ML18009A707
| ML18009A707 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 10/15/1990 |
| From: | Reyes L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | Eury L CAROLINA POWER & LIGHT CO. |
| References | |
| NUDOCS 9010260060 | |
| Download: ML18009A707 (46) | |
See also: IR 05000400/1990020
Text
October
15,
1990
Docket No. 50-400
. License
No.
Mr. Lynn W. Eury
Executive Yice President
Power Supply
P. 0.
Box 1551
Raleigh,
NC
27602
Gentlemen:
'UBJECT:
ELECTRICAL DISTRIBUTION SYSTEM FUNCTIONAL INSPECTION AT SHEARON
HARRIS (50-400/90-200)
This refers
to the inspection
conducted
by the Special
Inspection
Branch of
the Office of Nuclear
Reactor
Regulation
on
February
12 through
March 16,
1990.
The inspection
included
a review of activities authorized
by Operating
License
No. NPF-63 for the Shearon
Harris Nuclear Power Plant.
The report
documenting
this
inspection
was
sent
to you
by letter
dated
April 27,
1990.
The letter
informed you that potential
enforcement
items
described
in the
report
would
be
reviewed
by the
Region II Office for
enforcement action.
After reviewing
the
subject
inspection
report,
Carolina
Power
and Light
Company
requested
a meeting with
NRR to discuss
the apparent
inconsistency
between
the
NRC inspection
team conclusions
of program
weaknesses
drawn from
the identified deficiencies
(See
Enclosure 2).
The meeting
took place
on
June
12,
1990
and at the conclusion
to this meeting
NRR suggested
that
CPSL
respond in writing to the deficiencies identified in the report.
CPSL submitted
formal
comments
(See
Enclosure
3)
on these
deficiencies
in
a
letter
dated
July 6,
1990.
Region II has
reviewed
these
comments
.and
additional clarifications
as given by Mr. John
Eads
and other
members of your
staff during subsequent
telephone
conversations
in the latter part of August
1990.
Region II
has
concluded
its
review of your
comments
on
the
inspection
deficiencies
and
reached
the
conclusion
that
no
enforcement
action
is
warranted
on Items
1, 2, 3,',
5, 7, 8,
and, 9.
Item 6 is considered
to be
a
non-cited violation.
Enclosures:
(See
page
2)
I
~
~ l~
5'010260060
901015
ADOCK 05000<00
0
PNU
Sincerely,
Original signed
by
Ellis W. Merschoff
Luis A. Reyes,
Director
Division of Reactor Projects
Mr. Lynn W, Eury
October 15,
1990
Enclosures:
1.
Region II Conclusion
of Deficiencies
Identified
2.
NRC Inspection Deficiencies
3.
CPSL
Comments
cc w/encls:
W. Lanning,
R. Becker,
A. Goutam,
bcc w/encls:
A. Gibson
C. Julian
D. Verrelli
R. Carroll
T. Conlon
N. Merriweather
RII:DR
NMerriweather:tj
09/g/90
RII:D
Ton
n
P0/ / /90,
R
I@ps
J tian
/ w/90
I P
S
AGs
on
09/
90
RII:DR
DVerre1 l i
P/~o/90
i fiI /~0
r'
ENCLOSURE I
Region II Conclusion of Deficiencies Identified
EDG Load Sequencing
Calculation (Deficiency No. 90-200-01)
The
licensee's
response
clarified the effect of sequencer
time delay
relay drift on the
EDG sequential
loading.
The
minimum possible
time
between
load block starts
is four seconds
with the worst time delay relay
drift situation.
The voltage recovery times of 1.01 seconds
to 90 percent
rated
voltage
and full recovery in less
than
two seconds
for the
is within the worst
case
condition [four seconds]
between
load block
starts.
The licensee
stated
that the
computer
code
used for system loading
and
voltage calculations
is
a vendor
program not controlled
by NED.
There is
no regulatory
requirement
to validate
or control
such
vendor
owned
computer
codes.
Based
on the licensee's
response,
Region II does
not consider this issue
to
be in violation of regulatory
requirements
and
no further action is
required.
2.
EDG Air Tank Relief Valves (Deficiency No. 90-200-02)
The licensee
agrees
that the qualifications
documentation
maintained
by
was
inadequate
-to establish
total
seismic
qualification of the
subject
valves.
However,
the
licensee
had
performed
an engineering
evaluation
in April 1989
based
on verbal information from the Perry Plant
and
determined
that the Harris valves
were
enveloped
by the acceptable
portion of the Perry seismic test data.
The test documentation
has since
been
procured
from Cleveland Electric Illuminating and incorporated
into
the qualification files.
Since the valves
were ultimately found to be qualified and the supporting
documentation
was easily retrievable,
Region II does
not consider this
issue to be in violation of Regulatory requirements.
3.
Water Heaters
(Deficiency No. 90-200-03)
The
postulated
common-mode
failure of the
subject
heaters
due to
a
seismic event is not considered
credible for the following reasons:
a.
If the heaters
were to fail, it would take several
hours for the
to reach
normal
ambient conditions.
b.
The
lube oil and jacket water temperatures
are
recorded
every six
hours
by an auxiliary operator at Shearon Harris.
Enclosure I
c ~
If a seismic'vent,
of a magnitude sufficient to fail the heaters,
were to occur during winter conditions it would
be reasonable
to
assume
plant personnel
would
be
aware of it. If the seismic
event
caused
a loss of non-IE power, the diesels
would automatically start.
Failing that, plant personnel
would have sufficient time to manually
start
them.
d.
The
EDG building is equipped
with space
heaters
and there is ample
evidence
in the industry that
these
would fast start
under
normal ambient conditions.
Region II does
not
consider
this
issue
to
be in vio'lation of
Regulatory requirements.
4.
EDG Air Receivers
(Deficiency No. 90-200-04)
Shearon
Harris
Technical
Specifications
3/4.8. I
A.C.,
Sources,
Surveillance
Requirements
4.8.1.1.2.a.5
requires,
"verifying the pressure
in at least
one air start receiver to
be greater
than or equal
to l90
psig."
Neither the
NRC nor the licensee
were able to determine
the basis
for the
above
line item.
Review of background
documents
such
as:
Standard
Review
Plan,
Regulatory
Guides
and
Generic
Letters
proved
fruitless with respect
to defining
a standard for the
number of engine
starts
and the pressure
at which these
consecutive starts
should begin.
Nevertheless,
there is sufficient documented
data
(Transamerica
Delaval,
Inc. (TDI), Grand Gulf and
Shearon
Harris Tests)
which confirms there is
five start
capacity
at
pressures
of less
than
190 psig.
Region II
concludes
that
no violation of Regulatory requirements
exist.
5.
Design Basis Control (Deficiency No. 90-200-05)
This deficiency consists
of minor errors
in the design calculations for
the
EDG fuel oil system
and the
a.
Fuel Oil System Setpoints for Storage
and
Day Tanks
As previously
stated
in the
cover letter,
supplemental
verbal
information
was
obtained
from the
licensee
in late
August
1990.
Specifically the gallonage
at each level in both the day and storage
tanks
was quantified.
~oa
Tank
Low level tank alarm (535 gal)
Low level transfer
pump start
(628 gal)
High level transfer
pump stop
(2792 gal)
High level alarm (2947 gal)
High level transfer
pump discharge
valve closure
(2978 gal)
Enclosure
1
The
day tank allows
one
hour of diesel
operation at the low level
alarm.
This allows adequate
time to replace/repair
the transfer
pump
and is consistent with regulatory positions
on diesel fuel systems.
Stora
e Tank
Low level alarm (104,975 gal)
Fuel oil below suction line (unusable)
(11,663 gal)
The licensee
furnished the time (54 minutes) for the transfer
pump to
restore
the
day tank from low level start to high level stop
and the
fuel
consumption
(445 gal/hr) for the
EDG at
100 percent
load.
Simple computations
show
13,000
excess
gallons
above the
seven
day
required
75,000 gallons in the storage
tank.
Based
on the licensees'esponse,
Region II concludes that the issue
is not
a violation of regulatory requirements.
b.
