UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II,
101 MARIETTASTREET, N.IN.
ATLANTA.GEORGIA 30303
NOV 15
1978
In Reply Refer To:
RII:JCB
50-400/78-06
50-401/78-06
50-402/78-06
50-403/78-06
Carolina
Power
and Light Company
ATTN:
Mr. J.
A. Jones
Executive Vice President
Engineering,
Construction
and Operation
336 Fayetteville Street.
Raleigh,
27602
Gentlemen:
This refers
to the inspection
conducted
by
W.
B.
Swan of this office on
October 3-6,
1978 of act.ivities authorized
by ÃRC Construction
Permit.
Sos.
CPPR-158,
CPPR-159,
CPPR-160,
and
CPPR-161
for the Shearon Harris nuclear
Plant, Units
1, 2, 3,
and
4 facility, and to the discussion
of our findings
held with MR.
R.
M. Parsons,
Site Manager,
at. the conclusion of the
inspection.
Areas
examined during the inspection
and our findings are discussed
in the
enclosed
inspection report.
Within these
areas,
the inspection
consisted
of selective
examinations
of procedures
and representative
records,
inter-
views with personnel,
and observations
by the inspector.
During the inspection, it was
found that. certain activities under your
license
appear
to be in noncompliance
with NRC requirement.s.
This item and
references
to pertinent.
requirements
are list.ed in the hotice of Violation
enclosed
herewith
as Appendix A.
This not.ice is sent
to you pursuant
to
the provisions of Section
2.201 of the
NRC's "Rules of Practice,"
Part
2,
Title 10,
Code of Federal
Regulations.
Section
2.201
requires
you to
submit, to this office; within 20 days of your receipt of t.his notice,
a
written statement
or explanation
in reply including:
(1) corrective
steps
which have
been
taken
by you,
and the results
achieved;
(2) corrective
steps
which will be taken to avoid further noncompliance;
and (3) the date
when full compliance will be achieved.
%81-z s 80 83@
Carolina
Power
and Light Company
In accordance
vith Section
2.790 of the NRC's Rules of Practice," Yart 2,
Title 10,
Code of Federal
Regulations,
a copy of this letter
and the enclosed
inspection
report vill be placed in the
NRC's Public Document
Room.
If
this report contains
any information that. you (or your contractor)
believe
to be proprietary, it is necessary
that
you make
a written application
vithin 20 days of this office to withhold such information from public
disclosure.
Any such application
must. include
a full statement
of the
reasons
on the basis
of which it. is claimed that the informati'on is
proprietary,
and should
be prepared
so that, proprietary information
identified in the application is contained
in
a separate
part. of the
document,.
If we do not hear
from you in this regard within the specified
period,
the report. will be placed in the Public Document
Room.
Should
you have
any questions
concerning this letter,
ve vill be glad to
discuss
them vi th you.
Sincerely,
Charles
E. Morphy, Chief
Reactor Construction
and Engineering
Support.
Branch
Enclosures:
1.
Appendix A, Notice of 'Violation
2.
Inspection
Report. Nos.: 50-400/78-06,
50-401/78-06,
50-402/78-06
and 50-403/78-06
cc v/encl:
Mr. Roland Parsons,
Site Manager
Shearon Harris Nuclear
Power Plant.
P.
0.
Box
101
Nev Hill, North Carolina
27562