ML18019A264
| ML18019A264 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 06/05/1985 |
| From: | Fredrickson P, Maxwell G, Prevatte R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18019A262 | List: |
| References | |
| 50-400-85-16, NUDOCS 8507110558 | |
| Download: ML18019A264 (28) | |
See also: IR 05000400/1985016
Text
~8 REOIj
(4
P0
Cy
nO
e
/p ~+*++
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I I
101 MARIETTASTREET, N.W.
ATLANTA,GEORGIA 30323
Report No.:
50-400/85-16
Licensee:
Carolina
Power and Light Company
411 Fayettevi lie Street
Raleigh,
NC
27602
Docket No.:
50-400,
Facility Name:
Harris
Inspection
Conducted:
April 20
May 20,
1985
Inspectors:
G.
F.
Maxwe
R.
L
evat
Approved by:
P.
E. Fredr ckson,
Sect1on
Chief
Division of Reactor Projects
License No.:
CPPR-158
P twlZP
Date Signed
s fm/zg
Date Signed
D
e
S gned
SUMMARY
Scope:
,This routine,
announced
inspection
entailed
280 inspector-hours
on site
in the areas
of licensee
action
on previous
enforcement
items;
unresolved
and
inspector follow-up items; status of Three Mile Island action items; electrical;
containment
structural
steel
welding; safety-related
piping (welding); storage;
fire prevention/protection;
instrumentation
and control;
heating,
ventilation,
and air conditioning systems;
independent
operational
inspections.
Results:
Of the eleven
areas
inspected,
no violations were identified in ten
areas;
one violation was found in one area (Violation - Failure to follow proce-
dures to control electrical field modification).
8507ii0558 850605
ADOCK 05000400
8
I
I
ll*
REPORT DETAILS
Licensee
Employees
Contacted
R. A. Watson,
Vice-President Harris Nuclear Project
G. A. Myer, General
Manager,
Milestone Completion
C.
C. Wagoner,
Project General
Manager,
Construction
- R. M. Parsons,
Project General
Manager,
Construction Confirmation
Completion
"J.
L. Willis, Plant General
Manager,
Operations
- E. J.
Wagner,
Manager Engineering
~J.
L. Harness,
Assistant Plant General
Manager,
Operations
"L. I. Loflin, Manager Harris Plant Engineering
Support
- M. Thompson, Jr.,
Manager Engineering
Management
B.
Van Metre,
Manager Harris Plant Maintenance
- N. J. Chiangi,
Manager
QA/QC Harris Plant
- C. S. Hinnant,
Manager Start-up
- J.
M. Collins,
Manager
Operations
"A. H. Rager,
Manager Construction
Inspection
"G. L. Forehand,
Director QA/QC
- C. S.
Bohanan,
Director Regulatory
Compliance
M.
DE Vernon, Superintendent
0 ~ A. McGaw, Superintendent
Other licensee
employees
contacted
included
eleven
construction
craftsmen,
twelve technicians,
twenty-two operators,
six mechanics,
two security force
members,
and two engineering
personnel.
- Attended exit interview
Exit Interview
The
inspection
scope
and
findings
were
summarized
on
May 20,
1985, with
those
persons
indicated
in paragraph
1
above.
No written material
was
provided to the
licensee
by the resident
inspectors
during this reporting
period.
The licensee
did not identify as proprietary
any of the materials
provided to or reviewed
by the resident
inspectors
during this inspection.
The violation identified in this report
has
been
discussed
in detail with
the licensee.
The licensee
provided
no dissenting
information at the exit.
Licensee Action on Previous
Enforcement
Items (92702)
(Closed) Violation 400/84-31-02
"Inadequate
Inspection."
The inspector
evaluated
CP&L's
responses
to
Region II dated
October 31,
1984
and
April 29,
1985.
CP@L has conducted additional training for inspection
personnel
in this area
and has additionally committed to reinspect all
previously installed
hangers for instrumentation
and control.
Follow-
up inspections
by the resident
inspector
indicate that this problem has
'
b.
I
been corrected.
This item will be routinely evaluated
as
a part of the
ongoing inspection
program.
This item is closed.
(Closed)
Violation 400/83-31-01
"Failure to Follow or Revise Instruc-
tions Specified
on
QA Hold
Tags
Prior to Performing
Actions
Which
Violate These Instructions."
The inspector
evaluated
CP&L's response
to Region II dated
December
30,
1983.
All cable reels in question
have
been stored properly and
QA hold tags
have 'been corrected.
Procedures
have
been revised to address this item,
and personnel
have
been trained
in procedural
requirements.
This item will be routinely evaluated
as
a
part of the ongoing inspection
program.
This item is closed.
(Closed)
Violation 400/83-25-01
"Inadequate
Inspection Activities with
Respect
to Installation
of Motor Control
Centers."
The
inspector
evaluated
CP&L's
responses
to
Region 'II dated
November
18,
1983,
November 30,
1983
and
July 26,
1984.
has
corrected
these
deficiencies
and revised applicable
procedures
to strengthen
inspection
in
these
areas.
Inspection
personnel
have
recei,ved
additional
instruction to prevent recurrence
of this item.
Follow-up inspections
have
been
conducted
in this area
by the
resident
inspector
with
no
deficiencies identified.
This item is closed.
4.
Unresolved
Items
and Inspector
Follow-up Items (92701)
~
~a.
Closed
Ins ecto
ol lo -u
Ite
00
(
)
p
r
F
w
p
m
4
/84 36 01
'Unauthorized
Work or
Tampering with Completed
and
Inspected
Installations".
This
concern
has
been
reviewed
by
CP&L; an audit of this area
was conducted
by the
Quality Assurance
surveillance
group.
It was determined that the root
causes
of the
problems
were
craftsmen
working outside
of procedure
guidelines;
working
in
advance
of written direction,
and
personnel
causing
damage
while working or gaining
access
to nearby
equipment.
CP&L management
has provided written instructions to all site personnel
on the protection of installed
equipment,
and additional training has
been
conducted
in this area.
The resident
inspector will continue to
monitor this area
in future inspections.
This item is closed.
b.
(Closed)
Unresolved
Item 400/84-24-03
"Closure
of FCRs."
CP&L wi 11
close
FCRs in the following manner:
(1)
FCRs classified
as "generic",
wherein
the conflict/condition is
applicable to
a specific item or requirement of an existing design
document,
are closed
by Harris Plant Engineering Staff (HPES)
when
the
approved
change
is incorporated
into the applicable
document
as specified in Administrative Procedure
AP-IX-05.
(2)
FCRs classified
as "generic",
wherein the conflict/condition is
not
applicable
to
a
specific
electrical
item
or requirement
detailed/specified
ir. exi sting
design
document(s),
will remain
open
as
.long
as its design
content (clarification or amplifica-
tion)
is
necessary
for
electrical
installation/inspection
activity.
FCRs
of this
type
are
"voided"
by
HPES following
~
~
, I
notification of completion of all affected
work by Harris Plant
Construction Staff.