EDG Building Fan
Calculation
was
performed
by the
licensee
to evaluate
changes
to
the
HVAC air hand'ling unit that
took
place
during
design/installation.
This
calculation
was
not
performed
to
initially size the unit.
An initial heat
load
and
HVAC calculation
9-OGB Section
E
was
performed to determine
the size
and type of air handling unit.
The licensee
performed
system
testing
to determine;
flow in each
duct,
fan
and
motor
rpm,
manometer
readings
(inches
of
H 0),
amperage,
discharge
total
pressure
and static
pressure.
Th( test
data confirmed the adequacy
of the initial calculations.
Region II concludes
that the calculations
were adequate
and that this
issue
does
not constitute
a violation of regulatory requirements.
6.
Emergency
Load Sequencer
Modifications (Deficiency No. 90-200-06)
The
licensee
had
issued
LER-89-016
dated
September ll,
1989,
which
identified
a
substantial
difference
between
alternating
current
(AC)
contac't rating
and
the direct current
(DC) contact rating of the relays
used
in the load sequencer
and
had issued
Plant
Change
Request
(PCR)
4765
for testing of the circuits in the sequencer.
This action was taken priot
to the
EDSFI.
Based
on the
above
information it is evident that the
licensee
had identified this deficiency,
had reported it to the
NRC and
begun corrective action.
This item is identified as
a Non-cited Violation 90-200-0I,
Emergency
Load
Sequencer
Deficiencies.,
This licensee .identified violation is not being
cited
because
criteria specified
in Section
V.G. 1 of the
NRC Enforcement
Policy were satisfied,
and
a licensee
response
is not required.
Enclosure
1
7.
Commercial
Grade Breakers
and Relays (Deficiency No. 90-200-07)
The
NRC has deferred
enforcement
related to commercial
grade
procurement
and dedication
programs
pending
reevaluation
of Agency policy in this
area.
Region II believes
that
the
above listed actions
apply to this
item
and that
no enforcement action'ill be taken.
8.
Failure of LK-16 Circuit Breakers
(Deficiency No. 90-200-08)
This item was previously identified
as
an unresolved
item (89-13-01)
by
the
NRC resident
inspector.
This item is being followed by the resident
inspector
and will not be addressed
as part of the
EDSFI findings.
9.
Testing of Class
IE Underground
Cables
(Deficiency No. 90-200-09)
The licensee's
response
states
that the testing of underground
cables
is
performed
to ensure
the integrity of the spare
6.9
kv and
480 vac
power
cables
as
the result of
a
FSAR concern
related
to underground
power
cables.
This concern is addressed
in the
FSAR, Section 8.3. 1.2.37.
Region II concludes
that the licensee
is meeting its commitment to test
the
power cables
as
required
by Section
8 of the
FSAR.
The licensee
advised that testing is being
performed
as required
which meets
the
commitment.
This item is closed.
ENCLOSURE 2
APPENDIX A
Deficiencies
OEF ICIENCY NUHBER 90-200-01
Deficiency Title:
EOG Load Sequencing
Calculation
(Unresolved
Item - Section 2.1.2 of report)
Descrf tion of Condition:
The emergency diesel generator
(EOG) calculation
17-EP established
the m5nfeem
voltage available at thc 6.9-kV emergency
buses
during thc sequencing of
'afety-related
loads onto the
EOG to be used
as input to other system loadfng
and voltage calculat5ons.
The team noted the following deficiencies in the
ca 1 cul at 5on:
The effect of sequencing
time drift on the tfm5ng of load blocks was not
addressed
fn the calculation.
(If orfft becomes
excessive,
the voltage
resulting from the two adjofnfng load blocks could overlap,
causing
4 voltage dfp beyond the tolerance of the load's cqu5pment.)
The computer
code
used to perform this calculation
had not been adequately
val5dated
and quality assurance
measures
had not been taken, contrary to
the Nuclear Engineering
Department
procedure
(Reference
1).
Information fn the calculation
on the sources
of input data were inade-.
quate to allow audit ard verification, contrary to Harris plant procedure.
(Reference 2).
The transient effect of the suddenly-applied
load, which reduces
the speed
of the generator
and hence
the generated
voltage,
was
assumed to be
neglfgfble.
The team considered this assumption
nonconservatfve
and the
calculation dfd not justify or establish
the upper
bound of its effects.
All loads
(both starting
and running) were assumed to be accurately
represented
as constant
fmpedances.
The accuracy of this'ssumptfor,
depended
on the mfx of loads'fn each
load block.
In view of the Shearon
Harris load mfx, the constant-impedance
assumption
was considered
not
properly justified or bounded
fn the calculation.
The licensee
provided additional information and stated that
loading test performed during the qualification of the eaergency
dfesel
generators
(Peference
1) demonstrated
the basic validity of the calculation.
The transient
loading test consisted of a block-loading
sequence
intended to
approximate
the actual
loading on the Shearon Harris
EOGs
as closely as tes't
facility limitations allowed.
The
NRC team agreed that the qualification test
enveloped
the plant conaftfons
and prcvfded reasonable
assurance
that the
results cf the calculation were conservative.
Although there were no iarnedfate
safety concerns
because
the qualification tests
confirmed the adequacy of the
EOG system,
the team concluded that the content of the calculation dfd not
assure
that sufficient voltages
were delivered to safety-related
loads during
an event of loss cf offsfte power,.
Enclosure
2
The licensee staff ~ill revise calculation 17-P by append)ng clarification of
the calculation methodology
and 3ustif.ication of the nonconservat$ ve assumptions
to the calculation.
The licensee stiff also vill to add additional information
on the verification and control of the computer
code.
Refere'nces:
TRP Revision 8, April 10, 1981, "qualification Test Report for TpI
Stardby Generator
Set"
A-2
Enclosure
2
DEFICIENCY HUHBER 90-200-02
~Dfl1
Tll:
EDGAR
't kRl~fVl
. (Potenti ~ 1 Enforcement Finding - Section 3.1 of report)
Descr1 tion of Condition:
The vendor for Crosby air tank relief valves
had issued
a Part
21 report on
fa1lures of these
valves at the Perry Huclear Plant.
The licensee
had
installed Crosby a1r tank relief valves in the
EDG air starting
system per
plant change request,
PCR 4406.
There was inadequate
documentation
to
determine if the rel1ef valves were seismically qualif1cd in. accordance
with
thc
FSAR and
ASNE Section Ill (References l and 2),
PCR 4406 sho~ed that the Crosby relief valves were similar to those installed
at the Perry Huclcar Plant.
The Perry investigation
had determined
these
valves to b'e shock sens1tive
and had included
a seismic test confirming that
the valves
renaine'd properly seated
up to their set point for a certain seismic
spectra.
Accelerations
above
these limits werc determined
by Perry to result
in a
cowmen-node
fa11ure.
The Shearon
Harris 11censec
performed
a safety
evaluation for PCR 4406 and determined that the accelerations
for the installed
rel1ef valves vere less than the limits of the Perry test
and were therefore
qualified.
However, the licensee
had taken
no action to obtain and properly
review th1s test to ver1fy.assumptions,
anomalies
ard plant-specific applica
tion.
The team concluded that the licensee
had not performed
a formal design
evaluation for the qualif1cation of these valves.
The licensee will perform a-.
formal design evaluation to ensure that the Perry seismic test bounds the
Shearon Harris'uclear Plant requirements
and to complete the
IEEE 344-75
documentation
requirements
for these relief valves
by April I, 1990,
10 CFR Part 50, Appendix B, Criterion III, Design Control, requires
design
control measures
to be provided for verifying or checking the adequacy of
des1gn
by performing design reviews, using alternate or simplified
calculational
methods,
or providing a suitable testing program.
References:
1 ~
FSAR,Section 9.5.6.1,
Design Bases,
states
in c) that "the portions of the
air starting
system necessary
for emergency
operation
meet
Se1smic
Categcry I, Safety Class
3 requirements"
and in d) that "the air
receIvers,
piping and valves
from the receivers
up to the d1esel
engine
are designed to Safety Class
3 and Seismic Category I requiren~nts (refer
to Table 3.2.1-1)"
2.
