ML18005A683
| ML18005A683 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 10/18/1988 |
| From: | Conlon T, Ruff A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18005A681 | List: |
| References | |
| RTR-REGGD-01.097, RTR-REGGD-1.097 50-400-88-29, GL-82-33, IEB-84-02, IEB-84-2, IEB-88-003, IEB-88-3, NUDOCS 8811030356 | |
| Download: ML18005A683 (21) | |
See also: IR 05000400/1988029
Text
oc
EA<<AKCVrWp0
/~
oo
~o
~**<<<<
UNITED STATES
NUCLEAR REGULATORY COMM)ASSlON
REGION II
101 MARIETTAST., N.W.
ATLANTA,GEORGIA 30323
Report No.:
50-400/88-29
Licensee:
Carolina
Power
and Light Company
P. 0.
Box 1551
Raleigh,
NC
27602
Docket No.:
50-400
Facility Name:
Shearon
Harris Nuclear
Power Plant
License No.:
Inspection
Conducted:
August
29 - September
2,
1988
Inspector:
Alber t B.
Ruff,
Team
Leader
Team Members:
C. Paulk,
Region II Inspector
M. Miller, Region II Inspector
P. Fillion, Region II Inspector
Approved by:
T.
E. Conlon, Chief
Plant
Systems
Section
Engineering
Branch
Division of Reactor
Safety
l0 rp
P te Signed
Date Signed
SUMMARY
Scope:
This special,
announced
inspection
was conducted
in the areas
of the
licensee's
conformance
to Regulatory Guide (RG) 1.97, Instrumentation
for Light-Water-Cooled
Nuclear
Power
Plants
to
Assess
Plant
and
Environs Conditions During and Following an Accident.
A follow-up of
NRC open
items
and inspection for Bulletin responses.
Results:
In . general,
the
licensee
has
performed
the
installation
and
modifications of instruments
to comply with Regulatory
Guide
1.97.
There
were exceptions
noted
in the Safety
Evaluation
Report
(SER)
issued
on January
21,
1986,
and
subsequent
correspondence
with the
NRC.
Additional
items
were identified during this inspection
which
are
discussed
in the report.
The licensee
drawing 2166-S-9000,
Post
Accident
Monitoring
(PAM)
Equipment,
is
a
compilation
of
the
licensee's
intent and exceptions
in meeting
This drawing is
a good tool and provides
a single document that
shows the licensee's
instrumentation.
This
drawing
needs
to
be
updated.
The
licensee
stated that this would be accomplished.
8811030356
881025
ADOCK 05000400
6
PNU
A weakness
was
identified
in
the
licensee's
program
concerning
trending
and
evaluation
of as-found
out of tolerance
reading
on
instrument calibration (Paragraph 2.c.(2)(a)).
REPORT DETAILS
1.
Persons
Contacted
Licensee
Employees
- J. Brown, Senior Specialist,
Corporate
W. Edwards,
I&C Engineer,
Nuclear Engineering
Dept.
- E. Evans,
I&C Project Engineer,
Nuclear Engineering
Dept.
"C. Hinnant, Plant General
Manager
"A. Howe, Senior Specialist,
Regulatory Compliance
"M. Jackson,
Electrical/I&C Supervisor
- D. McCarthy, Principal Engineer,
Nuclear Engineering
Dept.
"C. McKenzie, Principal
Engineer,
Quality Assurance/Quality
Control
"T. Morton, Manager of Maintenance
J.
Presson,
Specialist,
Nuclear Engineering
Dept.
K. Russell,
On-site Nuclear Safety
"M. Turkal, Senior Specialist,
Nuclear
Fuel
& Licensing Dept.
"R.
Van Metre,
Manager of Technical
Support
Other
licensee
employees
contacted
during
this
inspection
included
engineers,
operators,
mechanics,
security force members,
technicians,
and
administrative
personnel.
NRC Resident
Inspectors
- W. Bradford, Senior Resident
Inspector
"M. Shannon,
Resident
Inspector
- Attended exit interview
2.
Inspection
of
Licensee's
Implementation
of Multiplant Action
A-17
Instrumentation
for Nuclear
Power
Plants
to
Assess
Plant
and
Environs
Conditions
During
and
Following
an
Accident
(Regulatory
Guide
1.97)(25587).
Criterion 13,
"Instrumentation
and
Control",
of Appendix
A to
10 CFR Part 50 includes
a requirement that instrumentation
be provided to monitor
variables
and
systems
over
their
anticipated
ranges
'for
accident
conditions
as appropriate
to
ensure
adequate
safety.