(3)
Some
FCRs/PWs require
no field work/rework and are issued only for
document
changes.
These
FCRs/PWs
are
closed
by
Electrical
Discipline Engineer s when approved for incorporation into affected
documentation
(Procedure
Change Notice ¹1, AP-IX-05, R/31).
(4)
In accordance
with AP-IN-05, Field
Change
Request
(FCR/PW),
FCRs
are
closed
by
Electrical
Discipline
Engineers
when
(a) the
affected
design
documents
are
revised/issued
incorporating
the
specified
change
or (b) by visual field verification that all
affected work/rework has
been
completed
and inspection
accepted
by
Construction
Inspection documentation.
A statement is provided in
the implementation
section of the majority of FCRs to indicate
how
implementation is accomplished.
After reviewing the
above clarification
on this issue,
the inspector
considers this item closed.
c ~
d.
(Closed)
Inspector
Follow-up Item 400/83-24-08
"Disposition of
Embed
Plate
Gouge."
During
an inspection
the inspector
observed
a 1/16" to
1/8" deep
gouge
about
2"
long
on
a ceiling
embed
plate
on
hanger
EA 26148.
The gouge
was parallel to the weld of a gusset
to the
embed
and about 3/4" from the weld.
This deficiency
was
documented
by
on
Deficiency
and
Disposition
Report
(DDR)
1773.
The
gouge
was
repaired
and reinspected
and the
DDR was closed
on October 7,
1983.
Additional
instruction
was
provided
to craft
personnel
to
reduce
recurrence
of problems in this area.
This item is closed.
(Closed)
Inspector
Follow-up
Item
400/83-37-05
"gA Monitoring of
Start-up Activities."
CP&L has
provided
a vigorous
gA surveillance
program of all operations activities.
Support
has
been
provided
by
site construction
inspection or quality control,
as required to assure
that start-up activities are conducted
in accordance
with site require-
ments.
This item is closed.
e.
(Closed)
Inspector
Follow-up Item 400/84-24-04
"Operations
Management
Staffing."
Amendment
17 to the
FSAR revised
Section
13. 1 eliminating
the
position
shown
as
manager
of plant operations.
This
item is
closed.
(Closed)
Inspector
Follow-up Item 400/85-04-03
"Evaluation of Mainten-
ance
Work Requests
and Authorizations for Reportabi lity."
CP&L has
revised
the applicable
operations
procedure
(AP-034) to clarify the
information
needed
on work requests
for evaluating
them as potentially
reportable
items.
This item is closed.
5.
Status of Three Mile Island Action Items (TI2514/01
25401B)
a
0
Item I.A.l.l. "Shift Technical Advisor."
FSAR Section 13.2.1.1.3;
Section
13. 1.2.2;
CP&L Response
to
NRR Licensee Qualification Branch
Question
630.7
dated
July 25,
1983;
CP&L Operations
Procedure
OMM-1
Section 3.2.7;
and Harris Plant Technical Specification Section 6.2.4
address
CP&L's commitments to action required for this TMI item.
This
TMI,Action Item is closed.
b.
C.
Item I.A.1.2 "Shift Supervisor Administrative Duties."
This item is
addressed
in the
SER as
an outstanding
issue.
FSAR Section
13. 1';
Section
13'. 1;
TMI Appendix Page
3; Harris Plant Technical Specifica-
tion Section
6. 1.2
and 6.2,
and
Operations
Procedure
OMM-01 Section
3.2.3 address
CP&L's commitments to TMI Action Item I.A.1.2.
The shift
foreman's administrative responsibilities
have
been clearly delineated
in Procedure
OMM-01.
Section 3.2.3.J
of the procedure
requires
that
his administrative
functions
do not detract
from his primary duties.
However,
the
inspector
could
not
determine
how all of the shift
foreman's administrative duties
can
be accomplished
without detracting
from his primary responsibilities.
This is
an Inspector
Follow-up Item
"I.A.1.2 Shift Supervisor Administrative Duties" 400/85-16-01.
Item I.A.1.3 "Shift Manning."
NUREG 0737 was revised
and
affected
the
action
required
by
TMI Item I.A.1.3.
addressed
Item I.A.1.3
in
Page
4;
Harris
Plant
Technical Specification Section 6.2.2
and Operations
Procedure
OMM-01
Section 3.3.6.
The inspector previously evaluated this TMI Action Item
and identified an Inspector
Follow-up Item as 400/83-37-03
"Scheduling
Overtime."
The Harris Plant Technical Specification Section 6.2.2
and
Revision
1
of
Procedure
OMM-01,
Section
3.3.6
clearly
delineate
compliance with this
TMI Action Item.
IFI 400/83-37-03
and
TMI Item
I.A.1.3 are closed.
d.
Item I.A.2. 1
"Immediate
Upgrading of
RO and
SRO Training Qualifica-
tion."
TMI Appendix
Page
5;
CP&L response
to
Licensee
Qualification Branch Question
630.4
and
SER Section
13.2. 1.3 conclude
that
CP&L has satisfied
the requirements
of this action
item.
This
item is closed.
e.
Item
I.A.2.3
"Administration
of Training
Programs
for
Licensed
Operator."
FSAR Section
1.8 and 13.2.2;
CP&L response
to
NRR Licensee
Qualification Branch Question
630.5
and
SER Section
13.2. 1.3 conclude
that
CP&L has satisfied
the
requirements
of this action
item.
This
item is closed.
Item I.A.3.1 "Revised
Scope
and Criteria for Licensing Examinations."
Page
7,
commits
CP&L to utilize
a simulator
as
a
part of the licensing examinations.
This item is closed.
Item
I.B.1.2
"Independent
Safety
Engineering
Group."
Appendix,
Page
8 and Section
13.4;
SER Section
13.4
and Harris Plant
Technical Specification Section 6.5.4
address
CP&L's
commitments
to
have
an
on site independent
safety
engineering
group.
This group
has
been
established
at
the
site
and
is
functioning
as
the
on site
Corporate
Nuclear Safety section.
This item. is closed.
Item I.C. 1 "Guidance for the Evaluation
and Development of Procedures
for Transients
and
Accidents."
TMI Appendix,
Page
9;
response
letter
to
Harold
Denton,
dated
September
18,
1984;
Section
13.5.2. 1;
SER Section 13.5.2.3;
and
Supplement
1
address
steps
which
CP&L will take to comply with this action
item.
CP&L has
submitted the
Emergency Operating
Procedures
(EOPs) generation
package
to
NRR and
has
developed
the plant specific
EOPs.
To satis-
factorilyy
resolve this item requires:
the
plan and address
their findings in a supplement
to the
SER;
and
an
NRC
follow-up review will be required to resolve
any questions
which
may
result
from evaluating
CP&L's plan.
This is
an
Inspector
Follow-up
Item "I.C. 1 Guidance for the Evaluation
and Development of Procedures
for Transients
and Accidents" 400/85-16-02.
Item I.C.8 "Pilot Monitoring of Selected
Emergency
Procedures
for NTOL
Applicants."