FSAR Table 3.2.l-l lists components
under the heading "Diesel Generator
Air Starting System
as
ASHE lll, Class 3, Seismic Category I, the Diesel
Generator air receivers
and associated
piping, tubing and valves essential
for emergency
operat1on"
A-3
Enclosure
2
DEFICIENCY NUMBER 90-200-03
~Df1i
. tel: tmib
Oll
dJ kilfi
M
t
(Potent1al
Enforccmcnt Finding - Section 3.2 of report)
Dcscri tien of Condition:
During standby the
EDG lube oil system temperature
was maintained at 140of
ainimum by a non-Class
lE inversion heater
located in the
sump tank,
The
jacket water
system heater temperature
was also maintained at 140
F minimum by
a non-Class
lE irarersion heater
located in the standpipe.
The Shearon Harris Technical Specifications
(Reference
1) required the diesel
generator to be derrenstrated
to be operable
by verifying that it could start
within 10 seconds,
with a test
us1ng the manufacturer's
eng5ne prelube
and
warmup procedures.
The technical specifications
gave
no reference to
low-temperature limits.
During standby only non-Class
lE heaters
were avail-
able
and could be lost 1f'a corwen-mode fa1lure occurred during
a seismic event
because
there
was
no evidence that the
EDG had the capability to cold start in
10 seconds ~ithout the lube oil and jacket water heaters.
This was contrary to
FSAR requirewnts
(Reference 2).
The team determined this to be an unreviewed safety
concern with regard to the
des5gn of the plant.
After a seismic event during winter. conditions, the
EOG,.
may not be able to star't in.l0 seconds.
The licensee
took 5amediate corrective
action
and estab11shed
temperature
limits for jacket water (40'F) and lube oil
(70'F) below which the
EOG would be considered
The licensee x5ll
establish administrative controls to monitor the temperatures
of the heaters
and taking appropriate
actions to restore
the
EDG to optimum cond5t5ons if
temperatures
approached
these limits.
~Re ufrenents
10
CFR Part 50, Appendix 8, Criterion 111, Design Control requires design
control rreasures
to be provided for verifying or checking the adequacy of
design
by performing design reviews, using alternate
or simplified
calculational
methods,
or providing a suitable testing program.
References:
1.
Technical Specification 3/4.8.1 A. C., Sources,
Surve1llance
Requirements
4.8.1.1.2.a.4,
1dentifies that 'each diesel generator shall
be demon-
strated
OPERABLE by verifying the diesel
can start ... with1n 10
seconds.'n
the notes it is stated that 'this test shall
be conducted in accordance
with rranufacturer's
recormendatio'ns
regard1ng
engine prelube
and warmup
procedures,
and
as applicable regarding
loading recommendations"
2.
FSAR Section 8.3.1.1.1.5,
Standby
AC Power Supply, b), states that 'each
diesel generator
has
been provided with a preheat
system which maintains
adequate
engine temperature
to ensure fast starts"
A-4
Enclosure
2
DEF 1c 1EHCY NUHBER 90-200-04
~ll II I
litt .'IIIDl I
(Potcntfal Enforcement
Ffnd5ng - Sectfon 3.3 of report)
Dcscrf tfon of Condition;
The
EOG afr start
system
had not been adequately
evaluated to demonstrate i,
five-stari capabf lfty of the diesel it a starting afr rece1ver
prcssure of
l90 psig.
The team observed
the present
alarm set point for the starting ifr
receiver fn the plant was
190 a
5 ps5g.
The present technical specffication
surveillance
requirements
(Reference l) specified
a minimum prcssure of
190 psfg fn each rccefvcr.
-The
FSAR (References
2 ind 3) stated that each
starting afr-receiver shall
be demonstrated
by test io successfully start the
dfesel five times without recharging
the receivers.
During plant pre-
operatfonal testing,
the licensee
had demonstrated
that the diesel generator
had
a five-start capability, but thfs test
was done it high initial pressures
of up to 248 psfg,
and not at the technical specification requirement of 190
psfg.
Test data
provided by the diesel generator
vendor demonstrated i seven-start
capaHlfty for the
EDG, but this test
was not done
on
a receiver 1dentfcal to
the
EOG afr receivers at Shcaron Marrfs.
During thc inspection per5od,
the
licensee
provided relevant test data from the Grand Gulf Nuclear Power Plant
Unit l w1th a similar
EDG afr start
system configuration to the Shcaron Harris
a1r start
system which demonstrated
five or morc starts at in initial pressure
of lower than
190 psig.
The licensee
dfd not make any comnftment to perform testing of the starting ifr
receivers
(actual
equ5pment) for the five-start capability, as coamftted to fn
the
FSAR (Reference 2).
The licensee
stated that i retest would cause
exces-
sive wear on the diesel generator
and afr start system.
Mowcver, the licensee
did perform an evaluation of the Transamcrfca
Delaval (vendor)
Grand Gulf test,
and Shearon
Marrfs preoperat1onal
testing to conclude that the
conbfnatfon of these tests result in a safe condition and an adequate
demon-
stration of the five-start capability at 190 psfg.
The tean:
had
no fnnedfate safety
concerns after reviewing the licensee's
evaluat1on,
but noted that no engineer 5ng evaluation
had been performed for
this concern before the inspection; other than the Shcaron
Marr5s pre-
operatfc nal test.
The team considered
the prc-operational test by itself to be
an unacceptable
resolution with regard to meeting licensing conmftments to
denonstrate
a five-start
EDG capability at
a set point of l90 psfg.
l0 CFR Part 50, Appendix B, Criterion ill, Design Control, requires
design
control measures
to be provided for verifying or checking the adequacy of
des1gn
by performing design reviews, using alternate or simplified
calculatfonal
methods,
or providing suitable testing program.
I
I
~
Enclosure
2
References:
1.
Technical Specification 3/4.8.1
A. C., Sources,
Surveillince Requirements
4.8.1.1.2 states
that each diesel generator shall
be demonstrated
by (item 5)" ... verifying the pressure
in at least
one air start receiver
to be greater
than or equal to 190 psig"
2. 'SAR 8.3.1.2,14
k, qualification Testing Program, identifies that qualifi
. cat1on testing of the diesel generator for the
SMNPP consists mainly of
three test steps:
(1) Factory Run-ln Test, (2) Type Qualification Test,
and (3) Sit<< Test.
'Test Steps
1 I 2, performed at the manufacturer's,
facility, established
test conditions similar to what can
be expected at
the actual site except that the intake and exhaust
system
and starting air
of the test facility is substituted for the actual equipment.
burin
reo erational test at the site
test ste
3
the actual
e ui men
uti
zeo.
s
sect
on
urt er
e
nes t e sterttnp
a r capac ty
test pertormed at toe manufacturer's tactltty under step 2, (3) as "start-
ing Air Capacity Test:
This test demonstrates
the eng1ne-generator's
ability can
be successfully
stated
a minimum of five times without
recharging
the air rece1vers'
~
FSAR Sect1on 9.5.6.1,
Design Basis, states
in a) that "each starting air
receiver will supply sufficient compressed air to crank the cold d1esel
engine five times without recharging
the receiver.
Each cranking cycle
brings the diesel generator
up to
a speed of 200 rpm'
A-6
Enclosure
2
DEFICIENCY NU~1BER 90-200-05
~Df14
VI I
'.
5
1g
B
I
C t
(Potential
Enforcement Finding - Section 3.4 of report)
Descri tion of Condition:
The team found errors
and inconsistencies
in the design calculations for the
fuel oil transfer
system
and
HVAC systems,
Calculations establishing
setpoints for the fuel oil storage
tank (Refer
ence
1) and fuel oil day tank (Reference l) vere not retlected in the
present plant setpoints.
No design basis
had been provided in calculations
(Reference
2) for the
technical specification (3/4.8.1)
minimum fuel oil storage
tank volume
requirement of 100,000
ga lions.
Calculations
(Reference
4) for the
EDG building fans did not provide the
fan curve analysis of HVAC air handling unit AH-85 static pressure,
nor
did it provide
a conclusion.