Regulatory
Guide
1.97
(RG 1.97)
describes
a
method
acceptable
to
the
NRC staff for
complying with the
Commissions
regulations
to provide instrumentation
to
monitor plant variables
and systems
during and following an accident.
The
purpose
of this inspection
was to verify that the
licensee
has
an
instrumentation
system
for assessing
variables
and
systems
during
and
following an accident,
as discussed
in
Under accident conditions
it is
necessary
that
the operating
personnel
have
(1) information that
permits the operator
to take preplanned
actions to accomplish
a safe plant
shutdown;
(2) determine
whether
the
reactor
trip,
Engineered
Safety-
Feature
Systems
(ESFS),
and manually initiated safety
and other
systems
important
to
safety
are
performing
their
intended
functions;
and,
(3) provide information to operators
that will enable
them to determine
the potential
for causing
a gross
breach
of the barriers
to radioactive
release
and to determine if a breach
has occurred.
It is essential
that
indicators
be
provided
to
the
operator if the
barriers
are
being
challenged that will allow the release
of radioactive materials.
For this
reason multiple instruments with overlapping
ranges
may be necessary.
The
required
instrumentation
must
be
capable
of surviving
the
accident
environment for the length of time its operability is required.
It is
desirable
components
continue to function following seismic events.
As
a result,
five types of variables
have
been
specified that
serve
as
guides
in defining criteria
and
the
selection
of accident-monitoring
instrumentation.
The types
are:
Type
A - Those variables
that provide
information needed
to permit the control
room operating
personnel
to take
specified
manual
actions for which
no automatic
control is provided
and
that are
required for safety
systems
to accomplish their functions for
design
basis
accident
events.
Type
8 -
Those
variables
that
provide
information
to
indicate
whether
plant
safety
functions
are
being
accomplished.
Type
C -
Those
variables
that
provide
information
to
indicate the potential for barriers
being breached
or the actual
breach of
bar riers
to fission
product
release.
Type
D -
Those
variables
that
provide information to indicate operation of individual safety
systems
and
other
systems
important
to
safety.
Type
E
Those
variables
to
be
monitored
in determining
the
magnitude
of the
release
of radioactive
materials
and for continuously assessing
such release.
The design
and qualification criteria
are
separated
into three
separate
categories
that provide
a graded
approach
to requirements
depending
on the
importance
to
safety
of
the
measurement
of
a
specific
variable.
Category
1 provides
the
most stringent
requirements
and is intended for
key
variables.
Category
2
provides
less
stringent
requirements
and
generally
applies
to instrumentation
designated
for indicating
system
operating
status.
Category
3 is
intended
to provide
requirements
that
will ensure
that high-quality off-the-shelf instrumentation
is
obtained
and applies
to backup
and diagnostic
instrumentation.
A key var'.able is
that single
accomplishment
of
a safety function
(Types
8
and
C), or the
operation
of
a
safety
system
(Type 0),
or radioactive
material
release
(Type E).
Type
A variables
are
plant
specific
and
depends
on
the
operations
that
the
designer
chooses
for
planned
manual
actions.
Inspection
of Categories
1
and
2
equipment,
was
performed
as
described
below.
Category
1 Instrumentation
The instrumentation listed in the Category
1 Table, of this section,
was examined
to verify that the design
and qualification criteria of
had
been
satisfied.
The
instrumentation
was
inspected
by
reviewing drawings,
procedures,
data
sheets,
other documentation,
and
performing
walkdowns
for
visual
observation
of
the
installed
equipment.
The following areas
were inspected:
(1)
(~)
(3)
Equipment Qualification - The
EQ Master
Equipment List and the
Q-List were
reviewed
for confirmation that
the
licensee
had
addressed
environmental
qualification requirements
for class
1E
equipment.
Redundancy
-
Walkdowns
were
performed
to verify
by visual
observation
the
specified
instruments
were
installed
and
separation
requirements
were
met.
In addition
Loop drawings
were reviewed,
to verify redundancy
and channel
separation.
Power
Sources
Loop
drawings
were
reviewed
to verify the
instrumentation
is energized
from a safety-related
power source.
Display
and
Recording - Walkdowns
were
performed
to verify by
visual
observation
that
the
specified
display
and
recording
instruments
were installed.
Loop drawings
were
reviewed
to
verify there
was at least
one
recorder
in
a redundant
channel
and two indicators,
one per division (channel) for each
measured
variable.
Range - Walkdowns
were
performed
to verify the actual
range of
the indicator/recorders
was
as specified in
RG 1.97 or the
SER.
