ML18036A754
| ML18036A754 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 06/17/1992 |
| From: | Breslau B, Julian C NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18036A752 | List: |
| References | |
| 50-259-92-15, 50-260-92-15, 50-296-92-15, NUDOCS 9207010346 | |
| Download: ML18036A754 (50) | |
See also: IR 05000259/1992015
Text
~p,R AE0II,
(4
0
Cy
I
0O
w+ +**++
UNITEDSTATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETTASTREET, N.IN.
ATLANTA,GEORGIA 30323
Report Nos.: 50-259/92-15,
50-260/92-15,
and 50-296/92-15
Licensee:
Valley Authority
6N 38A Lookout Place
1101 Harket Street
Chattanooga,
TN
37402-2801
\\
Docket Nos.:
50-259,
50-260,
and 50-296
License Nos.:
and
Facility Name:
Browns Ferry Units 1, 2,
and
3
. Inspection
Dates: April 20-24,
Hay 4-8,
and Hay 18-22,
1992
Inspectors:
. Breslau,
Team Leader
Team Hembers:
P. Fillion
G. HacDonald
E. Christnot
S. Rudisail
Da e Signed
NRC Consultants:
F. Nuzzo,
AECL
B. Pendelbury,
AECL
G. Skinner,
AECL
A. Gibson, Director, Division of Reactor Safety
C. Julian, Chief, Engineering
Branch
C. Patterson,
Senior,
Resident
Inspector
H. Shymlock, Chief, Plant Systems
Section
J. Williams, Project Hanager,
ate S'gned
Approved by:
C.
u ian, Chief
Engineering
Branch
Division of Reactor Safety
Accompanying
NRC Representatives
Hay 21-22,
1992:
SUHMARY
Scope:
This Special
announced
inspection
was conducted
in the areas of design of
electrical
systems
and related engineering
and maintenance activities.
NRC
Temporary Instruction 2515/107,
"Electrical Distribution System Functional
Inspection
(EDSFI)", issued
October 9,
1990, provided guidance for the
inspection.
920701034b
920bi8
ADOCK 05000259
8
Results:
In the areas
inspected,
one violation was identified.
The violation involved
failure to have
an adequate
procedure for setting the Unit Station Service
Transformer tap setting switch (paragraph 2.2.1.2).
A summary of team findings is provided in Appendix A and will be identified as
Inspector
Fol 1 ow-up Item'IFI) 50-259,260,296/92-15-02.
TABLE OF
CONTENTS
PAGE
EXECUTIVE SUMMARY................................=.......................
1 .0
INTRODUCTION..........................................4...........
2.0
ELECTRICAL SYSTEMS......................................
2.0. 1
EDS Description.............................
2.0.2
EDS Review..................................
Concluslonsooooooo
~ .oo...oo.ooooooo...
~ ....oo.oo.o
0ffsite power.....................................
2.2. 1 Degraded
Grid Voltage Protection............
2.2. 1. 1 Calculations for Bus Voltage During
Sequencing.'.....................
2.2. 1.2 Procedures for Setting
The
USST Load
Changer Selector Switch.........
2.2. 1.3 Surveillance Instructions for Calibr
the Degraded
Voltage Relays.....
2.2. 1.4 Available Equipment Terminal Voltage
Degraded
Grid Conditions........
2.3
Medium Voltage and Safety Related
480 Volt Systems
2.3. 1'Short Circuit Calculations..................
2.3.2 Containment Electrical Penetrations...
.. ..
2.3.2. 1 Continuous Loading............ .....
2.3.2.2 Short Circuit Loading...............
2.3.2.3 Protective
Device Coordination......
2.3.3
Medium Voltage Protection
and Coordination..
2 .3.4 480 VAC.....................................
2.3.4. 1 Short Circuit Anal'ysis....
. .......
2.3.4.2 Protective
Device Coordination......
2.3.4.3
Load Voltages.......................
2.3.4.4
Ground Fault Detection System.......
2.3.5 120/208 VAC.................................
2.3.5. 1 Short Circuit Analysis..............
'2.3.5.2 Protective
Device Coordination......
2.3.5.3
Load Voltages.......................
2.4
Emergency Diesel
Generators. r.....................
2.4. 1 Static Loading Analysis.....................
2.4.2 Dynamic Loading Analysis....................
2.4.3
DG Protection
and Controls..................
2 .5
DC Systems........................................
2.5. 1 Short Circuit Analysis......................
2.5.1.1
250 VDC.........................
2.5. 1. 2 '125 VDC..............................
2.5.2 Batteries
and Battery Charger...............
2.5.2.1
250 VDC.............................
2 ~ 5 ~ 2 ~ 2 125
VDC ~
~ o ~
~
~
~
~
~
~
~ ~ ~ ~
~ ~
~
~
~
~
~
~ ~
~
~ o
~
~
~
2.5o3 Protection
Device Coordination..............
2 ~ 5 ~ 3 ~ 1 250
VDC ~
~ ~
~
~
~
~
~ ~
~ ~
~
~ ~
~
~
~ ~
~
~
~
~ ~
~
~
~
'
~
~
2 ~ 5 ~ 3 ~ 2 125
VDC ~ ~
~
~ ~
~
~ o
~
~
~
~ ~ ~
~ ~
~
~
~ ~ ~
~
~
~
~
~
~ ~
~
2.5.4
Load Voltages...............................
2.5.4. 1 250 VDC.............................
CA
~
~ ~
~
~
Load
~
~
~
~ \\ ~
ap
~
~
~
~
~
~ o
~
~
ation of
~
~ ~
~
Unde
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~
~ ~
~
~
~
~
~
~
~
~
~
~
~
~ ~ ~
~ ~ ~
~
~
~
1
1
2
3
3
3
3
4
5
5
5
5
6
6
6
7
7
7
8
8
9
9
9
10
10
10ll
11llll
12
13
13
13
14
15
15
15
15
15
2.5.4.2
125 VDC.......................................
16
2.5.4.3
DC Systems
Ground Fault Protection............
17
3.0
HECHANICAL SYSTEHS....................................
3..1
Concl usi ons
~
~
~
~ ~
~
~ ~ ~ ~
~ ~ ~ ~
~
~ ~ ~ ~ ~ ~ ~
~ 'o ~
~ ~
~ ~
~
~ ~ ~
~ ~
~
~
~
3.
M ~
'l
I
D ~
.2
Diesel Loading...................................
3.3
Diesel Air Start System....'..'....................
3.4
Jacket
Cooling System............................
3.5
Emergency
Equipment Cooling Mater System.........
3.6
Diesel Oil System........................-.......
3.7
Heating Ventilation and Air Conditioning........
3.7. 1 Diesel Generator
Room Ventilation.........
3.7.2 Tornado Generated
Missile Strike and Depre
protection................................
3.7.3
DG Room Battery
Fume Hood.................
3.7.4 Battery
Rooms
152 Ventilation Requirements
3.7.5 Diesel
Engine Intake
and Exhaust Piping An
~
~
~
~ ~
~ ~ ~
~
~
~
~ ~
~
~
~
~ ~
~ ~
~
~ t
~
1( ~
~
~ ~
~ ~
~
~
~
~
~
ssurizati
~
~
~
~
~ ~
~
~
~
~
~
~
~
~
~
~ ~
~
~
~
~
~
~
~
0
~
~
alySl S ~
~
~
...
17'7
18
18,
19
19
...
20
...
20
...
20
on...
21
...
21
...
21
...
21
4.0
HAINTENANCE, TESTING,
CALIBRATION, AND CONFIGURATION CONTROL
.1
Conclusions...........................................
4.2
Equipment Walkthroughs................................
4.3
Equipment Haintenance,
Testing,
and Calibration.......
4.4
Preventative
Haintenance...
...
22
...
22
...
23
...
25
...'6
5.0
ENGINEERING AND TECHNICAL SUPPORT............
5.1
Conclusions............................
5.2
Organization
and Staff.................
5.3
Haintenance
and Operations Support.....
5.4
Problem Identification and Resolution..
5.5
Hodifications..........................
~
~
~
~
~
~
~ ~
~
~ t
~
~
~
~
~
~
~
26
...
27
...
27
...
27
...
28
...
28
6.0
EXIT HEETING............................................-.........
229
Appendix A: Findings
Appendix B: Acronyms
and Abbreviations
Appendix C: Persons
Contacted
EXECUTIVE SUMMARY
A Nuclear Regulatory
Commission
(NRC) team conducted
an Electrical
Distribution System Functional
Inspection
(EDSFI) at the Browns Ferry nuclear
station.
This inspection
was performed
by Region II staff and consultants
from April 20 to May 22,
1992.
The objective of this inspection
was to assess
the capability of the
EDS to perform its intended functions during all plant
operating
and accident conditions.
A secondary
objective was to assess
the
performance of the licensee's
engineering
and technical
support groups in
activities related to the design,
maintenance
and operability of the
EDS.
The team's
inspection
addressed
design, calibration, maintenance,
and the "as
installed" configuration of the
EDS including associated
mechanical
systems
and equipment.
The areas
inspected
by the .team were the 500
kV and
161
kV
transmission
systems
and switchyard; the 500- to 20.7-kV and 20.7- to 4.16kV
unit station service transformers;
the 161- to 4. 16
kV common station service
transformers;
the 480
V system;
the 250/125
VDC systems;
and the
120
VAC
instrument
buses.
Mechanical
systems
included electrical
equipment
rooms,
HVAC, the emergency diesel
generators,
and support 'systems.
The team's
conclusions
and findings for the systems
and, areas
inspected
are
summarized
in
the following paragraphs.
The team concluded that offsite power
was flexible and reliable
and that the
onsite
EDS was generally in compliance with the TS/FSAR/SER.
Design
documentation
including calculations
and analyses
were available
and
retrievable.
The design
was supported
by a knowledgeable
team
and
a
comprehensive
set of calculations.
However,
a few calculations
contained
errors or omissions,
but these
were considered
exceptions
to an otherwise
good
quality calculation program.
In addition, the team noted that
some procedures
relative to the operation
and surveillance of the
EDS could have resulted
in
unanalyzed
or undesired
operating conditions.
A violation was identified in
this area.
Design of mechanical
systems
supporting the
EDS was adequate.
However, the
air start
system relied
on
a single check valve as
a pressure
boundary for the
safety related portion.
The licensee
had independently identified the
weakness
and initiated
a revision to their Surveillance Instruction.
In the area of seismic qualification, the air receivers
in the
DG air start
system were not formally qualified to sustain
seismic events.
Even though the
EECW was adequately
protected
from external flooding events,
the dewatering
pump and the grating at the top of the concrete
were not qualified.
Also
the
DG Room Battery
Fume
Hood was not seismically qualified.
However, all
support
systems
came under
NRC Unresolved Safety Issues
A-46.
Several
undocumented
assumptions,
inconsistencies
and reference
errors
were
noted in the calculation that determined
hydrogen concentration
in Battery
Rooms
1
& 2.
The licensee
revised the calculation;
a review of the
preliminary calculation indicated that the ventilation was adequate.
In the area of configuration control, the team identified several
discrepancies
between the "as installed" molded case circuit breakers
and the
design drawings.
The team noted
a potential configuration control problem
with br'eaker
change
out in the 480
V shutdown boards.
The licensee identified-
two non IE General Electric type AK circuit breakers
located in 1E shutdown
boards.
A,problem evaluation report
had already
been issued.
Several
instances
were noted of improperly terminated
spare wiring in the
250
VDC RNOV boards
and in several
main bank battery chargers.
Additionally, two
SDB battery charger
disconnect
switches
were incorrectly left in the "on"
position.
Two drawing discrepancies
were noted in the thermal
overload
setting drawings.
The team noted
a weakness
in the fuse control program
regarding fuse labelling.
The licensee initiated corrective actions.
Walkthrough inspections
determined that the material condition of the plant
equipment
was good.
However, cracked
thermal 'overload relays were found in
the 480
V and
250
VDC RNOV boards
and
a cracked
fuse block was found in a 480
V RMOV board.
Additionally the
SDB battery
C had
a degraded intercell jumper
cable.
The licensee initiated corrective actions.
Housekeeping
was generally
good in the switchgear,
motor control centers
and
electrical cabinets.
The equipment
was clean
and properly maintained.
An
exception
was battery board
2 where several
examples of poor housekeeping
and
excessive dirt were noted.
In the area of preventive
maintenance,
the team noted that the bus insulation
on the
4 kV shutdown
boards
was not being inspected.
.The licensee
was
utilizing thermography for checking
bus connections,
and this was identified
as
a strength.
The team noted that the maintenance
records
and procedures
for
4
kV and 480
V switchgear maintenance
were adequate.
Protective relays were being calibrated
on
a scheduled
basis.
In the area of
testing
and surveillance the team noted that the licensee
had implemented
an
adequate
program for testing molded case circuit breakers
which encompassed
all safety related breakers.
Battery discharge tests
revealed that several
batteries
were nearly at the
replacement
point.
The licensee
indicated that they had design
change
packages
to replace
many of the batteries
during the upcoming refueling
outage.
A procedure
inconsistency
in battery post terminal torque
requirements
was noted in the
DG battery discharge test procedure.
In the area of testing
and surveillance for the
DGs, the team found these
functions were adequately
accomplished.
Maintenance
and operations
support
was adequate.
The System -Engineering
group
in particular was cognizant of system
and component function and performance.
The group provided strong support for EDS activities
and involvement in
problem identification and resolution
was good.
