ML18044A498

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-255/79-20 on 791022-26,29 & 30.Noncompliance Noted:Failure to Make Temporary Changes to Tech Specs Re Power Reductions & Conduct Surveillance Tests as Required by Tech Specs
ML18044A498
Person / Time
Site: Palisades Entergy icon.png
Issue date: 12/18/1979
From: Baker K, Little W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18044A496 List:
References
50-255-79-20, NUDOCS 8002070381
Download: ML18044A498 (13)


See also: IR 05000255/1979020

Text

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-255/79-20

Docket No. 50-255

Licensee:

Consumers Power Company

212 West Michigan Avenue

Jackson, MI

49201

Facility Name:

Palisades Nuclear Generating Plant

Inspection At:

Palisades Site, Covert, MI

Inspection Conducted:

October 22-26, 29 and 30, 1979

Inspector: ~~~

v}Y~"'-

Approved By: -42-~~-:~:ting Chief

Nuclear Support Section 1

Inspection Summary

License No. DPR-20

Inspection on October 22-26, 29 and 30, 1979 (Report No. 50-255/79-20

Areas Inspected:

Routine, unannounced inspection of surveillance of

safety related components and equipment; implementation of ASME Code

Section XI for pumps and valves.

The inspection involved a total of 56

inspector-hours on site by one NRC inspector.

Results:

Of the areas inspected, six items of noncompliance were identi-

fied (Infractions - Control of Test Equipment, 10 CFR SO, Appendix B,

Criterion XII, Paragraph 5; Failure to report as required by Technical

Specifications 6.9.2.a(6), Paragraph 4; Failure to test as required by

Technical Specifications 4.5.3.a, Paragraph 3; Failure to make a tem-

porary change as required by Technical Specification 6.8.3, Paragraph 4;

Failure to conduct surveillance tests at the interval specified by Tech-

nical Specification 4.13.c, Paragraph 8; Failure to implement ASME

Section XI test requirements for valves, Paragraph 9.

8002070 3g'

1.

DETAILS

Persons Contacted

  • R. DeWitt, Vice President Nuclear Opeations
  • J. Lewis, General Manager - Palisades
  • F. Butler, I&C Engineer
  • B. Schaner, Operations Supervisor
  • R. Vincent, Senior Engineer
  • G. Gilbody, QA Engineer
  • D. Kennedy, Associate Engineer
  • J. Meineke, Reactor Engineer
  • D. Powers, QA Engineer
  • G. Petitjean, Technical Engineer

H. Palmer, Technical Superintendent

S. Ghidotti, Shift Supervisor

T. Konicki, Shift Supervisor

The inspector also contacted several other licensee employees.

  • Denotes those attending the exit interview.

2.

Surveillance of Safety Related Components or Equipment

a.

Purpose of Record Review

The inspector reviewed plant surveillance records to verify:

(1)

Test procedures are approved in accordance with the Tech-

nical Specifications.

(2)

Test procedures include appropriate (a) prerequirsites and

preparations, (b) acceptance criteria, and (c) instructions

to ensure tested item is restored to operation following

the test.

(3)

Technical content of procedures assures compliance with

the Technical Sp~cifications and/or Inservice Inspection

Program.

(4)

Tests were performed within the time frequencies specified

in the Technical Specifications and Inservice Inspection

Program.

(5)

Tests were performed by qualified individuals.

(6)

Test results were reviewed as required by facility

administrative requirements .

- 2 -

(7)

Test results were in conformance with Technical Specifica-

tions and Inservice Inspection Program.

(8)

Appropriate action was taken for test results not meeting

the acceptance criteria.

b.

