ML18026A401

From kanterella
Jump to navigation Jump to search
Insp Repts 50-387/90-20 & 50-388/90-20 on 900902-1006. Violation Noted.Major Areas Inspected:Operations, Radiological Controls,Maint/Surveillance Testing,Emergency Preparedness,Security,Engineering/Technical Support
ML18026A401
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 11/08/1990
From: Swetland P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18026A402 List:
References
50-387-90-20, 50-388-90-20, NUDOCS 9011210062
Download: ML18026A401 (39)


See also: IR 05000387/1990020

Text

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION I

1)

Report

Hos.

50-387/90-20;

50-388/90-20

License

Nos.

NPF-14;

NPF-22

Licensee:

Pennsylvania

Power

and Light Company

2 North Ninth Street

Allentown, Pennsylvania

18101

Facility Name:

Susquehanna

Steam Electric Station

Inspection At: Salem Township, Pennsylvania

Inspection

Conducted:

Inspectors:

September

2,

1990 - October 6,

1990

G.

S. Barber,

Senior Resident

Inspector,

SSES

J.

R. Stair,

Resident

Inspector,

SSES

C.

H. Woodard,

Senior Reactor

Engineer,

DRS

P.

D.

Kaufman, Project Engineer,

DRP

Approved 8

~

~

P.

D. Swetland,

Chic

Reactor Projects

Section

No.

2A,

F

Ins ection

Summar

Date

Areas

Ins ected:

Routine inspections

were conducted

in the following areas:

operations,

radiological controls, maintenance/surveillance

testing,

emergency

preparedness,

security,

engineering/technical

support,

safety

assessment/quality

verification,

and Licensee

Event Reports

(LER),

Significant Operating

Occurren'ce

Reports,

and Open

Item Followup.

Results:

During this inspection period, the inspectors

found that the

licensee's

activities were directed

toward nuclear

and radiation safety.

One

violation and'o deviations

were identified.

An Executive

Summary is

included

and provides

an overview of specific inspection findings.

901 121 0062 901 109

PDR

ADOCK 05000387

Q

PNU

a

TABLE OF CONTENTS

I.

EXECUTIVE SUMMARY

II .

DETAILS

1.

SUMMARY OF OPERATIONS

Page

1. 1

Inspection Activities

.

1.2

Susquehanna

Unit 1.

1.3

Susquehanna

Unit 2.

2.

OPERATIONS

1

1

1

2.1

Inspection Activities ..... ~........

1

2.2

Inspection

Findings

and Review of Events

.

.

.

.

.

2

2.2. 1

"C" Diesel Generator

Inadvertent Start

.

.

.

.

.

.

2

3.

RADIOL'OG ICAL CONTROLS

3.1

Inspecti on Activities

.

3 '

Inspections

Findings

4.

MAINTENANCE/SURVEILLANCETESTING

2

2

4.1

4.2

4.3

4.4

Maintenance

and Surveillance

Inspection Activity

Maintenance

Inspection Activities

.

Surveillance

Inspection Activity

Inspection

Findings

.

5.

EMERGENCY PREPAREDNESS

5. 1

Inspection Activity .

5.2

Inspection

Findings

.

6.

SECURITY

6.1

Inspection Activity .

6.2

Inspection

Findings

.

7.

ENGINEERING/TECHNICAL SUPPORT

7. 1

Inspection Activity .

7.2

Inspection

Findings

.

7.2. 1

Diesel Generator

Damage

Due to Sandblast Grit

8.

SAFETY ASSESSMENT/QUALITY VERIFICATION

4

5

5

5

C

8.1

8.1.1

8.1.2

8.1.3

Licensee

Event Reports, Significant Operating

Occurrence

Reports,

and

Open Item Fo11owup

Licensee

Event Reports

Significant Operating Occurrence

Reports

Open

Items

7

~

>

7

8

8

9.

MANAGEMENT AND EXIT MEETINGS

9 '

Routine Resident Exit and Periodic Me'etings

9.2

Attendance

at Management

Meetings

Conducted

By

Region

Based

Inspectors

13

13

EXECUTIVE SUMMARY

Susquehanna

Inspection

Reports

50-387/90-20;

50-388/90-20

September

2,

1990

-

October 6,

1990

~0 eratioaa

(30703,

71707)

Operators effectively controlled plant evolutions

and identified plant

problems.

An inadvertent start of the "C" Diesel Generator

was appropriately

responded

to by plant operators.

Radiolo ical Controls (71707)

Individual workers

and Health Physics

personnel

implemented radiological

. protection

program requirements.

Periodic inspector observation

noted'no

inadequacies

in the licensee's

implementation of the radiological protection

program.

Maintenance/Surveillance

(61726',

62703)

Inadequate

cleanliness

control of DG intercooler cleaning resulted

in

intrusion of sandblast

in the "B" and "D" DGs air intake and combustion

chambers.

In addition,

one safety

system actuation

was attributable to

surveillance activities.

This occurred

when the "C" DG inadvertently started

during'erformance

of a 4160V

ESS

bus undervoltage

channel calibration.

a

Emer enc

Pre aredness

No emergency

preparedness

issues

emerged

during the period.