Review
of calibration
procedures
verified
sensitivity
and
overlapping
requirements
of
RG 1.97 for instruments
measuring
the
same variable.
(6)
(7)
Interfaces
The
loop drawings
and Q-List were
reviewed
to
verify that
safety-related
isolation
devices
were
used
when
required to isolate
the circuits from non-safety
systems.
Direct Measurement - Loop drawings were reviewed to verify that
the parameters
are directly measured
by the sensors.
Service,
Testing,
and Calibration - The maintenance
program for
performing
calibrations
and
survei llances
was
reviewed
and
discussed
with the
licensee.
Calibration
and
surveillance
procedures
and
the latest
data
sheets
for each
instrument
were
reviewed to verify the instruments
have
a valid calibration.
CATEGORY
1 TABLE
Variable
Pressure
RCS Hot Leg
Temperature
RCS Col d Leg
Temperature
Containment
Water Level
Wide Range
PT-402
PT-402
PR-402-1
PT-403
PT-403
PR-402
I
I
IIIIIII
TE-413A
I
TI-413A
I
TR-413-1A I
TE-423A
I
TI-423A
I
TR-413-2A I
TE-433
I
TI-433A
I
TR"413-3A I
TE-410B
II
T1-410B
II
TR-410-1B II
TE-420B
II
TI-420B
II
TR-410-2B II
TE-430B
II
T1-430B
II
TR-410-3B II
LT-7162
LI-7162
LT-7162
LI-7162
Instrument
No.
Channel
or Train
Loop and
46574,
sheet
22
46577,
sheet
8
92079,
sheet
11
2166 B-401,
sheet
197
46574,
sheet
23
46574,
sheet
24
92079,
sheet
12
2166 B-401,
sheet
183
46574,
sheet
21
46575,
sheet
18
92080,
sheet
19
2166 B-401,
sheet
184
47236,
sheet
40
47241,
sheet
44
2166 B-401,
sheet
1046
Containment
Pressure
PT-950
PI"950
PR-950-1
PT-951
PI "951
PR-950-2
PT-952
PI-952
PT-953
P I-953
I
I
IIIIIIIIII
III
IV
IV
46574,
sheet
12
46575,
sheet
12
46576,
sheet
13
46577,
sheet
10
2166 B-401,
sheet
185
Variabl e
(cont'd)
Instrument
No.
Channel
or Train
Loop and
W~ii
0
RMST
Level
Pressurizer
Level
Steam
Line
Pressure
Auxi l iary
Flow
LT"990
LT-990
LR-990-1
LT-991
LI-991
LR-990-2
LT-992
LT-992
LT-993
LI-993
LT-459
LI-459
LR-459
LT"460
LI-460
LT-461
LI-461
PT"474
PI-474
PT-484
P I-484
PT-494
PI-494
PT-475
PI-475
PR-475-1
PT-485
P I"485
PR-475-2
PT-495
PI-495
PR"475-3
PT-476
PI-476
PI-486
PI-486
PT-496
PI-496
FT-2050
FI-2050
FT-2050
FT-2050
FT-2050
FI-2050
FR-2050
I
I
IIIIIII
II I
III
IV
IV *
I
I
IIIIIIII
III
IIIIIIIIIIIIIII
III
III
III
III
III
III
III
III
IV
IV
IV
IV
IV
IV
46574,
sheet
16
46575,
sheet
16
46576,
sheet
18
46577,
sheet
9
2166 B-401,
sheet
1045
46575,
sheet
20
46576,
sheet
19
46580,-sheet
20
92079,
sheet
10
2166 B-401,
sheets
145
&
146
46575,
sheet
21
sheet
23
sheet
25
46576,
sheet
26
sheet
28
sheet
30
46577,
sheet
18
sheet
20
sheet
22
92080,
sheet
18
sheet
20
2166 B-401,
sheets
988
8
989
47236,
sheet
6
47241',
sheet
8
2166 B-401,
sheet
1957
Yariable
(cont d)
Instrument
No.
Channel
or Train
Loop and
Wirin
Drawin
s
Condensate
,
LT-9010
A
Storage
Tank
LI-9010
A
Level
LT-9010
B
LI-9010
B
47236,
sheet
3
2166 B-401,
sheet
2092
Containment
LT-7150
A
Spray Additive LI-7150
A
Tank
LT-7166
B
Level
LI-7166
B
47236,
sheet
27
sheet
39
2166 B-401,
sheet
1041
b.
Category
2 Instrumentation
The instrumentation
listed in the Category
2 Table, of this section,
was examined to verify that the design
and qualification criteria of
had
been satisfied'he
instrumentation
was
inspected
by
reviewing drawings,
procedures,
data
sheets,
other documentation,
and
performing
walkdowns
for
visual
observation
of
the
installed
equipment.
