assemblies are only subjected to a radiation harsh

environment of 1 x 106 rads, this failure mechanis~ will n~t

be present.

It is therefore concluded that there was no safety

significance regarding the presence of the electrically

disconnected motor brake assemblies.

PSE&G had test reports

to support the qualification of the brakes for their location

specific environment.

Thus, Salem Station Limitorque

actuators outside containment are qualifiable in their

installed configuration by the original basis supplied in

Report F-C2485-01.

A more detailed analysis has been

performed by Engineering and is on file at PSE&G.

Al88/4

PUBLIC SERVICE ELECTRIC AND GAS

TECHNICAL ASSESSMENT

ISSUE 5

AUXILIARY FEE.rMATER FLOW TRANSMITTER CONNECTORS

. I.

STATEMENT OF CONDITION

As described in LER 86-007, PSE&G identified during a

self-initiated walkdown four (4) Auxiliary Feedwater

Flow Transmitters in both Units 1 and 2 that were

terminated in junction boxes with terminal blocks.

PSE&G determined that these connections should have been

made with qualified splices.

I I.

ROOT CAUSE

During an effort by PSE&G to upgrade saf~ty-related

transmitters and associated equipment, the AFW flow

transmitter square root extractors were relocated.

The

AFW transmitters were also replaced by design change

packages.

These design change packages were later.

modified to include terminal blocks inside a junction*

box to facilitate the relocation of the square root

extractors.

In review of terminal block use for

response to_ IE Information Notice 84-47, these

connections were not discovered.

The revised

configuration was identical for each of the circuits and

represents an isolated oversight in the review process.

III. CORRECTIVE ACTIONS TAKEN

PSE&G promptly corrected this condition, prior to

restart from the Unit 1 March, 1986 refueling outage

and ~ntered an unscheduled outage for Unit 2 in May 1986

to assure a complete review and to implement corrective

actions.

PSE&G had taken corrective actions prior to the

. discovery of the deficiencies that would likely have

precluded its occurrence in that procedures had been

modified to require that a field walkdown by the project

. team members be perf_ormed prior to DCP closeout

(Engineering Procedure GM8-EMP-009, Revision O,

December, *1985).

The procedure also ensures that all DCPs receive a

review by the EQ section to ensure EQ compliance.

Al88/5

i":.:: ... :-..

-.;'..:*~**~J-*_, ... --~~: *. :. - *.:

'*

  • ~ .. : .

..

Is s u e 5 ( Cont * )

2

Therefore, any EQ-related drawings which are contained

within the DCP are required to be reviewed by the EQ

section.

IV.

SAFETY SIGNIFICANCE

The condition was not safety significant.

Configuration is qualif iable as discussed in

Appendix A.

These transmitters are not essential to the

mitigation of an accident.

The EOP in place at the time (EOP-TRIP-1) directed

the operator to verify total AFW flow to be greater

than 44,000 lbs/hr as the second step of the

immediate actions, immediately after the

verification of turbine trip.

This flow

verification will occur in less than two minutes

following the initiation of the accident.

Because

the connections were inside a closed EQ junction

box, the adverse conditions which could have

affected the AFW flow indications in the penetration

area (2/4 loops) would not have developed before the

flow verification was completed.

Subsequent usage

of the AFW flow indication is as a reference

indication for maintaining the established flow

until steam generator level is within the narrow

range.

The AFW flowrate is then governed by steam

generator level, and not the indicated flow.

Since

the AFW flow indication has no control function, the

flow would remain at an adequate level regardless of

whether the flow indication failed and steam

generator level would still be attained.

V.

STATUS

Al88/5

Full compliance with respect to these connections

was achieved by May 5 (Unit 1) and May 6 {Unit 2),

1986.

AUXILIARY FEEDWATER FLOW TRANSMITTER CONNECTORS

APPENDIX A

BASES FOR QUALIF!ABILITY

The following synopsis highlights the evaluation of .the

terminal blocks installed in AFW flow transmitter circuits:

The primary concern for inadequacy of terminal blocks in

instrument circuits, as delineated in NUREG/CR-3691, is the

formation of surface moisture film which can induce

unacceptable leakage currents during steam line break

conditions.