Administrative Documents and Test Records Reviewed

(1) . Test Records

(a)

D-W-1, Daily, Weekly Operations

Surveillance, Rev. 9

(b)

M0-20 Inservice test procedure,

Charging Pumps, Rev. 11

(c)

MT-15 Reactor Internals Noise

Monitor Test, Rev. 8

(d)

Q0-5 Valve Test Procedure, Rev. 11

(e)

QE-9 Diesel Fire Pump Battery

Surveillance, Rev. 2

(f)

A0-3 Shutdown Cooling System Test,

Rev. 4

(g)

AE-5 DC Lighting Test, Rev. 3

(h)

R0-22 Control Rods Drop Time,

Rev. 5

(i) Fuel Oil Samples T-10

(2)

Personnel Qualification Records

Date of Test

10/22-25/79

1/16/79, 2/19/79,

3/15/79, 4/16/79,

5/23/79, 6/18/79

5/30/79, 6/8/79,

6/15/79, 6/18/79,

6/22/79, 7/2/79,

7 /11/79, 7/20/79,

7/31/79, 8/16/79,

8/17/79, 8/31/79,

9/7 /79

10/8/78, 1/17/79,

4/17/79, 7 /15/79

9/7/78, 12/5/78,

3/2/79, 6/6/79

7/5/78, 7/29/79

5/30/78, 5/17 /79,

4/9/78

Monthly results

August 1978 through

October 1979

The qualification for two individuals involved in the tests

identified in 2b.a and 2b.h above were reviewed to determine

if the individuals were qualiffed in accordance with the

Technical Specifications and ANSI N18.1

- 3 -

3.

(3)

The following facility administrative documents were used

during the review;

(a)

EM-09-04, fnservice Testing of Selected Safety Related

Pumps, Rev. 2

(b)

QAPP 11-51, Test Control for Nuclear Plant Operations,

Rev. 0

(c)

EM-09-01, Technical Specification Testing, Rev. 19

(d)

EM-09-02, Inservice testing of Plant Valves, Rev. 4

(e) Administrative Procedure Number 6 Technical Admini-

stration, Rev. 4

(f)

QAPP 6-51 Distribution and Control of Quality Related

Document

(g)

Administrative Procedure 10-3, Document Distribution

and Control

(h)

Administrative Procedure 10-3-1, Temporary Procedure

Change

(i) Administrative Proceudre 17.0, Control of Measuring

and and Test Equipment

(j)

QAPP 12-51 Control of Portable and Laboratory Measuring

and Test Equipment

(k)

QAPP 15-51, Contr~l of Nonconforming Items

c.

Findings

Unless discussed in the following sections of the report, the

surveillance activities were found to be in compliance with

regulatory requirements.

Shutdown Cooling System Test A0-3

The inspector reviewed the content of the test to determine if it

fulfilled the surveillance requirements of Technical Specification 4.5.3.a(l) "The portion of the shutdown cooling system that is

outside the containment shall be tested either by use in normal

operation or hydrostatically tested at 255 psig at the interval

specified in 4.5.3.d," 4.5.3(2) "Piping from valves CV-3029 ...

to discharge of safety injection pumps and containment spray

pumps ... 100 psig ... ," 4.5.3a(3) "Visual inspection made for ex-

  • cessive leakage ... ," and the acceptance criterion of 4.5.3.b of

"less than 0.2 gpm under the normal head from the SIRV tank .

- 4 -

l

Test A0-3, Rev. 4, dated November 17, 1977, was performed July 5,

1978 and July 29, 1979, which fulfills the frequency requirement,

but the procedure does not fulfill the requirement of 4.5.3.a(l) in

that (1) Section 6.2 specifies a minimum test pressure of 255 psig.

The test pressure on July 5, 1978, was 225 psig and 227 psig on

July 29, 1979.

(2) The Section of piping between MOV3016 and valves

3199 and 3190, which contains a portion of the shutdown cooling

system that is outside the containment is not tested by the proce-

dures.

These two items appear to be in noncompliance with Technical Speci-

fication 4.5.3.a(l).

The test pressure as specified in Section 6.1 of the test procedure

is 100 to 150 psig in the suction piping of shutdown cooling system.