TMI Appendix,
Page
16,
and
SER Section
13.5.2.3
address
this item.
The
SER states
that the
NRC staff does
not plan to
review selected
Emergency
Operating
Procedures
in accordance
with TMI
Action Item I.C.8.
The staff plans to review the
based
on
Action Item I.C. l.
This item is closed.
Item I.C.2 "Shift and Relief Turnover Procedures."
Page
10;
FSAR Section
13.5. 1.3;
SER Section
13.5. 1 and
CP&L Operations
Procedures
OMM-022 address
CP&L's compliance with this action
item.
The inspector evaluated
procedures
OMM-001 and
OMM-002 and
found them
to
be
an
acceptable
method
of assuring
that
operating
shifts
are
properly relieved.
This item is closed.
Item I.C.3 "Shift Supervisor
Responsibilities."
TMI Appendix,
Page
11;
Section
13. 1.2;
Section
13.5. 1;
Harris
Plant
Technical
Specification,
Section
6. 1.2,
and
Operations
Procedure
OMM-001 clearly establish
the
command duties of the shift supervisor
and emphasize
the primary management
responsibility for safe
operation
of the plant.
The inspector
evaluated
procedure
OMM-001 and found it
to clearly define the duties,
responsibilities
and authority of the
shift
supervisor
( shift
foreman)
and
the
control
room operator s.
Harris
Plant
Technical
Specifications,
Section
6. 1.2,
addresses
a
management
directive
signed
by
the
vice-president
Harris
Nuclear
Project to be issued yearly to all plant personnel.
The directive is
required to state
that the shift foreman is responsible
for the safe
operations
of the plant.
This item is closed.
~
~
Item I.C. 4 "Control
Room Access."
TMI Appendix,
Page
12;
Section 13.5.1;
Section
13.5.1
and
CP&L Operations
Procedure
OMM-001 describe
the control
room access
limitations and the authority,
responsibility
and
succession
in the
control
room.
The
inspector
evaluated
the applicable
sections
of procedure
OMM-001; the procedure
adequately
addresses
the concerns
identified in this TMI Action Item.
However,
the
procedure
has
not yet
been
implemented.
This is
an
Inspector Follow-up Item "I.C.4 Control
Room Access"
400/85-16-03.
Item I.C.5 "Procedures
for Feedback
of Operating
Experience
to Plant
Staff."
Appendix,
Page
13;
Section
13.5. 1;
Section
13.5. 1;
CP&L Qual.ity Assurance
Procedure
CQAD 80-1; Operations
Procedures
ONSI-1
and
D-AP-31
describe
the
guidance
required
to
ascertain
that operating
experience
is fed back to the plant's staff.
The inspector evaluated
the applicable site procedures
(ONSI-l, 0-AP-31
and Enclosure
1 to
CQAD 80-1)
and found them to address
adequately
the
concerns
identified in TMI Action Item I.C.5.
This item is closed.
n.
0.
Item I.C.6 "Verify Correct Performance
of Operating Activities."
TMI Appendix,
Page
14;
SER Section
13.5. 1;
CP&L Operations
Procedures
OMM-001;
Section 5.2,
and
OMM-05 describe
CP&L's current
position
relative
to
TMI Action
Item I.C.6.
The
inspector
evaluated
the
applicable
CP&L operations
procedures
and
discussed
the
content
of
these
procedures
with the responsible
CP&L personnel.
The inspector
was
informed that
CP&L is reevaluating its position
and will provide
additional clarification.
This is
an Inspector
Follow-up Item "I.C.6
Verify Correct Performance
of Operating Activities" 400/85-16-04.
Item I.C.7
"NSSS
Vendor
Review of Procedures."
References:
Appendix,
Page
15;
FSAR Section
14.2.3.2;
SER Section
13.5.2.3;
response
to
a draft
Open
Item
Number
194 (letter
dated
July 1,
1983);
and
CP&L letter clari fying company
position
concerning
Action Item I.C.7 (letter dated
February
18,
1985).
The clarification
was provided to inform NRR that
CP&L does
not plan to require Westing-
house (the
NSSS vendor) to review the
Emergency
Operating
Procedures.
CP&L has
committed
to Westinghouse
review of low power
and
power
ascension
procedures
which are related
to
NSSS, prior to fuel load.
The inspector will verify that these
reviews
are accomplished.
These
reviews
are Inspector
Follow-up items "I.C.7. 1
Vendor
Review of
Low Power Test Procedures"
400/85-16-05
and "I.C.7.2 NSSS Vendor Review
of Power Ascension
Procedures",
400/85-16-31.
P..
Item I.D. 1 "Control
Room Design
Review."
Page
17;
SER Section
18;
SER Supplement
1, Section
18;
and
Supple-
ment 1,
summarizes
the
requirements
and outstanding
issues
which must
be
addressed
in order
to close this
TMI Action Item.
The inspector
will track
NRR closeout
action
on this
item.
This is
an
Inspector
Follow-up Item "I.D.1 Control
Room Design
Review" 400/85-16-06.
I
~
~ (L
I.G.1 "Special
Low-power Testing
and Training."
FSAR Section
13.2.-
1.1.2;
FSAR Section
14.2.12.2.26
(Amendment ll) and
Section
14
describe
CP&L's commitments that each
Reactor Operator
(RO) and Senior
Reactor Operator
(SRO)
who performs
RO and
SRO duties shall participate
in the initiation, maintenance
and recovery
from natural circulation.
The inspector inquired about plans which CP&L's training department
may
have
made to resolve this item.
The inspector
was informed that
plans to document
a training program to require the necessary
observa-
tions to
address
satisfactorily
the
TMI Action Item.
The inspector
will observe portions of training during low-power testing.
This is an
Inspector
Follow-up
Item "Special
Low-power Testing
and Training."
400/85"16"07.
II.B.1 "Reactor
Coolant
System
Vents."
Page
22;
FSAR Section 5.4. 12.5;
SER Section
15.9. 1 and
CP&L Emergency Operating
Procedure
EOP-FRP-I.3
describe
the Harris Plant
Reactor
Coolant
High
Point Vent System.
The design of the vent system
has
been
reviewed by
and
found acceptable,
as
discussed
in the
SER.
The
inspector
assessed
the
construction
status
of the
system
and
found it to
be
partially completed.
Those sections yet to be installed include:
the
piping connections
to the reactor
vessel
head
and to the pressurizer;
the electrical
power
supplies
to the
solenoid-operated
valves;
and
control
room indication for flow and valve position.
The inspector
evaluated
EOP-FRP-I.3
and found it to address
only the reactor
vessel
head
vent.
The
procedure,
when addressing
the reactor 'vessel
vent,
does
not identify the
valves
to
be
manipulated.
The Harris
Plant
Technical Specifications
Section 3/4.4. 11 addresses
the operability
and
surveillance
requirements
for
the
vents.
This
is
an
Inspector
Follow-up Item "II.B.1 Reactor
Coolant System Vents" 400/85-16-08.
II.B.2 "Plant Shielding to Provide
Access
to Vital Areas
and Protect
Safety
Equipment for Post-accident
Operation."