The following areas
were inspected:
(2)
(3)
(4)
,Equipment Qualification - The
EQ Master
Equipment List and the
Q-List were
reviewed
for confirmation that
the
licensee
had
addressed
environmental qualification requirements
for Class
1E
equipment.
Power
Sources
-
Loop
drawings
were
reviewed
to verify the
instrumentation
is
energized
from
a
high
quality
or
a
safety-related
power source.
Display
and
Recording - Walkdowns
were
performed
to verify by
visual
observation
that
the
specific
display
'and
recording
instruments
were
installed.
Loop drawings
were
reviewed
to
verify there
was at least
one recorder,
where
required
by
in
a
redundant
channel
and
two indicators,
one
per
division (channel) for each
measure
variable.'ange
Walkdowns
were
performed
to verify the actual
range of
the indicators/recorders
was
as specified in
RG 1.97 or the
SER.
Review
of calibration
procedures
verified
sensitivity
and
overlapping
requirements
of
RG 1.97 for instruments
measuring
the
same variable.
(5)
Interfaces
-
The
loop drawings
and Q-List were
reviewed
to
ver'ify that
safety-related
isolation
devices
are
used
when
required
to isolate
the circuits
from computer
systems
(Not
safety-related).
(6)
Direct measurement
- Loop drawings were reviewed to ver'ify that
the parameters
are directly measured
by the sensors.
(7)
Service,
Testing,
and Calibration - The maintenance
program for
performing
calibrations
and
surveillances
was
reviewed
and
discussed
with
the
licensee.
Calibration
and
surveillance
procedures
and the latest
data
sheets
for each
instrument
were
reviewed to verify the instruments
have
a valid calibration.
CATEGORY 2 TABLE
Variable
Tank(s)
Level
Tank
Pressure
Fl ow
Instrument
No.
Channel
or Train
LT-920
LI-920
LT-922
LI"922
LT-924
LI-924
LT-926
LI-926
LT-928
LI-928
LT-930
LI-930
PT-921
PI-921
PT-923
PI-923
PT-925
-PI-925
PT-927
PI-927
PT-929
P I-929
PT-931
PI-931
FT"605A
FI-605A
FT-605B
FI-605B
Loop and
Wirin
Drawin
s
46579,
sheet
8
sheet
9
sheet
10
46661,
sheet
12
sheet
13
sheet
14
2166 B-401,
sheets
452
&
453
46579,
sheet
8
sheet
9
sheet
10
46661,
sheet
12
sheet
13
sheet
14
2166 B-401,
sheets
452
&
453
46580,'heet,
33
92078,
sheet
7
2166 B-401,
sheet
334
Variabl e
(cont d)
Instrument
No.
Loop and
~CC
TI
I
IiIC~~iii
i
Heat Exchanger
Outlet
Temperature
Containment
'ater
Level
Narrow Range
Containment
Spray
Flow
Tank(s) Discharge
Valve Position
6. 9KV
Emergency
Bus Voltage
Diesel Generator
(a)
Voltage
(b) Field
Voltage
(c) Current
(d) Field
Current
(c) Power
Battery Current
Battery Voltage
TE-606A
TR-604
TE-606B
TR-606
LIT-7160A
LI-7160A
LIT-7160B
LIT-7160B
FT-7122A
FT-7122B
8808A
8808B
8808C
EI 6956Al
'I
6956Bl
EI 6955A
EI 6955B
EI 6954A
EI 695AB
EI 6951A.
EI 6951B
EI 6950A
EI 6950B
EI 6957A
EI 6957B
EI 6963A1A
EI 6963B1B
EI 6961A1A
EI 696181B
46579,
sheet
13
46580,
sheet
5
2166 B-401,
sheet
334
47236,
sheet
39
47241,
sheet
29
2166 B-401,
sheet
1041
47236,
sheet
39
47241,
sheet
38
2166 B-401,
sheets
1041
8
1042
2166 B-401,
sheets
411,
412,
413
2166 B-401,
sheets
1729
and
1730
2166 B-401,
sheets
1994
and
2013
2166 B401,
sheets
1994
and
2014
2166 B401,
sheets
1993
and
2014
2166 B401,
sheets
1994
and
2014
2166 B401,
sheets
1994
and
2014
2166 B401,
sheets
1798
and
1799
216B401,
sheets
1798 and
1799
Discussion
(1)
Open
Items Identified in the
SER.