~Securit

(71707)

r

Routine observation of protected

area

access

and egress

control

showed

good

control

by the licensee.

En ineerin /Technical

Su

ort (71707,

92720,

93702,

35702)

The effects of intrusion of sandblast grit into the "B" and "D" DGs was

evaluated

and repairs

were performed to return the

DGs to operable

status.

Your lack of procedures

to direct sandblasting

of these

intercoolers

along

with poor control of the work activity was

a significant weakness.

One

violation was identified.

Safet

Assessment/Assurance

of ualit

(90712,

92700,

92701,

92720)

A total of 75 Significant Operating

Occurrence

Reports

were reviewed during

the period,

2 of which were followed up in this report.

0

Details

SUMMARY OF OPERATIONS

Ins ection Activities

1.2

The purpose of this inspection

was to assess

licensee activities at

Susquehanna

Steam Electric Station

(SSES)

as they related to reactor

safety

and worker radiation protections

Within each inspection area,

the inspectors

documented

the specific purpose of the area

under

review,

the

scope of inspection activities and findings, along with appropriate

conclusions.

This assessment

is based

on actual

observation of licensee

activities, interviews with licensee

personnel,

measurement

of radiation

levels,

independent

calculation,

and selective

review of applicable

documents.

Abbreviations are

used throughout the text.

Attachment

1

provides

a listing of these abbreviations.

Sus

uehanna

Unit 1 Summar

1.3

Unit

1 entered

the inspection period at

99 percent full power,

commencing

coastdown at approximately one-half -percent

per day until

beginning the unit's fifth refueling outage.

Shutdown

began

on

September

11,

and the turbine generator

was taken off line at 3:46 a.m.

on September

12.

Cold shutdown

was achieved

on September

14 at 12:05

a.m.

During the period,

a full core offload was completed

and major

work on

ECCS

and

ESF systems

was performed.

On October 4,

an

inadvertent start of'he "C" Emergency

Diesel Generator

occurred while

performing

a surveillance.

See Section 2.2. 1 for details.

Sus

uehanna

Unit 2 Summar

Unit 2 operated at or near full power for the entire inspection period.

Scheduled

power reductions

were conducted during the period for control

rod pattern adjustments,

surveillance testing,

and maintenance.

No ESF

actuations

or scrams

occurred during the period.

2.

OPERATIONS

2.1

Ins ection Activities

The inspectors verified that the facility was operated

safely

and in

conformance with regulatory requirements.

Pennsylvania

Power

and Light

(PP8L)

Company

management

control

was evaluated

by direct observation of

activities, tours of the facility, interviews

and discussions

with

personnel,

independent verification of safety

system status

and Limiting

Conditions for Operation,

and review of facility records.

These

inspection activities were conducted

in accordance

with NRC inspection

'rocedure

71707.

The inspectors

performed

177 hours0.00205 days <br />0.0492 hours <br />2.926587e-4 weeks <br />6.73485e-5 months <br /> of normal

and back shift inspections

including deep backshift inspections

on September

7, from 1:45 a.m. to

6:00 a.m.;

September

22, from,7:00 a.m. to 2:00 p.m.;

and,

September

28,

from 4:00 a.m. to 6:00 a.m.

2.2

Ins ection Findin

s and

Review of Events

2.2. 1

"C" Diesel Generator

Inadvertent Start

At 8:40 a.m.

on October 4,'an inadvertent start of the "C" DG

occurred.

The start occurred during performance of the

18 month

undervoltage

channel calibration

on 4160

VAC ESS

bus

1A203 when the

DC

knife switch supplying control

power to the bus

was reclosed.

To

prevent the

DG from starting during the surveillance,

the

DC knife

switch is to be opened,

the fuses

labeled

"Sequence

Start" are to be

removed

and the

DC knife switch then reclosed

to restore control

power

to the bus.

Due to labeling

and permit wording problems,

incorrect fuses

labeled "Diesel. Generator Start" were pulled leaving

the

DG start logic intact.

When the

DC knife switch was then reclosed

and the undervoltage

sensed,

the

DG started

per design.

The licensee

determined

the root cause to be due to inconsistencies

between

design

drawing nomenclature

and labeling of the fuses to the

DG start logic

in conjunction with wording on the permit which was not precisely in

accordance

with the labeling.

The "C" DG was shut

down 22 minutes later

and work was temporarily

stopped to determine

why the

DG started.

The permit was then

changed

to more clearly reflect the labeling wording for the correct fuses.

The appropriate

ENS call per

10 CFR 50.72

was

made within the required

time period.

An interim Operational

Instruction

was issued

which

dictates that there shall

be absolute

agreement

between

Equipment

Release

Forms,

Permits,

and field labeling.

If there

are differences

between field labeling and the permit, permit tags shall not be

applied.

Other actions

being evaluated

to prevent

a recurrence

are to

develop

a switchgear inspection

plan for fuse identification, labeling

and drawings for potential

improvements

and for electrical

maintenance

to address

switching error

actions'he

inspector

discussed

the event

and the corrective actions

taken

and

being evaluated with plant personnel.

The inspector

considered

the

licensee's

acti'ons

in response

to the event appropriate.