TMI Appendix,
Page
25;
Sections
12.2.1.12,
12.3.2.16
and
3.11;
and
'ection
12.2
describe
CP&L's design
review of plant
shielding
and
environmental
qualification of spaces
or systems
which may be used in
post-accident
operations.
This
TMI Action Item
was
evaluated
and
accepted
by
NRR; the results
are
documented
in the Harris Plant
SER.
As a result of the applicant's
review,
no modifications were identified
as
being
required.
Region II will review this
area.
This is
an
Inspector
Follow-up Item "II.B.2 Plant Shielding to Provide
Access
to
Vital Areas" 400/85-16-32.
II.B.3
"Post-accident
Sampl ing
Capability."
Appendix,
Page
26;
FSAR Sections 6.2.5
and 9.3.2,
and
SER Section 9.3.2.2 address
CP&L's
post-accident
sampling
system.
CP&L personnel
informed
the
inspector
that
the
sampling
system
is
being
installed
and
the
supportive procedures
are being drafted.
CP&L expects
the system to be
installed
and procedures
to
be
completed
in late
1985.
This is
an
Inspector
Follow-up
Item "II.B.3 Post-accident
Sampling
Capability"
400/85-16-09.
II.B.4 "Training for Mitigating Core
Damage."
TMI Appendix,
Page
27;
FSAR Section
13.2;
SER Section
13.2. 1.3,
and
CP&L response
to
the
NRR Safety Evaluation
Licensee Qualification Branch Question
630.6
address
CP&L's compliance
with this
TMI Action Item.
The inspector
reviewed
the training
records
for the Harris Plant shift technical
advisors
and operating
personnel
from the Plant General
Manager through
the operating chain, including licensed operators.
These
records
show
that
these
personnel
have
been
trained,
as
required
by the
Mitigating Core
Damage Training
Program.
Training for managers
and
technicians
in the
Instrumentation
and Control,
Health Physics,
and
Chemistry Sections
is
an
ongoing
program which will not
be completed
until
fuel
loading.
This
is
an
Inspector
Follow-up
Item "II.B.4
Training for Mitigating Core
Damage" 400/85-16-10.
II.D.1 "Performance
Testing of Boiling Water Reactor
and Pressurized
Water Reactor Relief and Safety Valves."
Page
28,
SER Section
3.9.3
and
CP&L response
letter to
NRR concerning
Confirmatory
Item
Number
6
dated
June
28,
1984
document
CP&L's
compliance
with this
TMI Action Item.
This
item will remain
open
pending
NRR review
and
approval
of CP&L's plant specific
response
submitted
on
June
28,
1984.
This is
an
Inspector
. Follow-up
Item
"II.D.1 Performance
Testing of Boiling Water Reactor
and Pressurized
Water Reactor
Relief and Safety Valves" 400/85-16-11.
II.D.3 "Relief
and 'Safety
Valve Indication."
TMI Appendix,
Page
29,
and
SER Section 7.5.2 address
CP&L's compliance with this TMI
Action Item,
The installation of the
hardware
has
not yet
been
completed
for the relief
and
safety
valve indicators.
This is
an
Inspector
Follow-up Item "II.D.3 Relief and Safety
Valve Indication"
500/85"16-12.
II.E. 1. 1
"Auxil iary
Re 1 i abi 1 ity
Eval uati on."
Appendix,
Page
30;
Section
10 '.9;
Supplement
1,
Section
10.4.9,
and
FSAR Section
10.4.9 address
CP&L's compliance with this TMI
Action Item.
The inspector
was
informed
by
CP&L that the auxiliary
system did not require
any plant modification concerning this
Action Item.
NRR has reviewed
and accepted
the Harris Plant auxiliary
feedwater reliability evaluation.
This item is closed.
II.E. 1.2
System Initiation and
Flow."
Appendix,
Page
31;
FSAR Sections
7.2.2,
7.3. 1, 7.3.2,
7.5
and 10.4.9;
and
SER Section 7.3.3. 1 address
CP&L's compliance with this TMI Action
Item.
has
accepted
the
design
of the
Harris
Plant
auxiliary
system
controls.
However,
the
indicators
and
control
circuits have not yet been insta'lied.
This TMI Action Item will remain
open until the electrical
hardware
and controls for the auxiliary
system
have
been installed
and the installation evaluated
by
Region II.
This is
an
Inspector
Follow-up Item "II.E.1.2 Auxiliary
System Initiation and Flow" 400/85-16-13.
z.
II.E.3 ~ 1 "Emergency
Power for Pressurizer
Heaters."
FSAR Section 8.3.1
and
SER Section
8.4
~ 8 address
CP&L's compliance with this
TMI Action
Item.
The
SER states
that
CP&L will have
procedures
for manually
loading the pressurizer
heaters
onto the class
1E buses
following loss
of off site power.
The inspector selectively evaluated
the procedures
which
CP&L has
in place to require
the
manual
loading of pressurizer
heaters
onto the
lE buses
as
required
by the
TMI Action Item.
This
item is closed.
aa.
II.E.4. 1 "Containment
Dedicated
Penetrations Hydrogen Control."
TMI Appendix,
Page
33;
and
SER Table
1'. clearly indicate that
utilizes redundant
in-containment
thermal
recombiners;
therefore this
TMI item is not applicable to the Harris Plant.
This item is closed.
bb.
II.E.4.2
"Containment
Isolation Dependability."
TMI Appendix,
Page
34;
FSAR Sections
6.2.4,
7.3. 1. 1,
and 7.3. 1.3;
and
SER Section
6.2.4 address
CP&L's position concerning this TMI Action Item.
NRR has
reviewed
the
CP&L design
and
has
addressed it in
the
SER.
Section 6.2.4
requires
CP&L to provide
Technical
Specifications
for
containment
isolation
setpoint
pressure.
has
submitted
the
requested
sections
of the Technical
Specifications
by
a letter dated
April 23,
1985.
This
item
remains
open
pending
review
and
acceptance
of the
proposed
technical
specifications.
Region II will
follow
up
on this
item 'to
determine
acceptability
of the
final
installed
hardware.
This is
an
Inspector
Follow-up
Item "II'.'E.4.2
Containment Isolation Dependability" 400/85-16-14.
cc.
II.F. 1
"Additional Accident
Monitoring Instrumentation."
Appendix,
Page
35;
FSAR Sections
11.5.2,
12.3.4,
6.3
and
6.2;
response
letters
to
dated
July 1,
1983,
July 15,
1983,
September
21,
1983,
October 24,
1983,
and
October 26,
1983;
Sections
11.5 and 10.4.2;
SER Open Items
9 and 10;
and
SER Confirmatory
Item 24,
25 and
26 address
CP&L's compliance with this TMI Action Item.
(1)
Subparts
(2.a)
and
(2.b) of the action
item require
noble
gas
effluent
radiological
monitoring,
sampling
and
analysis.
The
design for these monitors
has
been
completed
but their installa-
tions
have
not
been
completed.