The
licensee,
Carolina
Power
and
Light
Company
(CP&L),
was
requested
by Generic Letter 82-33 to provide
a report to the
NRC
describing
how the
PAM instrumentation
meets
the guidelines
of
as
applied
to
emergency'esponse
facilities.
The
licensee's
response
to
RG 1.97 was provided.
As the result of
a detailed
review and
a technical
evaluation of the submittals,
the
NRC issued
the
by letter dated
January
21,
1986.
The
evaluation identified
a requested
exception that the Accumulator
Tank Pressure
and Level instruments
be exempted
from the
E(} Rule
This exception
was
not approved.
CP&L letter
to
NRC of December
10,
1987,
requested
a deferral
on this issue
pending further
NRC review.
This deferral
was
approved
by
NRC
letter to
CP&L dated
May 19,
1988.
(2)
Comments
and
Open
Items Observed
During the Walkdown,
and Review
of Document
and Drawing for
RG 1.97 Equipment.
(a)
(Open)
Deviation 50-400/88-29-03,
Evaluating
and Trending
Out-of-Tolerance
Calibration
Data.
As
part
of this
inspection, calibration data
sheets
were reviewed to verify
instrument
and loop calibration.
The review was di.fficult
because
total loop calibration data
was not available
as
a
package
for
each
selected
parameter.
The
method
of
calibration
and data filing, although acceptable,
made the
loop calibration
data
review difficult and
inconvenient'he
licensee's
program
allows
overlap
calibration
and
testing, i.e.,
the
components
can
be
done
separately
or
together.
Because
of the way the procedures
are structured
and
implemented,
i.e.,
instruments
in
the
loop
are
calibrated
at
different
times,
the
data
sheets
were
provided
as filed in time sequence
instead of a package for
each loop.
During
the
review
to
verify
the
calibration
of
instruments, it was noted'hat
data
recordings
for "as
found" readings
were not in the allowable
range for
some
transmitters'or
this
condition,
the
calibration
procedures
require
that
the Shift
Foreman
be
notified
immediately
and
the
I&C Foreman
be notified
as
soon
as
possible.
This
was
documented
in all required
instances
except for MST-I0004 which did not
have
the required
sign
off for notifying the
Shift
Foreman.
the
calibration
procedure
for
PT-0951,
Containment
Pressure
Transmitter,
was performed
on August 17, 1987.)
10
Fifty Maintenance
Surveillance
Test
(MST)
calibration
procedures
were
reviewed
and
27
had
"as
found"
values
outside of the allowable
range.
Discussions
with
a Shift
Foreman,
an
Foreman,
and
a
Maintenance
Supervisor
indicated that
no further evaluation
was performed
when
an
instrument
was
found outside
the
allowable
range if it
could
be
adjusted
(calibrated)
to
be within acceptable
tolerances.
The
licensee
is
committed
in
FSAR Section
1.8 to
IEEE
Standard
338-1977
(Reg.
Guide
1. 118)
and
ANSI N18.7 (Reg.
Guide 1.33).
The
IEEE Standard
338-1977
establishes
the
criteria for periodic
testing
of
1E
systems.
The
IEEE
standard
(Section 6.2.2,
6.6. 1.5,
6.6. 1.9,
6.6.2.9
and
6.6.2. 13)
states
that
a
program
shall
be
designed
to
produce
objective data for evaluating
the
performance
and
availability
of
the
tested
systems/components.
IEEE
Standard
and
ANSI N18.7 require
a Trending
Program.
ANSI
N18.7Property "ANSI code" (as page type) with input value "ANSI</br></br>N18.7" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process. [Section
4. 1(4)3 also states
that the testing
program
should provide trend data
and
the capability to determine
degradation
which
may
not
be
apparent
to
a
day
to
day
observer.
The testing
program at
SHNPP
does
not provide
trending
or evaluating
of out of tolerance
readings.
The
basis for the
IEEE Standard is to provide
a testing
program
that will contribute to the attainment
of desired
system
operational
availability and identify performance
that is
not within the allowable limits.
The
above
discussion
is
considered
to be
an indication of a deviation
from an
commitment
and is identified as Deviation 50-400/88-29-03,
Evaluating
and Trending Out-of-Tolerance Calibration Data.
This item was initially discussed
as
an unresolved
item at
the exit meeting.
However,
the
licensee
was notified at
that
meeting
that
the
item
would
be
evaluated
at
the
region.
By
a
subsequent
telephone
call
to
the
Plant
Manager
on
September
7,
1988,
the
licensee
was notified
that the item would be upgraded
to
a deviations
(Open)
URI 50-400/88-29-01,
Justification/Exemption
Letter
on
RCS Temperature
Elements
Concerning
Redundancy
The licensee
has
designated
RCS hot leg water
temperature
(Th)
and
RCS cold leg water temperature
(Tc) as
a Type A,
Category
1 variable.
