ML18057B455

From kanterella
Jump to navigation Jump to search
Insp Rept 50-255/91-24 on 911105-1216.Violations Noted. Major Areas Inspected:Operational Safety Verification, Reactor Trips,Maint,Outages & Quality Program Activities
ML18057B455
Person / Time
Site: Palisades Entergy icon.png
Issue date: 12/27/1991
From: Jorgensen B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18057B453 List:
References
50-255-91-24, NUDOCS 9201070029
Download: ML18057B455 (15)


See also: IR 05000255/1991024

Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION III

Report No. 50-255/91024(DRP)

Docket No. 50-255

Licensee: Consumers Power Company

212 West Michigan Avenue

Jackson, MI

49201

License No. DPR-20

Facility Name:

Palisades Nuclear Generating Plant

Inspection At:

Palisades Site, Covert, MI

-

Inspection Conducted:

November 5 *through December 16; 1991

Inspectors:

Heller

2A

Approved By:

DATE

1

ection Summar

pection from November 5 through December 16, 1991

(Report No. 50-

255/91024 (DRP))

  • Areas Inspected:

Routine unannounced safety inspection by resident .

inspectors of* actions on previously identified items, operational safety

verification, reactor trips, maintenance, outages, and quality program

activities.

No Safety Issues Management system {.SIMS) items were

reviewed.

Results: Of t~e six areas inspected, no violations or deviations ~ere

identified in five a~eas. *One violation wa~ identified (failure to

document bases that an unreviewed environmental question does not exist

Paragraph 7) in the remaining area.

Strengths, weaknesses and open items are discussed in paragraph 9;

"Management Interview." .In summary, strengths were identified in a

conservative operating philosophy, in open communications, in strong

technical documentation to support resolution of an engineering problem;

in control room leadership, in well planned maintenance activities, and in

outage preparations.

Weaknesses were noted in the lack of a complete

response to a Notice of Violation, in plant reliance on an offsite group

to determ.i,ne*Technical Specification .applicability, in component

identifiers not matching checklist description, in the lack of a screening

mechanism £or maintenance activities which could expand the cold-weather

protection envelope, and in poor coordination of the emergency down-power

event that occurred on December 9, 1991 .

9201070029 911227

PDR

ADOCK 05000255

Q

PDR

1.

DETAILS

Persons Contacted

Consumers Power Company

  • G.
  • R.
  • P.
  • K.

J.

R.

  • K.
  • J.
  • R.
  • L.

D.

c.

w.

R.

K.

  • T.

B.

M.

M.

M.

L.

B.

E.

L.

D.

D.

s.

L.

w.

A.

J.

Slade, Plant General Manager

Rice, Plant Operations Manager

Donnelly, Safety & Licensing Director

Haas, Radiological Services Manager

Hanson, Operations superintendent

Kasper, Maintenance Superintendent

Osborne, System Engineering Superintendent

Kuemin, Licensing Administrator

Orosz, Engineering and.Constrtiction Manager

Morse," Licensing Clerk *

Hice, Chemistry Superintendent

Kozup, Technical Engineer

Roberts, Senior Licensing Analyst

Smedley~ Staff Licensing Engineer

Toner, Electrical/I&C/Computer Engineering Manager

Palmisano, *Administrative & Planning Manager

Nuclear Regulatory Commission (NRC)

  • w. D. Shafer, Chief, Reactor Projects Branch 2

B. L. Jorgensen, Chief, Reactor Proj.ects Section 2A

  • J. K. Heller, Senior Resident Inspector
  • J. R. Roton, Resident Inspector

Denotes some of those present at the Management Interview on

December 18, 1991.

Other members of the plant staff and several members of the contract

security force were also contacted. during the inspection period.

  • 2.

Actions on Previously Identified Items (92701, 92702)

Pump.

The licensee response of December 9, 1991, did not provide the .

information requested by the Notice of Violation.

For example, the

letter did not admit or deny the violation, the cover letter did not

state "Reply to a Notice of Violation", it was not addressed to the

correct person, and the response pertaining to testing components

after installation of .a breaker and fuse was not consistent with the

information provided at the enforcement conference and to the

inspector during the inspection.