NRR has
reviewed
the monitoring
and sampling
system design
and has
provided
comments
in the
SER.
These
subparts
have
been identified by
NRR as
SER Open Items
9 and
10,
and
Confirmatory
Items
24,
25,
and
26.
Upon satisfactory
resolution
of the
design
between
and
CP&L,
Region II will
verify that the final design installation
has
been
completed
and
that procedures
are
issued.
This is
an Inspector
Follow-up item.
"II.F.1 Subparts
(1)
and
(2) Effluent Radiological
Monitoring,
Sampling
and Analyses" 400/85-16-15.
(2)
Subpart (2.c) "Containment High-range Radiation Monitor."
NRR has
reviewed
and accepted
the design of the Harris Plant containment
high-range radiation monitors,
as discussed
in SER Section 12.3.4.
The
monitors
have
not yet
been
installed.
Upon
completion
10
Region II will verify installation.
This is an Inspector Follow-
up
Item "II.F.1
Subpart
(3)
Containment
High-range
Radiation
Mon itor" 400/85-16-16.
(3)
Subparts
(Z.d)
and (2.e)
"Containment
Pressure
and Water
Level
Monitors."
NRR has
reviewed
and accepted
the design of the Harris
Plant containment
pressure
and water level monitors,
as discussed
in SER Section 7.5.2.2.
The monitors
have not yet been installed.
Upon completion
Region II will verify installation.
this is
an
Inspector
Follow-up Item "II.F.1 Subparts
(4) and (5) Containment
Pressure
and Water Level Monitors" 400/85-16-17.
(4)
Subpart (2.f) "Containment
Concentration
Monitor."
has
reviewed
and accepted
the design of the Harris Plant contain-
ment hydrogen concentration
monitoring system,
as discussed
in SER
Section
7.5.2.2.
The
system
has
not yet
been
installed;
upon
completion
Region II will verify installation.
This
is
an
Inspector
Follow-up Item "II.F.1 Subpart (6) Containment
Concentration
Monitor" 400/85-16-18.
dd.
II.F.2 "Instrumentation
for Detection
of Inadequate
Core
Cooling."
TMI Appendix,
Page
36;
Section 4.4;
CPSL
responses
to
dated April 18,
1984,
December
6,
1983,
and
November 4,
1983;
and
Supplement
1, Section
4 identify this item as
a license condition which
must be resolved prior to operating
above
5% power.
The installation
of the
hardware
associated
with this
TMI Action Item is incomplete.
The procedures
associated
with the reactor
vessel
water level indica-
tion
system
have
been written
and
are available for implementation.
This item remains
open until the hardware is installed
and the instal-
lation
can
be evaluated
by Region II.
This is an Inspector
Follow-up
Item "II.F.2 Instrumentation for Detection of Inadequate
Core Cooling"
400/85-16-19.
ee.
II ~ F.3 "Instrumentation for Monitoring Accident Conditions (Regulatory
Guide 1.97)."
The
NRC staff has
been instructed to use
Supplement
1 to
in the
implementation
of emergency
response
capability
(including
requirements
for
post-accident
monitoring)
~
Therefore,
conformance
to the guidelines
of Regulatory
Guide
1.97 will be
included
in the
evaluation
of designs
for the
emergency
support facilities.
The
implementation
schedule will be
established
in
conformance
with
Supplement
1
of
The
completion of the review of this item will be performed during the post
implementation
review discussed
under
NUREG 0737 III.A.1.2
"Upgrading
Emergency
Support Facilities."
This item is closed.
ff.
II.G. 1 "Emergency
Power for Pressurizer
Equipment."
Page
37;
FSAR Section
8.3. 1.2
and
Section
8.4.8
address
CPKL's
compliance with this
TMI Action Item.
NRR has
reviewed
and
accepted
the
Harris
Plant
design
as
discussed
in
Section 8.4.8.
The
installation
and testing of the
hardware
has
not yet
been
completed.
11
Upon completion of the
hardware
and testing,
Region II will evaluate
the
configuration.
This
is
an
inspector
Follow-up
Item
"II.G.1
Emergency
Power for Pressurizer
Equipment" 400/85-16-20.
gg.
II.K.1 "IE Bulletins
on
Measures
to Mitigate Small-break
LOCAs and
Loss-of-feedwater Accidents."
Pages
38,
39
and 40;
FSAR Section 7.3. 1 and
SER Section
15.9 address
CP&L's compliance with
this TMI Action Item.
(1)
Subpart II.K.1.5
"Review of
ESF Valves."
CP&L has
committed to
have
procedures
which address
the positioning of
ESF valves
and
will establish
methods of demonstrating,
on
a regular basis,
that
these
valves
are
in the
proper position.
The
procedures
are
currently being developed.
Region II will evaluate
these
proce-
dures
when
they
have
been
completed.
This
is
an
Inspector
Follow-up Item "II.K.1.5 Review of ESF Valves" 400/85-16-21.
(2)
Subpart
II.K.1. 10
"Operability Status."
CP&L is
developing
procedures
for removing safety-related
systems
from service
(and
restoring to service)
to assure
that the operability status
is
known; Operations
Procedures
OMM-001, OMM-003 and
OMM-005 provide
this assurance.
However, the independent verification sections of
OMM-001 and
OMM-005 are being evaluated
by CP&L for clarification.
Upon resolution of the
independent
verification item, identified
earlier
as
an Inspector
Follow-up Item 400/85-16-04,
the proce-
dures
associated
with Item II.K.1. 10 will be further evaluated.
This is an Inspector
Follow-up Item "II.K.1. 10 Operability Status"
400/85-16-22.
(3)
Subpart
II.K.1. 17 "Trip Per
Low Level Bi-stable."
The Harris
Plant design
does
not include
a low pressurizer
level coincident
with low pressurizer
pressure,
as
discussed
in
Sections
7 2
1
1
and
7
3
1 1.
Safety
Injection is initiated
by
low
pressurizer
pressure.
The Harris Plant
has incorporated this
Action Item into the plant design;
therefore this item is closed.
hh.
II.K.2.13 "Thermal
Mechanical
Report."
This item is addressed
in the
Page
41;
and
SER Section 15.9.4,
and Appendix C.
As
discussed
in the
SER, the
NRC staff concludes that the Harris Plant can
be operated
before complete resolution of this issue
and completion of
the proposed
rulemaking without undue risk to the health
and safety of
the public.
This item is closed.
ii.
II.K.2.17 "Potential for Voiding in the
RCS During Transients."
This
item is discussed
in
TMI Appendix,
Page
42;
and
SER Section
15.9.5.
This item is discussed
in the
Section
15.9.5
as
being
reviewed
by
NRR.
If NRR determines
that plant operating
procedures
must
be modified,
CP&L will be required to implement
the
changes
for
the Harris Plant.
This item is not considered
an outstanding
issue in
the
SER.
This item is closed.
I
'I
I
II
II.K.2.19 "Sequential
Flow Analysis."