A calculation
(Reference
5) demonstrated
the effect of winter condition
temperatures
on diesel generator building areas/rooms,
but did not address
acceptance
of non-Class
lE unit heaters
for aeintenance
of the area/room
temperatures.
The team noted that discrepancies
in the format and content of these calcula-
tions ~as contrary to plant procedures
(Reference 6).
In addition, the
1icensee
did not have
a program to ensure that the mechanical
and electrical
design
bases
had been maintained
and properly translated
into plant operating
procedures.
~di:
1C CFR Part 50, Appendix B, Criterion III, Design Control, requires the design
basis to be correctly translated
into specifications,
drawings,
procedures,
and
instructions.
References:
l.
Calculation EgS-28,
Fuel Oil Day Tank
2.
Calculation E(5-23, Fuel Oil Storage
Tank
3,
Calculation
EgS F0-5, Fuel Oil Storage
Tank
4.
Calculation 9FP-BE-OB,
HVAC Air Handling Unit
5.
Calculation 9-DGB, Tab 0,
EDG Building Temperature
1
NED Gl E-4, Revision 0, February k3, 1989,
"NED Guideline-Preparation,
Documentation
and Control of Calculations
A-7
F'
Enclosure
2
DEFJCIENCY
NUHBER 90-200-06
~ltfli
Ill:
E
I
yL d5q
llof1
(Potentfal
Enforcement
Ffndfng - Section 4.2.l of report)
Desert tfon of Condftfon:
Durfng the fnspectfon,
the team questfoned
the adequacy of the contact r'atfng
for load sequencer-relays.
Hodfffcatfons of the load sequencers
were fmple-
mented under
PCR-4765 to elfmfnate relay contact overload condftfons that had
led to relay ccr.tact faflures.
ln addftfon,
an analysfs of relay contact
'loads
was undertaken
by the lfcensee tu verffy the adequacy of the sequencer
desfgn.
Ho~ever,
the safety analysfs dfd not provfoe an acceptable
basis for the
adequacy
of the dc fnductfve ratfngs of the contacts.
The lfcensee
was able to conffrm that the contacts of the suspect
relays,had
been fnspected
and were observed to show no sfgns of damage;
therefore,
there
was
no fmmedfate safety concern.
However, the lfcensee fnftfated a test
program to establfsh
an acceptable
relay contact fnductfve load ratfng for
Potter-Brumffeld relays
used fn dc cfrcufts and scheduled to complete thfs test
program by September
1, 1990.
Reaufrements:
10
CFR Part 50, Appendfx B, Crfterfon ill, Desfgn Control, requfres
measures
be
establfshed
for determfnfng the suftabflfty of materfals
and equfpment that are
essentfal
to the safety-related
functfons of the systems
and for verffyfng or
checkfng the adequacy of the desfgn.
References:
1.
NRC Regulatory
Gufde 1.32, Revfsfon 2, 'Criterfa for Safety Related
Electrfc Power
Systems for Nuclear
Power Plants"
2.
lnstftute of Electrfcal and Electronfcs
Engfneers,
Standard
lEEE 308-
1980,
" lEEE Stanoard Crfterfa for Class
)E Power Syst'ems for Nuclear Power
Generatfng
Statfons'-8
Enclosure
2
DEFICIENCY
NUMBER 90-200-07
~Dfll
Ill.'C
I I.G
d
B
I
dRly
(Potential
Enforcement
Find1ng - Section 4.2,3 of report)
Descri tion of Condition:
The team reviewed the plant procedure
(Reference I) for performing coeeercial-
grade dedications
and noted that the procedure did not require the documenta-
tion of critical characteristics
and did not specify methods to verify critical
characterist1c.
The storage
and maintenance
sheets for <<olded-case circuit,
breakers
also contained
no testing or inspections to verify the seismic
qualification of conrnercial-grade
breakers.
The 11censee's
response
to an
NRC violation dated
November 8, )989, shwed that
the licensee
had installed several
correercial-grade
<<olded-case circuit break
ers in safety-related
applications without a proper revie~ for seismic qualifi-
cat1on or other important critical characteristics.
The response
to the
violat5on, ho~ever,
did not address
other corvercial-grade
breakers that may
have
been installed for a sim1lar deficiency.
The licensee identified 35 commercial-grade
breakers
installed in
safety-related
applications,
and at the team's request,
contacted
several of
the c1rcuit breaker manufacturers
who indicated that changes
had been
made to
the breakers
since their original qualification.
The licensee
was not aware of
these
chinges
and their effect on capab111ty of these circuit breakers to
perform their safety function.
The team also identified several
comnercial-grade
Potter
and Brumfield relays
installed in safety-related
applications.
No testing
was apparently
done to
verify the critical characteristics
of these relays including those for seismic
qualif5cation, contact ratings,
p1ckup,
and dropout for Class
IE applications.
As a result of these
concerns,
the licensee will demonstrate
the Class jE
qualification of the co<<~ercial-grade
breakers
and relays or replacing
them
prior to startup
from the next outage.
~Rd
i:
IO CFR Part 50, Appendix 8, Criterion III, Design Control, requires measures to
be established for determining the suitab1lity of materials
and equipment,
essential
to the safety-related
functions of systems
and
components
and for
verifying or checking the adequacy of the design.
Peferences:
).
Procedure
THY-104, "Determination of Technical
and
gA Requirements for
Procurement
Documents"
A-9
\\
10
DEFICIENCY NUMBER 90-200-08
P
~otM
Till:
F 1l
f BIC t/p
LK-lS.Ct
8
B
k
(Unresolved
Item - Section 4.3.1 of rcport)
Dascrf tfor of Condition:
, Past failures of BBC type LK-16, 1600A-.frame,
480-Y (600-Y class)
power cfr cuit
breakers to open
on demand fn non-Class
lE distribution switchgear
had occurred
after the breakers
had experienced
a relatfvely large
number of cycles
between
preventive maintenance.
The team noted that the non-Class
1E type LK-16
breakers at Shcaron Harris were physically identical to the Class
1E breakcjs
installed at the plant.
The licensee
stated that the LK-16 breakers
in
Class
IE service operated only during operational
surveillance,
post-
m'ntenance
testing,
and accidents
and consequently
accumulated relatively few
cycles
o
The licensee
reported that the basic design of the openfng
mechanism of the
breakers failed to prcvfde enough force to separate
the movable-and stationary
contacts
against
the clamping force of the contact springs, especially
when the
crritact surfaces
had been
roughened
by repeated
cycling.
The licensee
had been
working with the cfrcu)t breaker vendor,
Asea
Brown Boverf (ABB, successor
to
BBC), as well as independently
to resolve this problem.
CPSL and
ABB attempted
a variety of "fixes'ith unsatisfactory
results,
and
ABB apparently withdrew
from the effort.
The licensee
had 'established
an internal engineering
task
force before this
NRC inspection,
but had not established
a root cause for
failures for the past
4 years.
In response
to the team's
concerns,
the licensee
prepared
a safety evaluation
(Reference
1) to justify the continued operation of the plant with the
18 LK-16
breakers
fn Class
1E applications
and conmftted to an accelerated
program of
preventive
maintenance
(Reference
2) on the Class
1E breakers.
The licensee
also will oetermfnc the root cause of the failures by the end of Harch 1990.
Reoufrements:
1G CFR Part 50, Appendix 8, Crit'erfon III, Design Control, requires
design
control measures
to be provided for verifying or checking the adequacy of
design
by performing design reviews, using alternate
or simplified
calculatfonal
methods,
or providing a suitable testing
program.
References:
1,
Licensee's
safety evaluation,
"Response
to
NRC question
on LK-16
Swftchgcar Breakers" (with attachments
A and B), February 26, 1990
2..
CPhL Letter No. HS-903128(0),
L. J.
Moods to d. F. Nevflle, LK-16
Breakers,
Harch 12,
1990
A-10
Enclosure
2
DEF ICIENCY HlNBER 90-200-09
D~fl I
'Hl:
T
t1N
fC1
lEUd
y
dnbl
(Unresolved
Item
Section 4.3.4 of report)
Oescri tion of Condition:
The
FSAR (Reference
1) requires
a random sample of Class
1E cables in the
underground
cable system to be tested to demonstrate
that the dielectric
integrity of the insulation is maintained throughout the life of the cables.