This appears to be in conflict with Technical Specification 4.5.3a(l),

but the basis contained on page 4-35 of the Technical Specification

states, "The test pressure (270 psig) achieved either by normal

system operation or by hydrostatically testing gives an adequate

margin over the highest pressure within the system after a DBA.

Similarly, the hydrostatic test pressure for the return lines from

the containment to the shutdown cooling system (100 psig) gives an

adequate margin over the highest pressure within the lines after a

DBA."

It was also noted the Specification requires testing at a minimum of

250 psig while the basis used 270 psig.

It was also noted that the acceptance criteria is given as 0.2 gpm

leakage.

The values recorded in the test are in milliliters per

minute.

It would seem logical to give the acceptance criteria in

the same units as the measurement is made to reduce errors.

Add-

itionally, Section 7 .1. 3 of the procedure requires that if the

leakage equals or exceeds one-half gallon per minute, a deviation

report will also be initiated. It would seem that one should be

initiated when the leakage exceeds the Technical Specification

acceptance criteria.

The above was discussed with the licensee and the licensee stated

the items would be resolved.

4.

Iodine Removal System Valved Out

During a review of completed. "Shutdown Cooling System Test" A0-3,

the inspector noted indications that for the test performed on

July 29, 1979, that valves 3364ES and 3363ES, NAOH to SI, had been

left in the closed position upon completion of the test, then at

some later time returned to the open position.

The valve line up

sheets to restore the system after testing (Appendix 5 and 7 of the

- 5 -

test) required these valves to be closed.

The pages containing the

signoffs for these valves were photocopies, which had then been

marked over in ink to show the valves had been opened.

The mark

over had been done by a shift supervisor who was on duty subsequent

to the completion of the test.

A temporary change was initiated on

August 1, 1979, to change the valve position on the checklist from

closed to open.

Piping Instrument Diagram M-204, Rev. 15 requires these valves to be

locked open.

The valves are manual valves located in the Engineered

Safeguards Rooms.

The function of the system is to add sodium

hydroxide to the recirculation water after a LOCA to establish a

neutral pH.

This addition requires operator action to operate

valves from the Control Room.

Location of the valves 3364ES and

3363ES would make them difficult to impossible to open after a LOCA

due to radiation levels in the Engineered Safeguards Rooms.

Tech-

nical Specification 3.19.1 requires the Iodine Removal System to be

operable during power operation.

System inoperability for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />

is allowed by the Technical Specifications.

A review of test records, logs and discussions reveal the following:

a.

July 29, 1979, sometime during A shift (00-08) - valves 3363ES

and 3364ES were closed in preparation for surveillance test

A0-3.

Basis - Initials on valve check off sheet and list of personnel

on A shift.

b.

July 29, 1979, sometime during B shift (08-16) - valves 3363ES

and 3364ES checked in closed position following test.

Basis - Initials and signatures on valve check off sheets and

list of personnel assigned to B shift on July 29, 1979.

c.

July 29, 1979, sometime during C shift (16-24) - a second check

of valve line up in accordance with check off sheets of A0-3

was conducted.

The valves were in the closed position.

Basis - Shift supervisors written notes in procedure, signature

on completed valve sheets and discussion with shift supervisor.

d.

July 30, 1979, sometime during A shift, the valves were opened.

The shift was following up on a question of valve numbering

they had had on the 29th but had not had time to resolve.

The

shift supervisor in attempting to resolved the matter sent an

operator to look at the valve labels.

The operator reported

their labeling and said they were closed.

The shift supervisor

questioned this and compared the present position to that

- 6 -

required by startup valve check lists CL3.l and 3.2.

He then

ordered the valves open.

The shift supervisor then marked up

the completed copy of A0-3 to show the positions he had placed

them in.

A memo was sent to the Technical Superintendent re-

questing the A0-3 procedure be corrected.