Although much testing has indicated that

terminal blocks are not normally acceptable for use in

transmitter cir~uits, consideration must be given to the

following factors:

(1)

Applicability of test reports

(2)

A~equacy of performance mea~ures

(3)

Performance requirements *

(4)

Safety function

Because the majority 6f industry testing did not monitor low

level leakage. currents, only one test report is used in this

evaluation.

This test report contained the same manufacturer

and type terminal block, the same installation configuration,

was monitored for functionability to the same transmitter

type~ was exposed to steam line break conditions and

monitored leakage currents in the micro-amp range.

The

results of this test showed that the tested terminal block in

tested configuration showed no leakage current above 50

micro-amps and permitted the.proper functioning of the

attached Rosemount transmitter.

This test provides

documentation of acceptability of the.terminal blocks

installed inside EQ junction boxes in the AFW flow

transmitter circuits.

As -an additional measure of assurance of the acceptability of

the subject terminal block/junction box configuration,

evaluation of the actual safety function of the flow

transmitters was reviewed.

The functional use of the flow

transmitters for steam line break accident resolution is as

an indication of AFW flow for steam generator level

recovery.

This reading from the flow indicators will occur

in one to two minutes from accident initiation as it is the

second step in emergency operating procedures.

The following

Al88/5

-~--~-~~--------.. -... - ..

~;:-::-=-=-----~~-

.*~-. .

.:~ .** ~ ... ;-,.*-~-*-*- .:_ ...... ,_,. __ ,.... .. __ 1_ .. ~.*.;z;-;--_..,._._,,.-:--.._-;-___ *.~-*-

--~ ~, ....... c

Appendix A (Cont.)

2

points summarize the evaluation of acceptability in regard to

the safety function and safety impact of the flow transmitter

signals:

( 1)

Significant ~igna.l ert*or induced by steam ~nter ing the

closed junction box and moisture film forming across the

block would be unlikely to affect the indication before

the control room had verified flow.

(2)

If an error were induced at initial flow verification,

subsequent operator action would, by procedure, preclude

any safety impact due to the error.

(3)

At most only two transmitters can be affected by any one

accident which leaves two steam generators unaffected.

Only two steam generators are required for safe

mitigation of the accident.

Al88/5

  • .

"

PUBLIC SERVICE ELECTRIC AND GAS

ASSESSMENT OF THE MODIFIED EQ ENFORCEMENT POLICY

(GE-NERIC LETTER 88-07) AND ITS APPLICATION TO

THE DEFICIENCIES IDENTIFIED IN LER 86-007

BACKGROUND

On April 7, 1988, NRC issued Generic Letter 88-07, the most

recent in a series of Generic Letters (including GL *85-15 and

GL 86-lS) intended to establish a separate enforcement policy

for the environmental qualification of safety-related

electrical equipment.

PSE&G recognizes NRC's desire to

.convey to the industry the need for concerted action to

comply with the requirements of 10CFR50.49.

PSE&G has

interpreted this guidance as a pronounced effort by the NRC

to ensure that a utility is not in gross violation of and/or

negligent with regard to the requirements of 10CFR50.49.

The

following assessment of the application of the Modified EQ

Enforcement Policy (Generic Letter 88-07) as it relates to

the EQ deficiencies in LER 86-007 will show that PSE&G was

not ~egligent with regard to 10CFR50.49, and that the

deficiencies represented isolated failures to properly

implement established Salem EQ program guidelines.

PSE&G recognizes that the LER 86-007 deficiencies existed

prior to the November 30, 1985 mandatory EQ deadline.

However, the following discussions of each deficienc~ provide

information to support PSE&G's contention that enforcement

action under Generic Letter 88-07 is not appropriate.

al88/asm

J~ ** :

~ * ~ '*

  • ,

. -~--

. ,~~*. c --...:.* ,_._ *** *-* -~- __ .,_ ** ,._ ** _; ** *
  • - -

.. _. ,._r-.,_ --* '-.4-~'4***"">.ol'~d-- - ... -:c:::-.............. __ -~ ..* _ ......... _ .... '-.*--.!... --

---'* ..... .