In addition,
RG 1.97 specifies
these
variables
as
Type
B, Category
1.
RG 1.97 specifies
that
Category
1
variables
should
be
monitored
by
redundant
instrument loops.
The Harris plant has
one instrument
loop
per reactor
loop for the
Th variable.
However,
the
power
supply for each
loop is the Channel
I inverter.
Therefore,
11
the Harris plant
does
not
have
redundant
instrumentation
for Th.
The
Tc variable
has similar instrumentation
except
that it is
powered
from the
Channel
II inverter.
The
licensee
states
in his submittal,
dated
September
6,
1983,
that diverse
information for Th is provided
by the
core
exit
thermocouples
(Type
C,
Category 1),
and
diverse
information for Tc is provided
by the
steam line pressure
(Type
A, Category 1).
Nevert'heless,
the lack of redundant
power supplies for the
Th and
Tc variables
may constitute
a
deviation
from
Since
the
licensee's
submittal did not clearly describe
the
power supplies,
this
matter
was
not specifically reviewed
by the
NRC.
in order
to resolve
the
matter,
the
licensee
agreed
to
make
a
supplementary
submittal
to
NRC describing
their
instrumentation
for
Th
and
Tc,
diverse
measurements
instrumentation
power supply
and
any justification they
may
wish to provide for acceptability
of the present
design.
This
item
is designated
as
URI 50-400/88-29-02
pending
licensee
and
NRR action
on this item.
(Open)
50-400/88-29-02,
Update
and
Licensee's
Drawing for
PAM Instruments,
and
Ensure
MCB
has
Proper
Designator
for
PAM Instrument.
A review of
the
instruments
in
the
and
those
listed
on
Drawing
No. 2166-S-9000,
Rev. 0,
Post
Accident
Monitoring
Equipment,
identified
several
discrepancies.
Some
items that were listed in the
FSAR were not listed
on the
drawing
and
some
PAM items that were listed in the drawing
were not in the
FSAR.
In addition,
Note
1 in the drawing
did not provide
a complete definition of all variables
and
the
drawing
was
not
annotated
to
show
the
instrument
indicators
that
had
the
common
PAM designator
on
the
control
panel
(the later is considered
to be
an enhancement
for the
drawing).
The
licensee
committed to review
and
revise both of these
documents
such that the next update of
the
(which will be approximately
October
1989) will
include the changes.
Rev.
3,
requires
that
"Types
A,
B,
and
C
instruments
designated
as
Categories
1
and
2
should
be
specifically identified with
a
common designation
on
the
control panels
so that the operator
can easily discern that
they
are
intended
for
use
under
accident
conditions."
During inspection
in the Control
Room,
discrepancies
were
noted
in the distinct labelling of
PAM instruments.
For
example,
all
Type A, Category
1 variables
did not
have
a
common designator
(a yellow border trimming the
PAM readout
indicator)
on the control
board.
Some
Type
D, Category
2
variables did.
Type
D PAM instruments
are not required
by
12
R.G.1.97
to
have
this distinct labeling.
To
add
these
common designators
for Type
D instruments
is considered
to
be
a licensee's
prerogative.
The licensee
has committed to
review the control
board designations
to ensure
that all
Type A,
B,
and
C
variables
of Categories
1
and
2
are
properly
labeled.
The
licensee
also
stated
that
an
evaluation will be
performed
for those
Type
D variables
that
are
designated
for accident
conditions.
This
is
identified
as
50-400/88-29-02,
Update
FSAR,
Instrument
Drawing and
MCB PAM Designations.
Control
Room Envelope
states
that it provides
the
minimum
number
of
variables
to
be
monitored
by
control
room
operating
personnel
during and following an accident.
This statement
could
be interpreted
to
mean that the variable
should
be
monitored in the control
room.
The
1'icensee
has
designated
containment
concentration
as
a
Type A, Category
1 variable.
This is
not
monitored
in
the
control
room.
The
licensee's
submittal,
dated
September
6,
1983, indicates that percent
concentration
is displayed
in the
control
room
envelope,
processed
by the
computer
and
recorded.
During
the
inspection, it was
confirmed that
percent
concentration
in
the
containment
is
displayed
on
a
continuous
real
time indicator and continuously recorded at
the
analyzer
panel.
The
panel
is located
in
a
room adjacent
to
the
main
control
room
that
would
be
readily accessible
during
and following an accident.