This resulted in a

temporary change being initiated on August 1, 1979.

Basis - Initials on valve lineup sheet, July 30, 1979, memo

from shift supervisor, temporary change T-79-036, and discus-

sion with shift supervisors.

A review of the completed test procedure for the test ran

July 5, 1978, revealed that the valves had been left open upon

completion of the test.

The valve list had been modified to

indicate the valves should be left open with the shift super-

visor's initials. It appears that this was a change to the

procedure which was not made in compliance with the require-

ments of Technical Specification 6.8 and Administrative

Procedure 10-3-1, "Temporary Procedure Change."

This item is

considered to be in noncompliance with Technical Specification 6.8. If the procedure had been changed properly the problem

would not have occurred in 1979.

Technical Specification 6.9.2.a(6) requires a written report be

submitted to the NRC within 14 days of procedural inadequacies

which prevent or could prevent, by itself, the fulfillment of

function required of systems required to cope with an accident

analyzed in the FSAR.

The error in the A0-3 test procedure

could have prevented the sodium hydroxide system from fulfilling

its function and should have been reported as required by

Technical Specifications 6.9.2.a(6) when the error was detected

in the procedure.

This appears to. be an item of noncompliance.

5.

Control of Measuring and Test Equipment

During reviews of completed "Shutdown Cooling System Test" A0-3

procedures for traceability of test equipment used and proper

calibration of test equipment, the inspector noted the following:

a.

July 5, 1978 test.

No serial number was recorded on the data

sheet (Appendix 3) for the pressure gauge used during the test.

A calibration sheet was attached to the completed procedure

which indicated a gauge serial number 6-20-78-1, "new test

gauge" had been calibrated for A0-3 test on June 20, 1978.

The

calibration sheet recorded that dead weight tester serial

number 8428-100018 was used to calibrate the gauge on June 20,

1978.

The dead weight tester had last been calibrated on

June 13, 1977, and had a calibration due date of June 13, 1978.

The calibration sheet contained a reference to Deviation Report

-

7- -

(DR)78-220.

A review of the DR showed it had been initiated

on June 20, 1978, and an evaluation due date had been assigned

of July 21, 1978.

The tester was calibrated on September 18,

1978, and found to be in calibration.

The evaluation and dis-

position of the DR was completed on November 28, 1978.

Dis-

cussions with personnal and review of* the DR show that at the

time of use it was known the tester was past due for calibration

and DR was initiated to document this.

The decision to use the

tester had been.made by the I&C Engineer as no other tester was

available at the time and that the tester appeared to be in

fine working condition.

b.

July 29, 1979 test.

Three different serial numbers had been

recorded on the data sheet (Appendix 3) for the gauge used

(only one gauge used in the test).

Two of the serial numbers

had corresponding calibration dates recorded.

Calibration

data sheets attached to the procedure showed gauge serial

number 8-676-1 had been calibrated on July 17, 1979.

This

gauge serial number corresponded to one of the serial numbers

recorded on the data sheet.

During the inspection on October 23,

1979, a licensee's representative placed a note on this sheet

that the gauge was broken on A shift July 29, 1979.

The inspector

observed a gauge with this serial number that had been broken.

The second calibration data sheet attached did not record a serial

number for the gauge being calibrated.

The date of this calibra-

tion was July 29, 1979.

The review section of this calibration

data sheet had not been signed off.

Under the calibration equipment

used in calibrating this gauge a test gauge serial number 8428-00392

was recorded.

This serial number also appeared on the A0-3 data

sheet.

The licensee showed the inspector a gauge in a plastic

bag (for contamination control) that had a tag attached which was

annotated as A0-3 test gauge and had a calibration sticker dated

July 29, 1979.

A manufacturer's QC type sticker on the back of

this gauge contained the number 8620 which was also one of the

numbers recorded on the A0-3 data sheet.