ISSUE 1

LIMITORQUE T-DRAINS

PSE&G believes that the as-installed configuration (i.e. the

Limitorque operator motor bell housings without the T-drains)

does not warrant escalated enforcement action.

The motor operators were qualifiable in the as-installed

configuration.

PSE&G believes that the "qualifiability"

argument should be admitted in this case as well as other

issues noted in LER 86-007 since PSE&G was not given the

opportunity to db so during the NRC EQ inspection of Salem on

August 11-15, 1986.

The NRC inspection team stated at that

time that the deficiencies identified in LER 86-007 would be

considered under the then existing EQ Enforcement Policy (GL 86-15) but that they would not be looked at during the

inspection.

PSE&G had no need at that time to perform a

qualif iability determination because T-drains had

conservatively been installed on all the inside containment

Limitorque operators prior to startup fro~ the Salem 1

refueling outage which commenced in March, 1986, and the

subsequent voluntary shutdown of Salem 2 in May, 1986.

Had

this concern been formally raised during the inspection, a

qualif iability .evaluation could have been generated at that

time by PSE&G.

A summary of the qualifiability determination

is presented in Appendix A to the technical discussion of the

Limitorque T-drain issue.

This deficiency should not be classified as a "clearly should

have known" condition under the Modified EQ Enforcement

Policy because:

Prior to November 30, 1985, PSE&G's EQ personnel were

aware that T-drains were required as evidenced by sev.eral

PSE&G memoranda referencing the installation requirement.

DCPs lEC-1788 and 2EC-1789 were issued in 1984 and 1985

to upgrade existing operators.

Included in the DCPs for

installation purposes were excerpts from Section 6 of

Limitorque Test Report B0058 which noted that

in-containment actuators use T-drains to accommodate the

extreme temperatures and pressures of Design Basis Event

environments.

The vendor instructions attached to the new actuator

motors included direction regarding installation of the

T-drains.

,

al88/asm

...

  • "'

. _,. '_':. *- .. --**~--~*-**" - . -. . .. -;" . *~ .. :.* *,. "*

Issue 1 (Cont.)

2

Reasonable post-installation verification measures had

been taken in the form of QA field verification walkdowns

on a ~ampling basis.

Although more detail concerning T-drain installation

could have been included in the DCP, PSE&G believes this

deficiency should be categorized as an isolated oversight

and not a "clearly should have known" case.

Based on the qualifibility of the configuration and the

"clearly should have known" evaluation, this deficiency

should be evaluated against the General Enforcement Policy

and classified as a Severity Level V.

The Modified Policy is

not applicable.

al88/asm

  • '

"

ISSUE 2

CONAX.CONNECTORS FOR PASS SOLENOID OPERATED VALVES

PSE&G believes that this self-identified deficiency does not

_ warrant escalated enforcement action and should be classified

as no more than a Severity Level V violation.

PSE&G has performed an evaluation which demonstrates that

these solenoid operated valves were qualif iable in their

as-installed configuration.

A summary of the qualifiability

evaluation is presented in Appendix A to the technical

discussion of this issue.

PSE&G does not believe that enforcement action should be

taken under the Modified EQ Enforcement Policy for the

followin~ reasons:

1.

The PSE&G EQ program clearly directed that Conax

connectors be installed on the solenoid valves in both

Salem Units prior to November 30, 1985.

The PASS DCPs ( 1EC-0540A and 2EC-0541A) for the ASCO

solenoid val~es for both units contained the same

reqtiiremeni.

(The connectors were only missing from

the Unit 1 PASS System, Panel 801....:lA).

A large amount of evidence exists which demonstrates

that Conax connectors have been installed in EQ

applications as required.

Nearly 750 Conax connectors

had been properly installed within both Salem Units in

accordance with similar directions.

The deficiencies were at most isolated* occurrences of

non-adherence to applicable program requirements~

2.

This condition ~hould not be classified as a "clearly

should have known" condition under the Modified EQ

Enforcement Policy.