These discrepancies were verbally

2

provided to the licensee on December 12.

revised response dated December 1.4.

The licensee submitted a

No.violations, deviations, unresolved or open items were identified.

3.

Operational.Safety Verification (71707, *71710, 71714, 42700)

Routine facility operating activities were observed as* conducted in

the plant and from the main control room.

Plant startup, steady

power operation, plant shutdown, and system lineup and operation were

ob~erved as applicable.

The performance of reactor operators and senior reactor operators',

shift engineers, and auxiliary equipment operators was observed and

evaluated.

Included in the review were procedure use and adherence,

records and logs, communications, shift/duty turnover, the degree.of

professionalism of control room activities, ~nd performance during a:

plant transient.

a.

General

The* plant began the inspection period at essentially full power.

During the reporting period the unit was derated to

approximately 35 percent power from November 5 through 9, to

resolve condenser tube leakage. The unit was offline from

December 9 through 14, to resolve problems with the turbine-

generator seal oil system.

The plant ended the reporting period

at essentially full power.

b.

Turbine Driven Auxi'liary Feedwater Pump.Inoperable

On N_ovember 13, CV-0521, "Alternate Steam Supply to the Turbine

Driven Auxiliary Feedwater (TDAFW) Pump," failed to stroke open

during a surveillance test.

The valve and the TDAFW pump were

declared inoperable.

Subsequent attempts to open the valve by

.normal means were successful.

The valve stem was lubricated and

an internal corrective.action document (D-PAL-91-187) was

written to evaluate the problem.

The preliminary evaluation of

D-PAL-91-187 determined that the valve was operable based on the

maintenance performed and successful stroking of the valve.

This. evaluation reviewed historical valve performance, which did

not identify any negative trends .. The evaluation did raise the

question*of valve reliability.

To address this question, the

valve was placed on increased stroking frequency (daily and

weekly) until root cause analysis was completed.

The licensee completed a week of daily stroke timing on *t.he

valve ?nd had reduced to weekly stroke testing when the valve

failed to stroke a second time.* The valve and TDAFW pump were

declared inoperable.

While the maintenance department attempted

to open the valve, the Plant Review Committee (PRC) evaluated

3

the problem and considered the available options.

The

maintenance department was able to open the valve by light~y

tapping the top of the stem.

The valve was successfully

stroked, the actuating air pressure increased and the valve

placed on a daily stroking frequency until the next outage.

The

licensee has not been able to determine the root cause and it is

not likely that the root cause will be determined prior to the

  • outage.

The inspector discussed the following items with members of the

plant staff.

(1)

(2)

The inoperability of the TDAFW pump was discussed with the *

Operations superintendent and the Director of Safety and

Licensing.

The inspector concluded that th~ decision to

.

conservative operating philosophy.

This conclusion was

based on these facts: the other steam supply valve (CV-

OS22B) receives the auto-open signal ~nd was operable; the

operation of CV-0521 was not directly discussed in the

FSAR; no credit was taken in an accident analysis; and the

Technical Specification does not directly discuss

operability. of CV-0521..

The use of mechanical force to open the valve was discussed

with-the Maintenance Superintendent and the Safeguards

System Engineering Section Supervisor.

Both stated that

the mechanical force was minimal arid use of mechanical

force to assist component operation in lieu of corrective

maintenance was not a tolerated practice.

The use and type

of force was documented on the work order and freely

communfcated to plant management.

In addition,. the

applicable Work Order (WO 24105346) clearly identified the*

need to use torce to open the valve. *

\\

The general topic of applying force to assist component

operation and lessons learned at other plants was discussed

at the Management Interview .

. (3)

The corrective actions taken, which consisted of increasing

the actuating air pressure and increasing the valve

stroking frequency, were discussed with members of the

plant staff. All stated that these were interim corrective

measures untii the plant was piaced in a mode that

permitted repair of CV-0521.

The inspector considered enforcement action for failure to take

appropriate corrective action when the valve failed to *stroke

the first time. The inspector does not consider enforcement

action appropriate at this time based on the detailed

documentation contained in D-PAL-91-187.