Planned modification
activities were appropriately controlled
and documented.
In general,
responses
and proposed corrective actions
were appropriate.
1.0
INTRODUCTION
'revious inspections
o'f nuclear
power plants
by NRC teams,
and various
LERs have identified conditions in the
EDS at various operating
plants
that could compromise the design safety margins of the. plants.
This
resulted, .in part, from a lack of proper engineering
and technical
support,
which resulted in the introduction of various design
deficiencies during the initial design or subsequent
design
modifications of the station
EDS.
Examples of some of these
deficiencies
were unmonitored
and uncontrolled load growth on s'afety-
related
buses,
inadequate
modifications, technically inadequate
calculations,
incorrect facility configuration,
inadequate
testing,
improper application of, commercial
grade
components,
lack of fuse
control,
and improperly installed electrical
connections.
The primary objective of this inspection
was to assess
the capability of
the Browns Ferry
EDS to perform its intended functions during plant
operating
and accident conditions.
A secondary
objective
was to assess
the capability 'and performance of the licensee's
engineering
organization in providing engineering
and technical
support to'DS
activities.
The team reviewed the Browns Ferry
EDS design with respect to regulatory
requirements,
licensing
commitments
and pertinent industry standards.
The
EDS components
reviewed included the 500
kV and
161
kV transmission
system
and switchyard; the 20.7
kV system;
4. 16
kV system;
the 480
VAC
system;
the 250/125
VDC systems;
and the
120
VAC instrument
buses.
- Mechanical
systems
reviewed included electrical
equipment rooms'VAC,
~the emergency diesel
generators,
and support
systems.
Within this report
FINDINGS are identified and are defined
as follows:
FINDINGS are facts or conclusions related to how well the electrical
distribution system meets its intended function.
FINDINGS may indicate
a requirement
or an accepted
industry practice that was not fully
implemented.
FINDINGS may indicate discrepancies
or omi'ssions
in
documents
where these
problems
could credibly result in the intended
functions being compromised.
The licensee's
working knowledge of the
design
as well as their control of design
documents
may be the subjects
of FINDINGS.
'FINDINGS typically make statements
about the need for
corrective actions.
2.0
ELECTRICAL SYSTEMS
2.0. 1
EDS Description
The Browns Ferry Nuclear Station
was connected
to the transmission
system through
seven lines serving the
500
kV switchyard
and two lines
serving the -161
kV switchyard.
Power was supplied to Units
1 and
2
through several
shared
components
and systems.
During normal operation,
auxiliary loads were supplied
by the main generators
through four. USSTs,
two per unit, which in turn power six 4 kV Unit Boards
and two 4
kV
Recirculation
Pump Boards.
ESF loads of both units were supplied from
two shared
4 kV shutdown
busses.
The normal supply for Shutdown
Bus
1
was the
X winding of USST
1B via Unit Board lA.. The normal supply for
Shutdown
Bus
2 was the
X winding of USST 2B via Unit Board
2A.
The
1B
and'B transformers
were equipped with load tap changers
to regulate
voltage
on the shutdown busses.'ach
shutdown
bus supplied two 4 kV
Shutdown Boards,
designated
A,B,C, and D, from which all
4 kV and 480
VAC ESF loads were supplied.
Each of the four shutdown
boards
were
provided with emergency
standby
power from its own diesel
generator set.
The Unit 3 auxiliary power system
was similar to that described for
Units
1 and
2 with interties to the other units at several
levels in the
distribution system.
Unit 3 was served
by an additional four diesel
generators
which were relied upon for Unit 2 shutdown
under certain
circumstances.
A number of 480
VAC SDBs had
been provided to supply essential
motor
loads,
feeders to HCCs,
and to
MG sets.
480
VAC RHOV boards
2A,2B, and
2C were supplied directly from SDB whereas
RMOV boards
2D and
2E were
supplied via
HG sets
which existed to prevent propagation of a fault to
a SDB.
Transfer of power to an alternate
source
was performed manually
except that for the
HG sets,
transfer from normal to alternate
sources
was automatic, with a'manual
reset.
Additiona'l loads were carried
by
480
VAC diesel auxiliary boards
A and
B for Units
1 and 2,
and
3A and
3B
for Unit 3.
The 480
VAC systems
were ungrounded
and ground detection
equipment
was provided at each
SDB.
Unit
1 and
3
SDB were similar to
those in Unit 2.
The 480
VAC SDB provided power to two safety related
120
VAC systems
via
the
IEC and the
RPS systems.
The former was to provide two independent
class
1E sources of power for each unit to the vital IECs,
and the
latter, through
HG sets,
provided two independent
power sources for the
operation of neutron instrumentation
and solenoid valves for scram
initiation.
To support the operation of the 480
VAC auxiliary system,
three safety
related
250
VDC battery systems
were provided
on a plant basis with five
250, VDC safety related battery systems
associated
with the
4 kV and 480
VAC SDB.
Each of the eight
DG had its own 125
VDC battery system for
essential
starting
and running loads,
each battery having its own
battery charger
and instrumentation
monitoring the status of the system,
including ground fault detection
equipment.
2.0.2
EDS Review
The team reviewed the offsite-power sources
feeding the safety related
ESF busses,
to determine availability of offsite power.
The team also
reviewed the
4
kV ESF system to ensure that electrical
power of
acceptable
voltage, current,
and frequency would be available to
equipment supplied
by the
EDS.
Additionally, the
Emergency Diesel
Generators
were reviewed to assess
both their steady state
and transient
loading capabilities.
Review of the 480
VAC auxiliary system consisted of load center
switchboard
SDB 2B and
HCC switchgear
fNOV Boards
2D and 2E; due to the
interrelationship
between the boards,
the review included parts of other
, boards.
Factors
such
as available short circuit currents,
equipment
capacity,
coordination of protective equipment,
and voltages at the
loads were examined.
Compliance with GDC 17 and the single failure
criterion,
and conformance with separation
requirements
were also
factors considered
by the team.
At the
120
VAC level, only class
1E systems
were considered.
For the
system only the 250 and
125
VDC class
lE subsystems
were included, with
the 48 and
24
VDC subsystems
being excluded
from the review.
In all
cases,
the factors outlined above were examined to ensure
adequacy
.of
'design.
2.1
Conclusions
The team concluded that the offsite power was flexible and reliable
and
that the
EDS was generally in compliance with the TS/FSAR/SER.
Design
documentation
including calculations
and analyses
were available
and
, retrievable.
These
documents
demonstrated
that equipment
and systems
were appropriately selected
and applied
so that the
EDS was capable of
providing adequate
power to essential
loads.
The design
was supported
by a knowledgeable
team
and
a comprehensive
set of calculations.
However,
a few calculations
contained errors or omissions,
but these
were considered
exceptions
to an otherwise
good quality calculation
program.
In addition, the team noted that
some procedures
relative to
the operation
and surveillance of the
EDS could have resulted
in
unanalyzed
or undesired
operating conditions
as noted below..
2.2
Offsite Power
2.2. 1
Degraded
Grid Voltage Protection
The, team noted the following problems in calculations
and procedures
relating to Degraded
Grid Voltage Protection.
/
2.2. 1. 1
Calculations for Bus Voltage During
LOCA Load Sequencing
Calculation
ED-Q2000-870026,
"4. 16 kV and 480
V Busload
and Voltage Drop
Calculations with Offsite Power", Revision 9, did not contain sufficient
data to determine that the relay would reset following voltage dips.
In
response,
the licensee
provided additional
computer runs which enabled
th t
t
'fyp
p
p
ti
fthm
ly. ~SA
d'
Findin
1
2.2.1.2
Procedures
for setting the
USST Load Tap Changer Selector,
Switch
Instructions in SOP 6055
and 0-GOI-3001 for setting the
USST tap changer
selector switch did not require the switch to be set to monitor the
winding supplying the shutdown
bus.
This was
an operating constraint
identified in calculation
ED-f2000-870026,
"4. 16kV and Busload
and
Voltage Drop Calculations with Offsite Power", Revision 9.
The
calculation demonstrated
that adequate
safety system operation
was only
possible
when the load tap changer selector switch was monitoring the
.
winding supplying the Shutdown Board.'owever,
SOP 6055
and 0-GOl-3001
collectively specified that the most heavily loaded winding shoul'd
be
monitored,
which could be the winding supplying non-essential
loads.
If the tap changer control
was not monitoring the winding supplying the
SDB when
a
LOCA occurs,
the tap changer
would not properly respond to
the voltage drops resulting from LOCA load. sequencing.
This could
result in actuation of the undervoltage
protection
scheme
which would
isolate the preferred (offsite) source
from the SDBs.
A walkthrough of
the control
room revealed that the selector switch for USST
1B was
actually set to monitor the winding not supplying the shutdown
bus.
In
response,
the licensee
revised the procedure to require that the
selector
switch be set to monitor the winding supplying the shutdown
bus.
This item is identified as
VIO 50-259
260 296 92-15-01.
2.2. 1.3
Surveillance Instructions for Calibration of the Degraded
Voltage Relays
The acceptance
criteria in Surveillance Instruction 3-SI-4;4.A.4.c(I),
Revision
1, did not reflect the
26
V tolerance
determined
in calculation
ED-(2211-890144,
"Setpoint
and Scaling Calculations
4 kV Bus Degraded
Voltage Relays
(ITE 27N)", Revision 4,
as follows:
Instructions
allowed the relay reset voltage to be left as high as
3987.7
V, which would permit drift above the
TS limit of 3999 V.
Instructions did not provide
a lower limit for the reset voltage.
The limit could have
been set close to the dropout value.
This
would permit convergence
of the dropout
and reset
due to setpoint
drift.
Instructions
allowed the dropout voltage to be left as low as
3911.25
V, which would permit drift below the
TS allowable limit
of 3900 V.
In response,
the licensee
revised the setpoint calculation
and
surveillance instruction to assure that the settings
would not allow
drift outside
TS allowable values.
See
A
endix A
Findin
2
2.2.1.4
Available Equipment Terminal Voltage=Under Degraded
Grid
Conditions
Calculation
ED-(2000-870027,
"460
V Class
1E Motors and Equipment Volt
Drop", Revision 3, demonstrated
that two motors did not have the minimum
required terminal voltage of 414
V (90% of 460 V) stated in section
8.4.8. 1.4 of the
FSAR.
In response,
the licensee
included the necessary
corrections to their next
FSAR submittal to allow departures
from the
90% criteria.
See
A
endix A
Findin
3
In the cases
noted
above,
the calculation, relied on equipment design
margins to justify voltage below manufacturer's
recommended
minimums
rather than removing
known conservatism
or correcting circuit
deficiencies.
In addition, the justification'id not evaluate
the
ff
f
1
d
t t
d
d
tt'g .~gg
df
A
Findin
4
The team also noted the following items relative to degraded grid
voltage calculations:
Bus voltages
used in calculation
ED-(2000-870027
used to calculate
equipment terminal voltages
were not correct in some cases..
Calculation
ED-(2211-890144 incorrectly concluded that two
Degraded
Voltage Relays would not drift in the negative direction
simultaneously.
Calculation
ED-(2211-890144
used
an incorrect value for minimum
steady state voltage.
Calculation
ED-(2211-890144 incorrectly concluded that degraded
voltage relay dropout
and reset
would always drift in the
same
direction.
The team determined that these
anomalies
did not have
a significant
adverse effect on the results of the calculations
and the licensee
corrected
them during the inspection.
See
A
endix A
Findin
4
2.3
Medium Voltage and Safety Related
480 Volt Systems
2.3. 1
Short Circuit Calculations
The team reviewed calculation ED-(2000-87-0029,."4
kV Short Circuit
Calculation", Revision 5,
and determined that equipment
was adequately
sized for existing fault duties.
Ratings for medium voltage switchgear
provided adequate
margin of 5.6% over interrupting fault duty and
2.2%
over momentary fault duty.
2.3.2
Containment Electrical Penetrations
2.3.2. 1
Continuous
Loading
The team reviewed in particular, penetrations
where the heat loadings
exceeded
the
recommended
values of IEEE 317-1983.
In the case of
EB and
EE, test data from the Conax Corporation indicated
that
a loading of 54 watts/foot
had
been
achieved
where the measured
temperature
at the steel/concrete
interface
had not exceeded
150 degrees
F.
In the case of penetrations
EA and
EF,
a document
from the G.E.
Company indicated that
a value of 56 watts/foot could be used
as
an
upper limit in the allocation of current to the conductors.
In all
cases,
the calculated current loading was found to be less than these
limits.
For all other penetrations
the, heat loading was well below the value of
30 watts/foot
and the team concluded that all penetrations
were
adequately
designed
and that circuit currents
had
been
chosen
conservatively.
2.3.2.2
Short Circuit Loading
I
The team noted that short circuit currents
as calculated at the various
were based
on the conservative
assumption that
a bolted
fault would occur
on the containment
side of the penetration,
of a
magnitude
based
on the maximum current available at the beginning of the
circuit under consideration,
and modified to take into account the
effect of extra
impedance of the feeder cables
from the nearest
bus to
the penetration.
The penetration
conductor insulation was rated at 90
degrees
C. continuous
and
an increase to 250 degrees
C. was allowed on
'hort
circuit of the conductor.
Values of I't used in the calculations
for the design of the penetrations
were the
same
as given in table
A5 of
standard
and in no case
were these
values
exceeded.
The
team, therefore,
concluded that the penetrations
were adequate
to
withstand the thermal effects of a short circuit current.