PSE&G identified .the need to install qualified

connectors.

The DCPs (1EC-0540A and 2EC-0541A) for the PASS valves

specifically called for Conax connectors for both

Units 1 and 2.

The total number of appropriately installed Conax

connectors in EQ applications is indicative of

effective equipment installation and verification

programs.

Based on qualifibility and the "clearly should have known"

evaluation, the General Enforcement Policy should apply.

. . - .... , , ........... .

.

~ . ,,.

. -* : ... _

..~ .*.-.
. _.

\\ .. : **-** .*:.. .. -.:::.-~:~ .. -*-' .......... ;

  • -~****'*'*..:,.~ :,.: **-**

ISSUE 3

ELECTRIC JUNCTION BOX SEALS

PSE&G believes that this self-identified deficiency has no

safety significance, does not warrant escalated enforcement

action and should not be classified as more than a Severity

Level V violation.

The junction boxes have been determined by PSE&G to be

qualif iable in their as-installed configuration.

A summary

of the qualifiability evaluation is presenteq in Appendix A

to the technical discussion of this issue.

PSE&G does not believe that enforcement action should be

taken under the Modified EQ Enforcement Policy for the

following reasons:

1.

Design change documentation incorporated EQ requirements

by providing a drawing with instructions.

These Generic

installation instructions for the proper sealing of EQ

junction boxes were confusing and led to misinter-

pretation in some cases.

The EQ engineer failed to properly transfer a limited

number of junction boxes from the original EQ list to an

updated EQ Master List.

2.

PSE&G should not have clearly known the above

deficiencies existed because:

The engineering oversight and the confusion over the

installation instructions were isolated events not

indicative of a breakdown in the EQ requirements for

junction boxes.

Verification was based on a sample and could not

reasonably have been expected to identify every

possible error.

Based on qualifibility and the "clearly should have known"

evaluation, the General Enforcement Policy should apply.

al88/asm

. ........ _ ... ;:*-*.-*

~*--*

... *, . - ...

. *

..

ISSUE 4

LIMITORQUE MOTOR BRAKES

PSE&G believes that escalated enforcement action is not

warranted for this self-identified condition and should be

classified no more than a Severity Level V violation.

~he Limitorque motor operetors with tha motor bra~e~

installed are qualifiable.

A summary of the qualifiability

eval~ation is prdsented in Appendix A to the technical

discussion of this issue.

Enforcement action under the Modified EQ Enforcement Policy

is not warranted because the deficiency does not represent a

"clearly should have known" condition.

Only a limited number

of the Limitorque motor operators were installed without the

motor brakes physically removed.

In the vast majority of

cases, the DCP instructions were understood.

In some cases,

however, the DCP instructions were not fully understood, and

a field questionnaire was written to seek clarification as to

whether the brakes were to be physically removed or

disconnected.

For purposes of responding to the field

questionnaire, the EQ sponsor engineer states that he was

given information verbally by Limitorque that physical.

-removal of the motor brakes was not necessary.

This

vendor-supplied information provided a basis to cionclude that

the configuration was adequate.

_,

Based on qualifiability and the "clearly should have known"

evaluation, the General Enforcement Policy should apply.

al88/asrn

., . * .

ISSUE 5

AUXILIARY FEE~ATER FLOW TRANSMITTER TERMINATIONS

PSE&G believes that the self-identified deficiency does not

warrant escalated enforcement and should be classified as no

more than a Severity Level V violation.

A qualif iable configuration existed in the terminal block~

located inside a qualified junction box.

A summary of the

qualif iability evaluation is provided in Appendix A *to the

technical discussion of this issue.

PSE&G does not believe that enforcement action should be

taken under Generic Letter 88-07.

The deficiency should not

be cl~s~ified as a "clearly should have known" condition

because:

In responding to Information Notice 84-47, PSE&G

evaluated these configurations for qualification and

determined that no additional action was required

because, among other components, transmitters were to

be installed with qualified Raychem splices.

In fact,

at Salem Station, over 200 transmitters had been

replaced in 1982 and 1983 and Raychem splices were

used in accordance with Engineering directions for all

transmitter terminations.