The documentation

4

c.

d.

included a fault tree analysis of the potential fault paths and

  • a reason for not considering a fault path.

Control Room Observations

On December.14, the inspector observed control room personnel

taking the reactor critical through the p'oint of adding heat.

The shift supervisor displayed a strong command presence and a *

high degree of professionalism.

The inspector *noted that *

although the-Operations Superintendent and the Operations

Manager where present throughout the evolution, they remained in

the background allowing the Shift Supervisor uninhibited controi

and.direction of the evolution~ In addition, the inspector

observed the performance of a recently licensed operator

performing the. rod w.ithdrawal steps. *

The manner in which other

members of the shift provided insights and recommendations,

based OI) their experience, Was noteworthy.

50.72 Notifications

During power escalation on December 15, the licensee added

additional non-safety related loads to non-safety related bus

"lE" which caused undervoltage relays to activate on the "lC"

and "lD" safety related busses.

The non-safety related bus and

the safety related busses are fed from a common safeguards bus.

The undervoltage was sensed by both safety related busses and

subsequently caused the auto-start of poth diesel generators.

This undervoltage condition was not' of sufficient duration to

activate the load shed sequencers.

The licensee secured the

diesel generators and continued with the power escalation.

The

~ystem was designed such that undervoltage sensed on either

safety related bus would cause an auto start of both diesel

generators.

Initial reports indicated that the plant electrical loads may

.have been lined-up in an unusual condition.

Subsequent reviews

determined that whil.e the safety related busses wer.e unevenly

loaded, the electrical lineup was not unusual.

The inspector had no additional questions concerning this event.

Additional reviews will be performed when the LER is issued.

In

addition, the li~ensee was informed that Region III Division of

React.or Safety inspection specialists* are reviewing this item.

e.

System Walkdowns

The inspector verified operability of the systems listed below

by using the applicable checklist and confirming that major

flowpath valves were in their correct position.

No items were

found that degraded the systems .

5

(1)

Diesel Generators, *cL No. 22.1

(2)

Feedwater System, *cL No. 12 .1.

The inspector found this checkli_st to be difficult to

utilize.

Valve designators had been ch.anged without

revising the checklist.

The checklist was last reviewed on

May 27, 198.8, and is not due *for its next periodic review

until May 1993.

Due to the seemingly large number of

system designator changes, the inspector indicated _that an

earlier review may be prudent.

(3)

Main Turbine Electro-Hydraulic Oil System, CL No. 8.1

( 4 ).

Engineered Safeguards System Iodine Removal

Instrumentation, CL No~ 3.7

f.

. Cold Weather Preparations

The inspector reviewed* the licensee cold weather protective

measures program.

The program consisted of two operating

checklists - CL-CWCL-1, "Cold Weather Checklist," and CL-CWCL-2,

"Cold Weather Checklist (Electrical)" - which are scheduled

annually.

Each checklist has a thirty day completion window.

The inspector conducted walkdowns of Cl-CWCL-1 and.CL-CWCL-2.

There were no significant problems identified; however, .there

was no formal feedback mechanism to ensure that systems which

have been subjected to maintenance and/or modification during

the past year are considered for-cold weather preparations.

This was discussed at the Management Interview.

g.

Tours

During tour.s of the auxiliary building with two members of NRC

Region III Management, the number and method of control of the

yellow plastic catches used to control the f lowpath of

potentially contaminated liquid was discussed with the Radiation

Protection staff. It was determined that the number of catches

was small and an informal method of control wasappropria:te for

now.

The staff was able to identify those that were in-place

for contamination control because a piece of equipment was

leaking and scheduled for repair; and those that were in-place

because boric acid had been. cleared from-the component and an

evaluation was underway to determine if leaking was present and

a repair was necessary.

There were a couple of catches in-place.

to control the condensation from room coolers. It is *

appropriate to control the condensation in this manner, however,.

if this is a. long term problem th.en a permanently installed drip

pan may be more appropriate.

This was discussed at the

Management Interview.

6

  • *

No violations, deviations, unresolved or open items were identified.

4.

Reactor Trip (93702)

The unit was removed from service at 5:22 p.m. on December 9, 1991,

when the air side turbine~generator seal oil system failed resulting

in a reduction of generator hydrogen pressure.

a.