The )icensee
indicated that their current test program procedures
only required
power cables of large 6.9-'V and 480-Y rotating equipment to be tested for
insulation dielectric integrity,
The team was concerned that the licensee's
test program did not fully meet the intent of the
FSAR as all cable types were
not being tested (i.e., power, instrumentation,
and control) ~
The licensee
acknowledged
the concern
and will include appropriate
underground
cables
in the
test program.
Region il will folio~ up on review of testing of appropriate
cables.
10 CFR Part 50, Appendix B, Criterion XI, Test Control, requires that all
testing required to demonstrate
that
components will perform satisfactorily in
service are identified and performed.
References:
1.
FSAR Section 8.3,1.2.37E,
Test program for Class
1E Underground
Cables
ENCLOSURE 3
CPEL Comments
Def iciency Muaber 90-200-01
EDC Load Sequencing
Calculation
~dank round
The
EDSFI
reviewed
Emergency
Diesel
Generator
(EDC)
Loading
Calculation
17-EP.
The
purpose
of
this
calculation
is
to
demonstrate
acceptable
voltage
and frequency of the safety-related
Electrical Distribution System
when loads
are being
sequenced
onto
the
EDC.
This
calculation
was
prepared
by
the
vendor
of
the
generator
(Parsons
Peebles/Electric
Products)
that
is
mounted
on
the
EDC skid.
The purpose
of the
EDSFI revie~
was to verify that
the
content
of
the calculation
provided
adequate
assurance
that
the
EDC would provide
an acceptable
power supply.
NRC Deficiencies
Although
containing
several
individua'l,
items,
this
EDSFI
deficiency addressed
the following major issues:
1.
Documentation
and
conclusions
on
the
effect
of
sequencer
relay timing drift.
2.
Absence
of validation information for the
vendor's
computer
model.
3.
The calculat ion
package
did not contain al.l the information
that is required
by existing
CP&L design guidelines.
believes
that
there
is
no
technical
issue
in
rhis
deficiency.
The
issue
is
the
quantity
and
presentation
of
technical
information
in
the
calculation.
Responses
to
the
specific points listed
above are
as follows:
l.
As
shown
in the
computer
printouts
included
in Calculation
17-EP,
the worst
case
recovery
time to
90Z voltage is
1.01
seconds
with full recovery in less
than
2 seconds'ince
the
maximum drift on timer setpoint
is 0.5
seconds,
the
minimum
,possible
time between
load block starts
is
4 seconds
assuming
a late
start
of
one
block
and
an early start
of the
next
block.
These
values
are
confirmed
through
performance
of
Engineering
Surveillance
Tests
EST-316
and
EST-317 'ince
the diesel
generator
voltage will recover in appreciably
less
time
than
the
minimum possible
time
between
sequenced
load
blocks,
there will be
no
adverse affect
from sequence
timer
drift.
This topic will be addressed
in the next revision of
the subject calculation.
In
summary,
the
calculation
contained
the
essential
information to
reach
a
favorable
conclusion
even
though it
was not stated
in explicit terms.
MEM/HO-9001130/4/Osl
Enclosure
3
2.
NED
procedures
related
to
softMare
control
cover
programs
used
in-house,
and
therefore
are
not applicable
to previous
Work performed
by vendors.
Control
and verificatiori of the
sof tMare
is
covered
by the manufacturer's
QA program.
The
software
used
in the
above
calculation
was
developed
and
is
maintained
by
the
manufacturer
(Parsons
Peebles/Electric
Products).
3.
During
the
audit,
the
calculation
preparer
(Parsons
Peebles/Electric
Products),
verbally
provided justification
for
the
assumptions
used
in
the
calculations.
has
requested
the
reference
documentation
Mhich vill
be
incorporated
in
the
next
revision
of
the
calculation
for
cl'arity.
Conclusion
CPhL
believes
that
there
is
no
technical
issue
in
this
deficiency.
However, additional
supplemental
information Mill be
added
to the calculation.
HEM/HO-9001130/S /Os 1
Enclosure
3
Deficieocy Number 90-200-02
EDC hi r Tank Relief Valves
~Back round
CP&L initiated
an
engineering
evaluation
on
April.
14,
1989
to
review the application of the Crosby Starting Air Relief Valves
on
the
EDC at
Harris
based
on
receipt
of
a
Nuclear
Network Report
(NO.
OE-3260)
from the
Perry, Plant.
The evaluation
(PCR-4406)
assessed
the Perry acceleration
(g) values
determined
by test
(and
obtained
verbally from Perry) to determine
that
the Harris valves
were
enveloped
by
the
Cleveland
Electric
Illuminating
(CEI)
Reports
This
was
based
on
specific
Harris
seismic
input.
An
additional
condition
considered
was
valve
positions
The
Perry
problem
was initiated
when
the valves,
mounted
in the horizontal
position,
were
bumped.
The
Harris
valves
are
mounted
in
the
vertical
position further
reducing
the possibility
of
a similar
occurrence.
The
evaluation
concluded
these
valves
were
acceptable'he
fact that the actual qualification report
was not
obtained
at
that
time
was
based
on the fact that
the valve
was
assured
qualified
for
initial
design
conditions
(with
documentation
included with the
EDC package)
and
was evaluated for
specific
loadings
and
criteria
identified,
not
'totally
requalified.
The total qualification report
was later
obtained
and
a complete qualification package
generated.
On January
17,
1990,
the original equipment
vendor
(Transamerica
DeLava1 )
informed
under
10
CFR
Part
21
that
the
valves
procured
for
the
Shearon
Harris
Plant
had
not
been
seismically
qualified,
contrary
to their original responsibilities
to
CP&L.
Because
of the evaluation
performed,
based
on the Nuclear
Network
Report,
CP&L determined
that there
was
no immediate safety
problem
at Harris'n
March 9,
1990
ICE. Notice 90-18
was
issued
by the
NRC.
The
EDSFI report stated
that "the team concluded
that
the licensee
had not performed
a formal design evaluation for the qualification
of these valves" based
on the
absence
of the seismic qualification
report being on file.
The
EDSFI does
not adequately
and accurately
portray the
sequence
of
events
surrounding
this
issue.
agrees'hat
the
qualification documentation
maintained
by
CP&L was
inadequate
to
establish
total
seismic
qualification
of
the
subject
valves.
However,
the conditions
questioned
were
thoroughly
evaluated
and
found
acceptable.
The
seismic
qualification
package
has
subsequently
been
upgraded
to
include
the
qualification
information based
on the receipt of the Part
21 from Transamerica
DeLaval.
The seismic test report
was procured
from CEI, subjected
MEM/HO"9001130/6/OS1
Enclosure
3
to
an
engineering
revie~
and
incorporated
into
the
seismic
qualification files'P&L disagrees
with
the
impression
that
prior to the
EDSFI,
the
issue
had
been dealt with on
a less
than
formal basis.
The
issue
had
been dealt
with from the standpoint
of the
anomalous
behavior of the valves at
CEI and
subjected
to a
detailed engineering
evaluation.
Conclusion
This
issue
was
subject
to
previous
and
ongoing
CP&L reviews
in
accordance
with the
review of Part
21 notices
made
to
CP&L.
As
such,
the
issue
of lack of qualification documentation
had
been
already
identified
to
CP&L and
would
have
been
corrected,
The
technical
issue
of the applicability of the valve had already
been
the
subject
of
engineering
evaluation
based
on
reliable
test
information from CEI about
the valves'eismic qualification test.
HEH/H0-9001130/7/OS1
Enclosure
3
Deficiency Number 90-200-03
EDC Lube Oil and Jacket
Mater Heaters
~Back tound
The
design
of
the
Harris
Emergency
Diesel
Generators
(EDCs)
includes
non-safety
related
heaters
in the lube oil reservoir
and
jacket
water
reservoir.
The
heaters
are
used
for maintaining
temperatures
for minimizing wear
on the
EDCs during
an
EDC start
as
described
in
FSAR Sections
9
5
5
2
and
9 5.7.2.