However,

this event

was significant because it had the potential to cause

severe

personnel

injury and/or

damage

safety related

equipment.

RADIOLOGICAL CONTROLS

3.1

Ins ection Activities

PPKL's compliance with the radiological protection

program

was verified

on

a periodic basis.

These inspection activities were conducted

in

accordance

with NRC inspection

procedure

71707.

3.2

Ins ection Findin

s

Observations

of radiological controls during maintenance

acti'vities and

plant tours indicated that workers generally

obeyed postings

and

Radiation Work Permit requirements.

No inadequacies

were noted.

Y,

4.

MAINTENANCE/SURVEILLANCE

4.1

Maintenance

and Surveillance

Ins ection Activit

On

a sampling basis,

the inspector

observed

and/or reviewed selected

surveillance

and maintenance activities to ensure that specific

programmatic

elements

described

below were being met.

Details of this

review are documented

in the following sections.

4.2

Maintenance

Observations

The inspector

observed

and/or reviewed selected

maintenance activities

to determine that the work was conducted

in accordance

with approved

procedures,

regulatory guides,

Technical Specifications,

and industry

codes or standards.

The following items were considered,

as applicable,

during this review:

Limiting Conditions for Operation

were met while

components

or systems

were

removed

from service;

required administrative

approvals

were obtained prior to initiating the work; activities were

accomplished

using approved

procedures

and quality control hold points

were established

where required;

functional testing

was performed prior

to declaring the involved component(s)

operable; activities were

accomplished

by qualified personnel;

radiological controls were

implemented; fire protection controls were implemented;

and the

equipment

was verified to be properly returned to service.

These observations

and/or reviews included:

"B" DG inspection of damaged cylinder liners, pistons,

etc.

on

September

5,

1990.

VOTES

MOV Diagnostic Test of HPCI

F002 Valve per

WA S00691

on

September

27,

1990.

"D" DG removal inspection

and installation of cylinder heads

per

WA

S04803

on September

28,

1990.

Removal

and capping of

1 inch

HRC 108/1 inch JRD 128 pipe section

for ESW modification per

WA C03543

on September

28,

1990.

Installation of Unit

1

ESW Loop "A" Supply and Return Lines

Building Freeze

Seal

Spools

and Valves per

WA C03581

on September

28,

1990.

Installation of new

RHRSW Loop "A" Heat Exchanger Inlet Outboard

Isolation Butterfly Valve per

WA C03430

on September

28,

1990.

4.3

Surveillance

Observations

The inspector

observed

andlor reviewed the following surveillance tests

to determine that the following criteria, if applicable to the specific

test,

were met:

the test conformed to Technical Specification

requirements;

administrative

approvals

and tagouts

were obtained before

initiating the surveillance;

testing

was accompli shed

by qualified

personnel

in accordance

with an approved

procedure;

test instrumentation

was calibrated;

Limiting Conditions for Operations

were met; test data

was accurate

and complete;

removal

and restoration

of the affected

components

was properly accomplished;

test results

met Technical

Specification

and procedural

requirements;

deficiencies

noted were

reviewed

and appropriately resolved;

and the surveillance

was completed

at the required

frequency.

These observations

and/or reviews included:

SO-024-013

"Offsite Power Source

and Onsite Class

1E Operability Test"

performed

on September

7.

SO-251-002

"Quarterly Core Spray

Flow Verification," - Unit 2,

performed

on September

21.

SI-180-303

"18 Month Calibration of Reactor

Vessel

Water

Level Channels

LIS-B21-1N031A,B,C,D," - Unit 1, performed

on September

27.

SO-151-002

"Quarterly Core Spray

Flow Verification,"

LOOP "A" Unit 1,

performed

on October 5.

4.4

1ns ection Findin

s

The inspector

reviewed the listed maintenance

and surveillance

activities.

The review noted that work was properly released

before its

commencement;

that systems

and components

were properly tested

before

being returned to service

and that surveillance

and maintenance

activities were conducted properly by qualified personnel.

Where

questionable

issues

arose,

the inspector verified that the licensee

took

the appropriate

action before system/component

operability was declared.

No unacceptable

conditions were identified.

5.

EMERGENCY PREPAREDNESS

5. 1

Ins ection Activit

The inspector

reviewed licensee

event notifications

and reporting

requirements for events that could have required entry into the

emergency

plan.

5.2

Ins ection Findin

s

No events

were identified that required

emergency

plan entry.

No

inadequacies

were identified.

6.

SECURITY

6. 1

Ins ection Activit

PP5L's

implementation of the physical security program was verified on

a

periodic basis,

including the adequacy

of staffing, entry control, alarm

stations,

and physical

boundaries.

These

inspection activities were

conducted

in accordance

with NRC inspection

procedure

71707.

6.2 'ns ection Findin

s

The inspector

reviewed access

and egress

controls throughout the period.

No unacceptable

conditions were noted.

7.

ENGINEERING/TECHNICAL SUPPORT

7. 1

Ins ection Activit

The inspector periodically reviewed engineering

and techni'cal

s'upport

activities during this inspection

period.