Both calculations
considered
only the heating effect's of short circuit
and continuous currents,
but not the mechanical
strength of the
penetr ations subject to the electromagnetic
effects of short circuit
currents
in the conductors.
This subject
was discussed
with the
licensee
and details of the high energy penetrations
containing
1000
HCH
conductors
were sought.
The licensee
produced
a notarized partial test
report dated April 23,
1970, indicating that short circuit tests of the
P.S.L. penetrations
(Type AA-AF) had
been
conducted
up to a peak value
of 35 kA, compared with a maximum available current of 3500 amperes
symmetrical.
The team concluded that the penetrations
would not incur
mechanical
damage
from the effects of short circuit currents flowing in
the penetration
conductors.
2.3.2.3
The team reviewed the suitability of circuit breakers
and fuses. in
protecting the conductors of the electrical penetrations
against
the
effects of sustained
overloads or of short circuits;
and found that all
conductors
wer'e adequately
protected
from damaging effects
by the
primary protective device.
2.3.3
Hedium Voltage Protection
and Coordination
The team reviewed calculation
ED-(2000-870548,
"Cable
and
Bus
Protection/Breaker
Coordination
For
4 kV Switchgear
and 480
V Load
Centers",, Revision
10, which determined
medium voltage relay settings.
The calculation demonstrated
appropriate
equipment protection
and
coordination of protective devices.
2.3.4
480
VAC
2.3.4. 1
Short Circuit Analysis
The short circuit currents potentially available in the Unit 2 480
V
system
are derived in calculation
ED-f2000-870030 Revision 4, which
takes
a conservative
approach
using the
MVA method,
and neglecting all
cable
impedances
that would result in lower values of current.
In
addition, the 4160/480 volt transformers
supplying the various
switchgear
boards
were
assumed to supply all induction motor loads of a
magnitude equivalent to the
FA rating of the transformer,
and with short
circuit reactance
values of 0.25 p.u..
The reactance
of a
transformer'hat
was
assumed
to control the short circuit current from the source
was taken
as the minimum of the set of values
determined for that class
of -transformer.
The maximum three
phase
short circuit current,
calculated
at the bus supplied
from a
1
MVA transformer
was 21.9
kA
symmetrical
compared with a circuit breaker interrupting capacity of 22
kA.
The team considered
the basis
and accuracy of the calculation to be
satisfactory.
2.3.4.2
Protective
Device Coordination
Calculation
ED-(2000-870548
Revision 10,
examined the coordination of
the protective devices
and feeder cables to and from the
4 kV switchgear
and the 480
V SDB load centers.
For the motor loads,
the calculation
used.
as
a design basis,
the relationship that the long term setting of
the molded case circuit breakers
had to be greater
than or equal to the
full load cur rent of the motor multiplied by factors
1.28
and 1.39 for
motor service factors of 1.0
and
1. 15 respectively.
The team noted that.
the motor powering the Control
Bay Water Chiller B did not meet this
criterion,
and that operation at the minimum bus voltage of 445
V would
produce
a motor load current that would lie in the tripping region of
the circuit breaker.,
See
A
endix A Findin
5
All other motors, with the exception of three non-lE cases
were
satisfactory
and the long term pickup settings of the circuit breakers
were adequate.
The team examined the coordination curves for all loads
and considered
that coordination
between the board
2B circuit breakers,
the supply feed circuit breakers
from the
4 kV shutdown boards,
and the
outgoing feede'r cables,
were satisfactory.
The team reviewed calculation
ED-(2000-870549
Revision
11,
and in
particular,
the protective devices for the 480
V RMOV boards
2B and
2D,
the Control
Bay Vent Board
B, the -Diesel Auxiliary Board
B, and the
Standby
Gas Treatment
board.
In general,
the load cables
were protected
against
the effects of overcurrents
by the associated circuit breakers,
but in a few cases,
where conformance to the normally accepted
upper
limit on conductor temperature
could not be achieved,
the
licensee'tated
that the conductor insulation would be below the auto-ignition
temperature
of the material.
Extensive
use of "Flamemastic",
a fire
retarding material,
would ensure that fire, if it occurred,
would not
propagate
to conductors of other .loads.
The team accepted this position.
Coordination
between
the circuit breaker
on load center
SDB 2B supplying
circuit breakers
on 480
V RMOV Board 2B; and between
SDB 3A and circuit
breakers
on the Control
Bay Vent Board B; and between
MG sets
2DN,
2DA
and circuit breakers
on
RMOV Board 2D; was also found to be
satisfactory.
In general,
motor overload heater tripping curves
and
motor starting curves
were not shown
on the coordination curves.
However, the team was able to ascertain that overload heate'rs
had
been
selected correctly and that motor starting currents
would not trip the
protective circuit breakers.
2.3.4.3
Load Voltages
The team reviewed calculation
ED-(2000-870027
Revision 6, which examined
the voltages at the 460
V class
1E motors
and other loads
such
as the
Standby
Gas Treatment
and
DG heaters
and battery chargers,
under
degraded grid voltage conditions.
For the worst case voltages at the
480
V busses,
the calculation identified two Unit 3 loads
(Control
Room
Air Handling Unit A and
El 593 Air Handling unit 3A), supplied
from
Control
Bay Vent Board A, which just failed to meet the running voltage
criterion of 0.9 p.u.
In discussions
with the team,
the licensee
stated
that the Board
Room Emergency
Supply
Fan
3B load
had
been mistakenly
included in the calculation
and that the Unit 3 Chilled Water
Pump A,
which also failed the criterion,
was not required for Unit 2 operation.
The team examined,
in particular,
the voltages available at the
SDB
battery chargers
SB-A,B,C,D,
and
3EB for which the input voltages
were
below the manufacturer's
specified figure of 480
V less 7.5/, or 444 V.
The licensee
had performed
a separate
test
on one of the chargers,
indicating that
an output of 266
VDC at
12 amperes
had
been
observed for
an input voltage of 391 V, with a ripple content of less
than the 1.3
volts quoted in the equipment specification.
The minimum bus voltage at
the 480
V RMOV board
1B which supplies this charger,
was calculated
at
438
V giving a charger voltage of 419
VAC, at the
DC output conditions
referred to above.
The team concluded that since =the float voltage
was
260
VDC and the continuous loading on this battery
was
11 amperes,
the
above
low voltage condition would be satisfactory,
though there will
probably
be
no capability of equalizing the battery under this condition
-of degraded
voltage.
However, since this low voltage condition was post
accident,
the team accepted this uncertainty.
All other loads were
considered
acc'eptable
by the team.
2.3.4.4
Ground Fault Detection
System
The 480
V auxiliary system
was ungrounded,
supplied through
1000
KVA
4160/480
V delta-delta
connected
transformers.
Ground fault detection
equipment
was provided
on each
480
V SDB board in the form of three
single
phase
480/120
V transformers
connected
in a wye-wye configuration
with a grounded
secondary
neutral
and supplying loads of one
incandescent
lamp per phase.
A test switch used for connecting the
primary and secondary neutrals,
and protection fuses
per phase
complete
the system.
The test
and indication equipment
were mounted
on each
480
volt SDB board
and
a ground test
was performed
once per shift.
The team raised the question of continuity of monitoring for ground
'faults, with the particular consequence
of maintenance
induced
ground
faults at isolated
loads remaining undetectable
with the existing design
of the ground fault detection-system.
The licensee
stated that the
bridge
and megger testing
was the last activity performed after
completion of maintenance
work, and that any ground faults occurring at
that time would be discovered.
The team reviewed maintenance
instructions
ECI-0-000-HOV001
and ECI-0-000-NOTOOl and considered
the
present
design to be acceptable.
2.3.5
120/208
VAC
2.3.5. 1
Short Circuit Analysis
.
The team reviewed calculation
ED-f2000-870031
Revision
3 in which the
values of short circuit current for the
I&C and the
RPS systems for Unit
2 had
been determined.
The calculation
used
a conservative
approach,
ignoring impedances,
and in accordance
with the standard
used the three phase'olted
fault approach for the grounded neutral
system.
For Unit 1,2 and
3
I&C busses,
the magnitude of the short circuit
current
was found to be 3390 amperes
under normal operating conditions
with the regulating transformer in circuit, and 6980 amperes
with this
transformer
bypassed.
All circuit breakers
in this system
had
an
interrupting rating of 10 kA and the busses
had a.withstand capability
of 25 kA.
For the
RPS system,
the largest short circuit current
was found to be
6670 amperes
when the alternate
feed from the 480/120
VAC regulating
transformer
was used.
All circuit breakers
in this system
had
an
interrupting rating of 10
kA and the busses
had
a withstand capability
of 25 kA.
The team concluded that there were
no problems with the short circuit
ratings of protective equipment in .these
systems.
2.3.5.2
Protective
Device Coordination
Calculation
ED-92000-880086,
Revision 7, examined the coordination
between various protective devices
and cable withstand capabilities for
the
120
VAC I&C and
RPS systems.
Protection of these class
1E circuits
which are required for normal-operation "and
.a safe -shutdown of Unit 2,
had
been considered
in this calculation, together with non-required
loads
powered from 1E sources.
The team ascertained
that all non-class
1E loads were protected
by class
lE circuit breakers.
The team examined the circuit from the 480
V SDB 2B to the 480-120/208
V
3 phase
75 KVA transformer,
hence to the 208-208/120
V 3 phase
50
KVA
regulating transformer
and to the
I&C bus
B of battery board 2, panel
8,
as being typical.
Feeders
to circuit breaker
board 9-9 cabinet
3 of
10
Unit 2; to the alternate
input to circuit, breaker
board 9-9 cabinet
3 of
Unit 3;
and to the non-class
lE battery chargers for the unit 24
VDC
battery system,
completed the circuit.
Adequate coordination existed
between all circuit breakers
in these circuits,
and cable
and
transformer'sizes
had
been
chosen
such that there would be no damage to
these
components prior to clearance
of a fault by the appropriate
circuit breaker.
However, in the case of the
RPS system,
the calculation
showed that
coordination
was not achieved
between the
MG set output generator
circuit breaker
and particular load circuit breakers
mounted in the
bus panel at the battery board.
The calculation offered
an acceptable
solution but stated that this would not 'be implemented prior to the
restart of Unit 2.
The licensee
stated that the change
had not been
installed,
and after further discussions,
the team concluded that this
would not present
a problem in this particular case.
The
MG set itself
was
a non-class
lE component
and suppli'ed
a number of solenoid valves
for scram initiation, together with neutron instrumentation for powe'r
measurements.
Channels
A and
B were provided, with a loss of one
channel
leading to a half scram condition which initiated implementation
of operating
procedure
2-AOI-99-1.
A loss of AC supply to either or
both sets of loads
on one channel
produced the
same effect,
and the'team
concl'uded that the absence
of coordination
was
no worse than the loss of
the non-class
lE
MG set.
2.3.5.3
Load Voltages
'The team reviewed calculation
ED-(2000-870028,
Revision 7, which
determine
the worst case voltage distribution on class
IE systems,
buses,
and the
RPS, during operation
and shutdown of the Unit 2 reactor.
Some
common loads
on the
IKC buses for Units
1 and
3 were required for
Unit 2 and
had
been included.
The team checked
the voltages at the
bus
2A; at the panels 9-15 and
25-5A buses;
at the scram pilot valves;
and at the scram discharge
volume drain
and vent valve, which had
been derived using
a computer
program
VOLTDROP/VD21.
The calculation took a conservative
approach
by
assuming
conductor temperatures
of 60 degrees
C. for current loadings
up
to 8 amperes
and
90. degrees
C. for power conductors;
by taking the
longest conductor lengths
and
maximum current draw;
and with 25/ of
deenergized
loads considered
to be energized.
The maximum load occurred
at bus
2A and was calculated
as ll KVA.
The minimum voltage
was
determined
as 112.5
V at the scram valve solenoids with 0.98 p.u. at the
generator,
and this compares
favorably with a requirement of 102
V
minimum for these valves.
The team found that all loads in the
system were adequately
supplied with voltages at the loads higher than
the minimum required.
2.4
Emergency Diesel
Generators
2.4. 1
Static Loading Analysis
The team reviewed calculation
ED-92000-870071,
Revision 8, which
determined
the loading
on the diesel
generators
during the shutdo'wn of
Unit 2 with a loss of offsite power,
and with or without a concurrent
LOCA.
The team noted that Diesel Generator
A would be loaded in excess
of its continuous rating during the two hour period following a
LOOP/LOCA (2781
kW loading vs.
2600
kW rated).
This loading was below
its
2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating of 2860
kW but the calculation did not analyze loading
after
2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />.
The licensee
stated that it was highly likely that the
loading would be reduced
below the continuous rating within the two hour
limit and that operating
procedures
provided for paralleling additional
diesel
generator
sets to the shutdown
boards during
an emergency.
In
addition, the diesel
generators
have
a short time rating of 2900
kW for
200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br />.
Based
on current plant operating configurations
and the
diversity of onsite
and offsite power sources,
these justifications were
deemed
acceptable.
2.4.2
Dynamic Loading Analysis
A formal dynamic loading analysis
had not been performed.
In lieu of
calculations,
the licensee
had performed extensive transient
load
testing,
including regulator/exciter
and governor calibration.
The
results of these tests
were reported in TVA Memorandum
B22 '89 00117
010,
Browns Ferry Nuclear Plant
(BFN) - Diesel
Generator
Evaluation
Report,
dated January
17,
1989.