The heaters
are
not
required
during
EDC operation.
The
maintenance
of the
proper
engine
temperatures
is
subject
to
routine
(daily)
verification by the logging of
EDC parameters.
The fact that
the jacket water heaters
are
powered
from non-safety
related
power supplies
is identified in the
FSAR (see
Section 9.5.5.2).
The
FSAR does
not clearly state
that the
lube
oil heaters
are
powered
from a non class
lE bus.
The plant design
philosophy
as
stated
in
FSAR Section
3.2.1.1
is
that
Class
1E
power
would
be
required
only if the
function
is
necessary
to
assure:
a)
b)
c)
The integrity of the
reactor
coolant
pressure
boundary
(RCPB),
The
capability
to
safely
shutdown
the
reactor
and
maintain it in a safe condition, or
The capability
to prevent
or mitigate
the
consequences
of
accidents
which
'could
result
in potential offsite
exposures
comparable
to the guideline exposures
of 10CFR
Part
100
~
These
heaters
do not perform such
a function.
The
EDSFI reported
that
the
NRC team position
was that the heaters
must
be
powered
by
a Class
1E power
source.
The
bases
that
was
given for this position
was that if the
non Class
1E power supply
were
lost
during
extreme
cold outside air
temperature,
the
EDC
would
no longer'be
capable
of a successful
emergency
start within
the required
10 seconds.
The response
to this
issue
contains
two basic points.'he first
(also
discussed
in Deficiency 90-200-05 ) is that heaters
required
solely for temperature
maintenance
of equipment
and not required
during
emergency
operation
of equipment
need
not
be
designed
to
Class
1E
requirements.
This
design
philosophy
is
utilized
throughout
the design for SHNPP.
This design
philosophy is based
on the
NRC's guidance
provided in Reg
Guide
1.29
"Seismic
Design
Classification."
MEH/HO-9001130/8/Osl
Enclosure
3
In the
specif ic example
of the
EDC heaters,
it is unlikeLy that
the
non-Class
LE
power
supply
system
would
be
lost
without
resul t ing
in
the
operat ion
of
the
EDG.
The
Class
LE
buses
are
dependent
on
the
same offsite circuits,
transformers
and
6.9
KV
distribution that
feeds
the non-Class
LE distribution system.
If,
on the other hand,
the
Loss of the heaters
is due to a malfunction
of the heaters,
this failure
would
be possible
regardless
of the
qual ification of the heaters
~
The
loss
of
a specific heater
is
discussed
in the second
point ~
Secondly,
the deficiency
does
raise
the
issue
whether
there
is
a
Lo~er
limit for
successful
operation.
A
review
of
the
technical
information and
past
EDC starts
at lov oil temperatures
established
that there
are
lover limits of jacket water
and
lube
oil
temperature
which
are
required.
has
determined
that
jacket
vater
temperature
must
be
maintained
greater
than
40
degrees
F and that lube oil temperature
must
be maintained greater
than
70
degrees
F.
These
limits
have
been
established
in
appropriate
administrative
procedures
and vill require
that if
these
temperatures
cannot
be
maintained,
then
the
EDG vill be
declared
Conclusion
It is
CP&L's position
that
the
key issue
is maintaining
the
lube
oil
and
jacket
vater
temperatures
within the
appropriate
limits.
However,
the
components
to maintain
these limits do not
necessarily
require
the
use of Class
LE equipment.
The basis for
this
position
is
that
only
those
components
necessary
for
operation of safety related
equipment
are required to be Class
LE.
HEN/H0-900 I 1 30/9/OS I
Enclosure
3
Def iciency Number 90-200-04
r
EDC Ait Receivers
~Bakcround
The
EDCs including the air start
systems
for SHNPP,
were
procured
from TransAmerica
DeLaval
~
The qualification testing
for the
EDC
included
factory run-in tests,
type qualification tests,
and site
tests.
The
in Section
8.3.1.1.2.14.k.2,
defines
which of
these
tests
were
used
to
satisfy
the
applicable
regulatory
requirements.
For
SHNPP,
the
vendor
demonstrated
adequate
air
start
receiver
capacity
using
a prototype air start
and
exhausr.
system.
The
FSAR clearly states
that the qual.ification of the air
start receiver capacity, was
performed
as
a type qualification test,
in
the
vendors
faci lity.
Section
14 .2 . 12. 1. 16,
which
discusses
the specifics
on
the onsite testing, clearly omits
the
air start receiver capacity testing.
Notwithstariding
these
commitments
and their approval
by the
NRC
SER,
CPhL conducted
an onsite air receiver
capacity test.
This
testing
was
performed
with
a
starting
air
pressure
of
approximately
235 psig.
This pressure
is the nominal air receiver
pressure
that results
when the associated
air compressors
complete
a running cycle.
The
purpose
of the onsite. air receiver testing
was
for commercial
reasons.
Differences
between
the air start
system
used
at
the
factory
and
the
onsite
installati'ons
are
minimal.
The size of the piping and
number of components
are the
same
~
The main exception
is that
the size of the air receiver at
the test facility had
a smaller
volume than those at Harris.
NRC Deficienc
The
EDSFI
team
concluded
after
reviewing
the
start
and
load
acceptance
test
(performed
onsite)
that
the
system
had
not
been'dequately
evaluated
to demonstrate
a five-start capability of the
EDC at
a 'starting air receiver
pressure
of 190 psig.
CPhL Res
nse
The interpretation
of
the
by the
EDSFI is incorrect.
The
section
is incorrectly
and
incompletely
referenced
by
the
inspection report.
The entire
FSAR passage
is provided
below'.
8.3
~ 1 ~ 1.F 14.K
Qualification
Testing
Program
- qualification
testing
of
diesel
generator
for the
SHNPP plant consists
mainly of the
following
steps.'.
Factory run-in test.
2.
Type qualification test
MEM/H0-9001130/10/OS I
Enclosure
3
(a)
Start
and
load acceptance
qualification
(b)
Load capability qualification
(c)
Hargin qualificacion
(d)
Sequencial
loading test
(e)
Starting air capacity test
3.
Site test
(a)
Start
and
Load acceptance
test
(b)
Load capability test
(c)
Design load test
(d)
ELectrical tesc
Test
Steps
1
& 2,
performed
at
the manufacturer's
faciLity,
estabLished
test
conditions similar to Mhat can
be
expected
at the actual site
except
that the intake
and
exhausc
system
and starting air of the test facilicy is substituted
for the
actual
equipmenc.
Ifuring
che
preoperacional
test
at
che
site, test
Step 3, the actual
equipment is utilized.
This
clearly
shoMs
that
CP6L's
commitment
on
the
air start
receiver. capacity test did not include the requirement
to perform
a site test
Mich che air tanks inirially at
190 psig.
Conclusion
The
commitmenc
has
been
properly
addressed
by existing
tescing
and
no further testing is required.
HEMIHO-900 1'1 30 I 1 1 IOS 1
I
Enclosure
3
Def iciency Number 90-200-05
Des ign Bas i s Cont ro 1
This, item
addressed
four specific
mechanical
calculations
that
were
reviewed
during
the
EDSFI
~
The first and
second
items
are
addressed
together
and
the latter
two
are
addressed
separately
below.
A suranary conclusion for all four items is presented
after
the conclusion of the fourth item.
Items
A & B)
Fuel Oil Tank setpoints
(Two examples)
~Back raund
The
Main
Fuel Oil Storage
Tanks
for
SHNPP
were initial,ly sized
when
the
SHNPP
was
a four unit design.
The design
consisted
of
four underground
tanks.
Each
tank
was
to
be
shared
between
two
EDCs
from separate
units.
Because
of this,
the original size
was
determined
to
be
175,000
gallons
(suf ficient
to
accommodate
accident
loads
on
one
unit while allowing safe
shutdown
of the
other unit).
Subsequently,
the size of the station
was
reduced
to
a
single
unit.
The
required
quantity
of
fuel
was
revised
downward.
The result
was that
74,760 gallons
of useable
fuel oil
would
be acceptable.
The value is the result of calculation
EQS-
23,
Rev.3
(January
14,
1986).