The on-site Technical

(Tech)

section,

along with Nuclear Plant Engineering

(NPE) in Allentown,

provided engineering

resolution for problems during the inspection

period.

The Tech section generally addressed

the short term resolution

of problems while NPE scheduled

modifications

and design

changes,

as

appropriate,

to provide long lastirig problem correction.

The inspector

verified that problem resolutions

were thorough

and addressed

at

preventing

recurrences.

In addition, the inspector

reviewed short term

actions to ensure that the licensee's

actions

provided reasonable

assurance

that safe operation could be maintained.

7.2

Ins ection Findin

s

7.2. 1

Diesel Generator

Dama

e

Due to Sandblast Grit

As previously discussed

by

NRC Inspection

Report 50-387/90-15,

the "B",

and "D" EDG units'ngines

were extensively

damaged

by grit which was

introduced into the engines

by means of residual

sandblast grit from

the maintenance

cleaning of the cooling water tubes of the

turbocharger

intercoolers.

The licensee

removed the air intake manifolds

and the intercoolers

from the

EDG units.

The intercoolers

were purged of entrained

sandblast grit within the cooling fin assembly

by means of an agitated

hot water solvent bath over

a period of several

hours in which the

solvent

was replaced with new solvent several

times until the coolers

were considered

to,be adequately

cleaned.

The coolers

were then

0

subjected

to high velocity air purging in order to assure

that

combustion air through the coolers

would not transport

any additional

material

from the finned intercoolers.

During this cleaning

process

the licensee

removed

more than

a cup of sandblast grit from each

intercooler.

The licensee's

cleaning

procedures

appeared

to be

adequate

for the, removal of the grit from the intercoolers.

Mith the aid of the

EDG manufacturer's

field service personnel,

the

licensee

conducted detailed degradation

evaluation

inspections

of the

engine parts which may have

been

subjected

to the sandblast grit.

Engine

components

examined

include pi'stons, cylinder liners, cylinder

heads,

valve components,'rankshaft

journals,

connecting

rod bearings,

and engine driven oil pumps.

The licensee

found it necessary

to

replace

several

pistons,

piston wrist pins,

and cylinder liners on

each of the

EDG units.

Examination of selected

crankshaft journals

and connecting

rod bearings

did not reveal

evidence of abrasive grit

inclusion in the bearings

or scoring of the crankshaft journals.

Examination of oil pump lobes

revealed

no degradation.

Intake

and

exhaust

valves

and valve guides

were

undamaged.

Valve seats

were

refurbished

where necessary.

The camshaft,

cams

and bearings

revealed

no degradation.

The inspector

reviewed the licensee's

acceptance/rejection

criteria

for the pistons, wrist pins and cylinder liners

and performed

an

independent

visual inspection of these parts.

Based

upon these

inspection observations, it appeared

that the licensee's

inspection

criteria was adequate

to ensure

the detection

and replacement

of

defective

components.

Sand/grit in the cylinders which abrades

the piston

and cylinder liner

surfaces

can fall into the lubricating oil.

The licensee

performed

sampling

and analysis

to determine

the lubricating oil system

had

been

contaminated with abrasive particulate materials.

Findings were

as

follows:

Four main lube oil filter elements

The filters contained

what

"appears

to be very small metallic particles with a few glassy

particles" which were 1-2 'mils in size.

Oil sample

downstream of the oil filter - Analysis of this sample

revealed

no abrasive

contaminants.

Oil strainer

(downstream of oil filter) - The strainer

was found to

be contaminated

with what "appears to be construction debris

brass particles,

rust, glassy

spheres

and angular particles.

Two oily rags with oil wiped from the inside of oil delivery hoses

to main bearings.

Each of these

rags

had

a small quantity of fine

black and glassy particles

1-2 mils in size.

(Bearing to crank

clearances

are 7-8 mi ls.)

Turbocharger filter element.

This filter contained

"a very small

quantity of fine black and glassy particles

1-2 mils in size.

The

glassy particles

were described

as "ground up white, clear

particles."

From these

analyses

and the directly observable

good condition of the

engine bearing

surfaces

(which were not exposed

to direct

impingement'f

the sandblast grit), it appeared

that the oil filters provided

effective removal of any of the grit which did not settle to the

bottom of the crankcase.

In order to remove

any residual

sand

from

the oil system,

the licensee

flushed the oil system,

hand wiped the

crankcase,

replaced

the engine oil with fresh oil and installed

new

oil filters.

The inspector

reviewed the licensee's

evaluation of the potential root

causes.

The licensee

considered

procedural

deficiencies

and poor work

practices

to be the primary root causes

why the cleaning

sand

was

permitted to enter

and

become

lodged within the finned assembly of the

air side of the coolers.

Combustion air through the intercoolers

then

transported

the grit directly into the cylinders'ombustion

chambers

which resulted

in the internal

engine

damage,

The inspector

agreed

with the licensee's

root cause

assessment.

The failure of the licensee

to establish

and implement documented

instructions,

procedures,

and

controls for this critical sandblast

operation of class

1E equipment

is considered

a violation of 10 CFR 50 Appendix

B Criterion V.

(NV4

50-387/90-20-01

(Common))

8.