The testing adequately
demonstrated
the
ability of DG sets to start
and accelerate
the required
sequenced
loads
following a
LOOP/LOCA.
The team note'd that
a severe voltage dip
(46% of
nominal)
occurred during
RHR Pump motor starting.
This was
demonstrated
to be within 'the capabilities of the diesel
generators
by
the testing,
and was determined
not to have adverse effects
on connected
480
V loads
by calculation
ED-(2082-880557,
"Undervoltage Analysis of
BFN Electrical Auxiliary System During Diesel
Generator
Sequencing",
Revision
1.
However, the team noted that the existing analyses
and testing only
justified starting the
RHR Pump upon closing of the diesel
generator
breaker with n'o other
4 kV loads connected
and
480
V loads in an
initially deenergized
state.
A review of operating
procedures
revealed
that there
was
no prohibition against restarting the
RHR Pump while
other loads were connected
following load sequencing.
In response,
the
licensee
stated that
a revision would be made to the applicable
p
tungi
t
ti
t
dd **th
. ~Adi
A
~Fi di
6
2.4.3
DG Protection
and Controls
The team noted that the alarm response
procedure for a diesel
generator
ground fault annunciation,
O-XA-55-23A, Revision
11,
window
10, did not provide adequate
guidance
as to the possible
causes
of the
12
alarm or corrective actions.
In response,
-the licensee
revised the
procedure to provide appropriate
guidance.
See
A
endix A
Findin
6
2.5
DC Systems
2.5. 1
Short Circuit Analysis
2.5.1.1
250
VDC
The team reviewed calculation
ED-(2000-870045,
Revision 5, which covered
all battery systems.
In general,
the calculations
were conservative
in
assuming
cable temperatures
of 25 degrees
C., circuit breakers
and fuses
and
DC busses
having zero resistance;
and that all battery chargers
and
continuous rated motors would contribute to the fault current.
The team
concu} red with the assumption that the contribution from the
50
motors driving the
120
VAC HG sets
and the Turbine Emergency
Bearing Oil
Pumps would be zero,
because
of the introduction of blocking diodes
preventing
a reverse flow of power into a fault on the
DC system.
In
both cases,
the loads were not considered
to be extreme
and excessive
voltage rise at the motor would not be
a problem.
The calculation
was
based
on
a battery terminal voltage of 2
V per cell
and
an electrolyte temperature of 77 degrees
F.
The team concurred with
the first of these
assumptions,
but the question
was raised of increased
short circuit current at
a higher electrolyte temperature
of 96 degrees
F., which had
been recorded during
a daily check.
The licensee
stated
that
a test
had been
conducted
by TVA in conjunction with other industry
groups.
The results of which indicated that
a rise in electrolyte
temperature
would increase
the capacity of the battery but not the
magnitude of the short circuit current,
and that pre-fault voltage
considerations
would also not affect the magnitude.
A submittal
had
been
made to the
IEEE committee responsible for standard
IEEE 946 to
have these findings incorporated into the next revision.
The calculation'also
considered
the pre-fault voltages at the
DC motors
to be 240
VDC, whereas
the team considered that this voltage would be
closer to the equalizing voltage of the battery of 279 V.
The licensee
agreed
on this point and presented
the team with a revised calculation
which incorporated
the
new motor voltages.
There were no significant
change to the 'conclusions
arrived in the calculation
and the worst case
value of short circuit current remained
below the circuit breaker
and
bus rating of 20 kA.
The short circuit currents
were determined for each safety related
bus
when supplied from appropriate
normal
and alternate
sources,
and
when
supplying the required loads during
a shutdown of Unit 2 and for
maintaining Units
1 and
3 in a cold shutdown (de-fuelled) condition.
A
maximum short circuit current of 18.3
kA was obtained,
at main board
1
as expected,
with smaller currents of 16.3
kA at main boards
2 and 3.
The busways
and associated
circuit breakers
had withstand or
interrupting ratings of 20 kA, and fuses in the system
had interrupting
ratings of 10,
20, or 100 kA.
The team confirmed that all equipment
13
could adequately, withstand or interrupt the short circuit currents
available at each location,
using inputs
as predicated
in the
'alculation.
The team was concerned,
however, that the calculated short circuit
current from'he large 300 ampere battery chargers
connected to the main
battery systems,
had
been determined at the current limit settings of
llOX of full load capacity i.e.
330 amperes.
Since this type of charger
used silicon controlled rectifiers for rectification and control; it had
been postulated that the short circuit output current of the charger
could be up to ten times its full load rating for a period of 8
milliseconds.
The team was informed that this issue
had also
been
presented
to the
IEEE for clarification.
2.5.1.2
125
VDC
Calculation
ED-(2000-870048,
Revision 3,
used the conservative
assumptions
of conductor temperatures
being at
25 degrees
F.
and the
resistance
of DC busses,
circuit breakers
and fuses
being zero
ohms.
All sources of fault current from the batteries,
and battery chargers
operating at
a current limit setting of 150/ of rated output,
were
included.
The maximum short circuit current
was found to be,
as
expected,
at the bus of the largest battery system
(3D) and
had
a value
of 2680 amperes;
well below the withstand rating of the bus of 10 kA,
and the interrupting capacity of associated
circuit breakers
and fuses
of at least
5 kA.
The team considered that the equipment
connected
to
these battery systems
were adequate
to handle
a short circuit on the
system.
The team again raised the issue of short circuit currents
related to electrolyte temperature
(maximum recorded electrolyte
temperature
of 95 degrees
F.),
and considered
that the disposition of
this item will be as for the 250
VDC battery.
2.5.2
Batteries
and Battery Chargers
2.5.2.1
250
VDC
The team checked calculation
ED-(2000-870041,
Revision 8, in which the
sizing of the main plant class
1E batteries
were developed.
The plant
conditions were postulated to be Unit 2 in normal operation with Units
1
and
3 in a col'd shutdown condition (de-fuelled);
and when Unit 2 was
subjected
to a loss of offsite power followed by a
LOCA event.
The
computer
program
BATCALC, an in-house
program employing Lotus 123,
was
used to size both the batteries
and battery chargers.
The team noted
that the calculation modelled motor starting loads
as constant
resistance
loads
and motor running loads
as constant
power loads; .that
motor operated
valves were modelled
as
an inrush current for 2 seconds
followed by
a running current for one minute;
and that
pump motors
reached their operating
speed
in 5 seconds.
The team considered
the
assumptions
to be acceptable.
14
The calculation
used the method of sizing, batteries
described
in IEEE 485-1983,
and included
a temperature
correction factor of 1.1
(60
degrees
F.),
and
an aging factor of 1.25.
The maximum demand
on battery
1 system
was with battery
3 out of service
and
on battery
3 system with
battery
2 out of service.
The selection of 16 positive plates/cell for
battery
1 and
14 positive plates/cell for batteries
2 and
3 gave
'apacity
margins of 48,36,
and 23K respectively for batteries
1,2,
and
3;
The minimum voltage of the batteries
was found to be 214.8
VDC- for
battery
3 with battery
2 out of service
compared with a committed value
of 210
VDC given in the
FSAR.
For the battery chargers,
the method given in IEEE 946-1985
was used
resulting in a requirement for a 300 amperes'harger
with a battery
recharging time of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />
and
no margin in the worst case of battery
3
with battery
2 out of service.
The team concurred with these
findings.'he
sizing of the 250
VDC control
power batteries
SB-A,B,C,D,
and
3EB
were handled in calculation
ED-Q2000-870042,
Revision 4, along with the
sizing of the battery chargers.
Again the team concurred
with the
methods
used in the calculation,
and the findings of a capacity margin
of 18/ for battery
SB-3EB and
155 for the remainder,
together with a
margin of 71% for the sizing of the
20 amperes
battery charger.
The
minimum voltage of the batteries
was found to be 214.8
VDC for battery
SB-A compared with a committed value of 210
VDC given in the
FSAR.
2.5.2.2
125
VDC
The sizing of the
DG class
lE batteries
was handled in calculation
ED-
Q2000-870046,
Revision 4, which examined
two duty cycles of.30 minutes
each,
one with two attempted starts of the diesel
generator
followed by
a successful
start at the beginning of the cycle,
and the other in which
the attempted
plus successful
starts fall at the end of the duty cycle.
In each
case,
the sta'rting of the
DG was enveloped
by a
1 minute supply
of starting current with a small continuous current for the remainder of
the period.
The number of attempted starts
was considered
by the team
to be conservative
when related to the
TS requirements for DG starts.
Also conservative,
was the assumption of a minimum electrolyte
temperature
of 40 degrees
F. since
a check of historical data over the
past
5 years
showed
a minimum measured electrolyte temperature
of 60
degrees
F.
The calculation
used the method of sizing batteries
described
in IEEE 485-1983,
including temperature
correction factors of
1.3
(40 degrees
F.),
and
an aging factor of 1.25.
The choice of 4
positive plates/cell for the
100 A-H battery,
gave
a margin of 4.4X over
the required capacity after the correction factors
had been included.
In a similar manner,
the choice of 3 positive plates/cell for the
240 A- .
H battery gave
a margin of 871. over the required capacity.
The team
found the calculation to be accurate
and the battery sizing acceptable.
The minimum voltages for the
100 and
240 A-H batteries
were calculated
to be 105.7
V and 110;8
VDC respectively at
an electrolyte temperature
of 40 degrees
F.
and for old batteries,
which compares
favorably.-with an
FSAR commitment of 105 VDC.
15
For the battery chargers,
the method given in IEEE 946-1985
had
been
used -in the calculation to size the battery chargers,
using
a
5 amperes
continuous
load and
a time to re-charge of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
Based
on the fact
that the batteries
were not substantially discharged
during the duty
cycl'e,'
charger size of 20 amperes
was considered
by the team to be
acceptable.
2.5.3
Protective
Device Coordination
2.5.3.1
250
VDC
The team checked calculation
ED-(2000-870550,
Revision 7, which examined
the coordination of the protective circuit breakers
and fuses,
and the
feeder
cable sizes.
Coordination
between the various
bus circuit
breakers
and fuses
were found to be acceptable,
as were the feeder cable
'sizes,
with the exception of a few conductors,
sized
14 to 10
AWG, for
which the cable
damage
curves intersected
the circuit breaker operation
curves.
On discussing this point with the licensee,
the team
was told
that these
cables
were acceptable
under the
10 CFR 50 Appendix
R
requirements,
which allowed greater conductor temperatures
on short
circuit than the
150 and
250 degrees
C. considered
as industry accepted
figures.
The'team
found that the cables
had
been
sprayed with
"Flamemastic",
a thermoplastic resin, containing flame retarding
chemicals
and inorganic incombustible fibers,
and that fire damage, if
created,
would be confined to
a particular cable.
On this basis,
the
team accepted
the calculation.
2.5.3.2
-
125
VDC
The team reviewed calculation
ED-(2000-880085,
Revision 3, which
examined the coordination of the protective devices in the
DG battery
systems
A-D and 3A-3D.
Fuses
were used as-protective
devices at the
higher current levels.
The team found that coordination
had
been
achieved
between the various circuit breakers
and fuses
and that
conductors
supplying the various loads were protected
from possible
overcurrent situations.
I
2.5.4
Load Voltages
2.5.4.1
250
VDC
The team reviewed the minimum and maximum voltages at all the loads
on
the
250
VDC systems,.-and
in particular at the 250 -VDC RMOV.boards
2A,2B,
and
2C; the
4 kV SDB A,B,C,
and
D; the 480
V SDB lA,1B,2A,
and
2B; the
4
kV cooling tower switchgear
boards A,B,C, and D; and the
2-I and 2-II.
The determination of these
load voltages
was given in
calculation
ED-92000-870054,
Revision 2, which utilized results
from
auxiliary calculations
ED-(2000-870043,
Revision 6,
and ED-(2000-870044,
Revision 9.
Assumptions
adopted for the calculation were that conductor
temperatures
would be at 60 degrees C.'or the control circuits;
that'he
minimum voltage at the
250
VDC
RMOV boards
2A,2B,
and
2C would be at
16
210
V (the minimum FSAR value);
and that maximum voltages of 279.6
V
(the battery equalizing voltage)
would occur at all points in the
system.
All assumptions
were found acceptable..
All loads at the
various switchboards
had guaranteed
operating voltages
below the
calculated figures with the exceptions of solenoids fitted to the
condensate
drain pot valve LSV-73-8 and the
RCIC Turbine Speed Control.
Calculated voltages of 205 and
208
VDC respectively
were compared with
requirements
of 225 and
220
VDC.
For the drain valve, the licensee
stated that this only operated
in a standby
mode
and that any condensate
would be adequately
removed
by the turbine exhaust drain line,
so that
valve actuation
would not be required during HPCI.
For the Turbine
Speed Control, the team found that
a memorandum
from the Moodward
Governor
Company advised that
a minimum voltage of 220
VDC was required
to prevent potential instability, overspeed
or shutdown of the turbine.
The licensee
advised that the
RCIC Turbine Speed
Control
was not
required for accident conditions but was required to meet
conditions.
The team examined the relevant portion of calculation
ED-
f0999-890059,
Revision 2,
and concluded that sufficient voltage
was
available at the
RMOV board
2B to activate this control unit for the
four hour
SBO condition.
In the case of maximum voltages existing at the loads during battery
float or equalizing
charg'e periods,
the calculation
showed that
auxiliary relays,
contactor coils,
and valve solenoids
had
a specified
maximum of 275
VDC and circuit breaker anti-pumping relays
had
a
specified
maximum of 260
VDC when energized
continuously.