All terminal blocks were

replaced with Raychem splices for transmitter

terminations in this effort.

Although the IN 84-47

was fully addressed the verification effort failed to

identify the auxiliary feedwater terminations.

This

was an isolated over~ight and not a

"cl~arly should

have known" case.

Based on qualifibility and the "clearly should have known"

evaluation; the General Enforcement Policy should apply.

al88/asm

' ... *.",...*;_';_,*: ..

.,,

..

PSE&G ASSESSMENT OF THE GENERIC LETTER 88~07

MITIGATION/ESCAIATION FACTORS

While PSE&G does not believe that escalated enforcement

action is warranted for any of the EQ deficiencies identi~ied

in LER 86-007, the civil penalty mitigation/escalation

factors noted in Generic Letter 88-07 have been evaluated as

requested in the NRC Region I letter of August 19, 1988,

which scheduled this enforcement conference.

If a civil

penalty is proposed for any or all of the self-identified

defici~ncies, full mitigation is warranted for the following

reasons:

  • PSE&G identified the conditions during self-initiated

walkdowns in March, 1986 (Unit 1 and May 1986 (Unit 2).

The conditions were timely reported to the staff in LER 86-007.

In each case, PSE&G promptly corrected the Salem

conditions by physical modification prior to restart.

PSE&G voluntaiily e~tended the Salem Unit 1 1985 outage

and entered an unscheduled shutdown of Unit 2 to

implement corrective actions in May, 1986.

PSE&G took prompt corrective measures to address the root

causes. through procedural and administrative changes.

These actions assured PSE&G was in full compliance prior

to restart and provided assurance that these conditions

should not occur~

The deficiencies re~resented isolated failures to

appropriately implement established Salem EQW program

guidelines.

A limited number of system and components were affected.

PSE&G employed its best efforts to compete implementation

of an EQ program prior to the November 30, 1985 deadline.

The five criteria, at the bottom of page 4, of the Generic

Letter denotes those factors which must be met in order for

full mitigation of any proposed civil penalty to be

considered.

PSE&G believes that consideration of its action

to discover, report and resolve the deficiencies of LER 86-007 along with the significance and overall etfect of

these deficiencies leads to the conclusion that full

mitigation is warranted.

al88/asm

PSE&G ASSESSMENT OF THE POTENTIAL FOR ENFORCEMENT

ACTION UNDER THE GENERAL ENFORCEMENT POLICY

  • ( 1 OCFR PART 2, . APPENDIX C)

NRC Generic Letter 88-07 presents two (2) conditions where

enforcement action related to EQ deficiencies which occurred

prior to the November 30, 1985 deadline is to be assessed

under the General Enforcement Policy (lOCFR Part 2, Appendix

C).

These are (1) when the equipment in questions

determined to be aqualifiable," as-installed, rendering the

deficiency not sufficiently significant for assessment of

civil penalties under the Modified EQ Enforcement Policy and

  • (2) when noted EQ deficiencies are not singularly significant

but, in the aggregate, are indicative of a programmatic

problem.

In the case of the EQ deficiencies noted in LER 86-007 the

following statements are relevant:

1.

The EQ deficiencies identified in LER 86-007 represent

configurations which were qualifiable in the as-installed

condition.

2.

The EQ deficiencies were identified by PSE&G during the

Salem Unit 1 1986 refueling outage and the voluntary

shutdown of Salem Unit 2 in May, 1986.

1.

The deficiencies were reported to the NRC in a timely

fashion -via the LER.

4.

After review of lOCFR Part 2, Appendix C,Section IX,

Supplement I, PSE&G believes that none of the

deficiencies individually should be categorized as more

than a Severity Level V violation.

5.

Appropriate corrective actions were taken promptly to

resolve the deficiencies and adminstrative changes were

made to preclude recurrence.

6.

There had been no previous inspection findings similar to

those deficiencies self-identified by PSE&G in LER 86-007.