SAFETY ASSESSMENT/QUALITY VERIFICATION

8. 1

Licensee

Event Reports

(LER), Significant Operating

Occurrence

Report

(SOORs),

and

Open

Item (OI) Followup

(90712,

92700)

8. 1. 1

Licensee

Event

Re orts

The inspector

reviewed

LERs submitted to the

NRC to verify that

details of the event were clearly reported,

including the accuracy of

the description of the cause

and the adequacy of corrective action.

The inspector determined

whether further information was required

from

the licensee,

whether generic implications were involved, and whether

the event warranted onsite followup.

The following LERs were

reviewed:

Unit

1

90-018-00

Sand Intrusion Resulted

in Two Diesel Generators

Becoming

Inoperable.

This event was,reviewed

in Inspection

Report

50-387/90-15;

50-388/90-15

and in Section 7.2. 1 of this

repor t.

SOORs are provided for problem identification and tracking, short

and

long term corrective actions,

and reportability evaluations.

The

licensee

uses

SOORs to document

and bring to closure

problems

identified that

may not warrant

an

LER.

The inspectors

reviewed the following SOORs during the period to

ascertain

whether:

additional

followup inspection effort or other

NRC

response

was warranted;

corrective action discussed

in the licensee's

report appears

appropriate;

generic

issues

are assessed;

and,

prompt

notification was

made, if required:

Unit

1

61

SOORs inclusive of 1-90-237 through 1-90-298

Unit 2

14

SOORs inclusive of 2-90-113 through 2-90-127

The following SOORs required inspector

fol,lowup:

1-90-294

documented

the inadvertent start of th'e "C" DG.

This event

is discussed

in Section

2'. 1.

1-90-242

documented

high chromium concentration

in the "8"

DG lube

oil.

This event

was reviewed in Inspection

Report

50-387/90-15;

50-388/90-15

and in Section 7.2.1 of this

report.

8.1.3

~0ee

Items

8. 1.3. 1

Closed

NC4 387/85-28-03.

388/85-23-02

Failure to Test Entire

Channel

Durin

Channel

Functional

Tests of HPCI Isolation and

Actuation Channels

During Routine Resident

Inspection

50-387/85-28;

50-388/85-23,

which

covered

the period August 26,

1985 through September

29,

1985,

one

violation concerning

HPCI monthly channel

functional tests

was

identified.

The inspector determined that the monthly channel

Functional

Tests

on the

HPCI isolation

and actuation

channels

did

not test the entire channel

as required

by the unit's TS.

Specifically, surveillance

procedures

SI-152-203,

SI-152-201,

SI-152-211,

and SI-180-205,

which implemented this requirement

on

the

HPCI steamline delta pressure

channels,

steam

supply pressure

~

channels,

turbine exhaust

diaphragm pressure

channels,

and the high

reactor

vessel

level trip channels,

respectively,

failed to test the

entire channel

since it did not test the last relay in the actuating

logic.

The corresponding

Unit 2 surveillance

procedures

also failed

to test the entire channel.

The response

by P.P.& L., dated

November

15,

1985,

requested

that

the Notice of Violation be withdrawn, since their position was that

testing in accordance

with their referenced

surveillance

procedures

represented

a valid interpretation of TS requirements,

rather than

a

noncompliance.

More specifically,

P.P.& L. disagreed

with the

use

of "channel"

as defined in IEEE Std. 603-1977 in the context of the

Channel

Functional

Test required

by TS.

The

SSES

TSs refer to an

instrumentation

channel

when requiring Channel

Checks,

Channel

Functional Tests,

and Channel

Calibrations.

P.P.& L. noted that the

IEEE standards

do not utilize the word instrumentation

in their

definition because

their

use of the channel

concept is not limited

to instrumentation.

In addition,

P.P.& L. stated that the

associated

relays

and contacts

referred to in the inspection report

are what is included in a Logic System'unctional

Test which is

performed

on an

18 month frequency.

P.P.& L. addressed

IE

Information Notice 84-37 which discussed

mitigation of the

potentially adverse

safety

impact of using jumpers

and lifting leads

in support of surveillance testing to note the potential

adverse

impact of performing,

as defined,

Channel

Functional

Tests,

in this

case,

since

they would require lifted leads

on booted contacts

and

could lead to system isolations.

Finally, P.P.& L. addressed

ANSI/IEEE Std. 338-1977

in support of their position to note that

the additional

burden

on plant resources

would be significant.

The

licensee

believes that these factors provide sufficient

justification for defining the end of an instrument channel.

Their

definition specifies

the instrument

channel

endpoint for the purpose

of channel

functional testing

as being the input node(s) of the coil

of the actuated

relay(s) which enter into combinational

logic with

logic provided

by other channels.

P.P.& L. believes this definition

satisfies

the requirements

of their TS in that it tests all alarm

and/or trip functions of the channel

and at the

same

time minimizes

equipment,

personnel,

and time in test status.

Their position was

established

to prevent the degradation

of the safe operation of

SSES.

Following the

November

15,

1985 letter,

NRC Region

1 in conjunction

with NRR reviewed P.P.

& L.'s response.

This review resulted

in the

initial determination that P.P.& L.'s methods

were not acceptable

because

certain

components

in the channel

upstream of the

combinatorial

logic are excluded

from the

CFT.