Because of
the conservatism
adopted in the calculation,
the team accepted
the
licensee's
position that overvoltages
would r aise the coil temperatures
slightly but that there would not be
a catastrophic failure of these
components.
2.5.4.2
=
125
VDC
Calculation
ED-(2000-870047,
Revision 7, determined
the maximum and
minimum voltages at the loads
on the
125
VDC battery systems for the
DG.
As part of the design basis for the calculation,
the minimum voltage was
expected to occur during starting'f the diesel
generators
under plant
accident conditions with the battery chargers
inoperative,
and the
maximum voltage
was expected to occur
when only the continuous
load was
being supplied
and the battery charger
was delivering the equalizing
voltage of the battery.
The calculation considered all eight battery
systems,
and
used conservative
assumptions
such
as conductor
temperatures
of 60 degrees
C. for intermittent loads
,
and
90 degrees
C.
for continuous
loads,
when determining
minimum load voltages;
and
25
degrees
C. when determining
maximum load voltages.
The calculation also
considered
a minimum battery voltage of 105
VDC in calculating
minimum
load voltages in accordance
with the commitments
made in the
FSAR.
The team checked
the results of the calculation
and noted the
conclusions
in the calculation that the air start solenoid valves
and
the exciter breaker auxiliary relays for the
DG A,B,C, and
D did not
meet the criteria.
On further review, the team agreed with the licensee
17
that the voltage at the auxiliary relays would be greater
than the
minimum required voltage at the time the breaker closed.
For the air
start solenoid valves,
the calculation
had
assumed
a status
inconsistent
with the operating conditions,
and
a reevaluation of'the voltage drop
calculation 'for these
elements,
showed that the voltage at the solenoids
would be greater
than the minimum 'specified
by the manufacturer. 'he
team accepted
that the minimum voltages at all loads were adequate.
2.5.4.3
DC Systems
Ground Fault Protection
The system at the
BFN uses
inverse logic, where
an operator conducting
a
daily check, interprets
a zero reading
as
a "no ground fault "
situation,
whereas
a zero reading
may also
be the consequence
of a
faulty meter or open circuited connections.
Checking
and calibration of
the meter was at three year intervals,
and results
from BFN indicated
that the incidence of faulty meters
was approximately
28%.
The )earn concluded that this system would not effectively monitor
grounds
having higher impedances.
The licensee
stated that
a weekly
test
may be initiated after further evaluation is conducted.
~See-
A
endix A Findin
7
3.0
MECHANICAL SYSTEMS
The team reviewed
and evaluated
the adequacy of mechanical
systems
required to support the
EDS during normal operations
and postulated
accidents.
These
systems
included the
DG and
DG support
systems,
e.g.,
diesel
fuel oil storage
and transfer, starting air, cooling water,
lubricating oil, and the air intake
and exhaust
systems.
Also reviewed
were the nuclear service water system interface with the
and the
HVAC for spaces
containing safety related electrical
equipment.
The
basis for the mechanical
load values
used in the
DG loading calculations
was evaluated.
Documents
reviewed included applicable portions of the
FSAR, engineering
and vendor
documentation,
operating
and maintenance
procedures,
mechanical
system calculations
and drawings,
pump performance
curves,
equipment
performance
data sheets,
and
EDS related modification-
packages.
3.1
Conclusions
The team concluded that the design of mechanical
systems
supporting the
EDS was adequate.
.However,
the=team
noted that the air start
system
'elied
on
a single check valve as
a pressure
boundary for the safety
related portion.
The Licensee
had independently identified the weakness-
and initiated
a revision to Surveillance Instruction (O-SI-4.9.A.l.a) to
conduct leak checks.
In the area of seismic qualification, the air receivers
in the
DG air
start
system were not formally qualified to sustain
seismic events.
Additionally, even
though the
EECW Cooling System
was adequately
18
protected
from external
flooding events,
the dewatering
pump and
the grating at the top of the concrete
were not qualified.
Also, the
Room Battery
Fume
Hood was not seismically qualified.
However, all
support
systems
were under
NRC Unresolved Safety Issues
A-46 and will be
reviewed accordingly.
Several
undocumented
assumptions,
inconsistencies
and reference
errors
were noted in the calculation that determined
hydrogen concentration
in
Battery
Rooms I & 2.
The licensee
revised the calculation;
a review of
the, preliminary calculation indicated that the ventilation was adequate.
3.2
Diesel
Loading
The team noted that the mechanical
loads,
based
on the mechanical
load
study,
were within the
DG ratings,
except for DG A.
The team observed
that even though diesel
A was below the
2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> rating
(2857 KW), the
figure was nevertheless
above the engine continuous rating
(2600 KW).
The Licensee
explained that these diesels
were also rated
2960
KW for
200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> per year
and according to operating
procedures,
the Unit 3
diesels,
which were loaded to approximately
50 / of their full capacity
were to be aligned, within ten minutes from the onset of the accident
with the corresponding
Unit 2 diesels,
effectively. absorbing
any
overload.
3.3
Diesel Air Start System
The
DG Air Start System
was credited with supplying enough air for one
engine start attempt per pair of air motors
on each side of the engine.
If the system failed to start the engine,
the air system would
automatically
be disabled,
both electrically and mechanically
and the
Diesel
Generator
becomes
unavailable.
The Licensee
could not locate the air receivers'izing
calculation,
however,
the licensee
made available
a baseline test requirements
document
BFN-BTRD-002, Revision
2 for the Diesel Starting Air System
and
an Air Start System Test Report
2-BFN-RTP-082 describing five
consecutive
diesel starting tests
aimed at proving the system
reliability.
Beginning at
a pressure
below the minimum recharging
set
point, the first three tests
were conducted with closed injectors to
prevent the engine from starting but allowing it to reach the required
starting
speed
(cranking only).
The last two tests
were conducted
allowing the system to actually start the engine.
The team accepted
this test
as sufficient evidence of size
adequacy for the air receivers.
The team questioned
the system capability to maintain its minimum
required pressure
since it relied on
a single check valve as pressure
boundary of the safety related portion.
The Licensee
had independently
identified the weakness
and initiated
a revision
by means of a Site
Standard
Practice
SSP-2.3
procedure to add steps to their Diesel
Generator
Monthly Operability Test Surveillance Instruction (0-SI-
4.9.A. l.a).
When 'in place,
the procedure will permit inspection of the
Diesel Air Start Compressor
discharge
check valves for air leaks.
19
Currently, the licensee
normally maintains the low pressure
set point at
a level
much higher than the actual
minimum allowable air start pressure
and monitors compressor
cycling:
an increased
operating
frequency would
indicate
a leak in the system
and.maintenance
action will be taken
as
soon
as reported.
The team regarded
the present practice in concurrence
with the
new steps
in the Surveillance Instruction
as adequate
protection against
check valve failures.
In the area of seismic qualification, the team noted that the air
receivers
in the DG,air start system did not appear to have adequate
seismic supports.
The team expressed
concern regarding this weakness
.
and questioned
the inconsistency
between the proper seismic
qualification of the piping on the one hand
and the lack of
qualification of the air receiver supports
on the other.
The licensee
responded
that all
DG support
systems
came under
regarding the seismic qualification of Equipment in operating nuclear
power plants
(Unresolved Safety Issue A-46), and
"Regulatory
Analysis for Resolution of A-46" as well
The licensee
stated that air receiver supports will be adequately
assessed
and possibly modified as
soon
as the
USNRC qualification
procedure or guidelines
are finalized and issued.
In conclusion the team found the measures
taken
by the licensee,
such
as,
set points with safety margins,
good maintenance
procedures,
and
'urveillance
and tests
conducted
were satisfactory in guaranteeing
an
adequate
air start
system performance.
3.4
Jacket
Cooling System
The team questioned
the simplified procedure
used to hand calculate the
jacket water outlet temperature
in calculation
BWP H2-NCR BWP-8213-3.
The average
temperature
across
the heat
exchanger
and therefore
the
overall transfer coefficient
(U) was not iterated
and sufficiently
,
converged.
The temperature
was critical and needed to be more precisely
calculated.
The Licensee
agreed
the calculation
was approximate
and
submitted another
more recent
computerized calculation HD-(2067-88021,
prepared
to map
EECW flow rates
versus
number of tubes
plugged at
various jacket water temperatures.
This calculation indicated that the
overall heat transfer coefficient U(T) was adequately iterated
and
temperatures
properly converged.
3.5
Emergency
Equipment Cooling Mater System
The team reviewed the design
and layout of the
EECM system
and the
pumps which provide cooling water to the Diesel Jacket
Cooling system.
Twelve
RHRSW pumps support various station cooling water systems,
four
of these
pumps
powered
by safety boards
are dedicated to .feeding two
redundant
EECM headers,
the North and South Headers,
which in turn feed
the
DG jacket cooling heat exchangers.
20
The team concluded that the
EECW Cooling System
was adequately
protected
from external
flooding events.
The only apparent
weakness
was again in
the area of seismic protection.
Two items in particular were noted,
namely the dewatering
pump and the grating at the top of the
concrete.
The licensee reiterated,
as for other seismic issues,
that
the state of seismic qualification of these
items fell within the'cope
addressed
by Unresolved Safety Issues
A 46.
Consistent with the intent
of the A 46 document,
the existing safety equipment
was currently
presumed to have sufficient margin of seismic capability.
In addition,
the licensee
maintained that based
on TVA's own engineering
experience,
the equipment
was basically the
same
as
had
been qualified in subsequent
TVA plants.
The team accepted
the analysis
as adequate for the
immediate term.
3.6
Diesel Oil System
After reviewing the
TS requirements,
the diesel
consumption tests,
the
fuel oil sampling procedure,
the 7-Day storage
tank sizing calculation,
the scaling
and set point document,
the team identified several
inconsistencies
in the diesel
fuel oil consumption.
On page
2 of
calculation HD-(2018-870164,
the design
consumption rate
was
assumed
to
be
213 Gal/Hr with no reference
to specific gravity.
On page
10 it
became
206 Gal/hr and
on page
20 A, 210 gal/hr was mentioned.
In
another
document,
the Incident Investigation
and Root Cause Analysis,
II-B-91-059 concerning
DG oil consumption,
the measured
consumption rate
of Unit 3 Diesels,
3C and
3D were reported
as being
as high as
235
gal/hr and
210 gal/hr respectively,
at full load.
However,
since the
total electrical
accident
loads for Unit-3 diesels
were approximately
50% of their rating, the Unit 3 Diesels would experience
a lower than
full load consumption.
The team determined that the fuel oil available in the 7-day storage
tanks with the present refilling procedure
was sufficient to=warrant
7
days of continuous operation
under accident condition in Unit 2.
3.7
Heating Ventilating and Air Conditioning
3.7.1
Diesel
Generator
Room Ventilation
Reviewing the Diesel
Generator
Room ventilation requirements,
the team
noted that calculation MD-003-870558,
as were other selective
calculations of safety related
rooms,
was
based
on
a maximum design
basis
ambient temperature
of 95 degree
F instead of 97 degree
F as
required
by the
FSAR.
Other calculations
were left with the 97
F
temperature
assumption.
The licensee
explained that in 1989,
a licensee
exception request
and approval
form was issued to revise design criteria-
BFN-50-715 Table l. 1-1 allowing the use of 95 degrees
F dry bulb and
75
degree
wet bulb temperatures
in the sizing calculations of HVAC
equipment required for unit 2 restart.
These temperatures
were
based
on
chapter
24 of the
ASHRAE Handbook.
The team reviewed the record of
temperatures
at the site in the past two years
and noticed that
temperatures
above
95 degree
F occurred
13 times in the period 1974-87.
21
The highest concentration
resulted in the year
1980 with 7 occurrence
at
97 degrees
F and
1 occurrence
at
100 F.
The licensee
adequately justified their position by stating that
abnormal
temperatures
in the diesel
room above the
120 degree
F design
could occur
as
a result of outside temperature
excursions.
These
conditions could exist for up to 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> per excursion
and they would
only occur for less
than
1 X of the plant life.
3.7.2
Tornado generated
missile strike and depressurization
protection:
The team reviewed the tornado protection
study. from missile strike of
the diesel
generator
rooms
and found that three tapered
areas of the
building itself did not have sufficient thickness to resist tornado
missile penetration spalling
as defined in FSAR section 12.2.2.9.2
and
design Criteria BFN-50-C-7101.
The licensee's
position was that Browns
Ferry had sufficient redundancy
in the diesel
generator
design to
support Unit 2 operation
and for a single missile strike,
several
additional
events
would have -to occur before affecting the safe
shutdown/cooldown capability of the station.
The combined probability
of occurrence of all additional
events
reduced
the tornado generated
missile strike contribution to crippling the safety systems of the
station
by two orders of magnitude
below the calculated
frequencies
and
would not significantly alter the public risk factor.
This position was
adequately
documented
in calculation
BFN RAG2-003.
The team also noted that the
DG room air intake
and outlet dampers
did
not have
a tornado depressurization
qualification.
The Licensee
generated
a new preliminary calculation
showing that there should
be no
damper failures at the pressure differential
imposed
by a tornado event
and that the
would not pose
a damage threat to the
safety equipment in the room.
3.7.3
DG Room Battery
Fume
Hood
/
The team expressed
concern regarding
a non qualified fume hood above the
batteries
in the
DG room.
The fume hood posed
a potential
impact to the
integrity of t'e safety related batteries
below.