Power Reduction

At approximately 4:30 p.m. an Auxiliary Operator noted that

turbine-generator seal oil pressure was decreasing.

Automatic

attempts by the backup seal oii system and manual intervention

by the Auxiliary Operator, as directed by the Shift Supervisor,

failed to stabilize the decreasing pressure.

The Shift

Supervisor ordered an emergency power reduction at 5:14 p.m.

The power reduction was successful, in that power was reduced

from 100 percent to approximately 20 percent in 10 minutes

without the activation of any automatic trips.

However, as

evidenced by the mismatch between turbine and reactor power -

which resulted in two reductions of the Primary Coolant System

Temperature below the minimum temperature for criticality - the

evolution was not well coordinated.

Additionally, the power

reduction was hampered by slow movement of control rod drive .

number 36.

This drive lagged the other control rods in the

group resulting in additional manipul~tions by the operator.

At approximately 5:25 p.m., the operators observed and

confirmed thatthe water level for the "B" Steam Generator

was above the auto isolation setpoint for main f eedwater

and approaching the manual trip setpoint; the operators

initiated a reactor and turbine trip.

The turbine trip was

activated before the reactor trip, resulting in an

automatic reactor trip due to loss-of-load with the reactor

above the loss-of-load setpoint.

b.

Unusual Event

At approximately 5:35 p.m., the Shift Supervisor declared an

Unusual Event because of the potential for explosive quantities

of hydrogen gas in the turbine building.

The Unusual Event was

secured at 12:50 a.m. on December 10, after the generator_had

been purged with carbon dioxide.

During the Unusual Event, the

turbine building was checked for explosive concentrations of

hydrogen; none were found.

In addition, turbine building

ventilation was increased to minimize the risk of explosion due

to hydrogen buildup.

The written statement from the Auxiliary Operator in the

safeguards room, at the time the Unusual Event was announced,

indicated that he did not hear the announcement and was unaware

7

._.

c ..

that an Unusual Event was declared.

Coinmunication problems due

to high noise level were the subject of IEB 79-18.

Discussion

with the NRC Region III Emergency Preparedness Staff identified

the need for an Open Item for a Region III Emergency

Preparedness.specialist to review the licensee program for in-

plant communication (Open Item 255/91024-0l(DRSS)).*

Post Trip Review

(1)

{2)

The post trip review indicated that a number of equipment

problems occurred during the trip.

None hindered the plant

response or the operators' ability to recover from the

trip.

However, they* did raise the frustration level in the

control room which could.have an indirect effect on the

operators' ability to respond.

In addition to the problems

malfunctioned, the offsi_te communicator auto-dialer

malfunctioned, and the telephone number to the power

controller resulted in a recording providing additional

numbers to call.

The post.trip review identified that the two backup trip

breakers failed to open when the associated trip push

button was pushed.

The primary trip contactors did open

- when activated by the reactor.protective system.

Pushing

the. backup trip breaker push button is a post trip

checkl_ist requirement.

Performance of this step wa*s

documented.

Later, because of the sequencing of a startup

surveillance test, the final step of tpe post trip

checklist (which verified the status of the trip breakers)

was not performed but was marked "N/A*".

The surveillance

procedure that was in progress required reset of the

reactor protective system.

In this case, the checklist

step was marked "N/A" because the breakers were closed to.

perform the test.

During a subsequent test, which'

concluded by opening the backup trip breakers, it was

discovered that one of the breakers did not open when the

push button was pressed.

Based on this information and

interviews conducted with the operators onshift during the

trip, the licensee concluded that both of the trip breakers

did not open.

This conclusion w~s based on information

obtained from the operator who stated he reset the reactor

protective system to perform the first surveillance test

without resetting the backup trip breakers *. The licensee's

investigation traced the problem to the push button, which

required a steady push to assure proper make up of the

internal contacts.

This information was provided, as part

of the shift turnover, to oncoming operators prior to

assuming the watch.

In addition, the licensee placed an

operator aid on the control panel next to the switch .

8

d.

Seal Oil

The licensee investigation of the air-side generator hydrogen

seal-oil: system determined that an in-line seal-oil filter

became clogged and resulted in a reduction in seal-oil pressure.