A CFT must test to

the point where single action signals

are combined.

An entire

channel

includes all contacts,

relays,

indications,

and alarms which

precede

the combinatorial logic.

In addition,

P.P.& L.'

contention

that "channel"

may be defined other than

as in the industry

standards

because

the

TSs

use the modifier "instrumentation" is

unacceptable.

On March 5,

1986,

NRC Region I responded

to P.P.& L.'s November 15,

1985 letter.

This letter informed P.P.& L. that Region I in

conjunction with NRR reviewed

and found P.P.& L.'s response

to the

10

violation unacceptable.

It was noted that

CFTs for instrumentation

channels

must test all components

up to the point where single

action signals

are

combined

and that P.P.& L.'s methodology for CFTs

for HPCI and other

ECCS and Isolation actuation

systems

excludes

certain

components (e.g., relays)

in the channel

upstream of the

combinatorial logic.

A meeting

was held

on March 14,

1986 at the

Region I office in King of Prussia,

PA, to discuss

P.P.& L.'

plans

and schedule

to correct the testing deficiencies

in the

CFTs for

instrumentation

channels.

On April 22,

1986,

a letter from P.P.& L. was sent to the

NRC Region

I to supplement

information provided in the November

15,

1985 letter

and the meeting

on March 14,

1986.

Information requested

in the

March meeting

was provided in addition to commitments

by P.P.& L. to

further enhance

the effectiveness

of their channel

functional tests.

Information provided included:

( 1)

A statement

of P.P.& L.

philosophy for Conduct of Instrument

Channel

Functional Testing,

(2)

Description of the Channel

Functional

Tests which do not conform to

existing

NRC criteria, (3) Example of the potential benefits of

extending

the

scope of the monthly channel

functional tests,

and (4)

P.P.& L.'

experience with relay failures.

P.P.& L. noted that

there are

28 monthly channel

functional tests

which do not conform

to the

NRC criteria and these

represent

approximately

10 percent of

required tests.

Following the March 14,

1986 meeting

and P.P.& L.'s submittal of the

additional

information requested,

P.P.& L.'s failure to test the

entire

HPCI isolation

and actuation

channels

during functional

testing

was revisited.

NRR found from this review that the design

of the 28 instrument channels

affected did not provide the

same

degree of testability of the function of the channel

to initiate the

actuation logic as originally intended

by the= station's

TSs.

Addi-

tionally,

NRR determined that testing performed

up to the last relay

may damage plant equipment or disrupt reactor operation

and that

implementation of R.G.

1.22 recommendations

would require

an excessive

number of lifted leads,

jumpers,

or placing the actuated

equipment

in an inoperable

status.

As indicated

by the licensee,

these relays

are the

same type that get exercised

monthly in other safety

systems

and

have

a demonstrated reliability.

NRR therefore determined that

the program for instrument

channel

functional testing at Susquehanna

was adequate.

In conclusion,

the

NRC found that the referenced

instrument channels

failed to provide the intended

degree of testability.

This constitutes

a deviation from design basis

commitments

and therefore

should

have

been highlighted for staff review prior to plant licensing,

rather

than after the

1985

NRC inspection.

The additional

information

PP&L

provided following the March 1986 meeting regarding

the

HPCI instru-

mentation's

design

was sufficient to allow NRC staff to determine

that

PP&L CFT methodology

was acceptable

for these

items.

Since the

original lack of full testability was

a failure to meet industry

standards

rather than

a failure to meet

a regulatory requirement,

the

1985 Notice of Violation is withdrawn.

This item is closed.

e

11

NRC acceptance

of P.P.& L.'s methodology applies,

of course only to

those limited cases explicitly addressed

during

NRC review of this

item.

Any future additions and/or modifications to channel

logic

shall

conform to all requirements

applicable to Susquehanna.

8. 1.3.2

Closed

UNR 50-387/89-28-04

Common

0 erabi lit

Re uirements for

Control Structure Ventilation Fans

During

a routine inspection,

an

NRC inspector

noted that six Control

Structure

Heating, Ventilating and Air Conditioning

(CSHVAC) fans

(OV-103A and B, OV-115A and B, OV-117A and B) were not included in

TS.

The inspector also noted that these

fans provided direct

support to the operability function of CREOASS

and was concerned

when

no

TS could be found to address their operability.

The

licensee

agreed to review this'oncern.

Two additional

concerns

were also noted with transient

equipment control

and the proper

latching of the suction

plenum doors during

a tour of the area.

The licensee

addressed

the inspector's operability concern

(PLIS-34529)

by writing a Technical Specification Interpretation

(TSI) 1-90-001 to be used

by control

room operators that requires

plant shutdown if one division of CSHVAC is inoperable for greater

than

30 days.

If both divisions of CSHVAC are inoperable,

plant

shutdown is required in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

In addition, the licensee

is

completing their evaluation of the

CSHVAC safety functions.

After

it's completed,

the licensee

has

agreed to consider requesting

a

TS

amendment

to address

the results of thei r evaluation.