The
SER,
Section 15.9.5,
identifies this
item as
not being applicable
to the
Harris Plant,
as it employes
the inverted
"U" tube
steam
generators.
This item is closed.
kk.
mm.
II.K.3.1 "Installation
and Testing Automatic
PORV Isolation Systems."
TMI Appendix,
Page
44;
and
SER Section 15.9.7
address
CP&L's
position
on this TMI Action Item.
Should
NRR's review of the Westing-
house
Owner's
Group report
(WCAP-9804) determine that modifications are
necessary,
CP&L will be required to address
the concerns.
There is
no
action required
by Region II.
This TMI Action Item is closed.
II.K.3.2 "Report
on Overall
Safety Effect of
PORV Isolation
System."
TMI Appendix,
Page
45;
and
Section
15.9.7
address
CP&L's
position
on this
TMI Action Item.
Owner's
Group Report
summari zes
the
col 1 ecti ve
data,
in
conjuncti on
with
industry generic probabilistic data,
and estimates
the probability of a
small-break
LOCA caused
by
a stuck
open
PORV.
Should
NRR review of
WCAP-9804 determine
the
need for changes
or modifications,
CP&L will be
requi red
to
address
these
needs.
There
is
no action
required
by
Region II.
This TMI Action Item is closed.,"
II.K.3.3 "Reporting of S/V and
R/V Failures
and Challenges."
Appendix,
Page
46;
Section
15.9.8
and
Harris
Plant
Technical Specifications 6.9. 1.4,
3.4..4
and 3.4.2.2
address
CP&L's compliance
with this item.
CP&L has
committed to document all challenges
to
a
safety or relief valve in the plant annual
report
as discussed
in the
plant technical specification section 6.9. 1.4.
Failure of the valves
are to
be reported
in accordance
with the plant
LER procedure,
which
has not been finalized.
Region II will evaluate this procedure
when it
has
been
completed.
This is
an ,Inspector
Follow-up
Item "II.K.3.3
Reporting of S/V and
R/V Failures
and Challenges"
400/85-16-23.
nn.
II.K.3.5 "Automatic Trip of Reactor
Coolant
Pumps
During LOCA."
TMI'Appendix, Page
47; Generic Letter 83-10C;
CP&L response
to Generic
Letter
83-10C,
dated April 22,
1983;
SER Section 15.9.9;
and
Emergency
Operating
Procedure
Network address
CP&L's compliance
with
this item.
This item is addressed
in the
SER as Confirmatory Item 33.
needs
to
address
CP&L's
response
to Generic
Letter
83-10C
and
supplement
the
as required.
This is
an Inspector
Follow-up Item
"II.K.3.5 Automatic Trip of
Reactor
Coolant
Pumps
during
LOCA"
400/85-16-24.
00.
II.K.3.9 "PID Co'ntroller Modification."
TMI Appendix,
Page
49;
and
SER Section
7.7.2.3
address
CP&L's commitment to this
TMI Action
Item.
CP&L has
committed to adjusting
the derivative action setting
for the
The PID controller for the
has
been adjusted to zero
and its adjustment circuit has
been disabled
to prevent inadvertent maladjustment.
This item is closed.
"A
13
pp ~
Ss.
uu.
VV'
I.K.3. 10
"Proposed
Antici patory
Trip
Modificati on."
Appendix,
Page
50;
and
SER Section
15.9. 10 state that
no modification
to the
standard
anticipatory trip has
been
proposed.
Therefore,
as
discussed
in the
SER section, this item is not applicable to the Harris
Plant.
This item is closed.
II.K.3.11 "Justification of Use of Certain
PORYs."
Page
51;
Table 1.1,
and
Section 15.9.7;
and
Section 3.2.4.4
address
the requirements,
and
CP&L's
commitments,
to
this item.
CP&L states that the "Control Component,
Inc." (CCI)
PORYs
are not utilized
on the Harris Plant pressurizer
and therefore this TMI
Action Item is not applicable.
This item is closed.
II.K.3.12 "Confirm Existence of Anticipatory Reactor Trip Upon Turbine
Trip."
TMI Appendix,
Page
52;
Section
7.2.2.5;
and
Section
7.2. 1. 1.2.f
address
CP&L's compliance
with this
item.
As
stated
in the
SER,
CP&L's design
of this trip feature
was
found
acceptable
by
NRR.
The inspector
evaluated
the Westinghouse
drawing
(108D831,
Sheet
15) which depicts
the anticipatory reactor trip upon
and
the applicable'arris
Plant
proposed
technical
specification
requirements
(Table 3.3-1)..
This item is closed.
II.K.3.17
"Report
on
Outages
of
ECCS;
Licensee
Report
and
Proposed
Technical
Specification
Changes."
Page
53;
and
Section
15.9. 11
commit
CP&L to
a program for collecting
outage
information for
NRC.
As discussed
in
SER Section
15.9. 11,
NRR has
found
CP&L to be in compliance with this TMI Action Item.
This item is
closed.
II.K.3.25 "Effect of
Loss
of
Power
on
Pump
Seals."
Appendix,
Page
54;
and
SER Section
15.9. 12 address
CP&L's evaluation of
the consequences
of loss of
RCP seal cooling.
In the
that adequate
cooling has
been provided
and that
no modifications are
necessary.
As discussed
in SER Section
15.9. 12,
NRR has
reviewed plant
RCP seal
cooling system design
and has found it to be adequate,
without
the need of plant modifications.
This item is closed.
II.K.3.30 "Revised
Small-break
LOCA Methods to
Show Compliance with
Appendix K."
Page
55,
and
SER Section
15.9.13
address
CP&L's compliance with this
TMI Action Item.
NRR has
accepted
the
original
small-break
model
as
in
compliance
with
Appendix
K.
This item is closed.
II.K.3.31 "Plant-specific Calculations
to
Show Compliance with 10 CFR 50. 46. "
TMI Appendix
and
Section
15.9. 14
address
CP&L'
position concerning this
TMI Action Item.
new small-
break
model
dated
March 26,
1982)
is
presently
undergoing
review by NRR.
CP&L has committed to submit plant specific
calculations
showing
compliance with
either
within one
year of NRR's approval of the model, or before fuel load, whichever is
later.
As stated
in the
SER Section
15.9. 14,
NRR has
determined
that
14
CP&L's commitment is acceptable.
No action is required
by Region II.
This item is closed.
XX.
zz.
aaa.
III.A.l. 1
"Upgrade
Emergency
Preparedness."
TMI Appendix,
Page
57;
and
SER Section
13.3.4
address
CP&L's compliance with this
item.
The requirements
of this item were
superseded
with issuance
of
the final rule on emergency
planning
(45FR55402).
As discussed
in the
SER,Section
13.3.4, this item is closed.
I
III.A.1.2
"Upgrade
Emergency
Support Facilities."
TMI Appendix,
Page
58;
and
SER Section
13.3.4 address
CP&L's compliance with this TMI
Action
Item.
NRC
conducted
an
evaluation
of the
Emergency
Planning
Program,
including the support facilities.
The results of the
evaluation
were
documented
in
Region II report
400/85-09.