Therefore, the deficiencies could not have been

prevented by corrective actions resulting from a previous

enforcement action~

al88/asm

..... - *****.': .*..... *. *-~*-. ******* .. - .......... , .... :.:.-. -~-~--'-*-* .. *.:.(* ..... ~-.-*.;..,.*-::1_. ........ ~ ....... -.. ..; ......... .

Assessment (Cont.)

2

7~

The EQ deficiencies noted in LER 86-007 are not safety

significant as noted in previous discussions.

For *these reasons, PSE&G believes that NRC should consider

exercising discretion under lOCFR Part 2, Appendix C, Section

V.G. and not issue a violation for any deficiency assessed

under the General Enforcement Policy.

alBB/asm

,...____,.___,.___,.~~~~~~~~___,.~___,.___,.___,.___,.___,.___,.___,.___,.___,.___,.___,.___,.___,.___,.___,...~~~~~~~~~~~~~~~~~.

. . . . .. :._~ ~--*: .-. ,* .. :. ..;, _:. "* ... <. : ~ .... :*: ... *.: ... :* ... :.:.: ';:.;...._.:;_.&:_.~ *** *. * . * ..... *-*** ~ *.* -

-*~.J-:.* _:: *. -...... - * -****** d."* ;. ~ ..........

    • _;

.,. -

," -

- ;

~-

  • ""

SALEM GENERATING STATION UNIT 1&2

PROGRAM STATUS

The following identifies actiotis taken by PSE&G after the

November 30, 1985 deadline to maintain and control the Salem EQ

program in accordance with the requirements of 10CFR50.49.

On March 22, 1986 PSE&G initiated an EQ walkdown for Maintenance

baseline during the Salem Unit 1 ref.ueling outage.

Planning for

this walkdown was started by the EQ task force during the first

quarter of 1985.

The objective of the walkdown was two fold:

1)

Verify the serial number of each component to establish the

exact installation date for start of qualified life and

follow-up maintenance considerations.

2)

Determine specif~c equipment location information (elevation

and column line identification) for use by the Station

Maintenance personnel.

At the same time an as-installed photograph was taken and several

other checks were made for program control.

These included

mounting orientation, installation of moisture seals (where

applicable) and splice or terminal block verifications.

Ag a result of the findings of the Salem Unit 1 walkdown, Salem

Unit 2 was shut down on May 1, 1986 so that a similar walkdown

could be performed.

The deficiencies identified by PSE&G during

these walkdowns were documented and submitted to the NRC in LER

  1. 86-007, dated May 8, 1986.

These are the deficiencies which

have been identified as the primary subject of this enforcement

conference.

These items are discussed in much greater detail in

the issues package enclosed with this handout.

In response to NRC Information Notice 86-53, "Improper

Installation of Heat Sh~inkable Turbine," PSE&G evaluated the

installation of Raychem splices i~ Salem Units 1 and 2 and found

that the splices in Salem Unit 1 had not been installed in

accordance with Raychem instructions.

PSE&G performed an

engineering analysis and determined that the "as-found"

installation was acceptable and posed no operability concerns.

Qualification data was obtained from Wyle Laboratories to support

this conclusion.

This investigation was documented in LER

  1. 86-015, dated August 7, 1986.

Al88/ps

Program Status (Cont.)

2

On August 6, 1986, PSE&G shutdown both Salem Units to replace

questionable wiring on Limitorque motor operators.

Although

initial review in response to NRC Information Notice 86-03 of

vendor documentation and purchase order information related to

subsequent field installed wiring in Limitorque motor operators

did not indicate a problem with the qualification of the wiring,

inspections of selected motor operators revealed questionable

internal jumper wiring.

Both units were shutdown so that a 100%

walkdown could be performed and documentation of the field

installed wiring in each Limitorque motor operator could be

established.

The questionable wires were replaced with qualified

Rockbestos Firewall III SIS wire.

The results of these

inspections were documented in LER #86...,018, dated September 5,

1986.

On August 11-15, 1986, the NRC conducted an inspection 6f the

Salem EQ program.

PSE&G has adequately responded to all the

issues raised by the NRC Inspection Team.

