UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION Ill
Docket No. 50-255
Consumers Power Company
ATTN:
Mr. R. B. DeWitt
Vice President
Nuclear Operations
212 West Michigan Avenue
Jackson, MI
49201
Gentlemen:
799 ROOSEVELT ROAD
GLEN ELLYN, ILLINOIS60137
i_0 r.i .,
1980
This refers to the inspection conducted by Mr. K. R. Baker of this. office
on October 22-26, 29 and 30, 1979, of activities at Palisades Nuclear
Generating Plant authorized by NRC Operating License No. DPR-20 and to
the discussion of our findings with yourself, Mr. J. G. Lewis and others
of your staff at the conclusion of the inspection.
The enclosed copy of our inspection report identifies areas examined
during the inspection.
Within these areas, the inspection consisted of
a selective examination of procedures and representative records, obser-
vations, and interviews with personnel.
During this inspection, certain of your activities appeared to be in non-
compliance with NRC requirements, as described in the enclosed Appendix A.
This notice is sent to you pursuant to the provisions of Section 2.201 of
the NRC's "Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office within twenty days of
your receipt:of this notice a written statement or explanation in reply,
including for each item of noncompliance: (1) corrective action taken and
the results achieved; (2) corrective action to be taken to avoid further
noncompliance; and (3) the date when full compliance will be achieved.
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter, the
enclosures, and your response to this letter will be placed in the NRC's
Public Document Room, except as follows.
If the enclosures contain in-
formation that you or your contractors believe to be proprietary, you
must apply in writing to this office, within twenty days of your receipt
of this letter, to withhold such information from public disclosure.
The
application must include a full statement of the reasons for which the
Consumer Power Company
- 2 -
JAN 2
1980
information is considered proprietary, and should be prepared so that
proprietary information identified in the application is contained in an
enclosure to the application.
We will gladly discuss any questions you have concerning this inspection.
Enclosure:
IE Inspection
Report No. 50-255/79-20
cc w/encl:
Mr. J. G. Lewis,
Manager
Central Files
Reproduction Unit NRC 20b
Local PDR
Ronald Callen, Michigan Public
Service Commission
Myron M. Cherry, Chicago
RIII
'7/,.
-;;,ii.A 'itJ
Yake;°/jp
"~ter
12/10/79
Sincerely,
. F. Heishman, Chief
Reactor Operations and
Nuclear Support Branch