Further
evaluation
of the
emergency
response
was conducted during the week of
May 13,
1985.
The
results
of this
evaluation
are
addressed
in
Region II inspection
report 400/85-20.
This is an Inspector
Follow-up
Item "III.A.1.2 Upgrade
Emergency
Support Facilities" 400/85-16-25.
III.A.2 "Improving Licensee
Emergency
Preparedness
-
Long Term."
Section
13.3.4;
Harris Plant
Emergency
Plan;
and
Supple-
ment
1
address
CP&L's compliance
with this
TMI Action
Item.
NRC
conducted
an evaluation of the
CP&L Emergency
Plan,
and the results
are
documented
in
Region II report
400/85-09.
The
program
was further
evaluated
during the week of May 13,
1985.
The concerns resulting from
this evaluation
are addressed
in Region II inspection report 400/85-20.
This is
an
Inspector
Follow-up
Item "III.A.2 Improving
Licensee
Emergency
Preparedness
Long Term" 400/85-16-26.
III.D.1.1 "Integrity of Systems
Outside
Containment
Likely to Contain
Radioactive Material."
Pages
59 and 60;
CP&L letter
of response
to
NRR dated July 11,
1984;
and
SER Section
9.3.5
address
CP&L's
compliance
with this
item.
The
leak
reduction
program,
as
described
in the
was reviewed
by
NRR with comments.
This
TMI Action Item is listed in the
as
an outstanding
issue.
After the
program
has
been
accepted
by
NRR,
Region II will verify
implementation
of the
leak reduction
program.
This is
an Inspector
Follow-up
Item "III.D.1. 1 Integrity of Systems
Outside
Containment
Likely to Contain Radioactive Material" 400/85-16-27.
III.D.3.3 "Improved
Inplant
Instrumentation
Under
Accident
Conditions."
Page
61;
Section
12.3.4.2;
and
Section
12.3
addr ess
CP&L'
position
on this
TMI Item.
The
equipment to be utilized by CP&L, concerning their position
on this TMI
Item,
has not yet arrived at the Harris Plant.
CP&L has not yet fully
completed
the
implementing
procedure
for
using
this
equipment.
Region II will verify installation
of
equipment
and
evaluate
the
equipment
operating
procedures.
This is
an
Inspector
Follow-up Item
"III .D.3. 3
Improved
Inp1 ant
Instrumentati on
Under
Accident
Conditions" 400/85-16-28.
15
bbb.
CCC.
III.D.3.4 "Control
Room Habitability Requirements."
Page
62;
FSAR Section 6.4 and 9.4. 1; and
SER Section 6.4 address
CP&L's
compliance
with this
TMI Action Item.
CP&L has
proposed
a technical
specification
section
(3.7.6)
as
required
by the Action Item.
As
discussed
in
Section 6.4,
NRR reviewed
and
accepted
the
Harris
Plant design
concerning this TMI Action Item.
No action is required
by
Region II in closing this item.
This item is closed.
Item I.D.2 "Plant Safety
Parameter
Display Console".
This TMI Action
Item has
not
been
addressed
in the
FSAR or the
SER.
The
NRC require-
ments concerning this item, are addressed
in Supplement
1 to
A detailed description of the Harris Plant
safety parameter
display
system is discussed
in
a
CP&L letter to
dated
December
2,
1983.
This letter
contains
the safety analysis
of
the Harris
system.
Representatives
from the
NRC
Human
Factors
Group
have
conducted
an onsite audit of the safety parameter
display system
and their
review is still
ongoing.
The
system
installation
is
incomplete
and the procedures
and training program are being developed.
This
TMI Action Item will remain
open
pending
NRR'
acceptance
of
CP&L's .safety parameter display system.
This is an Inspector
Follow-up
Item "I.D..2 Plant Safety Parameter
Display Console"
400/85-16-.29.
6.
Electrical
(51053C,
51063C,
92706B)
~
~
~
a.
The ins ector
observed
the
wo
p
rk and inspection activities associated
with completion
of FCR-I-1886
on the
secondary
control
board.
This
work involved modifications of internal wiring for indicating lights on
the control
switches.
This work was
being performed
under the di rec-
tion of the switch vendor,
Reliance Electric Company, with CP&L and the
vendor
QA personnel
conducting
the
inspection activities.
All work
activities
were
being
performed
under
work
procedure
"Assembly,
Disassembly,
Modification or Repair of "Q" Equipment"
(WP-137).
b.
The inspector
accompanied
CI inspection
personnel
on
an inspection of
conduits
10191E,
10191F and
16215E-SA in the containment building.
The
inspection
rejected
the
installation
because
all
required
conduit
supports
had
not
been
installed.
A review of the
status
of these
required
supports
by the inspector indicated that for many field routed
conduit,
the
design
and
installation
of
supports
was
not
being
completed prior to conduit installation.
Further
review
on this also
indicated that in many
cases
these
supports
were
being
designed
and
erected
under
the electrical field modification program.
This program
is described
in
CP&L construction
work procedure
"Installation
of
Seismically
Supported
Electrical
Cable Trays,
Conduits,
Boxes
and
Bus
Ducts" (WP-203).
This procedure
is designed
to allow field modifica-
tions to existing components.
This procedure basically allows for work
to "proceed-at-risk"
until the modification is
approved
by design.
Item 3. 15.6 requires
that these
modifications
be incorporated
into
a
Field Change
Request/Permanent
Waiver (FCR/PW) within five working days
or all
work
on this modification
must
be
stopped.
Item 3. 18 addi-
tionally requires that the modification will not be presented
for final
16
inspection
unless
the
modification
has
been
incorporated
into
an
approved
FCR/PW.
A review of the Electrical
Field Modification (EFM)
log
showed that neither of the above procedurally-required
controls is
being followed.
The log shows
EFM No.
118 was initiated
on March 25,
1985,
and
had
not
been
incorporated
into
an
FCR/PW to date.
EFM
No. 121, initiated on March 26,
1985,
has the
same status
and this- item
had also
been
presented
for acceptance
inspection.
A review of this
log,shows
many other instances
of the
same deficiencies.
The failure
to follow procedural
requirements
is contrary to the requirements
of
10
CFR
Appendix B,
Criterion V,
Section 1.8.5.5
and
the
Corporate
gA Program,
Section
6.
This is
a violation "Failure to
Follow
Procedures
to
Control
Electrical
Field
Modifications"
400/85-16-30.
After identification of this
item to the
licensee,
Nonconformance
Report
85-1293
was
written
to
document
this
item.
Except
as noted,
no violations or deviations
were identified.
7.
Containment Structural
Steel
Welding (55063C)
The inspector
accompanied
gC welding inspect,ion
personnel
on
a reinspection
for weld repair for structural
steel
in the
containment
building.
This
repair was for an undersized
weld on structural
steel joint 223.58-C3830N-71
in the core
key
sump area of containment at elevation 223'.
The connection
was identified
on the weld data
report
as
connection
9D1 at the
beam
and
right clip to embed.