It is PSE&G's

understanding that the issues raised during the above referenced

inspection are not subjected to escalated enforcement action

under Generic Letter 88-07.

I

During the August, 1986 inspection, the NRC recommended to PSE&G

that certain file improvements should be made to generally

improve and clarify the contents of the material and to correct

the minor documentation inconsistencies that were identified

during the review.

In October, 1987, the Engineering and Plant Betterment (E&PB)

department underwent a major reorganization.

As a result the

Program Analysis Group (PAG), which is part of the Nuclear

Engineering Sciences Section, was formed.

Experienced EQ

engineers from SAG were transferred to PAG as part of the

reorganization in order to ensure continuity of the program.

In

.recognition of the importance of this program additional staff

was also allocated to the maintenance of the program at this

time.

PAG assumed the responsibility for the Equipment Qualification

Programs for both Salem and Hope Creek Generating Stations.

A

centralized group has the advantage of consistency in program

implementation and development and establishing commonality

between Salem and Hope Creek with respect to the Environmental

Qualification of equipment.

The current major objectives of PAG in support of the Artificial

Island Environmental Qualification Programs are:

Al88/ps

,. --- * ..

  • ,

.. , ..... _. -*--** ~*'..-

_.~ * ... :.,:: __ :_*-,--*****-.:.-.*--:*-****' *. *--*-*;*******~ ~ .. 4*-*~-. , ___ , ......... :, *. ** ..... -*-*- ...... -

Program Status (Cont.)

3

1.

Restructure of Salem EQ files.

2.

Conversion of Hope Creek EQ files from a Purchase Order basis

to a Equipment type basis.

3.

Development of Programmatic Standards.

4.

Represent PSE&G in NUGEQ meetings and task forces.

The following is a short description of the above major

objectives:

1.

Restructure of Salem EQ Program

An extensive effort is nearing completion to implement a

comprehensive restructure of the Salem EQ file, in accordance

with E&PG procedure NO. DE-PS.ZZ-0002(Q)-A8.

This effort

included the review of all EQ related documents to assure

completeness of the EQ files, upgrade the System Component

Evaluation Worksheet (SCEW) and Equipment Qualification

Maintenance Instructions, organize the EQ binders in

accordance with a standard index contained in the procedure,

and review and approve each binder.

The primary emphasize

for this effort is to -establish a common file structure for

both Salem and Hope Creek.

2.

Conver~ion bf Hope Creek EQ Program

As committed to the NRC subsequent to the NRC EQ inspection

at Hope Creek, the Hope Creek EQ file binders will be

converted from a Purchase Order based file system to an

Equipment Type based file system.

This effort is scheduled

for implementation during 1989.

3.

Development of Programmatic Standards

An extensive effort is underway to develop Programmatic

Standards for the Environmental Qualification Program.

The

Programmatic Standard will serve as an Engineering Ma~ual for

consolidating the criteria, methods, and control of the

Environment~l Qualification Programs at PSE&G.

The issue of the Programmatic Standard is scheduled for

December 31, 1988.

Nuclear Department indoctrination on the ProgrammQtic

Al88/ps

':". *.

. ** ,,j,i>..

.... -- : ~ _, --*- _,_ :_ "- -... _: . -*

-*-

..;.. '. *----*...: _., -'* .. '

Program Status (Cont.)

4

Standard will be initiated following. formal issue in 1989.

4.

NUGEQ Participation

PSE&G is a member of the Nuclear Utility Group on Equipment

Qualification (NUGEQ) and participates in its meetings and

task forces on various issues.

Group participation provides

PSE&G with current information on EQ issues in the industry

and accessibility to a large data base of information and

documents to support our EQ program.

The information presented above is indicative of PSE&G's

commitment to continuous support of its Equipment Qualification

Program and assurance that the EQ program meets the requirement

of lOCFRS0.49.

PSE&G is confident that both the administrative and technical

aspects of the Salem EQ Program are well established and that

ongoing compliance with the requirements of lOCFRS0.49 will be

maintained.

The Salem EQ p~ogram is a dynamic one and will be enhanced, as

needed to reflect the latest information and tools available to

PSE&G.

Al88/ps