Subsequently,
the
Technical
Specification
value
for
the
Main
Fuel
Oil
Storage
Tanks
was
selected
in
1986.
This
value
was
chosen
to
be
100,000
gallons
(indicated)
to
envelope
the
result
of
the
most
recent
calculation.
The
Main Fuel Oil Tanks
level transmitter
feeds
a
local
indicator
at
the
Main
Fuel
Oil
Tanks
and
feeds
a
Main
Control
Board Annunciator.
The annunciator
is
set
to alarm
when
the
fuel oil
level
reaches
an
indicated
level
equivalent
to
104,970 gallons.
Each
EDC has
a dedicated
Day Tank with a capacity of approximately
3100 gallons
~
There are
several
functions
that
are
performed
by
the
level
transmitter
and
level
switches
on
the
tank.
In
ascending
tank level these
functions are:
1.
Low level tank alarm
2.
Low level transfer
pump start
3.
High level transfer
pump. stop
4.
High level alarm
S.
High level transfer
pump discharge
valve closure
Mhen Technical
Specifications
were
developed,
the Tech.
Spec
~ for the
Day Tank
be at the nominal
shutoff of the transfer
pump.
After licensing
of
was
determined
that
the
allowable
range
of
fuel
pioposed
that
point for the
the plant, it
oil specific
MEM/H0-9001130/12/Osl
Enclosure
3
10
gravity introduced
significant uncertainty
in determining if the
Tech.
Spec.
LCO (which vas
stated
in gaLLons)
vas met.
This
Led
co
che
implementation
of
a
g'raph
vhich used
the
most
recent
Day
Tank specific gravity and
the indicated level
on the Hain ControL
Board
co determine if the
LCO vas met.
ltBC Deficienc
On the firsc
icem,
the
EDSFI report
staces
chat
the calculations
vere not reflected in the present
plant setpoints.
On the
second
item the
EDSFI report states
that the basis for the
Hain
fuel
Oil
Scorage
Tank
Technical
Specification
LCO is
noc
reflected
in the calculation.
The
secpoints
thac
are
used
for instrumentation
and
alarms
are
consistent
with the values derived by'calculation.
The value
used
in
the
T.S ~
LCO
vas
chosen
to
envelope
the
value
derived
by
calculation
and
that
this
in
turn
does
not
require
additional
decaiL
be included in calculations.
Item C)
EDC Building Fan Calculations
~Sa
rrlrouad
Calculation
vas
performed
co
determine
the
minimum
requirements
for the
AH-85 fan.
Each
EDC building contains
tvo
AH-85
fans
housed
in
a
single
unit>
they
are
used
to provide
ventilation
for
the
electrical
equipment
rooms
in
che
EDC
Building.
The result of this calculation vas
a specified
minimum
flow capability for the individual fans at
a sp'ecified
discharge
pressure.
This calculation
vas
subsequencly
used
to evaluate
and
procure specific equipment for the
AH-85 application.
NBC Deficienc
The subject calculation did not provide the
fan curve analysis
of
the
HVAC air,handling unit static
pressure,
nor did it provide
a
conclusion.
CPCL Bes
nse
Calculation 9FP-BE-08
vas
performed
co anaLytically confirm system
losses
and
determine
flov
requirements'ans
vere
then
selected/purchased
to
meet
che
criteria
set
forth
in
the
calculation.
The
systems
vere
then
tested
and
balanced
during
pre-operational
testing
and performed satisfactorily.
The teits
MEH/HO-9001130/13/OS
1
Enclosure
3
demons traces
adequacy
oE
design.
This
in
turn
saci sf ies
the
design control requirements
of
LOCFR50 Appendix B.
Icem D)
Non Class
LE Space
Heaters
Eor the
EDC Building
~Baela rouad
The
EDC building at
SHNPP is
a
free
standing
reinEorced
concrete
building vhich
is
separate
from the
balance
of the
po~er
block.
The building is equipped with non-safecy
related
space
heaters
to
maincain
the
general
area
temperatures
above
freezing
during
vincer months.
The heaters
serve
no function subsequent
to an
EDC
scarc
as
the
singular
problem
becomes
one
of cooling
the
area
surrounding
the
EDC even during vinter temperature
extremes.
NRC Deficienc
A
calculation
demonscraced
the
effecc
of
vinter
condition
cemperacures
on
EDG areas
buc did not
address
the
acceptance
of
non Class
LE heater for maintenance
of the area
temperatures.
CP&L Res
nse
As
discussed
in Deficiency 90-200-03, it is
CP&L's position that
temperature
maintenance
can
be
performed
using
non
Class
LE
equipment.
It is irrelevant
vhether
the calculation
provides
a
specific
discussion
of
the
subjects
The
SHNPP
FSAR discusses
temperacure
maincenance
and
clearLy
states it is
non
Class
LE.
This is in agreement vith the guidance
in IEEE 622.
The
FSAR will
be
amended
to include
the
Diesel
Generator
Building and
the
Intake Structure
in Section 7.7. 1. 11.
Conclusion
Each of the examples listed
above
have
been
shown to not represent
an error in the calculation or an error in the implementation
of
rhe results of the calculation.
These facts vere presented
to the
applicable
members
of
che
EDSFI
team.
Notvithstanding
chis,
the
EDSFI report
includes
a statement
that
the "licensee
did not
have
a
program
to
ensure
that
che
mechanical
and
eleccricaL
design
bases
had
been
maintained
and
properly
translated
into
plane
operating
procedures."
CP&L's review of this specific deficiency
concludes
char.
these
specific
items
do
noc
to
such
a
conclusion.
MEM/H0-9001130/14/OSL
Enclosure
3
12
Deficiency Huaber 90-200-06
Emergency
Load Sequencer
Hodifications
~Back round
The emergency
load sequencers
are
used
to sequence
emergency
loads
following
a
loss
of
offsite
power,
Safety
Injection
or
a
combination
of
the
two.
These
separate
sequencer
programs
are
resred
routinely
(once
every
two
months)
using
test
circuitry
which
should
not,
cause
actual
operation
of
the
actuated
equipment.
On
several
occasions,
the
test
has
resulted
in the
unwanted
actuation
oE equipment.
The
most
recent
event
occurred
on
September
11,
1989
and
was
reported
to the
HRC in
LER Number
89-016-00.
The investigation
oE that
event
led to thediscovery
thar.
certain
relay
contacts
were
not
specifically
designed
to
interrupt the
DC inductive load that
was being switched
by certain
relays.
The affected
relays
were
only used
in the test circuit
and
in
the
circuit
used
to
reset
the
sequencer
following
restoration
of
offsite
power
or
following
reset
of
Safety
Injection.
@hen
the
overloading
problem
was
identified
as
a result
of the
evaluation
of the last
event, it was
determined
that
the
vendor
did
not
have
a
DC inductive
rating for the
contacts.
It
was
decided
to
approach
the
problem
along
two
paths.
First
the
contact
load
was reduced to a value that appeared
acceptable
based
on engineering
judgment.
Second,
testing
was to
be performed
to
quantitatively determine
an acceptable
rating.
a
This testing
had .not
been
completed prior to the
EOSFI
because
of
delays
in procuring the extra relays
Eor the test.
HRC Deficienc
The
design
control
for
the
application
oE
the
relays
in
circuits
in
the
load
sequencer
was
inadequate
in that
suitable
equipment
was not procured
Eor the specific application.
CP&L Res
ase
J
The
result
of
the
relay
testing
demonstrated
that
the
reduced
relay
contact
rating
was still not sufficiently low to
prevent
relay failure.
For the
case
of the Potter
Brumfie)d relays which
were
initially identified
with
the
overloaded
condition,
the
failure
mode
did not
prevent
successful
sequencer
operation,
but
did
prevent
sequencer
reset.
However,
the
testing
suggested
additional
equipment misapplication with microswitches
attached
to
Agastat
relays.
Testing of these
microswitches
demonstrated
that
these
switches
could also fail.
The failure mode
and consequences
were determined
to be
more severe.