This conclusion was' based on the fact that the backup system

functioned properly and attempts to rotate the filter, after the

trip, were unsuccessful.

This type of filter is manually

rotated once a shift to clean the internal-filter surface.

In

.addition, the licensee performed an air test of the generator

shaft seal to confirm its integrity.

e.

CRDM 36

During the power reduction, the movement of CROM 36 was slow,

resulting in manual operation by _the control room operator, to

keep the' rod within the group.

The -problem w'as attribut~d to

the drive package and it was replaced. *The required trip time

of the rod-was subsequently verified and found to be

satisfactory.

The inspector has reviewed' the post trip information and verified

that the problems were resolved prior to returning the plant to

service.

The inspectors have no additional questions at this time.

Additional reviews will be performed when the-10 CFR 50.73, "Licensee

Event Report" is issued .

. one open item and no violations, deviations, or unresolved items were

identified.

-

5.

Maintenance (627031 42700)

Maintenance activities-in the plant were routinely inspected,

including both co~rective maintenance (repairs) and preventive

maintenance.

Mechanical~ electrical, and instrument and control

group maintenance activities were included as available.

The Inspector verified that Limiting Conditions for Operation were

met while components or systems were removed from service, approvals

were obtained prior to initiating the work, activities were

accomplished using approved procedures, and post maintenance testing

was performed as applicable.

The following work order (WO) activities were observed:

a.

WO 24100421:

Diesel Generator K-6B Fuel Oil Pressure switch.

b.

WO 24104033: K-6B Starting Air Pressure Switch Incorrectly

Piped.

c.

WO 24104034:

K~6B Starting Air Pressure Switch Incorrectly

9

    • d.

Piped.

WO 24104056 :_

Replace 18 Fuel Pump Cover Gaskets on Diesel

Generator 1-2.

e.

wo* 24104462: *swap Fuel Pumps, Cylinder 7L with 2R,.on Diesel

Ge;nerator 1-2.

f.

WO 24103212:

Preventive Maintenance on Diesel Generator 1-2 Air

Compressor.

g.

h.

i.

WO 24102666:

Preventive Maintenance on Diesel Generator 1-2 A/C

Backup Gasoline Engine.

WO 24102096: *Replace Band Clamp on Air Inlet Pipe/Turbo Charger

on Diesel Generator 1-2.

WO 24104114:

Multi-009 Group, K-6B Air Start Motor Starting Air

Instrumentation.

For several of* the wos listed above, the inspector noted that the

mechanics or technicians involved in the_repair or maintenance

activity demonstrated a thorough understanding of the procedure.

The

procedures were clear and concise as to the work to be performed.

Tools and other documentation required to complete the task appeared

to be staged at the.job site indicating a. detailed pre-job review of

the work order was performed prior to starting the job.

j.

WO 24105743 and Specification Change 91-77:

E-50A Upper East

Handhole Leak.

During a containment tour on December 12, the licensee observed

a steam leak at a secondary side handhole for the "A" steam

generator.

The leak was caused by imp~oper installation of a

handhole cover, resulting in a non-uniform gap between the cover

and the flange.

The steam leak was from the gasket and did not

affect the integrity of the flange, cover, or fasteners.

The

attempted repair included retorqueing the nuts and installation

of an enclosure that was injected with a *liquid sealant.

The

inspector concluded, after consulta_tion _with Region III and

.

NRR, that this was ah acceptable repair because the structural *

integrity of a pressure retaining boundary was not compromised

or degraded.

Because of the ambient temperature, the liquid

_sealant solidified prior to securing the steam leak.

The

licensee was able to reduce the leak by approximately one third

before concluding that additional repair attempts were

unnecessary.

The specification change was provided to Region

III specialists for additional review.

The inspector has no

additional questions at this time.

k.

wos 24101783, 24102631, 24102603: nepair steam leaks on the

10

management of the forthcoming refueling outage.

The inspector

running vent lines for the EGA and E6B Feedwater Reheaters.

The wos documented that through wall pipe leaks exist in the 3

inch running vent lines.