The licensee
was
aware
of this deficiency
and restated,
as for other seismic issues,
that the
battery
fume hood seismic qualification was
an item that will be
reviewed to A 46.
3.7.4
Battery
Rooms
1
& 2 Ventilation Requirements
The team identified many undocumented
assumptions,
inconsistencies
and
reference
errors in the
room hydrogen concentration
calculation
HD-
93031-880242.
The licensee
recognized there were numerous errors
and
initiate revision to correct all deficiencies.
To quickly evaluate
the
possible influence
on the adequacy of existing equipment,
the licensee
conducted
a preliminary conservative calculation which indicated that
22
the maximum hydrogen generation
rate would be no'ore than 4.2 cubic
feet per hour with no adverse
consequences
on the equipment installed.
The team accepted
the justification.
3.7.5
Diesel
Engine Intake and Exhaust piping analysis
Reviewing the diesel
exhaust
system seismic qualification calculation
,
'D-(0031-8818838,
the team noted that the exhaust
pipe was not analyzed
using the applicable
code equations of piping analysis
but rather using
an approximate structural
method
and
a high
7 X damping factor.
The
licensee
acknowledged that the methods of piping analysis
would have
been
more. appropriate
in this case,
but the method
used
was conservative
since the analysis calculated
the frequency of the exhaust piping,
applying the moment of inertia of the smaller
end in determining the
acceleration
value -and conservatively'treating
the duct as simply
supported
instead of fixed.
The damping value of 7 5 was
based
on
a TVA
seismic test
program documented
in TVA report MA2-79-1.
The tea'm
accepted this explanation with no further questions.
4.0
MAINTENANCE, TESTING,
CALIBRATION, AND CONFIGURATION CONTROL
The team performed walkthrough inspections of the
EDS to identify the
material condition of the electrical
equipment
and panels.
Portions of
'he
"as installed" configuration of the
EDS were examined to determine
its compliance with design drawings
and documents.
The electrical
maintenance
program,
procedures,
surveillances,
and work orders
were
reviewed to ensure
the
EDS was being properly maintained to function for
the life of the plant.
Data sheets
from completed calibration
and
surveillance
procedures
were reviewed to verify the
EDS operates
in
accordance
with design specifications
and requirements.
The method
used
.for fuse control
was examined to determine if the correct sizes
and
types were installed.
Relay setting sheets
and drawings were reviewed
to determine if an effective -program had
been developed
and implemented
for controlling setpoints for protective relays,
circuit breakers,
switchgear
and timing relays.
Testing
and
surveillance
procedures
for the emergency diesel
generators, were
reviewed to determine if specifications
were being met.
4.1
Conclusions
In the area of configuration control, the team identified several
discrepancies
between the "as installed" molded case circuit breakers
and the design drawings.
The team noted
a potential configuration
control problem with breaker
changeout
in the 480
V SDBs.
The licensee
identified two non lE General Electric type AK circuit breakers
located
in IE shutdown boards.
A problem evaluation report
had already
been
issued.
The team found several
instances
of improperly terminated
spare wiring
in the 250
VDC RHOV boards
and in several
main bank battery chargers.
Additionally, two SDB battery charger disconnect
switches
were
incorrectly left in the "on" position.
Two drawing discrepancies
were
23
noted in the thermal overload setting drawings.
The team noted
a
weakness
in the fuse control
program regarding fuse labelling.
During 'the walkthrough inspections,
the team noted that the material
condition of the plant equipment
was good.
However,
cracked thermal
overload relays were found in the 480
V and
250
VDC fNOV boards
and
a
cracked fuse block was found in a 480
V RHOV board.
Additionally the
team noted that
SDB battery
C had
a degraded intercell jumper cable.
These conditions were adequately
addressed
by the licensee.
Housekeeping
was generally
good in the switchgear,
motor control centers
and electrical cabinets.
The equipment
was clean
and properly
maintained.
An exception
was battery board
2 where several
examples of
poor housekeeping
and excessive dirt were noted.
In the area of preventive maintenance,
the team found that'the
bus
insulation
on the
4 Kv shutdown
boards
was not being inspected.
The
licensee
was utilizing thermography for checking
bus connections,
and
this was identified as
a strength.
The team noted that the maintenance
records
and procedures
for 4 Kv and
480
V switchgear
maintenance
to be
adequate.
The team verified that the protective relays were being calibrated
on
a
scheduled basis.'n
the area of testing
and surveillance,
the team
noted that the licensee
had implemented
an adequate
program for testing
which encompassed
all safety related
breakers.
Review of the battery discharge tests
revealed that several
batteries
were nearly at the replacement'oint.
The licensee
indicated that they
had design
change
packages
to replace
many of the batteries
during the
upcoming refueling outage.
A procedure
inconsistency
in battery post
terminal torque requirements
was noted in the
DG battery discharge test
procedure.
Overall, maintenance,
testing, calibration
and configuration control
was
being adequately
accomplished.
4.2
Equipment Walkthroughs
3
The electrical
components
examined during inspection walkthroughs
included fuses,
overload heaters,
motor contactors,
protective relays,
circuit breakers,
switchgear,
batteries,
chargers,
HG sets,
cables,
cable trays, transformers,
cubicles
and panels.
The team primarily
examined Unit 2 equipment or shared
equipment required for Unit 2
operation.
The team inspected
the
4 Kv SDBs
and found them to be clean,
well
maintained,
and in conformance with plant'design
requirements.
The 480
V SDBs were also clean
and well maintained.
However breaker
changeout
had led to two non-lE breakers
being placed into the
1E 480
V SDBs.
24
The non-1E breakers
were determined
by the licensee to have
been
installed in safety related
480
V SDB 2A cubicle
3D and 480
V SDB 3A
cubicle 2B.
The licensee
had already
issu'ed
a problem evaluation report
BFPER920039 to investigate.
The breaker in SDB 3A was still installed.
This is identified as
a finding which the resident
inspectors wil'l
follow.
See
A
endix A
Findin
8
During the inspection of the 480
V RMOV boards the team identified
several
configuration control discrepancies.
On 480
V RMOV board
2A the
inboard
and outboard core spray valves (cubicles
13B and
14B) had 30
ampere
instead of the
7 ampere
breaker
called for on drawing 2-45E751-1.
'RHOV board
2B cubicle
15E for inboard
core spray valve had
a 30 ampere
breaker instead of the
7 ampere
breaker-
called for by drawing 2-45E751-3.
The licensee initiated
a
SCAR
BFSCA920006
and work requests
to replace the breakers.
The team
determined that the oversize
breakers
would not impact operability of
the core spray valves.
See
A
endix A
Findin
9
The team noted several
instances
of degraded
equipment in the 480
V RMOV
boards.
In cubicle
4E of RMOV board
2E,
a cracked fuse block was found..
The licensee
issued, work request
C111446 to repair.
During inspection
of 480
V RMOV board
2A the team found cracked
thermal
cubicles
4E,
10A,
and
17A.
Work requests
C105431,
C105439,
and
C105438
were issued to repair.
Additionally, the team noted cracked
thermal
overload relays in 250
VDC RMOV board
2A, cubicle
3D and
RMOV board
2B
cubicle 5B.
The team determined that the cracked
components
would not
impact equipment operability.
The licensee
issued
work requests
C104029
and
C104030 to correct.
See
A
endix A
Findin
10
The team noted two drawing discrepancies
while inspecting
thermal
overload relays in the 480
V RMOV boards.
RMOV board
2A cubicle
6B had
the correct overload heater installed.
However, the thermal
overload
setting drawing incorrectly specified the heater.
The licensee
issued
potential
drawing discrepancy
PDD 92-200 to correct the drawing.
Cubicle
7B of RMOV 2A was
shown wired for 3 thermal
overloads while the
installed configuration was
3 thermal
overloads with the
B phase
not
wired.
Potential
drawing discrepancy
PDD 92-201
was issued to correct
the drawing.
See
A
endix A
Findin
9
During the inspection of the
DGs, the team noted that the circuit
breaker for DG start circuit
1 had
a 50 ampere
breaker while drawing 0-
761E580-1 calls for a 30 ampere breaker.
See
A
endix A
Findin
9
During the plant walkthrough improperly terminated
spare cables
were
found inside
250
VDC battery chargers
1,2A,2B,3 and 4.
Additionally,
the team noted improperly terminated wiring in 250
VDC RMOV board
2A
cubicle 7A.
The licensee
issued
work requests
C10344 through
C10348
and
C10431 to correct.
See
A
endix A
Findin
9
The team noted spare battery charger disconnect
switches for SDB battery
chargers
B and
C left in the "on" position.'rawing
0-45E709-1
25
indicated that the disconnect
switches
should
have
been in the "off" .
position.
See
A
endix A
Findin '9
I
During the inspection of batteries,
the team found
a degraded intercell
jumper cable
between cells
60 and
61 of 250
VDC SD battery
C.
Approximately 50 X of the cable's
conductor strands'ere
broken.
Due to
the cable size
and ampacity rating the remaining conductors
would ensure
battery operability.
The licensee
issued
work request
C104393 to repair
the cable.
The team reviewed the fuse control program
SSP 12.56.
The team
identified several
weaknesses
in 'the program.
The licensee
was in the
process of revising the fuse labelling in the plant.
New labelling was
being installed but old labels
were not always being removed.
As many
as three labels for the
same fuse existed in some panels.
Cleared
fuses
were to be replaced
by referring to the fuse label for fuse
identification.
Confusion over which label
was correct could result.
Procedure
DS-E 1.2.3 referred to in the fuse control program requires
special
instructions
such
as
"Do not substitute" to be indicated
on fuse
labelling.
Licensee
personnel
were not aware of the special
instructions to be indicated
on class
lE fuse labelling.
The licensee
revised
SSP 12.56 to require that the Site Engineering
issued Electrical
Fuse'abulation
Drawings
be utilized to determine correct fuse data for
replacement 'of 1E fuses..rather
than the fuse labels.
4.3
Equipment Maintenance Testing
and Calibration
The team reviewed the preventive
maintenance
for switchgear,
motor
control centers,
batteries
and battery chargers.
Maintenance
procedures
for the
4 Kv and 480
V switchgear
were considered
adequate.
was being utilized to inspect the swi,tchgear.
This is
considered
a program strength.
The team noted that inspection of bus
bar insulation of 4 Kv switchgear
was not included in the routine
maintenance
of the switchgear.
GE publication GEH-1802,
Metal Clad
Switchgear which is included in manual
BFN-VTM-G080-6060 on 4 Kv
switchgear
recommends
annual
inspection of the bus bar insulation.
Also
recommended
is resistance
measurement
for bus bar insulation for phase
to ground
and phase to phase.
The procedure 'for preventive maintenance
of motor control centers
was
reviewed.
The molded case circuit breaker testing
was found adequate.
All safety related
were included in the
test program.
Relay calibration for 4 Kv and 480
V systems
were adequate.
Calibration
procedures
and intervals were satisfactory.
The team noted that relays
are not always returned to mid-band during calibration if not found out
of acceptable
range.
For instance,
the overcurrent relay for the
pump
1D has
an acceptable
range of 36. 1 to 39.9 amperes.
The relay. was
found at 39.8
and left at 39.8 during the last calibration.
Relay
calibration is on
a 48 month frequency.
26
The team reviewed the testing
and surveillance
procedures
and results of
last, surveillances for the
DGs.
The results
and the surveillance,
procedures
were determined to be acceptable.
During the review of battery discharge testing the team noted that
several
batteries
were very close to the
80% capacity replacement
criteria.
C battery was determined to be at 80.67Ã capacity,
DG 3C
battery
was at 86.31. capacity,
and Main Bank 3 battery
was at 89.9X
capacity.
The licensee
indicated that design
change
packages
had
been
prepared to replace
many of the batteries
during the next refueling
outage.
The following DG batteries
were scheduled for replacement:
battery A,B,C,D,3A,3B, and
3C.
The following SD batteries
were
scheduled for replacement:
SD battery A,B,C,D,and 3EB.
Hain Bank 2 and
Hain Bank 3 batteries
were also scheduled for replacement
at the next
refueling outage.
This finding will be followed by the resident
inspectors.
See
A
endix
A
Findin
11
The team noted
an inconsistency
in the battery post terminal torque
requirements for DG battery
3D in the battery discharge test procedure.
One section of the procedure calls for a terminal torque of 10 inch
pounds while another
section requires
110 inch pounds.
The licensee
issued
a procedure
change
NIC-08 to correct the procedure.
4.4
Emergency Diesel
Generator
Preventive
Maintenance
The team reviewed the licensee's
mechanical
preventive maintenance
activities for the
DGs.
A total of 73 maintenance
procedures
were
identified by the licensee
as applicable to the eight DGs.
The
procedures
were written in accordance
with applicable
vendor manuals,
were clearly written and contained
adequate
sign off spaces.
During the team inspection,
the licensee
performed the yearly, three
year,
and six year
PH of the
3C
DG and
a follow-up maintenance
and
a
modification on the
D DG.
The follow-up maintenance
on the
D machine
involved the bolted connection tightness
check required to be performed
six months after the six year
PH.
The modification involved
ECN H7844
and implementing
WP 0031-92 which removed eight of 10 air receiver tank
relief valves.
The. team noted that during the activities involved with the
3C
DG a
voltage regulation failure occurred which drove the voltage to maximum
and also caused
a speed
decrease.
The system engineers
initiated
a TD
which described
the voltage
and
speed
excursion during the performance
of procedure 3-SI-4.9.A. I.d(3C), "Diesel Generator .Annual Inspection".