A review of the licensee QA program and administrative proce-

dures to implement the requirent of 10 CFR SO, Appendix B,

Criteria XII, Control of Measuring and Test Equipment, revealed

the following:

(1)

Administrative Procedure 17.0, Rev. 0 dated November 2,

1977, states the equipment will be traceable and will be

labelled to indicate status.

(2)

QAPP for Operations 12-51, Rev. 1, dated October 31, 1977,

Control of Portable and Laboratory Measuring and Test

Equipment in Section 5.11, states that test equipment not

recalibrated within the calibration interval are to be

considered nonconforming per QAPP 15-51 until corrective

measures have been taken per QAPP 16-51, which is basically

- 8 -

taped, marked or segregated to prevent use until released

for use after disposition of the DR is completed per QAPP

16-51.

The control of test equipment used in performing A0-3 on

July 5, 1978, and July 19, 1979, does not appear to be in

noncompliance with 10 CFR SO, Appendix B, Criterion XII

requirements and the licensee's QA Program Procedures

12-51.

6.

Overpressure Protection System Surveillance Testing

A review of procedures and test records was conducted to determine

the licensee's compliance with Technical Specification 4.1.la and b ..

This specification was issued on September 10,1979.

The facility

was in refueling at that time.

At the time of this inspection the

reactor vessel head was being installed, the CRD tool access flanges

were removed and the pressurizer safety valves were also removed.

Therefore, the only portion of the surveillance which was required

was verification of PCS vent path.

D-W-1 and SH-1 which are daily,

weekly and shift checks by the operators fulfill the requirements of

Technical Specifications 4.1.1.a3 and 4.1.1.b.

Shift records for

the period October 22-25, 1979, were reviewed to verify implementation

by the licensee.

The licensee presently has no approved procedures for the surveillance

requirements of Technical Specifications .4.1.la.1, 2 and 4.

These

are channel functional tests of the PORV, channel calibration, and

valve testing per ASME Section XI, Section IWV Category C valves.

The inspector discussed with the licensee that his surveillance in

accordance with these sections of the Technical Specifications must

be current prior to placing the PORV portion of the system in service.

That either he must be able to show testing of the PORV's per Section

IWV of the code within the last five years or test them prior to

placing them in service.

An acceptable alternative would be to ob-

tain a change to the Technical Specification.

This was also discussed

at the exit interview.

This item is considered an unresolved item pending actions by the

licensee. (255/79-20-1)

7.

Charging Pump Capacity

During a review of data and acceptance criteria for procedure M0-20

Inservice Test Procedure Charging Pumps the inspector noted that

acceptance criteria and data indicated flows below 40 gpm.

These

acceptance criteria are based upon reference values obtained in

accordance with ASME Section XI.

A review of section 14.14 of the

FSAR for the steam line break analysis shows two of the three 40 gpm

- 9 -

charging pumps are used to deliver concentrated boric acid.

Section

14.17 for the LOCA analysis also mentions charging pumps of 40 gpm

capacity.

The acceptance criteria used in M0-23 (Temporary Change

T-79-023 to M0-20, Rev. 11) allows flows as low as 34 gpm.

It is

not clear if the values given in the FSAR are nominal or minimum

valves.

If they are nominal, what is the lowest acceptable flow

rate?

The inspector discussed this with the licensee.

The inspector

stated that the acceptance criteria used must be consistent with the

values used in any safety analysis, even though they may be in com-

pliance with Section XI requirements.

That the licensee should not

enter a mode where the charging pumps are required, until he can de-

monstrate that flow rates below 40 gpm are acceptable.

The licensee

acknowledged the inspector's comments.

This item is considered to be an unresolved item pending actions by

the licensee. (255/79-20-2).

During the review of M0-20 the inspector noted that on April 12, 1979

the acceptance criteria (refernce value) for the B pump was changed

to 39.1-34 gpm.

The inspector questioned the reason.

The licensee

suggested it might have been because of maintenance.