This inspection
included the following:
'a
~
b.
C.
d.
e.f.
Completed weld size,
length
and location;
Visual quality;
Defect repair;
Adherence to drawings,
specifications
and procedures;
Documentation of inspection results;
gualification/certification of inspection
personnel.
No violations or deviations
were identified in the areas
inspected.
8.
Safety-related
Piping (Welding) (55083C)
The
inspector
observed
the
nondestructive
examination
(PT)
testing
on
completed
(A1-216-1-SW120-.FW371)
on the service
water
system piping.
This inspection
included the following:
a.
b.
C.
d.
NDE technique consistent with requirements;
Surface suitability for testing;
equal ificati on/certi ficati on of examiner;
Documentation of inspection results.
No violations or deviations
were identified in the areas
inspected.
17
9.
Storage
(50073C,
92706B)
The inspector
toured
warehouses,
1,
2 and 3, the operations
warehouse,
and
various
plant
equipment
storage
areas.
During
the tours,
the
storage
conditions of the equipment
were evaluated
to determine
whether requirements
are being met as follows:
a.
Piping and equipment,
in general,
were stored off the ground or floors
to prevent entry of dirt into them, or contamination
from environmental
conditions.
b.
The storage
areas
were identified sufficiently to provide identity and
locations
as required
by those
who
may
be
seeking
the
locations
of
parts or equipment.
c.
Access
was adequate
for placement or removal of parts
and equipment.
d.
Marehouse
equipment
was stored in the correct position.
e.
The
temperature
and
humidity controls
were
being
maintained
as
required.
f.
Access to plant storage
areas
were being maintained.
g.
Equipment installed heaters
were energized
as required.
h.
Protective
covers
were in place.
During the
observations,
the following were referenced
for requirements:
PSAR Section 1.8,
and construction
procedures
AP-XIII-07 and
PGD-002.
No violations or deviations
were identified in the areas
inspected.
10.
Fire Prevention/Protection
(42051C,
92706B)
a.
The inspectors
observed
the fire prevention
and protection activities
related to containing combustible materials
where the ignition of these
materials
could
damage
safety-related
structures.
The inspectors
also
observed
the ongoing site training activities for the construction fire
brigade.
b.
Some
of the specific
areas
observed
by the
inspectors
during this
period are
as follows:
(1)
Nonflammable protective
coverings
were
observed
over
such
equip-
ment
as
the electrical
control
cabinets at elevation 286'f the
reactor auxiliary building and over various safety-related
pumps
and components
located throughout the plant.
18
(2)
The inspectors
observed
during the various tours of the reactor
auxiliary building and the containment building that the accumula-
tion of combustible materials
in these
areas
was being minimized.
(3)
Flammable materials
were stored to prevent or reduce
the likeli-
hood of combustion.
(4)
Welding activities were observed
in at least
15 separate
locations
throughout
the site
and
in
each
instance it was
observed
that
appropriate
fire extinguishing
equipment
was
available
within
close'roximity of the welding activities. It was also noted that
the portable fire extinguishers
contained sufficient fire extin-
guishing
medium,
as
evidence
by displaying
current
inspection
stickers
and having unbroken seals.
(5)
The inspectors
observed that at the various elevations
throughout
the reactor auxiliary building and the containment building, fire
suppression
devices
are strategically
located
and readily
avai 1-
able for use.
During the
above
observations
the following were referenced
for require-
ments:
FSAR section
1.8
and 9.5;
Regulatory
Guide 1.39,
NFPA Standard
241
and AP-VII-03 (exhibits,
2,
3 and 4).
No violations or deviations
were noted in the areas
inspected.
ll.
Instrumentation
and Control
(52053C)
The inspector
accompanied
CI personnel
on
an inspection of the installation
of pressure differential transmitter
PDT-OICS-7263-S
and associated
sensing
lines.
The inspection
included the following:
'a ~
b.
C.
d.
e.f.
9.
h.i.
J
~
Instrument location, identification and mounting;
Use of correct materials;
Torquing of fasteners;
Tubing installation;
Physical integrity;
Adherence to drawings, specifications
and procedures;
gualification of inspection personnel;
Documentation of inspection results
and nonconforming conditions;
Clearances,
as specified;
Apparent
damage.
No violations or deviations
were identified in the areas
ipspected.
12.
Heating, Ventilation and Air Conditioning Systems
(HVAC) (50100)
'a
~
The inspector
accompanied
Construction
Inspection (CI) personnel
on
an
inspection
of
HVAC ductwork
on which work had
been
completed.
This
ductwork is identified
on site drawing HV/1-G-486.002
as pieces
3903,
3903D,
3904,
3905,
3906,
3907;
drawing
HV/1-G-486.015,
piece
3456;
'
19
drawing HV/1-G-486.022,
pieces
5874-1A and
3908;
and drawing HV/1-G-
519-501. 003,
sheet
153.
The
following wer e
evaluated
during thi s
inspection:
(1)
Proper
location,
configuration,
identification,
and
damage, if
any;
(2)
Installation in accordance
with approved drawings,
procedures,
and
instructions;
(3)
Attachments properly installed;
(4)
Fastening
material type, identification,
and torquing;
II'5)
Interferences
identified;
(6)
Welding in accordance
with approved drawings
and procedures;
(7)
Inspection
personnel
qualifications;
and
(8)
Inspection results
and nonconformances
properly documented.
b.
C.
The
inspector
accompanied
Quality
Control
(QC)
receipt
inspection
personnel
on
an
inspection
of
HVAC parts
that
had
been
recently
received
under
'purchase
order
NPCD-82-021,
shipment
no.
177,
from
Pullman Construction
Industries.
This shipment
included
14 pieces
of
ductwork,
12 guides
and
171 access
doors.
The following were evaluated
during this inspection:
(1)
Correct storage level;
(2)
Physical
damage;
(3)
Identification and marking;
(4)
Cleanness;
(5)
and preservatives;
(6)
Naterial certifications;
(7)
Nanufacturing documentation;
(8)
Sei'smic release;
(9)
Inspection
personnel
qualifications;
and
(10)
Inspection results
and nonconformance
properly documented.
The
inspector
reviewed
purchase
contract
No. NPCD-84-071
between
Carolina
Power
and
Light
Company
and Stahl-Rider,
Inc.
of Raleigh,
as it relates to the procurement of HVAC parts.
Stahl-
Rider,
under this contract,
supplies
primarily nonsafety-related
duct and miscellaneous
sheet
metal fabricated parts.
They additionally
fabricate
some
safety-related
HVAC parts.
For
the
safety-related
parts, all material,
including welding supplies,
are provided by
CP&L.
The welders
on safety-related
parts
are certified at the Harris Plant
and all work is performed
and monitored by CP&L QC personnel.
No violations or deviations
were noted in the areas
inspected.
20
13.
Independent
Operational
Inspections
(92706B and 82101)
The inspectors
participated in the onsite
emergency
preparedness drill which
was conducted during the week of May 13,
1985.
The results of the drill are
documented
in Region II report 400/85-20.