The
TD originally addressed
the failure in the accident
mode of the DG-
SINGLE UNIT.
The team asked
about the effect of the failure on the
other two modes of the
DG - UNIT IN PARALLEL and
PARALLELED W/SYSTEM.
The system engineers
revised the
TD to include
a discussion of the
effects of the failure on all three
modes.
The team noted that the
failure would have
an effect on all modes
and that
a loss of standby
power under certain conditions would occur.
The item was being reviewed
for possible follow-up.
27
5.0
ENGINEERING AND TECHNICAL SUPPORT
'The team assessed
the licensee's
capability and.performance
regarding
engineering
and technical
support associated
with the
EDS.
The basis
for this assessment
included the following areas:
technical
support
organizations'taff levels,
involvement in identification and
resolution of plant problems,
support of EDS related maintenance
and
operations activities,
and modifications.
5.1
Conclusions
Engineering
and technical
support for EDS activities and design controls
for EDS systems
and components
were generally
adequate
to monitor and
maintain the design function of the
EDS.
Staffing was.adequate
to
provide required
EDS related technical
support.
Maintenance
and
operations
support
was adequate.
The System Engineering
group in
particular was cognizant of system
and component function and
performance.
The group provided strong support for EDS activities
and
involvement in problem identificati,on and resolution
was good.
Design
Engineering
and Hodifications Groups planned modification activity was
appropriately controlled
and documented.
5.2
Organization
and Staff
Engineering
and technical
support for EDS related activities reviewed
by
the team was provided by the on site engineering
organizations
during
the period preceding this inspection.
The
BFN engineering
organization
does not have
an offsite design group
and the onsite group was larger
than most facilities.
This was due to the ongoing modifications
following Unit 2 restart
and the post Unit 2 recovery deferred
items.
The on site engineering staff for Unit 2 was approximately
300 technical
personnel
broken
down as follows:
190 design engineers,
90 of which
~
were contractors with 18 design engineers
assigned
to operations
support
and
8 in the electrical
area;
90 system engineers,
of which 15 were
assigned
to Unit 3 recovery,
25 assigned
to engineering
support
and
7
assigned
to electrical,
and
24 procurement
engineers of which 9 were
assigned
to electrical
procurement~
Three offsite groups provided support
and direct hands
on activities
involving the 'EDS.
The first group was corporate engineering
which
provided oversight
and technical
support to site design engineering
in
regards
to the
EDS both
as requested
and self initiated.
The second.
group was corporate
maintenance
which provided on-site technical
support
for plant maintenance.
The third group was Transmission
and Customer
Services,
which provided direct hands
on activities involving the
EDS.
The systems
engineering
organization at Browns Ferry was established
in
mid-1986.
A total of 19 system engineers
were assigned
to the
Electrical
and
IKC group with seven
engineers
assigned
to the
EDS
section
and one within the section specifically assigned
to the
DGs.
28
5.3
Maintenance
and Operations
Support
The majority of EDS related support
was provided by the System
Engineering
group which in conjunction with the design,
procurement,
operations
and maintenance
groups provided ongoing technical
support for
parts replacement,
procedure
changes,
event management,
design
change
plant acceptance,
USNRC requirements/inquiries,
tracking of punchlist
.
items,
and trending of, EDS equipment performance.'
sample of 37 trend failure reports
from the period of 1987 to present
were reviewed to determine engineering
involvement.
The TFRs from the
earlier time frame,
1987 to 1989, indicated
a lack of analysis for
trending.
During the
1987 to 1989 time period, trending of equipment
failures was performed
by maintenance
personnel.
A TFR from 1988 stated
that
a failure of the
same specific component
on several
DGs did not
indicate
a" trend because
the failure occurred
on different DGs.
Since
1989 engineering
involvement improved.
A TFR from 1990 involving.the A,
8,
C,
D DGs fuel oil transferring resulted in a design
change,
DCN
N9092, which removed the check valves in the suction line for the eight
(two per
DG) transfer
pumps.
During the
EDSFI, the team noted that all
trending failures were performed
by the system engineers.
5.4
Problem Identification and Resolution
The team reviewed engineering
involvement in problem identification and
resolution activities associated
with the EDS..
The Incident
Investigation
Reports
program,
which was the facilities primary
mechanism for problem identification and resolution 'was reviewed to
assess
engineering
involvement.
A sample of 38 IIRs, from September
1988 to March 1992 involving the
EDS, were reviewed for aspects
of root cause
analysis,
resolution,
corrective action,
and, engineering
involvement.
The IIRs during the
earlier time frame from September
1988 to December
1989
(a total of 13
IIRs) were lacking in root cause
analysis,
resolution, corrective action
and engineering
involvement.
An example of this was IIR 88-04 which
documented
an electrical fire inside
a
4
KV circuit breaker.
The root
cause
was not determined.
The IIRs during the later time frame,
December
1990 to March 1992 (a total of 14 IIRs), the level of root
cause
analysis
and corrective actions
performance
on the IIRs was
appropriate.
An example of this was IIR 91-04, which documented
a
temporary failure of an auxiliary switch contact
on
a
DG tie breaker
to
a 4 KV shutdown board.
This resulted in the corresponding
and
RHRSM pumps not sequencing
on during
an accident signal logic
actuation.
As a result of the IIR activities, the licensee initiated
a
design
change to provide reliable load sequencing
at 4 kV SDBs.
Additional engineering
involvement was indicated
by IIRs91-158
and 92-
017, which both resulted
in the initiation of DCNs.
Implementation of
these
DCNs were to resolve
a recurring
ESF actuation
problem and
make it
e'asier for plant personnel
to determine
what caused
the circuit
protectors to trip such
as overvoltage,
underfrequency,
and
5.5
Hodifications
The
BFN facility installed
numerous modifications affecting the
EDS to
support Unit 2 restart during the extended
outage
and recovery.
A
sample of these modifications were reviewed for post modification
testing,
10 CFR 50.59 safety evaluations,
material
procurement,
and the
interface
between
design
development
and installation responsibilities.
I
The team reviewed modifications installed
as
a result of trend analysis,
restart testing,
integrated
system testing
and system analysis.
Additionally, temporary modifications involving the
EDS and supporting
systems
were reviewed to determine engineering
involvement.
Appropriate
design controls were demonstrated.
The
PHTs indicated
adequate
acceptance
of the
DCN.
The team noted that
a procurement
problem was identified involving the
RHS-9 Hiero Versa Trip circuit breaker conversion kit modifications
used
in the
EDS.
This item was identified as
a result of the Unit 3 recovery
effort and
a contractors
design activities.
The team was informed by
the licensee that when the
RHS-9 trip units were procured for use in the
Unit 2 recovery effort, the procurement
documents
did not specify
an
ambient temperature
or a cabinet temperature.
The only temperature
specified
was
104 degrees
F, which was
an
Eg requirement.
The item was
being followed by the resident inspector.
6.0
EXIT HEETING
The team met with licensee
representatives
(denoted
in Appendix C) at
the conclusion of the inspection
on Hay 22,
1992, at the plant site.
There were no dissenting
comments received.
Proprietary information is
not contained
in this report,
APPENDIX A
FINDINGS
FINDING 1:
Existing Calculations
Did Not Contain Sufficient Data to Determine
LOCA Load Sequencing
Voltage Profile (paragraph
2.2. 1. 1)
DESCRIPTION:
Calculation
ED-(2000-870026,
Revision 9, "4.16 kV and Busload
and Voltage Drop
Calculations. with Offsite Power",, was intended to determine
minimum voltages
at safety
buses during
LOCA load sequencing.
However, the calculation'id not
contain sufficient data to establish
the actual voltage profile at the safety
busses
during worst case conditions.
The Licensee
provided additional
computer runs which established
the actual. profile and which demonstrated
adequate
system performance
SAFETY SIGNIFICANCE:
This calculation
was necessary
to establish that adequate
voltages
are
available during load sequencing
and that the degraded
voltage relays will
reset within required time intervals.
Failure of relays to reset
could cause
loss of offsite power to safety loads during
LOCA load sequencing
and present
unnecessary
challenges
to the standby
power systems.
FINDING 2:
Incorrect Acceptance Criteria for Degraded
Voltage Relay in
Surveillance Instruction (paragraph
2.2. 1.3)
DESCRIPTION:
The acceptance criteria in Surveillance Instruction 3-SI-4.4.A.4.C(I),
Revision
1,
"4160
V SDB 3EA and
3EB Under/Degraded
Voltage Time Delay Relay
Calibration", did not properly reflect the
26
V tolerance
applicable to the
Degraded
Voltage Relay dropout
and reset values,
as determined
in Calculation
ED-(2211-890144,
Revision 4, Setpoint
and Scaling Calculations
4 kV Bus
Degraded
Voltage Relays
(ITE 27N),
as follows:
The Surveillance Instruction,
paragraph
7.2.3. 12, allowed the relay
reset
value to be left at 3987.7
V.
Adding the tolerance
determined
in
the setpoint calculation,
the actual reset voltage could have drifted to
3987.7+26= 4013.7
V.
This is higher than the
TS allowable of 3999 V.
2.
3.
The acceptance criteria stated
in the Surveillance Instruction did not
provide
a lower limit for the reset voltage,
so that it could have
been
set close to the dropout value.
Acceptance criteria 6.1.3 stated that
reset
should
be "less than or equal to 1.5L above trip=-value."
This
could have resulted
in convergence
of the dropout
and reset
due to
setpoint drift.
The Surveillance Instruction,
paragraph
7.2.3. 13 allowed the dropout
voltage to be left as low as 3911.25
V.
Applying the tolerance
determined
in the setpoint calculation,
the actual
dropout could have
drifted as low as 3911.25-26=
3885.25
V.
This was below than the
TS
allowable of 3900 V.
The licensee
revised the Surveillance Instruction to conform to constraints
determined
in the latest setpoint calculation.
In addition, the licensee
stated that applicable administrative procedures
shall
be revised to assure
that appropriate
design inputs are
used in all Surveillance Instructions.
SAFETY SIGNIFICANCE:
Improper criteria used in this surveillance instruction could have resulted
in
operating voltages
below analyzed
minimum requirements,
or in loss of offsite
power to safety loads during
LOCA load sequencing
due to failure of Degraded
Voltage Relays to reset.
FINDING 3:
460
V Motors Do Not Have Critical Voltages Stated in FSAR
~
(paragraph
2.2.1;4)
DESCRIPTION:
Calculation
ED-(2000-870027,
Revision 3,
"460
V Class
1E Motors and Equipment
Volt Drop", Attachment
2, demonstrated
that certain motors did not have the
minimum required terminal voltage stated
in section 8.4.8. 1.4 of the
FSAR as
follows:
3M031515015
3M031515019
U3
CR AHU A
U3
EL 593
AHU3A
Component
Tag
'Description
Running Volts
Criteria 414
409.398
413.876
Percent of 460V
(90%)
(88.9%)
(89.9%)
The Licensee
demonstrated
adequate
equipment operation
based
on available
equipment design margins.
SAFETY SIGNIFICANCE:
This item represented
a deviation from a
FSAR commitment but did not have
safety significance since
adequate
equipment
performance
was demonstrated.
FINDING 4:
Calculation'Weaknesses
(paragraph
2.2.1.4)
DESCRIPTION'he
following weaknesses
were noted during
a review of various
EDS
calculations.
Calculation
ED-(2000-870027,
Revision 3,
"460V Class
lE Motors and
Equipment Volt Drop":
a 0
The calculation relied on equipment
design margins to justify
voltage below manufacturer's
recommended
minimums rather than
removing
known conservatism
or correcting circuit deficiencies,
for the following motors:
Component
Tag
3M031515015
3M031515019
Description
U3
CR AHU A
U3
EL 593
AHU 3A
, Running Volts
Criteria 414
409.398
413.876.
c ~
Section 7.0.2. justified voltage below the criteria stated
in
section 3.0 based
on adequate
torque available at 70
1. voltage for
NEMA B motors.
However, this justification did not consider the
effects of increased
current
and possible tripping of protective
devices.
In response,
the licensee
provided additional
justification which demonstrated
adequate
performance.
Calculation
ED-(2000-870027,
paragraph
3.7 stated that the
calculation tabulated
in Attachment
2 used the lowest actual
operating voltages at the various
buses
as determined
by
calculation
ED-f0999-890090.
However,
some voltages in attachment
2 did not match the lowest voltages in calculation
ED-(0999-890090.
Examples
are
as follows:
Bus
090 Calculation
Attachment
2
CB VENT BD A
434V (Table 1.2)
435V
DSL AUX BD A
446V (Table
1)
450V
The team determined that the use of non-conservative
voltages did not
affect the final results.
Calculation
ED-(2211-890144,
Revision 4, "Setpoint
and Scaling
Calculations
4 kV Bus Degraded
Voltage Relays
(ITE 27N)":
'a ~
Paragraph
8,
page
5a, stated that the
26
V tolerance
applicable to
the
DVR dropout setting-was
random
so that it was unlikely that
two relays would be subject to the maximum inaccuracy at the
same
time.
This contention,
combined with two out of three logic, was
used to justify using the actual setpoint of 3920
V as the lowest
possible
bus voltage rather than using the setting less tolerance.
However, at least
two of the factors contributing to the 26
V
tolerance
are not random
as applied to 'two separate
relays,
temperature
effect (TNe),
and power supply effect (PSEe).