A comprehensive

search of maintenance records failed to show any maintenance on the

pump at that time. It was later found that it had been changed due

to a Deviation Report initiated as the result of a QA audit which had

found the value should have been changed in January 1979.

The desir-

ability of prompt changes and the need to maintain the basis for re-

ference values in an easily retrievable location was discussed.

The

licensee acknowledged the inspectors comments.

8.

Reactor Internals Vibration Monitoring

The inspector reviewed completed tests MT-15 conducted. through the

period of May 30, 1979, to September 7, 1979, to determine compliance

with the surveillance requirement of Technical Specifications 4.13.

The following was noted:

a.

Data sheets used in the performance of the test were labelled

Rev. 7, instead of the current revision, Rev. 8.

A review of

the data sheets showed they were a Rev. 7 which had been altered

to contain the same requirements as Rev. 8.

This was brought

to the licensee's attention and the supply of the Rev. 7 sheets

was removed.

The potential for problems associated with the

control of data sheets was discussed with the licensee.

b.

Some graphs of data were not well labelled in that they required

explaination as to range, scale and various values.

This was

discussed with the licensee and the licensee agreed to improve

the labelling .

- 10 -

c.

A review of the frequency of the Phase I measurements for July

1979 revealed that they were taken on July 2, 11, 20, 31, 1979.

The facility operated at power for the entire month with no

trips.

Power reductions occured for short periods on July 11

and 25, 1979 due to equipment problems.

Technical Specification 4.13.c states that "as a minimum during normal plant operation,

Phase I measurements shall be recorded and analyzed once per

seven days.

The licensee's procedure does not define normal

operation.

The type of data taken would not be meaningful dur-

ing power changes or during large xenon changes.

Based upon

this, it would have been meaningless to take the measurement on

the 25th and possibly for a period on the 26th.

Data was taken

on the 11th prior to the power reduction.

Technical Specification 4.0.2 allows an extension of interval not to exceed 25% or about

nine days in this case.

Also, the total maximum combined interval

for any three consecutive intervals shall not exceed 3.25 times

the interval or about 23 days in this case.

The interval from

July 20 to 31, 1979, exceeds the 25% and the period from July 2

to 31, 1979, for three intervals exceeds the 3.25 times allowance.

Therefore, the above appears to be in noncompliance with Technical

Specification 4.13.c.

9.

ASME Section XI Valve Test

The inspector reviewed completed valve test procedure Q0-5 for the

licensee's implementation of inservice testing of valves in accordance

with ASME Section XI; 1974 Edition with Addenda through Summer 1975

as required by 10 CFR 50.SSa(g).

The licensee has applied for exemption

from some of this timing requirement of Section 1WV-3410c (3) and his

procedure reflects his exemption request.

Valve CV-0522B, Steam B to

turbine driven auxillary feedwater pump, stroke time was measured as

42.2 seconds on January 17,1979, and 57.0 seconds on May 17, 1979.

Even considering the licensee's exemption. request, the frequency of the

testing should be increased to once per month per the code.

This was

not done in this case and appears to be in noncompliance with 10 CFR

50.SSa(g) and ASME Code Section XI.

It was also noted that time for

MOV-2140 Boric Acid Injection valve increased from 2 seconds to seven

seconds between October 8, 1978 and January 17, 1979.

The review of

the test by the Project Engineer which is supposed to identify the

need for increased frequency of testing when there are changes in

stroke time does not appear to have been done for January 17, 1979

and April 17, 1979 test, based upon a discussion with the Engineer

and the lack of sign offs on the completed tests. It was also noted

that on the October 8, 1978, steam generator blowdown isolation valve

CV-0770 was not cycled, and no note was made as to why the valve was

not cycled.

- 11 -

10.

Diesel Fire Pumps Battery Surveillance

Technical Specification 4.17.2.2.b(2) requires the licensee, at an

interval of every three months, to verify that the specific gravity

of the starting battery bank is appropriate for continued service of

the battery.