The transient

equipment control issue

was discussed

with the

licensee

and the licensee

discussed it with the work crew and agreed

to write a transient

equipment control procedure

by December

31,

1990.

Poor control of transient

equipment

and tools was also noted

in previous inspections

and unresolved

items were written to document

these

findings and follow the corrective actions.

The transient

equipment control procedure will be reviewed under unresolved

items

50-387/87-12-004

and 89-81-002.

The inspector

had noted during inspection

89-28 that only three of

nine latches

were secured

on the suction

plenum door.

The licensee

classified this as

an undesirable

work practice

and its correction

was emphasized

with maintenance

personnel.

The safety significance

of the concern

was minimized since the fan suction

plenums are

maintained at

a slightly negative

pressure

which tends to hold the

doors closed.

The inspector

reviewed the licensee's

response

and noted that the

TSI adequately

address

the operability support function of CSHVAC

along with the licensee

agreement

to consider

a

TS amendment.

The

transient

equipment

and tools were

secured

and long term corrective

action

was provided.

The fan doors

were secured

and the licensee

noted this as

an undesirable

work practice.

Based

on the "above,

this item is closed.

I

12

Closed

UNR 50-387/85-09-01

Corrective Actions to Enhance

the

Vent Stack Monitorin

S stem

In May 1983,

the licensee identified a number of deficiencies with

the vent stack monitoring system

(SPING) operator interface

and

system design.

Thus,

the licensee

developed

a

SPING enhancement

project intended to improve the design of the vent stack monitoring

system

and its operator interaction.

The

SPING enhancement

project

was divided into five phases,

each consisting of various Design

Change

Packages

(DCP's) to install modifications to resolve the

identified deficiencies.

These

improvement modifications

can

be

accomplished

without affecting the system's

operation

and without an

outage.

Scope

and funding is complete for phases

1, 2,

and 4.

Some

of the DCP's/modifications within phase

1 and

4 have

been installed

and implemented (i.e.,

low point drain installation

on the Post

Accident Vent Stack Sampling Station

sample tubing and installation

of shut-off quick disconnects

on the sentry cart isolation valve

sample tubing).

Phase

1 includes the installation of a

new improved

control terminal insert to be supplied

by Eberline

and the redesign

of the Susquehanna

Terrain-Incorporating

Regional Effluent

Assessment

Model

(STREAM) interface

and is scheduled for

installation in December

1990.

The inspector

determined that the licensee

has developed

a thorough

an extensive

program to improve the performance of the vent stack

monitoring system.

Some of the planned

improvements

have already

been

implemented,

and the remaining

system

upgrades

are identified

and accurately

tracked

on the licensee's

Plant Problem List.

Therefore, this issue is considered

closed.

Even though this issue is closed,

the inspector considers

the

licensee's

actions untimely.

This item has

been

in process for

greater

than

seven years with little or no modification to the

power plant.

The inspector

has

noted that licensee

actions in

resolving technical

problem that require plant modification are

generally protracted.

The need to implement timely rev'iews in

resolving technical

concerns

has

been

emphasized

to the licensee

on

numerous

occasions.

Greater

management

involvement is necessary

in resolving technical

issues

in a timely fashion, especially

where

modifications are concerned.

The licensee

established

corrective actions to ensure that this

problem does not recur.

The air distribution in the radwaste

building will be contolled by installing portable hatch covers over

the north and south access

shafts

in the radwaste

carwash

area per

Engineering

Work Request

EWR-M-70187.

When the covers

are installed

in January

1991, the estimated ventilation supply will be

approximately

400 scfm and the exhaust air will be approximately

800

scfm.

This distribution of normal ventilation will maintain the

carwash

area slightly negative, relative to the rest of the radwaste

building.

e

13

Based

on this approach,

the inspector

has

reasonable

assurance

that

the covers will eliminate the transport of contamination

throughout

the radwaste building.

Therefore, this item is closed.

9.

MANAGEMENT AND EXIT MEETINGS

9. 1

Routine Resident Exit and Periodic Meetin

s

The inspector discussed

the findings of this inspection with station

management

throughout

and at the conclusion of the inspection period.

Based

on

NRC Region I review of this report

and discussions

held with

licensee

representatives, it was determined that this report does not

contain information subject to

10 CFR 2.790 restrictions.

9.2

Attendance

at

Mana ement Meetin

s Conducted

B

Re ion Based

Ins ectors

Dates

s

9/14

Subject

Emergency

Planning

~ins ection

~Re ort No.

90-18;90-18

~Re ortin

~ins ector

E.

Fox

ATTACHMENT

I'bbreviation

List

AP

ADS

ANSI

CAC

CFR

CREOASS

DG

'DX

ECCS

EDR

EP

EPA

ERT

ESF

ESW

EWR

FO

FSAR

ILRT

J IO

LCO

LER

LLRT

LOCA

LOOP

MOV

NCR

NDI

NPE

NPO

NRC

OI

PC

PCIS

PMR

QA

RCIC

RG

RHR

RHRSW

RPS

RWCU

SGTS

SI

SO

SOOR

SP ING

Administrative Procedure

Automatic Depressurization

System

American Nuclear Standards

Institute

Containment

Atmosphere

Control

Code of Federal

Regulations

Control

Room Emergency Outside Air Supply System

Diesel

Generator

Direct Expansion

Emergency

Core Cooling System,

Engineering

Discrepancy

Report

Emergency

Preparedness

Electrical Protection

Assembly

.