The temporary repair consisted of

enclosures which were injected with liquid sealant.

This

temporary form of repair was acceptable because the lines are

non-ASME code class lines. * The inspector questioned the use of

  • this type.of repair because of steam line problems at other

plants.

In addition, the NRC has not generally accepted this

type.repair.

The licensee stated that the repairs were

temporary and will be removed during the next outage.

wos

24-101996, 24103059, and 24103068 were issued to make permanent

repairs during the outage.

No violati_ons I deviations I unresolved or open i terns were identified.

~--

outages (86700)

The inspector reviewed various activities associated with the project

examined the management techniques and tools utilized to ensure that;

the outage was planned* in a safe and risk~free manner.

Several

  • strengths were noted during this review.

The licensee utilized

"system windows" to sequence work at the system level.

By overlaying

these system level work schedules onto various plant requirements,

such.as shutdown cooling, the licensee can determine when a system*

can be released for work without impacting plant safety.

Additionally, the licensee utilized the Artemis scheduling package

and the precedence scheduling technique.

The Artemis system is *

capable of handling large numbers of activities allowing the licensee

to schedule below the work order level.

This' allows for better work

load forecasting and resource loading.

The precedence *scheduling

technique allows the licensee.to develop schedules that reflect real

time accomplishm~nt. This a*11ows for the maximum utilization* of

limited outage time and better development of controlling path work~

No violations, deviations, unresolved or open items were identified.

7.

Quality Program Activities

Plant Procedure CH 3.42. "Betz Clam Trol 1 Treatment of Service Water.

System~"

The intent of CH 3.42 was to provide for treatment against zebra

mussel infestation and prevent blockage caused by their rampant

growth.

The inspector interviewed the author of the procedure and

reviewed the non-radiological environmental evaluation, the

unreviewed safety question evaluation,** the safety review, the *

environmental impact review and the Environmental Protection Plan.

The inspector's observations are discussed below.

11

a.

The licensee unsuccessfully treated the firewater system for

zebra mussels.

During the summer of 1991, the firewater system

was used to facilitate soil compaction of the independent spent

fuel storage installation foundation and support fire fighting

. activities at a nearby housing subdivision.

These activities

created the potential to contaminate the firewater .system with

~ebra mussels.

The firewater -system is an alte~nate source of

feedwater to the auxiliaryfeedwater pumps.

The firewater

system piping configuration to the auxiliary feedwater pumps

includes a section of piping (approximately 3 feet) which is

exposed to the elevated ambient temperature of the auxiliary

feedwater pump room. _ If a colony of zebra mussels is

established in this -- leg of piping, the colony rilay continue to

grow during the winter months because the ambient room

temperature may keep the piping and water above the zebra*

mussels_' dormant temperature.

This concern was expressed to the

licensee.

b..

The safety evaluation implied that fouling of heat exchangers

due to deceased zebra mussels will occur approximately one week

after.the treatment.

Discussions with NRC inspectors at power

plants that have dealt with zebra mussels,-- indicated that

fouling due to deceased zebra mussels may occur three weeks

after treatment.

This information was provided to the licensee~

c.

The Environmental Impact Review sheet (part of the support

documentation for .CH 3.42) requires ,an evaluation to determine

if the proposed procedure-modification resulted in an unreviewed

environmental question as defined in Section 3.1 of Appendix B,

"Palisades Environmental Protection Plan (EPP) to the Palisades

Facility Operating License."

The response was "no".

No review

comments were provided to document the bases_ for this response.-

Section 3.1 of the EPP requires an environmental review to

determine if activities which may affect the environment could

create an unreviewed environmental question.

One of *the areas

to be considered pertained to activities that were not evaluated

in the EPP and may have a sufficiently adverse environmental_

impact.

The use of Betz Clam Trol was not previously evaluated

in the EPP.

Section 3.1 also requires that records shall

include a written evaluation which provides the bases for

determining why an activity does not create an unreviewed

environmental question and does not constitute a decrease in the

effectiveness of _the EPP.

As stated above, the licensee determined that the activity did

not involve an unreviewed environmental question.

However, the

licensee did not provide a written evaluation which provided the

bases that the activity did not involve an unreviewed-

environmental question or decrease the effectiveness of the EPP.