The
consequences
included the
failure
oE
the
sequencer
to
properly
shift
from
the
loss
of
offsite power program to the Safety Injection Program if these
two
HEM/HO-9001130/15/OS
1
Enclosure
3
13
signals
did not
occur simultaneously.'he
sequencers
were
both
subsequently
modified to address
both of these
problems.
The
discovery
of this
additional
problem
was
determined
to
be
reportable
to
the
NRC
under
10CFR
50. 72
on
Hay
24,
1990.
LER
90-015
has
been
submitted
to
the
NRC to describe
in detail
the
corrective actions
that
have
been
taken.
The
issue
has also
been
determined
to
be
reportable
to
the
NRC under
PART
21
since
the
sequencer
design.was
developed
by Ebasco Services,
Inc.
~suassar
The
problem
with
the
sequencer
relays,
which
was
previously
identified by CP&L prior to the
EDSFI, has
now been corrected.
As
described
in
LER 90-015,
CP&L conducted
a
review of similar
relay applications
in sa'fety related circuits, without discovering
any similar misapplications.
HEH/HO-900 11 30/16/OS
1
Enclosure
3
14
Deficiency Number 90-200-07
Dedication of Coaznercial
Grade
Components
Background
Components
in
safety-related
motor
control
centers
and
relay
panels
for
the
SHNPP
were
replaced
using
coranercial
grade
equipment.
The
process
included
testing
for proper
operations
in the
intended
application,
but did not
include
new
seismic testing'f the parts.
The key as'sumption
in this approach
is that
the manufacturing
process
for the
breaker
or relay would
not
be
changed
to the
degree
requiring
new qualification testing
without having
some other result
on the physical characteristics.
This approach
was
presumed
to
be
an acceptable
practice.
However,
in recent
years,
the
industry
has
recognized
that
more
effort needs
to
be applied to confirm the critical characteristics
of commercial
grade
items prior to use
in safety"rel'ared
appli-
cations.
CP&L began
implementing
the guidance
of
NP-5652
on
January
1,
1990.
Rigorous
review of critical characteristics
is
now done for commercial
grade dedications.
CP&L had
made plans to
review past dedications
when generic critical characteristics
were
defined for a particular
component
type.
NRC Deficiency
The
EDSFI
report
stated
that
the
practice
of using'onxnercial
grade
breakers
in like-for-like replacements
without
a detailed
evaluation
of any
changes
that
may
have
been
introduced
by the
manufacturer
was unacceptable.
However,
in
a
subsequent
telephone
conversation
with members
of
the
NRC's
Region II staff,
CP&L was
informed
that
the
NRC would
not pursue this issue
based
on the generic nature of the issue
and
the active
work by the entire industry to investigate
and correct
current practices.
CP&L Response
The
commitments
made
with
regard
to
the
review of breaker
and
relay qualification are
proceeding
within the context
of the
new
commercial
grade
program.
The
actions
which
were
cormnited during the
EDSFI
inspection will be
complete
by the
end
~
of the next refueling outage.
HEH/HO"900'l l30/I 7/OS I
l'
n
J
Enclosure
3
't'
~
E
15
Deficiency Number 90-200-08
Failures of LK-16 Type Breakers
Background
The plant
design
employs
LK-16 circuit breakers
in approximately
120
nonsafety
related
and
18
safety-related
applications.
The
breakers
were
procured
based
on
successful
qualification of the
breakers
to applicable
industry
standards.
In addition,
safety-
related
breakers
were
seismically
qualified
in accordance
with
The LK-16 breaker
was
used both to control the
starting
and stopping of loads
(medium sired motors)
and for power
distribution
(motor
control
center'eeder
breakers).
Starting
during
hot
functional'esting
in
1986i
the
plant
experienced
failures of the
LK-16 breakers
in nonsafety
applications
to
open
on
demand.
From the
very beginning,
root
causes
were identified
and corrective
actions
implemented.
The specific history of the
breakers
and corrective actions will not
be repeated
here.
The
result
of
CP&L's
detailed,
independent,
multidisciplined,
interdepartmental
investigations
which
began
in the fall
oE
1989
have
resulted
in
two
important
facts.
First,
the
failure
mechanism
is
random
in nature
and
second,
the failure
mechanism
can best
be
summarized
as
dependent
on the addition
oE opening
and
closing 'resistive
forces
in each particular breaker.
The testing
performed in 1989 and early
1990 on the unmodified breakers
showed
that the failure rate
was
on the order of
1 failure for every
1000
demands.
NRC Deficiency
The
EDSFI
team
concluded
that
this
problem
was
an
apparent
violation
of
10CFR50 Appendix B Criterion III which
requires
design
control
measures
to verify that
equipment
is suitable for
the intended function.
CP&L Response
During the extensive
review of the
LK-16 problem,
there
have not
been
any
questi'ons
as
to whether
the initial'ualification per
industry
standards
was
in error.
It is
CP&L's opinion that the
tolerances
applied
in
the
manufacture
of
the
breaker
were
not
sufficient to achieve
acceptable
performance of the breaker
in the
field.
As indicated in the
EDSFI report,
CP&L has
implemented
an enhanced
preventive
maintenance
program
for
the
safety-related
LK-16
breakers'he
program is designed
to assure
that adequate
margin
exists
in the operating
mechanism
and
is
based
on the results
of
extensive
testing
performed
to
measure
the
net
forces
in
the
breaker.
MEM/HO-9001130/18/Osl
Enclosure
3
16
The root
cause
has
been identified
as
an inadequate
design
margin
in
the
opening
spring
force.
The
critical
characteristics
affecting
the
opening
and
restraining
force
balance
Mere
not
adequately
controlled
causing
random variations
in the threshold
force value required to open the breaker.
Several
modifications
have
been
proposed
and
subjected
to
a
CPKL
validation test
program.
A modification Mill be installed
Mhen
appropriate validation
and certification testing is completed.
Conclusion
CP6L
has diligently pursued
the
problems
With the
LK-16 breakers
and Mill continue until an acceptable
performance
is obtained
in
field
experience.
In
the
mean'time,
the
enhanced'reventive
Maintenance
program
for
the
safety-related
breakers
provides
assurance
that
a
failure
on
demand
remains
random
and
is
considerably
less
than
1 in 1000.
MEM/HO"9001130/19/OS
1
e
Enclosure
3
17
Def iciency Humber 90-200-09
-Testing of Class
LE Underground
Cables
Background
Prior
to
the
issuance
of
the
Construction
Permit,
during
the
review of the
PSAR,
the
HRC identified
a series
of concerns
with
regard
to
each
PSAR section.
A concern
was identified with the
compliance
with General
Design Criterion
17 dealing specifically
with
the
qualification
of
underground
power
cables.
CPSL's
response
was
to commit to institute testing
of underground
power
cables.
The
commitment
is written into
FSAR Section 8.3.1.2.37,
which deals
with the
power distribution
system.
During the
Last
two refueling outages,
6.9 kv and
480
vac
po~er cables
which are
installed
spares
were
meggered
to
verify
that
the
required
insulation characteristics
were available.
HRC Deficiency
The
EDSFI
report
contends
that
the
cori tment
unde rg round
cables
encompasses
1 ow
voltage
instrumentation
cables.
and
controL
cables.
The
testing
was
written
as
apparent
violation
of
LOCFR50, Appendix B, Criterion XI.
for testing
of
power
cable,
absence
of this
requirements
of
CPCL Response
The
safety
related
cables
used
in
underground
duct
banks
are
specificalLy
qualified
for
that
service
in
accordance
with
specification
CAR-SH-E"14A and 14'upplemental
testing is not
required
to demonstrate
adequate
qualification.
The requirement
to test
the higher voltage =power
cable
was 'he direct result
of
the
concerns
that existed
at
the
HRC in the late
1970s with high
voltage cable,
not with low voltage
po~er
and control cables
~
The
comnitment
to test
higher
voltage
cables
will be
reassessed
to
determine if it can
be
removed
from the
FSAR entirely.
Conclusion
The
FSAR commitment
was never
intended
to cover low voltage cables
as
presented
in the
HRC deficiency.
HEH/HO-900 LI 30/20/OS 1
t
~1
~ e A