Event Review Team

Engineered

Safety Features

Engineering

Service Water

Engineering

Work Request

Fuel Oil

Final Safety Analysis Report

Integrated

Leak Rate Test

Justifications for Interim Operation

Limiting Condition for Operation

Licensee

Event Report

Loca1

Leak Rate Test

Loss of Coolant Accident

Loss of Offsite Power

Motor Operated

Valve

Non Conformance

Report

Nuclear Department Instruction

Nuclear Plant Engineering

Nuclear Plant Operator

Nuclear Regulatory

Commission

Open

Item

Protective Clothing

Primary Containment Isolation System

Plant Modification Request

Quality Assurance

Reactor

Core Isolation Cooling

Regulatory Guide

Residual

Heat

Removal

Residual

Heat

Removal

Service Water

Reactor Protection

System

Reactor Water Cleanup

Standby

Gas Treatment

System

Surveillance

Procedure,

Instrumentation

and Contro'1

Surveillance

Procedure,

Operations

Significant Operating Occurrence

Report

Sample Particulate,

Iodine,

and Noble Gas

SSES

TS

TSC

VOTES

WA

- Susquehanna

Steam Electric Station

Technical Specifications

- Technical

Support Center

Valve operator test

and evaluation

system

- Work Authorization

U.

S.

NUCLEAR REGULATORY COMMISSION

NRC Form 766

(Substitute)

Principal Inspector:

S.

BARBER

Reviewer:

P.

SWETLAND

INSPECTOR'S

REPORT

~ins ectors:

BARBER/STAIR

Licensee/Vendor:

Penns

lvania Power

8 Li ht Co.

2 North Ninth Street

Allentown

Pa.

18101

Docket ¹/Ins ection ¹/Se

. ¹:

50-387/90-20

50-388/90-20

Transaction

T

e:

X I - Insert

M - Modify

D Delete

R - Release

(A)

(B)

Period of Ins ection:

Ins ection Performed

B

Organization

Code

of Re ion

Region Office Staff

X

Resident

Inspector(s)

Performance

Appr.

Team

Other

Type of Activity Conducted

(One Only)

From

To

~Re ion Division Branch

09/02/90 10/06/90

I

B

C

NRC Form 591

X

Regional

Office Letter

X 02-Safety

03-Incident

04-Enf.

05-Mgmt.

Audit

07-Special

08-Vendor

09-Mat.Acct.

10-Plt.Sec.

12-Shipment/Export

13-Import

14-Inqui ry

15-Inve sti gati on

Ins ection Findin s:

Letter of Re ort Transmittal

Date

A

B

C

D

NRC Form 591 or

Report Sent to

- Clear

X

X

- Violation

- Deviation

Violation 5 Deviation

Total

No. of

Violations and

Deviations:

Enforcement

Conference

Held

Report Contains

2.790 Information

NO

NRC Form 766A

(Substitute)

Ins ection

Re ort

Cont.

Docket No./Re ort No.

05000387/90-20

05000388/90-20

~Se

~

A

B

C

D

Module No.

10 CFR 2 App

C

Su

lement

No.

Severit /Deviation

1/2/3/4/5/6/D

Site

Related

5/35702

4

X

A

X

B

C

D

r

Violation or Deviation

52400 characters:

activities affectin

ualit

shall

be

rescribed

b

documented

instructions

rocedures

or drawin

s

a

ro riate to the circumstance

and shall

be

accom lished in accordance

with these instructions

.

10 CFR Part 50 A

endix

B

Criterion

V

Corrective Action

re uires that the

Contrar

to the above

commencin

on Au ust

29

1990 the licensee's

examinations

disclosed

extensive internal

dama

e of the

'B

and

D 'mer enc

diesel

enerators

units disclosed

extensive

internal

dama

ewhich was caused

b

the licensee's

failure to

rovide ade uate

rocedures.

This dama

e could

have led to the earl

traumatic failure of both of these diesel

enerators

had the

been called

u on to

o crate for accident conditions.

This is a Severit

Level

IV Violation

Su

lement I

9

MODULE INFORMATION A

NRC Form 766 (Cont.)

(Substitute)

Phase/

Direct

Module

Insp.

No.

Hrs.

Percent

~Com

1 ate

Status

Phase/

Direct

Module

Insp.

Percent

No.

Hrs.

~Com late

Status

5/30703

1

5/30702

5/61726

6

5/62703

16.5

5/90712

6

5/71707

36.5

5/92701

11

(71707)

5/35702

12

5/93702

2

5/92720

39.5

60K

C

MODULE INFORMATION B

Phase/

Module

No.

Direct

Insp.

Hrs.

Percent

~Com late

Status

Phase/

Direct

Module

Insp.

No.

Hrs.

M

Percent

~Com late

Status

5/71707

36

5/90712

4

5/62703,

3.5

5/92720

33

5/61726

3

5/92701

9

(71707)

5/92700

5/30702

12

s

60%

C