12

Failure to include written bases is a violation of Section 3 *. 1

of the EPP.

compliance to the EPP is a requirement of the

Facility Operating License, paragraph 2.c.(2) (Violation

255/91024-02(DRP)).

  • During interviews.with plant personnel, the inspector was

informed that it was not past practice to provide bases *when the

test, *change or modification was found not to constitute.an

unreviewed environmental-question.* Based on t.his information

the inspector concluded the problem was programmatic.

d.

The inspector observed that a-person or group that does not

directly report to the plant was determining compliance to the.

license as it applied to the Environmental Protection Plan ..

This was discussed with the licensee.

One violation was identified.

No deviations, unresolved or open

items were identified.

a .

Open Items

Open items are matters which have.been discussed with the licensee,

and will be reviewed further by the inspector.

These involve some

action on the part of the NRC or licensee or both.

An open item

identified during the inspection is discussed in Paragrap~ 4.b.

Management Interview

The inspectors met with licensee representatives - denoted in

Paragraph 1- -

on December 18, 1991, to discuss the scope and findings

of the inspection.

In addition, the likely informational content of

the inspection report with regard to documents or processes reviewed

by the inspectors during the inspection was also discussed.

The

licensee did not identify any such documents or processes as

proprietary.

-

Highlights of the exit interview are discussed-below:

a.

Strengths noted:

.

(1)

The licensee demonstrated a conservative operating

philosophy when dealing with the inoperable steam supply

valve to the.turbine driven auxiliary fe$dwater pump

(paragraph 3.b.(1), "Operations -Turbine Driven Auxiliary

Feedwater Pump Inoperable").

(2)

(3)

Open communication_* within the maintenance organization

(paragraph 3.b.(2), "Operations - Turbine Driven Auxiliary

Feedwater Pump Inoperable").

Strong documentation by system engineering when discussing

13

resolution of a problem (paragraph 3.b.(3), "Operations -

Turbine Driven Auxiliary Feedwater Pump Inoperable").

(4)

Control room leadership (paragraph 3.c, "Operations -

Control Room Observations").

(5)

Several examples were identified of well planned

maintenance activities and thorough understanding of

procedures and equipment by the workers (paragraph 5.i,

"Maintenance").

(6)

Scheduling of outages (paragraph 6, "Outages").

b.

  • Weaknesses noted: , .

.

.

.

.

c.

d.

e.

f.

g .

(1)

The lack of completeness of a* licensee response to a Notice

of Violation.

The inspector discussed the completeness and

.accuracy requirements of 10 CFR 50. 9 (par*agraph 2, "Actions

on Previously Identified Items").

(2)

(3)

(4)

(5)

The plant reliance on an offsite group to determine the

plant compliance with a Technical Specification (Pa.ragraph

7.d, "Quality Program Activities")..

Component identifiers that do not match the checklist

description (paragraph 3 .. e. ( 2 )_, "Operations - System

Walkdowns")~

Lack of a screening mechanism to*assure that maintenance

activities or modifications do not expand the cold weather

preparations envelope (paragraph 3.f, "Operations - Cold

Weather Preparations").

Poor coordination of the emergency down power (paragraph

4.a, "~eactor Trip - Power Reduction").

The inspector discussed the Notice of. Violation (paragraph 7.c,.

"Quality Program Activities").* *

The inspector discussed the potential of flow blockage of the

emergency f eedwater to the auxiliary f eedwater pumps as the

result qf flow blockage from zebra mussels (paragraph 7.a, *

"Quality Program Activities").

The 50.72 notification was discussed.

The inspector will

perform additional reviews when the associated LER is issued

(paragraph 3.d, "Operations -

50~72 Notifications").

The open.item. pertaining to inplant communication was discussed

(paragraph 4. b, "Reactor Trip - Unusual Event") ..

. A topic that was not documented in the inspection report but was

14

discussed at the exit interview pertained to lessons learned at

another plant.

Apparently there was a return to criticality

event during a plant cooldown.

The event was not documented or

communicated to plant management.

The lesson learned pertained

to the thr~shold for documentation and communication of

problems.

15