This
increase's
considerably the chance that drift in the
same direction
will occur simultaneously
on two (or three) relays.
In addition,
the magnitude of drift inaccuracy
(De) is time dependent
which
could effect all relays calibrated at the
same time similarly.
Consequently,
minimum voltage
used
as the basis -for degraded
voltage calculations
should reflect actual setting less tolerance.
The team determined,
however, that using the non-conservative
voltage did not have
a significant effect on the final results of
the calculations
concerned.
C.
Paragraph
8.0 stated that calculation
ED-(2000-870026
determined
the minimum steady state voltage
on
However, this figure could not be found in the referenced
~
~
d.
calculation.
The team determined
the actual
minimum voltage
was
4004
V which was less limiting than the referenced figure.
Paragraph
8.0 incorrectly stated that the dropout
and reset
would
drift in the
same direction
as justification for. the small
{20 V)
difference
between the two settings.
The licensee
revised the
calculation
and established
settings
which will prevent
convergence
of dropout
and reset
due to drift.
SAFETY SIGNIFICANCE:
The items noted
above were determined to be isolated
examples of weakness
in
otherwise generally conservative calculations.
None of these
items
represented
operability concerns
and all were appropriately resolved
by the
licensee
by calculation revision or other justification.
FINDING 5:
Control
Bay Water Chiller A and
B circuit breaker settings.
(paragraph
2.3.4.2)
DESCRIPTION:
Calculation ED-f2000-870548,
Revision
10, identified the analytical
basis for
the long term pick-up settings of the load center circuit breakers
{480 V).
For a motor having
a service factor of 1. 15 the calculation asserts
that the
setting should
be greater or equal to 1391 of the full load current.
This
constraint
had not been applied to all motor loads
(class
1E and non-1E)
and
in particular to the
1E load "Control
Bay Water Chiller B".
The result of this finding was that with the motor demanding full load current
at its rated terminal voltage of 460 V, the operating point on the
coordination curve lies within the tripping region of the circuit breaker.
The problem would be intensified at degraded
bus voltage conditions,
when the
motor was drawing more current.
The problem also occurs
on "Control Bay Water
Chiller A".
The licensee
stated that the circuit breaker setting
was inappropriate,
and
advised that
a safety
assessment
report
DCNGI7047A dated
September
27,
1991
had identified this condition;
and
a modification to the breaker
was being
initiated.
The circuit breaker will be fitted with a new G.E.
Type RHS-9 trip
unit set to 132/ of 'the motor full load current,
and work request
C044046
had
been written to install the unit.
SAFETY SIGNIFICANCE:
This equipment
was used to provide cooling for the control
room and equipment
rooms located
on elevation
593.
The equipment relying on the chiller for
cooling could operate for approximately
30 minutes before being adversely
affected
by the loss of cooling, giving adequate
time for operator action.
In
addition,
some cooling was available from chillers in Unit 3, which are not
subject to these possible
inadvertent trips because
of the different circuit
breaker settings.
5
FINDING 6:
Procedure
Weaknesses
(paragraph
2.4,2)
DESCRIPTION:
The following weaknesses
were noted in procedures for operating the
EDS:
l.
Alarm response
procedure I/2 ARP 9-23, Revision 12, did not provide
'dequate
guidance regarding Diesel Generator
Ground Fault Annunciation.
The diesel
generators
were grounded
using
a high resistance
scheme.
This limits the magnitude of ground fault currents
and permits continued
operation of the system during an emergency.
A ground fault was
annunciated
as
a "DIESEL GEN X GROUND FAULT".
In case of LOOP,
procedures
required transfer
back to the offsite source through the
USSTs, if it became available again.
.However,
these transformers
were
grounded
through
a low resistance
scheme
which would allow much larger
fault currents
and consequent
loss of the faulted load.
In case of'n
emergency,
continued operation with a fault limited to a small current
would be preferable to loss of the load.
However, the alarm response
'procedure
did not caution operators
against
attempting
a retransfer
.
prior to isolating the fault so that operators
could attempt to transfer
back to the preferred
source,
rather than first selective tripping
loads,
conditions permitting, to locate the fault.
In addition, the
"Probable
Cause" section of the'procedure
did not clearly alert the
operators that the fault could be anywhere
on the 4. 16
kV system,
not
just on the
DG.
The Licensee revised the procedure to address
these
concerns.
2.
Procedure
O-OI-82, Revision 35,
"Standby Diesel
Generator
System
Operating Instructions", did not provide guidance
on restarting large
loads,
in particular
a 2000 hp
RHR pump, should it become
disconnected
while being powered from a diesel generator.
In response
to this
concern,
the licensee
provided specific instructions for reducing load
on the
DGs to prevent overloading
and to check for any 480
V loads which
may be inadvertently tripped due to the voltage dip during restart.
SAFETY SIGNIFICANCE:
The above
examples
do not represent
threats to the operability of the
EDS but
could have resulted.'in
unnecessary
interruption of power to important loads.
FINDING 7:
D.C. Battery Systems
Ground Detectors
(paragraph
2.5.4.3)
DESCRIPTION:
Each class
1E battery system at the
BFN employs
a ground detection
system,
comprising principally a
DC center zero voltmeter acting
as
a null detector of
a Wheatstone
bridge, the
arms of the bridge being two resistances
connected
between the positive
and negative
poles of the battery supply, 'and the
resistance
to ground of each pole.
With no ground fault on the system the
voltmeter reading is zero.,
The system at the
BFN uses
inverse logic, where
an bperator conducting
a daily
check, interprets
a zero reading
as
a "no ground fault " situation,
whereas
a
zero reading
may also
be the consequence
of a faulty meter or open circuited
connections.
Checking
and calibration of the meter is at three year
intervals,
and results
from BFN indicated that the incidence. of faulty meters
t'o be about
28%.
A secondary
system employing meter relays
was also fitted to each battery
system,
the meter relays being energized
from non-1E
120
VAC supplies.
The
relay gives annunciation
in the control
room of a ground fault or of a relay
failure or of a loss of power to the unit.
The system
was not set to detect
a
high/medium
impedance
ground fault, and should
be self powered,
or powered
from the
DC battery, for reliable operation.
SAFETY SIGNIFICANCE:
Failure of the voltmeter or the connections
thereto, will not be recognized
during the daily check of the system,
and more than
one ground fault can occur
on the system without being detectable
by the existing monitor.
No
calculation
was available relating meter reading to ground fault resistance
but the -assessment
by the team was that
a significant ground
may occur before
the trip point setting of the associated
relay was reached
(175 volts for the
250
VDC and 240
VDC for the
125
VDC battery systems).
FINDING 8:
Improper Breaker Replacement
(paragraph
4.2)
DESCRIPTION:
The team identified that circuit breaker
changeouts
in the 480
V SDBs
had
resulted in two non-class
lE breakers
being placed in class
lE SDBs.
The
licensee identified that this improper circuit breaker
changeout
had occurred
in two instances.
The circuit breakers for 480
V SDB 2A, cubicle
3D and
480
V
SDB 3A, cubicle
2B were improperly replaced.
The licensee
issued
a problem
evaluation report
BFPER920039 to investigate this occurrence.
SAFETY SIGNIFICANCE:
Replacement
of class
1E circuit breakers with non-class
lE breakers
could
result in failure of the circuit breakers
during
a design basis
event
and
unavailability of safety related
equipment.
FINDING 9:
Configuration Control
(paragraph
4.2)
DESCRIPTION:
The team found the drawings for the
EDS correctly reflected the installed
condition of the
EDS with several
exceptions.
Instances
were found where
configuration control
had not been maintained.
In 480
V RMOV board
2A, 30
ampere
breakers
were installed for the inboard
and outboard core spray valves
of compartments
13B and
14B.
Drawing 2-45E751-1
indicated that
a 7 ampere
breaker
was required for these circuits.
In 480
V RMOV board
2B,
a 30 ampere
breaker
was installed for the inboard core spray valve.
Drawing 2-45E751-1
indicated
a
7 ampere
breaker
was required for this circuit.
The licensee
initiated work request to replace the breakers.
During the inspection of the
DGs, the team identified another incorrectly
installed circuit breaker.
Drawing 0-761E580-1 required
a 30 ampere
breaker
for the
DG start circuit 1.
The team observed
a 50 ampere breaker installed
in this circuit;
During the inspection of the battery chargers
the team observed
unterminated
and unidentified wiring in 250
VDC battery chargers
1,
2A, 2B,
3 and 4.
Improperly terminated
spare. cables
were found inside
250
VDC RHOV board
2A,
cubicle 7A.
The team noted during the inspection of the battery chargers that the position
of the
SD battery charger
spare disconnect
switch for chargers
B and
C were in
the "on" position.
Drawing 0-45E709-I indicated that the switch should
be in
the "off" position when the spare
charger
was not in use.
SAFETY SIGNIFICANCE:
Loss of configuration control
can result in lack- of plant integrity and
failure of safety
systems
to operate
in accordance
with design requirements.
FINDING 10: Cracked
Thermal
(paragraph
4.2)
DESCRIPTION:
The team noted instances
of cracked
thermal overload relays.
The relays
were
found in 480
V RMOV board
2A, cubicles
4E,
10A,
and
17A.
Cracked thermal
were also found in 250
VDC
RMOV board
2B, cubicle 5B.
Work
requests
were issued
by the licensee to replace
the cracked thermal overloads.
SAFETY SIGNIFICANCE:
Failure of thermal
overload relays could result in improper operation of the
relays
and unavailability of, safety equipment.
FINDING ll: Battery Capacity:
(paragraph
4.3)
DESCRIPTION'he
team noted that several
batteries
were nearing the replacement criteria of
80 / capacity.
Diesel
Generator
C battery
was at 80.67
% capacity.
The
licensee
indicated that during the next refueling outage the Hain Bank
2 and
Main Bank 3 batteries
were scheduled for replacement.
Also, scheduled for
replacement
were
SD batteries
A, B, C,
D,
and
3EB and
DG batteries
A, B,
C, D,.
3A, 3B,
and 3C.
SAFETY SIGNIFICANCE:
Inadequate
battery capacity could result in unavailability of battery
power to
meet design loading requirements
for the battery during loss of ac power.
AECL
A-H
AWG
C
EDS
~EDSFI
Eg
DCN
F
GDC
Hp
IS,C
IIR
IFI
IEEE
kA
KVA
kv
kW
LER
RMOV
SDB
SCAR
TD
TFR
TS'SST
VAC
VDC
APPENDIX B
ABBREVIATIONS AND ACRONYMS
Centigrade
Diesel Generator
Engineering
Change Notice
Electrical Distribution System
Electrical Distribution System Function
Emergency
Equipment Cooling Water
Environmental gualification
Design
Change Notice
al Inspection
Emergency Safety Function
Fahrenheit
Final Safety Analysis Report
General
Design Criteria
Horsepower
High Pressure
Coolant Injection
Heating, Ventilation and Air Conditioning
Instrumentation
5 Control
Incident Investigation Report
Inspector Follow-up Item
'nstitute
of Electrical
and Electronic
Kiloampere
Kilovolt-Ampere
Kilovolts
Kilowatts
License
Event Report
Loss of Coolant Accident
Motor Control Center=
Motor Generator
Planned
Maintenance
Post Modification Testing
Reactor
Core Isolation Coolant
Residual
Heat
Removal
Reactor
Heat
Removal Service
Water
Reactor 'Protection
System
Reactor Protection Trips
Reactor
Motor-Operated
Valve
Shutdown
Bus
Station Black Out
Significant Corrective Action Report
Safety Evaluation Report
Test Deficiency
Trend Failure Report
Technical Specification
Unit Station Service Transformer
Volts Alternating Current
Volts Direct Current
Violation
Engineers
Atomic Energy Canada,
Ltd.
Ampere Hour
American Society,
Heating, Refrigeration,
and Air Conditioning
Engineers,'nc.
American Wire Gauge
l ~
APPENDIX C.
PERSONS
CONTACTED
Licensee
Employees
J.
- H
- R
- D
D.
- C
- H
- R.
- J
T.
- S
R.
D.
H.
- R.
- D
T.
- J
F.
D.
+J
E.
R.
J.
- p
K.
B.
- S
- W.
- H.
"R.
- D
Ballard, Principle Engineer
Bajestani,
Technical
Support
Manager
Baron,
Manager Licensing
Burrell, Lead Electrical Engineer-
Byers,
System Engineer,
Diesel
Generators
Crane,
Maintenance
Manager
Crisler, Site Engineer-
Cutsinger, Civil Engineer
Dollar, Shift Operating Supervisor
Elms, Assistant Shift Supervisor
Hilmes, Supervisor
Technical
Support,
IKC
Hyde,
Procurement
Lead Engineer
Johnson,
Electrical Engineer
Jones,
.Engineering Specialist
Jones,
Operations
Superintendent
Kehoe,
gA
Langley, Principle Engineer
Maddox, Engineering
Manager
McCluskey, Vice President
Restart
Melville, Document Control
Nicely, Corporate
Senior Electrical
Engineer
Ridgell, Compliance
Engineer
Rogers,
Supervisor
Maintenance
Rupert,
Manager Engineering Modifications
Salas,
Compliance
Manager
Schouten,
Bechtel Calculation Engineer
Shingleton,
Compliance
Engineer
Spencer,
Licensing Project Manager
Troutt,
gA Specialist
Turner guality Assurance
Manager
Wright, Principal Electrical
Engineer
Zerinque,
Vice President
Browns Ferry
.*Attended exit meeting