The inspector reviewed completed QE-9 Diesel Fire Pump

Battery Surveillance Procedures from 9/7/78, 12/5/78, 3/2/79, 6/6/79.

The following was noted:

a.

The 9/7/78 test had an acceptance criteria for specific gravity

of 1.200 - 1.265 as established in temporary change T-78-051.

Cells 5 and 9 in lower bank P-41 had specific gravity readings

of 1.270. It appears no actions were taken on these readings

which exceeded the acceptance criteria.

b.

By the test on 3/2/79 T-78-051 had been incorporated as a

permanent change in Rev. 2.

The acceptance criteria was

1.200-1.265.

Data taken on 3/2/79 revealed a number of cells

at a specific gravity of greater than 1.265.

A temporary

change was written on 3/19/79 which raised the upper limit to

1.270 and the test results were approved on 3/20/79.

c.

Test data on 6/6/79 revealed a number of cells exceed the 1.270

limit.

Another temporary change was initiated and approved on

6/25/79 to raise the upper limit to 1.280.

The test results

were approved on 6/25/79 based upon the raised acceptance

criteria.

P41 upper bank had two cells with low specific

gravity.

A maintenance order was initaited on 6/8/79 and work

completed on 6/22/79 to raise the specific gravity.

d.

The inspector attempted to review the September 1979 results

and they were not in the file.

The test was found in the

electrical maintenance department.

Review had not been com-

pleted.

Data taken on 9/6/79 showed a number of cells exceeded

the 1.280 limit. A Deviation Report was initiated on 9/20/79.

As of 10/30/79, neither the DR or results of the test procedure

had been signed off as acceptable by the licensee.

The DR had

an evaluation due date of 10/21/79 assigned.

The time interval between observing a reading outside an accep-

tance criteria, slow corrective actions and continual adjustment

of acceptance criteria was discussed with the licensee. It is

not clear how the licensee can take credit for operable equipment

when the surveillance test results exceed acceptance criteria.

This is considered an unresolved item pending review by the

licensee and Region III.

(255/79-20-3)

- 12 -

11.

Surveillance Test Procedures

The inspector noted that a number of surveillance test procedures do

not specify the qualification of test personnel.

QAPP 11-51 requires

the qualification of personnel to be included in surveillance test

procedures.

This was discussed with the licensee.

The licensee

stated that presently procedures were in the process of receiving

periodic review and that this review would be correcting items such

as this.

The licensee's use of acceptance criteria in procedures is at times

questionable.

Examples are discussed in Section 3, 7, 9 and 10 of

this report.

These deal with incorrect, misleading, or not meeting

acceptance criteria.

Another example was observed in the review of

R0-22, Rev. S, Control Rod Drop Times.

As an acceptance Criterion

in this test, Section 3.2 states "Turbine runback will automatically

decrease the maximum power to less than or equal to 70% rated power."

The test procedure does not test the runback feature.

The runback

feature has been deleted from the facility. It only tests the rod

drop alarm.

The test results were reviewed and approved by the

licensee, which leads to questions as to the quality of review and

the comparison of results to acceptance criteria. In many of the

procedures the acceptance criteria are only listed in Section 3 and

not restated where the measurement or comparison is made.

The in-

spector believes some improvement can be achieved by restating the

acceptance criteria where the measurement is made.

This was discussed

with the licensee.

12.

Unresolved Items

  • Unresolved Items are matters about which more information is required

in order to ascertain whether they are acceptable items, Items of

Noncompliance, or Deviations.

Unresolved Items are disclosed during

the inspection as discussed in Paragraphs 6, 7 and 10.

13.

Exit Interview

The inspectors met with licensee representatives (denoted in

Paragraph 1) at the conclusion of the inspection on October 30,

1979.

The inspectors summarized the purpose and the scope of the

inspection and the findings.

- 13 -