The
variable is scanned
by the plant computer at
an appropriate
interval
and
may be displayed
on demand
on
a
CRT screen
in
the
main control
room.
The variable is also
recorded
by
the computer.
Based
on the
above
and
NRR's acceptance
of
the
licensee
submittal,
the
instrumentation
provided
(indicators
and recorders)
to monitor containment
concentration
in the control
room envelope is acceptable.
Concerns
Identified
By a Previous
Inspection and/or During
Part of the Malkdown Inspection for
PAM Equipment
During
a
routine
gA inspection
in October
19-23,
1987,
unterminated
cables
were
observed
in
the
relay
and
auxiliary relay
panels
outside
the control
room.
These
unterminated
cables
were
each
tagged
with
a
cable
identification
number which was identical
to
an installed
cabl'e
in the
same
panel.
The
licensee
researched
this
problem
and
determined
that the unterminated
cables
were
"spared"
and
should
be identified
as
abandoned
or spared
cables.
13
The
Site
Engineering
Unit
(SEU)
wrote
PCR-2444
dated
October 26,
1987
and
Form
2 dated
November 5,
1987,
to
specify
the
corrective
action
for the
spared
cables.
Technical
Support
issued
Form
2ÃX to close
PCR-2444
and
initiated
work request
authorization
WRA-87B1MF1.
This
work
ticket
was
cancelled
without
the
work
being
accomplished.
The inspector
was
informed that
WRAs
have
been
and
can
be
cancelled
without
the
work
being
accomplished
as
required.
This concern will be
addressed
by the resident
inspectors.
The
inspector
examined
relay
cabinet
ARP-4B/SB
and
identified fuses
Ll-2609 and
L5-2640
as
the Fault Trap
FT
6R type which did not appear to properly fit into the fuse
holders.
The licensee's
engineering
personnel
could
not
satisfactorily
explain this condition at the time.
This
concern will be addressed
by the resident
inspectors.
3.
Action On Previous
Inspection
Findings (92701)
(Closed)
IFI
50-400/86-42-01,
Review
Testing
Instructions
for
Periodic
Testing
of Circuits
Covered
by Appendix
R Coordination
Study.
In
a letter
to the
NRC,
dated
August 6,
1986,
(Serial:
CP6L described
a program for periodic testing of circuit
breakers.
The
purpose
of this
program is to demonstrate
that
the
breaker
coordination
study performed pursuant to
Section
9.5. 1,
Fire Protection
Program,
remains
valid; i.e.,
the
breaker
time-current characteristics
have
not significantly drifted.
At the
time of the fire protection
program inspection
conducted
on June 3-6,
1986,
the
program for periodic testing of circuit breakers
was not
yet in place.
An Inspector
Follow-up Item was established
to ensure
NRC
review of the
program.
That review was
conducted
during this
inspection (88-29),
and the program
was found to be acceptable.
In general,
ten percent
of each
type of circuit breaker
is tested
during
each
refueling
outage.
The Planning
Section
issues
a work
request for the testing of circuit breakers.
A maintenance
engineer
maintains
a list of breakers
to-be tested
and
records
of testing
dates
for each.
By referring to the
master list,
a
ten
percent
sample list can
be developed
for
a particular
outag'e.
The
sample
list is attached
to the work request
and given to the
foreman for
testing.
Testing is performed according to the following procedures,
which were reviewed
by the inspector:
Procedure
No:
MPT-E0023,
Revision 0,
480
VAC Power Circuit
Breaker (Safe
Shutdown) Solid State Trip Unit Test
This procedure
covered
long time element pick-up and time delay;
instantaneous
pick-up;
and short-time pick up and time delay.
14
Procedure
No:
MPT -
E 0022,
Revision 0, General
Electric 6.9
KV
IFC-53 (Safe
Shutdown)
Relay Calibration
This procedure
covered pick-up and target test,
time delay test
and instantaneous
pick-up test.
Procedures
No.:
MPT E0024,
Revision 0, Molded - Case Circuit
Breakers
(Safe
Shutdown) Test.
This procedure
covered inspection
and maintenance,
thermal trip
,test
and instantaneous
trip test.
This item is closed.
(Closed)
URI 50-400/86-62-02,
Review the Reportability of all NCR's
Involving Electrical
Cable
Separation.
Inspection
at
the
site
conducted
during
the
construction
phase
in the
area
of electrical
separation
resulted
in an Unresolved
Item being identified.
Numerous
Nonconformance
Reports
for separation
criteria violations
had
been
generated
by the
licensee.
However,
at the
time of the inspection
(July 7-25,
1986),
the
'nonconformances
were
not
being
reported
pursuant to 50.55(e).
The inspector believed
the separation criteria
nonconformances
were
reportable
because
they were discovered
after
the work was signed-off
as being completed
and inspected.
Subsequent
to
the
inspection,
the
licensee
did report electrical
separation
criteria nonconformances
pursuant
to 50.55(e).
The final report
on
the
separation
issue
was transmitted
on December
12,
1986,
by letter
No. HO-860395(o).
During this
inspection
(88-29),
the
licensee's
internal
reports
to resolve
the
issue
were
reviewed.
Corrective
Action/Noncomformance
Report 86-0517
was closed
on October
13,
1986.
This item is closed.
(Closed)
URI 50-400/86-88-02,
Evaluate
Repor tabi lity of Inadequate
Preop
Testing
of
Components.
It
was
establ i shed
during
an
inspection
conducted
on
November
17-21,
1986,
that
inadequate
preoperational
testing
of
the
sequencer
panel
constituted
a
viol,ation.
The
violation
was
issued
on
January
8,
1987.
The
licensee
responded
to
the violation,
and
the
response
has
been
reviewed
and
accepted
by the
NRC.
Unresolved
Item 86-88-02
was
associated
with this violation and concerned
the reportability of the
inadequate
preoperational
test
and
a defective
sequencer
panel.
It
has
been
determined
by the
NRC that
the
inadequate
preoperational
test procedures
was not reportable
under 50.55(e)
because it did not
constitute
a significant
breakdown
of
an entire
portion of the
quality assurance
program itself.
The defective
sequencer
panel
was
not reportable
under Part
21 because
the deficiency was already
known
to the
NRC and did not constitute
a possible
generic
problem.
This item is closed.
15
d.
(Closed)
BU-88-03,
Inadequate
Latch
Engagement
in
HFA Type Latching
Relays Manufactured
by G.E.
IEB 88-03 was issued
March 10,
1988,
and
requested
that licensees
ensure
that all
GE latching-type
HFA relays
installed in Class
lE applications
have adequate
latch engagement
and
that those relays which fail to meet acceptance
criteria
be repaired
or replaced.
By letter dated
June
22,
1988, to NRC,
CP5L stated that
there were
no
HFA type latching relays of the series
identified in
the bulletin in use
in safety-related
applications
at
SHNPP.
This
was also
documented
in the licensee's
response
to
HFA
Relays
in Class
1E Safety Systems.
Based
on the above, this item is
closed.
4.
Exit Interview
The
inspection
scope
and results
were
summarized
on
September
2,
1988,
with those
persons
indicated in paragraph
1.
The inspectors
described
the
areas
inspected
and discussed
in detail
the inspection
items
and concerns.
Proprietary information is not contained
in this report.
In the areas
inspected,
one deviation
and
two unresolved
items
'"(URI) were
identified as indicated below.
Unresolved
items are matters
about which more information is required
to determine
whether
they are
acceptable
or
may involve violations
or deviations.
Deviation
50-400/88-29-03,
Program Deficient for Trending
and Evaluating
As-found
Out-of-Tolerance
Readings
During
Instrument
Calibrations.
Paragraph
2.c.(2)a.
URI
50-400/88-29-01,
Licensee
to Submit Written Justification
on
Temperature
Elements
Concerning
Redundancy.
Paragraph
2.c(2)b.
50-400/88-29-02,
Update of Licensee'
Drawing 2166-S-9000.
Paragraph
2.c.(2)c.
5.
Acronyms, and Initialisms
OEV
DPT,
FI
FT
IFI
(System)
NRC Bulletin
Cathode
Ray Tube
Deviation
Differential Pressure
Transmitter
Environmental Qualification
Flow Indicator
Flow Transmitter
Final Safety Analysis Report
Inspector
Followup Item
Level Indicators
16
LIR
LR
LT
MCB
PR
RC
SEU
SHNPP
TE'I
TT
Level Indicating Recorder
Level Recorder
Level Transmitter
Main Control
Board
Maintenance
Surveillance
Test
Office Nuclear Reactor Regulation
Pressure
Indicator
Pressure
Indicating Recorder
Pressure
Recorder
Pressure
Transmitter
Residual
Heat
Removal
(System)
Reactor
Coolant
Regulator
Guide
Refueling Water Storage
Tank
Safety Evaluation
Report
Site Engineering Unit
Shearon
Harris Nuclear
Power Plant
Temperature
Element
Temperature
Indicator
Temperature
Indicating Recorder
Temperature
Recorder
Temperature
Transmitter
Unresolved
Item